International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 07 | July 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 3523
INVESTIGATION OF “DELAYS OCCURING IN CONSTRUCTION OF
COMMERCIAL BUILDING AS WELL AS ROAD CONSTRUCTION”
Nishant Narayan Patil1, Mansi Jayant Bullu2, Rasika Chandrakant Patil3, Amar Gajanan
Chaugule4
1-4B.E Student, Dept. of Civil Engineering, G. M. Vedak Institute of Technology Maharashtra, India
5Assistant prof. Vinayak Biradar, Dept. of Civil Engineering, G. M. Vedak Institute of technology,
Maharashtra India
---------------------------------------------------------------------***----------------------------------------------------------------------
ABSTRACT –Delays of construction project is defineas, late
completion of the project as compare to the planned schedule.
Construction delays are often resulting of miscommunication
between contractor, subcontractor, owners and suppliers. In
construction delays could be minimized only when there
causes are identified .The Aim of this study is to identified
different causes of construction delay, effect of delay and
methods for minimizing construction delay. A questionnaire
survey is to be done to find out the main causes of delay
through the contractor .The Aim of this project therefore, is to
investigate the current level of application of project
management and the obstacles that have been prevented due
to it is introduction in the Indian construction industry
Key Words: Delay, Effect, Methods, Miscommunication,
Questionnaire Survey
1. INTRODUCTION
“Delays in construction projects”isa universal phenomenon.
In construction of commercial building and road
construction delay could be defined as the time overrun
either beyond completion date specified in a contract or
beyond the date that the parties agreed upon for delivery of
a project. They are almost always accompanied by cost and
time overrun. The delay analysis involves not only
calculation of delay time but also identification of causes
Construction project delays have an adverse effect on
parties, namely:
I. Developer
II. Contractor
III. Consultant
If the work is delayed beyond the time specified in the
contract, they may suffer hardship, expense or loss of
revenue. Hence it is essential to define the actual causes of
delay in order to minimize and avoid the delays in any
construction projects.
2. OBJECTIVE of the study
1. To analyze the reasons and factors of project delay
2. To classify and evaluate delays, claims and related issues.
3. To understand, compare and specify their issues.
3. METHODOLOGY
Methodology is divided into two phases:
I. Literature study
II. Analysis and implementation
The first phase include review conducted through various
research papers, books, internet and international project
journals.
The second phase includes analysis of data and its
implementation.
STEPS:
STEP 1: Quantitative Data and Interview Data
STEP 2: Data Collection
STEP 3: Conclusion and Recommendation
STEP4: Data Analysis
4. METHODS for Analyzing Delay
A. Globle impact method
B. Net impact method
C. As planes vs as built method
D. Impact as planned method
E. Collaps as built method
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 07 | July 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 3524
5. CAUSES of delay
.
A. Labour productivity.
B. Availability of resources.
C. Third the uniqueness of the project.
D. Speed of decision making.
E. Poor or unrealistic scheduling.
F. Poor communication.
G .Lack of information party dependencies.
H. Lack of finance.
I. Site conditions
6. STEPS IN PROJECT SCHEDULING
EPS IN PROJECT
The completion date required for phase of the work. Mean
the schedule values the contractors submit against which
monthly progress payments will be made.
The process of sequencing and phasing individual activities
required to complete the project. A graphical presentation,
which shows the phasing rate of construction activities with
the starting and completion dates.
1. Time estimate for each activity
2. Time estimate for overall project
3. Quantity estimate
4. Utilise float time to cover critical activities
5. Make a overall project schedule
7. MINIMIZATION OF DELAYS
A. Detailed site investigations.
B. Careful monitoring and regular meetings.
C. Effective site management
D. Collaborative working and effective coordination.
E. Careful scheduling.
F. Full commitment to the project by all parties
8. QUESTIONNAIRE SURVEY
VISIT NO. 01
1. NAME OF FIRM: M/S Sheeyash Construction
2. PROJECT NAME: Commercial Building
3. PROJECT LOCATION: CBD Belapur
4. PROJECT DURATION: 2 Year
5. DELAY DURATION: 4Months
6. MAJOR DELAY CUASES:
A. Too short contract duration
B. Shortage of construction material in market
C. Mistake in design documents
VISIT NO .02
1. NAME OF FIRM: Apurva Builders and
Developers
2. PROJECT NAME: CNS Commercial Cubic Sheltor
3. PROJECT LOCATION: Kharghar
4. PROJECT DURATION: 4 Years
5. DELAY DURATION: 2 Years
MAJOR DELAY CAUSES:
A. Legal Disputes b/w parties
B. Delay in payment by owner
C. Difficulties in fancing the project
D. Sortage of Equipments
VISIT NO. 03
1. NAME OF FIRM: NANDRAJ CONSTRUTION
2. PROJECT NAME: Commercial Building
3. PROJECT LOCATION: Lalbaug, mumbai
4. PROJECT DURATION: 18 Months
5. DELAY DURATION: 18 Months
6. MAJOR DELAY CAUSES:
A. Levelling of Land
B. Problems during excavation
C. Weather condition
D. Accident on site
E. Traffic Issue
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 07 | July 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 3525
VISIT NO. 04
1. NAME OF FIRM: VIRAJ SOHAM CONSTRUCTION,
Kandivali west
2. PROJECT NAME: The time square
3. PROJECT LOCATION: Knadivli west
4. PROJECT DURATION: 2 Years
5. DELAY DURATION: None
6. REASONS for NO DELAY:
A. Effective planning and scheduling
B. Processing own Eqipments
C. Continuity of construction project
D. On time payment
9. RESULT
A. Questionnaire survey was done for almost 30 civil,
including some civil contractor.
B. Some significant and common reasons of delay in
construction of commercial builing were found.
C. Also engineers it was observed that well-Equipped
construction company can minimize delay to almost zero
by efficient planning and scheduling
Contribution of various parties to delay in
construction are as following
A. Delay according Consultant is 6%
B. Delay according Owner and Consultant is 12%
C. Delay according Government is 24%
D. Delay from Owner is 24%
E. As well as delay from Contractor is 44%
REFERENCES
• Nitin B Vidhate, ”A methodology for identifying the
different causes of delay in building construction projects,”
international journal of pure and applied research in
engineering and technology; Volume 3 (9): 211-218, May
2015.
• Nuhu Braimah,” Approaches to Delay Claims Assessment
Employed in the UK Construction Industry,”
Buildings;Volume 3: 598-620, September 2013.
• Kuei-Mei Huang, Jyh-Bin Yang, Chang-Hung Lee, and Ruei-
Yu Ku,” Case study of delay impact analysis of lost
productivity in construction projects.
• Ashwini Arun Salunkhe and Rahul S. Patil,” Statistical
Methods for Construction Delay Analysis,” IOSR Journal of
Mechanical andCivil Engineering(IOSR-JMCE);Volume9(2):
58-62, October 2013.
• Enas Fathi Taher and R.K. Pandey,” Study of Delay in
Project Planning and Design Stage of Civil Engineering
Projects,” International Journal ofEngineeringandAdvanced
Technology (IJEAT);Volume 2 (3): 456-461, February 2013.
• Jorvekar Shreyas Praaprao and Sushma ShekharKulkarni,”
Time Impact Analysis on Construction Projects,”
International Journal of Scientific Engineering and Research
(IJSER);Volume 3 (5): 141-146, May 2015.
• Mr. Salim S. Mulla and Prof. Ashish P.Waghmare,” A Study
of Factors Caused for Time & Cost Overruns in Construction
Project & their Remedial Measures,” International Journal of
Engineering Research and Applications;Volume5(1):48-53,
January 2015.
• Sandip Pawar and P. M. Attarde,“ TimeandCostPlanning in
Construction Project,” International Journal of Science and
Research (IJSR);Volume 4 (8): 422-425,August 2015.
• Mr. Satish A. Pitake and Prof. Dhananjay S. Patil,”
Visualization of Construction Progress by 4D Modeling
Application,” International Journal of Engineering Trends
and Technology (IJETT);Volume4(7):3000-3005,July2013.
• Megha Desai and Rajiv Bhatt,” Critical Causes of Delay in
Residential Construction Projects: Case Study of Central
Gujarat RegionofIndia,”International Journal ofEngineering
Trends and Technology (IJETT);Volume4 (4):762-768,April
2013.
• Desai Megha and Dr. Bhatt Rajiv,” A Methodology for
Ranking of Causes of Delay for Residential Construction
Projects in Indian Context,” International Journal of
Emerging Technology and Advanced Engineering;Volume 3
(3): 396-404, March 2013
10. CONCLUSIONS

More Related Content

What's hot

Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...IRJET Journal
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )Engr_Emad Khan
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential BuildingIRJET Journal
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
Estimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential BuildingEstimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential Buildingvivatechijri
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramIJAEMSJORNAL
 
ACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL JOSHI
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...IRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 

What's hot (16)

Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential Building
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
Estimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential BuildingEstimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential Building
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
ACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_Profile
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 

Similar to IRJET - Investigation of “Delays Occuring in Construction of Commercial Building as Well as Road Construction”

IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...ijtsrd
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projectsIRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...IRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...IRJET Journal
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodIRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET Journal
 

Similar to IRJET - Investigation of “Delays Occuring in Construction of Commercial Building as Well as Road Construction” (20)

IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case Study
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdfAlexander Litvinenko
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesChandrakantDivate1
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
Compressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI ApplicationsCompressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI ApplicationsMFatihSIRA
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdfKamal Acharya
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)ChandrakantDivate1
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...dannyijwest
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptamrabdallah9
 

Recently uploaded (20)

litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Compressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI ApplicationsCompressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI Applications
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.ppt
 

IRJET - Investigation of “Delays Occuring in Construction of Commercial Building as Well as Road Construction”

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 07 | July 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 3523 INVESTIGATION OF “DELAYS OCCURING IN CONSTRUCTION OF COMMERCIAL BUILDING AS WELL AS ROAD CONSTRUCTION” Nishant Narayan Patil1, Mansi Jayant Bullu2, Rasika Chandrakant Patil3, Amar Gajanan Chaugule4 1-4B.E Student, Dept. of Civil Engineering, G. M. Vedak Institute of Technology Maharashtra, India 5Assistant prof. Vinayak Biradar, Dept. of Civil Engineering, G. M. Vedak Institute of technology, Maharashtra India ---------------------------------------------------------------------***---------------------------------------------------------------------- ABSTRACT –Delays of construction project is defineas, late completion of the project as compare to the planned schedule. Construction delays are often resulting of miscommunication between contractor, subcontractor, owners and suppliers. In construction delays could be minimized only when there causes are identified .The Aim of this study is to identified different causes of construction delay, effect of delay and methods for minimizing construction delay. A questionnaire survey is to be done to find out the main causes of delay through the contractor .The Aim of this project therefore, is to investigate the current level of application of project management and the obstacles that have been prevented due to it is introduction in the Indian construction industry Key Words: Delay, Effect, Methods, Miscommunication, Questionnaire Survey 1. INTRODUCTION “Delays in construction projects”isa universal phenomenon. In construction of commercial building and road construction delay could be defined as the time overrun either beyond completion date specified in a contract or beyond the date that the parties agreed upon for delivery of a project. They are almost always accompanied by cost and time overrun. The delay analysis involves not only calculation of delay time but also identification of causes Construction project delays have an adverse effect on parties, namely: I. Developer II. Contractor III. Consultant If the work is delayed beyond the time specified in the contract, they may suffer hardship, expense or loss of revenue. Hence it is essential to define the actual causes of delay in order to minimize and avoid the delays in any construction projects. 2. OBJECTIVE of the study 1. To analyze the reasons and factors of project delay 2. To classify and evaluate delays, claims and related issues. 3. To understand, compare and specify their issues. 3. METHODOLOGY Methodology is divided into two phases: I. Literature study II. Analysis and implementation The first phase include review conducted through various research papers, books, internet and international project journals. The second phase includes analysis of data and its implementation. STEPS: STEP 1: Quantitative Data and Interview Data STEP 2: Data Collection STEP 3: Conclusion and Recommendation STEP4: Data Analysis 4. METHODS for Analyzing Delay A. Globle impact method B. Net impact method C. As planes vs as built method D. Impact as planned method E. Collaps as built method
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 07 | July 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 3524 5. CAUSES of delay . A. Labour productivity. B. Availability of resources. C. Third the uniqueness of the project. D. Speed of decision making. E. Poor or unrealistic scheduling. F. Poor communication. G .Lack of information party dependencies. H. Lack of finance. I. Site conditions 6. STEPS IN PROJECT SCHEDULING EPS IN PROJECT The completion date required for phase of the work. Mean the schedule values the contractors submit against which monthly progress payments will be made. The process of sequencing and phasing individual activities required to complete the project. A graphical presentation, which shows the phasing rate of construction activities with the starting and completion dates. 1. Time estimate for each activity 2. Time estimate for overall project 3. Quantity estimate 4. Utilise float time to cover critical activities 5. Make a overall project schedule 7. MINIMIZATION OF DELAYS A. Detailed site investigations. B. Careful monitoring and regular meetings. C. Effective site management D. Collaborative working and effective coordination. E. Careful scheduling. F. Full commitment to the project by all parties 8. QUESTIONNAIRE SURVEY VISIT NO. 01 1. NAME OF FIRM: M/S Sheeyash Construction 2. PROJECT NAME: Commercial Building 3. PROJECT LOCATION: CBD Belapur 4. PROJECT DURATION: 2 Year 5. DELAY DURATION: 4Months 6. MAJOR DELAY CUASES: A. Too short contract duration B. Shortage of construction material in market C. Mistake in design documents VISIT NO .02 1. NAME OF FIRM: Apurva Builders and Developers 2. PROJECT NAME: CNS Commercial Cubic Sheltor 3. PROJECT LOCATION: Kharghar 4. PROJECT DURATION: 4 Years 5. DELAY DURATION: 2 Years MAJOR DELAY CAUSES: A. Legal Disputes b/w parties B. Delay in payment by owner C. Difficulties in fancing the project D. Sortage of Equipments VISIT NO. 03 1. NAME OF FIRM: NANDRAJ CONSTRUTION 2. PROJECT NAME: Commercial Building 3. PROJECT LOCATION: Lalbaug, mumbai 4. PROJECT DURATION: 18 Months 5. DELAY DURATION: 18 Months 6. MAJOR DELAY CAUSES: A. Levelling of Land B. Problems during excavation C. Weather condition D. Accident on site E. Traffic Issue
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 07 | July 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 3525 VISIT NO. 04 1. NAME OF FIRM: VIRAJ SOHAM CONSTRUCTION, Kandivali west 2. PROJECT NAME: The time square 3. PROJECT LOCATION: Knadivli west 4. PROJECT DURATION: 2 Years 5. DELAY DURATION: None 6. REASONS for NO DELAY: A. Effective planning and scheduling B. Processing own Eqipments C. Continuity of construction project D. On time payment 9. RESULT A. Questionnaire survey was done for almost 30 civil, including some civil contractor. B. Some significant and common reasons of delay in construction of commercial builing were found. C. Also engineers it was observed that well-Equipped construction company can minimize delay to almost zero by efficient planning and scheduling Contribution of various parties to delay in construction are as following A. Delay according Consultant is 6% B. Delay according Owner and Consultant is 12% C. Delay according Government is 24% D. Delay from Owner is 24% E. As well as delay from Contractor is 44% REFERENCES • Nitin B Vidhate, ”A methodology for identifying the different causes of delay in building construction projects,” international journal of pure and applied research in engineering and technology; Volume 3 (9): 211-218, May 2015. • Nuhu Braimah,” Approaches to Delay Claims Assessment Employed in the UK Construction Industry,” Buildings;Volume 3: 598-620, September 2013. • Kuei-Mei Huang, Jyh-Bin Yang, Chang-Hung Lee, and Ruei- Yu Ku,” Case study of delay impact analysis of lost productivity in construction projects. • Ashwini Arun Salunkhe and Rahul S. Patil,” Statistical Methods for Construction Delay Analysis,” IOSR Journal of Mechanical andCivil Engineering(IOSR-JMCE);Volume9(2): 58-62, October 2013. • Enas Fathi Taher and R.K. Pandey,” Study of Delay in Project Planning and Design Stage of Civil Engineering Projects,” International Journal ofEngineeringandAdvanced Technology (IJEAT);Volume 2 (3): 456-461, February 2013. • Jorvekar Shreyas Praaprao and Sushma ShekharKulkarni,” Time Impact Analysis on Construction Projects,” International Journal of Scientific Engineering and Research (IJSER);Volume 3 (5): 141-146, May 2015. • Mr. Salim S. Mulla and Prof. Ashish P.Waghmare,” A Study of Factors Caused for Time & Cost Overruns in Construction Project & their Remedial Measures,” International Journal of Engineering Research and Applications;Volume5(1):48-53, January 2015. • Sandip Pawar and P. M. Attarde,“ TimeandCostPlanning in Construction Project,” International Journal of Science and Research (IJSR);Volume 4 (8): 422-425,August 2015. • Mr. Satish A. Pitake and Prof. Dhananjay S. Patil,” Visualization of Construction Progress by 4D Modeling Application,” International Journal of Engineering Trends and Technology (IJETT);Volume4(7):3000-3005,July2013. • Megha Desai and Rajiv Bhatt,” Critical Causes of Delay in Residential Construction Projects: Case Study of Central Gujarat RegionofIndia,”International Journal ofEngineering Trends and Technology (IJETT);Volume4 (4):762-768,April 2013. • Desai Megha and Dr. Bhatt Rajiv,” A Methodology for Ranking of Causes of Delay for Residential Construction Projects in Indian Context,” International Journal of Emerging Technology and Advanced Engineering;Volume 3 (3): 396-404, March 2013 10. CONCLUSIONS