SlideShare a Scribd company logo
1 of 4
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072
ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 227
Comparative Assessment of Delay Analysis Approaches in a
Road Project: A Case Study
Kiran Kaneriya1, Gautam Bhadoriya2
1Post Graduation Student, Department of Civil Engineering, MITS Gwalior, Madhya Pradesh, India
2Assistant Professor, Department of Civil Engineering, MITS Gwalior, Madhya Pradesh, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Delays are a common occurrence in
construction projects, and they can have a significant
impact on the project's cost and schedule. Delay analysis is
the process of determining the causes and effects of delays,
and it is an essential tool for identifying responsible parties
and recovering costs. Comprehensive studies that
systematically compare and assess the practical
applicability and limitations of various delay analysis
methods within the context of Road construction Addressing
this research gap is crucial for refining delay analysis
practices in Road projects and ensuring that project delays
are accurately identified, attributed, and mitigated. Such
studies would not only contribute to academic discourse but
also provide practical insights that could significantly
improve project management and dispute resolution
processes in road construction. This research endeavors to
enhance understanding and knowledge by evaluating
commonly employed Delay Analysis techniques (DATs)
through the examination of a real-time road case study
project. This study focuses on three specific Delay Analysis
Techniques (DATs) within the context of a road project.
Primary data sources are utilized to conduct and document
the study, enabling the identification of key sources of
project delays. The selected DATsโ€”impact as-planned (IAP),
Time Impact Analysis (TIA), and Window Analysis (WA)โ€”
were endorsed by the SCL protocol, and then employed on
the dataset. The implementation of these techniques utilizes
Primavera P6 software. Subsequently, a thorough
comparative analysis is performed on the obtained results.
The assessment of various DATs has led to the conclusion
that the window analysis methodology is a more accurate
method because it incorporates site progress and is gives
reliable results. This knowledge can be invaluable in
mitigating the risks associated with delays and disputes
during construction.
Key Words: Construction Delay, Delay Analysis
Techniques (DATs), Road Project, Primavera p6.
1.INTRODUCTION
Delays in the construction design phase can arise from
various factors, including actions or circumstances
involving the project owner, the contractor, unforeseeable
natural events, or external third parties.
Construction design frequently faces persistent delays.
Any task or activity that surpasses its scheduled
timeframe can impact on the project's overall pace,
potentially causing issues and legal disputes. As a result, it
is crucial to explore and understand the factors
contributing to construction delays. In the construction
industry, Primavera is a widely utilized software tool for
project planning, scheduling, and progress tracking. It can
also be employed for assessing claims for extensions of
time (EOT) and analyzing delays.
The aim of this study is to enhance our understanding of
Delay Analysis Techniques (DATs) by examining their
application in a real-time road case study. To achieve this,
we conducted a thorough literature review, critically
assessing various DATs and selecting three Techniques for
this study. We chose a specific road design project,
namely, the Baroda Main Road to Malpura via Chondpur,
as our case study. The primary sources of information
include insights shared by professionals who were
involved in this project and related data on delays.
1.1 Objective of the study
1. Identify the responsible parties and causes of
delays.
2. Assigning Responsibility to the Appropriate Party
for which action, who is responsible for which act.
3. To track the project progress and analyze the
reason for delays.
4. Comparative behavior of different DATs applied.
2. LITERATURE REVIEW
SelvaKumar and Manishankar (2020), The paper
discusses the use of Primavera software for delay analysis
in highway construction projects. A delay analysis is used
on Case study of four Laning of Cholapuram โ€“ Thanjavur
section of NH-45C highway construction project length is
47.835 kms. Including 184 nos. structure works in the
state of Tamil Nadu. A total of 8 types of delays were
considered in highway construction projects. The paper
concludes by discussing the benefits of using Primavera
for delay analysis and the temporary worker has
implemented an updated development schedule in
compliance with the contract terms, resulting in an
extension of the completion time by 364 days.[1]
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072
ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 228
Shubham Ashok Avhad, Satish M. Waysal (2020),
According to the contractor, this survey is conducted to
determine the timeliness of the road development project
and to identify the elements that contribute to delays. It is
conducted using the Questionnaire Survey, which was
completed with the with Google Forms' aid. According to
the study, there are 32 different reasons that can cause a
delay or failure of the Road. According to the report,
construction-related mishaps, rising material costs, and
the main factors that have the greatest impact on road
failure are cost and time delays. These elements were used
Excel for quantitative analysis and the Severity Index
Method for analysis and Google Forms, after which the
outcome was computed. There are six government
contractors on the panel. Six government contractors and
five private contractors will participate in the panel
discussion. Based on the survey, the maximum factors'
impact level is high (between 60% and 80%), and the
limited factors' impact is also high Moderate (40% to
60%) in intensity. [2]
Saravanan Karunakaran, M. A. Malek (2019), This
paper contributes a deep review on the factors that cause
delay in the construction industry, especially in the
construction of highway and road projects. The study
included 92 factors consisting of various construction
phase. The study investigated that topmost significant
factor that causes delay in construction projects was poor
project planning and scheduling with the highest
frequency of occurrences and percentage value which is
25 and 2.5% respectively. Therefore, these findings will be
useful for future planning and time management in order
to minimize the delay occurrences on the highway and
road construction projects.[3]
Suroj Ghimire and Anjay Kumar Mishra
(2019),Through the case study of an under-construction
hydroelectric project and a review of pertinent issues not
covered by the techniques, this research has made a
comparative study of the limitations and capabilities of
different Prospective "DATs," i.e., Impacted as Planned
method and Time Impact Analysis method, under the
same baseline program and under similar circumstances
of delay occurrence. According to the study's findings, the
contractor has not complied with any DATs in order to file
a request for a time extension. The contractor has
requested a 721-day time extension and presented a
revised construction schedule in accordance with the
FIDIC terms of the contract.
The delay to 620 is displayed when the Impacted as
intended approach is used. The Time Impact Analysis
approach indicated that the employer's delay was 529
days, whereas the contractor's delay was 101 days. [4]
Siddesh pai & neeraj anand (2018), A questionnaire
survey and personal interviews methodology was used for
this research. Most critical variables causing construction
delay were analyzed using factor analysis. These results
will significantly contribute in controlling the time
overruns in Indian road construction industry.
The exorbitant costs arising from delays in road
constructions results in considerable decline in the entire
stretch of roads constructed and repaired yearly or it may
lead to substandard quality of construction work.This
research provides fresh dimensions in project
management of road projects and guides the stakeholders
to successfully encounter the challenges that they occur
during any road construction project execution in India
and to mitigate the delays, handle challenging and
problematic matters in a timely way, maintain effective
project monitoring, serve as a prior warning system for
time and cost overruns, and help project team to take
timely decisions and the monitor projects so as to
upgrade, continue and/or terminate a project. [5]
Diksha Soni, Vijay Kumar Punjabi (2018), this research
would analyze and study the Land Acquisition Act of 1894,
the various amendments and causes for disputes in land
acquisition and intend to achieve this by a thorough
understanding of the intricacies of land acquisition act,
considering the various causes for disputes and analyzing
each reason through a case study. This study explores
alternate ways of dispute resolution and see if there is a
need to bring about any rectification in the basic dispute
resolution process.
This study concluded that it is imperative to ensure
accurate valuation for compensation calculations. Site
selection surveys should prioritize acquiring barren land
over fertile land to minimize impact. The use of urgency
clauses should be reserved for genuine emergencies. Land
surveyors must conduct their work with utmost
professionalism, accuracy, and transparency. When
compensating for crop damage, rates should align with
current market prices and the crop's maturity. [6]
Al- Gahtani, Khalid S (2011), This paper examines the
delay claim by analyzing current method using a fictional
case study. The case study is applied to all current
techniques of delay claims that have been identified from
previous studies. The comparison uses the delay claim
issues as criteria to evaluate all the delay claim techniques
from the case study results. It pinpoints the urgent need
for standardized approaches and supports the Day-by-Day
approach as standard for analyzing project delays. [7]
Jyh-Bin Yang, and Chih-Kuei Kao (2009), this study
based on Selecting a suitable analysis methodology for
resolving the schedule delay claims encountered. This
study reviews 18 delay analysis methods, and compares in
detail three process-based dynamic analysis methods,
namely, the snapshot analysis method, the windows
analysis method and the isolated delay type method. A
dynamic method is ideal for resolving a delay claim. The
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072
ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 229
differences among the dynamic methods in terms of the
capabilities, required documents, timing and analysis
process are discussed to help delay analysts to select an
appropriate method. Finally, this study attempts to
propose six suggestions on developing an ideal analysis
method. [8]
2.1 TYPES OF DELAYS
Types of Construction Delays are-
Prior to starting the schedule delay analysis, it is
important to thoroughly understand the general
categories of construction delays. Schedule construction
delays are categorized in many ways. According to
Trauner et al. (2009) identified four categories of
construction delay: [9]
๏‚ท Excusable or non-excusable
๏‚ท Compensable or non-compensable
๏‚ท Critical or noncritical
๏‚ท Concurrent or non-concurrent
2.2 CAUSES OF DELAYS
From causation perspective delays may be categorized
under the following types:
1.Delays caused by the contractor: these include delays
caused by parties for whom the contractor is responsible
in law. Under most contracts the contractor is neither
entitled to extension of time nor recovery of loss and/or
expense and may have to pay damages/penalties.
2.Delays caused by the owner: these include delays
caused by parties for whom the owner is responsible in
law. In most standard forms, the contractor is entitled to
extension of time and recovery of loss and/or expense
caused by this type of delay.
3.Delays caused by neither party: these include delays
for which neither the owner nor the contractor is
responsible, e.g. exceptionally adverse weather conditions.
Most contracts allow the contractor more time to complete
but with no corresponding entitlement to recover any loss
and/or expense caused and no damages/penalties
assessed.
3.METHODOLOGY
Fig.1. Methodology
3.1 About the study
Name of work- Construction of rural road under CMGSY
Name of Road-Baroda Main Road to Malpura via
Chondpur
Total length of Road- 3.225 Km
Location- Sheopur
Head- CMGSY
3.1 COMPARISON
A comparative analysis of delay assessment techniques
(DATโ€™s) was carried out, and it was observed that each
technique gave the same results. i.e., 24 days.
This occurred because the selected project had delays
from both the client and the contractor, causing all
following tasks to be delayed under the same baseline
program and under similar circumstances of delay
occurrence. Furthermore, the contractor completed all of
his tasks within the time frame specified. This explains
why each technique produced similar findings.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072
ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 230
Following table provides quick comparative review on the
outcomes from the application of Different DATs:
Table-1
Comparative Analysis of DATs
S.
No.
DATโ€™s Impacted
Completion
Date
Total
Delay
EC NN
1. IAP 21-June-
2021
24 days 19
days
5 days
2. TIA 21-June-
2021
24 days 19
days
5 days
3. WA 21-June-
2021
24 days 19
days
5 days
Notation
DATs Delay Analysis Techniques
IAP Impact As-Planned
TIA Time Impact Analysis
WA Window Analysis
EC Client caused delay
NN Contractor caused delay
4. CONCLUSION
From this research, the following conclusions have been
drawn:
The delays were caused by the client and the contractor
i.e. 19 days and 5 days respectively, the delay due to
critical activities extended the project duration by 24 days
in totality.
It is very important to assign the responsibility of the
delay to the particular party to avoid the disputes. Client
and contractor both are responsible for excusable and non
excusable delays in the study.
Project progress is monitored using Primavera P6 and the
CPM technique with Different Analysis . The causes of the
delayed events can be listed as follows: Delayed
procurement of Right of way, Delay in payment, Delay in
Excavation, Delay in Material Supply.
To find out how delays in events affect the project's
completion schedule, three primary DATs are chosen: IAP,
TIA, and WA (as advised by SCL Protocol).The windows
delay analysis approach is shown to be fairly accurate and
appropriate for usage when comparing all of the DATs
employed because it accounts for the effects of baseline
updates using fragnet. The actual impact of the delay
events on the identified actual or as built critical path is
determined via a retrospective delay analysis. It needs a
skilled and knowledgeable planner.
Generally, out of all the commonly utilized delay analysis
techniques (DATs) for claiming the Extension of Time
(EOT), window analysis (WA) is a better and more reliable
technique.
REFERENCES
[1] SelvaKumar, M., and S. Manishankar. "Delay Analysis
of Highway Construction Using Primavera."Emperor
Journal of Applied Scientific Research(2020).
[2] Avhad, Shubham Ashok, and Satish M.Waysal.
"Analysis of Factorโ€™s Causing Delays in RoadProject by
Severity Index Method."
[3] Karunakaran, Saravanan, M. A. Malek, and M. Z. Ramli.
"Causes of delay in construction of highway projects: A
review." International Journal of Civil Engineering and
Technology 10.2 (2019): 2374-2386.
[4] Ghimire, Suroj, and Anjay Kumar Mishra. "Comparative
study of prospective delay analysis techniques
(DATs)."Saudi J Civ Eng3.5 (2019): 84-95.
[5] Pai, Siddesh, et al. "Developing a framework for
mitigation of project delays in roads and highways sector
projects in India." J Manag Res Anal 5.3 (2020): 357-366.
[6] Soni, Diksha, and Vijay Kumar Punjabi. "Delay in
Projects due to disputes in land acquisition." International
Research Journal of Engineering and Technology (IRJET) e-
ISSN (2018): 2395-0056.
[7] Al-Gahtani, Khalid S., and Satish B. Mohan. "Delay
analysis techniques comparison." Journal of Civil
Engineering and Architecture 5.8 (2011): 740-747.
[8] Yang, Jyh-Bin, and Chih-Kuei Kao. "Review of delay
analysis methods: A process-based comparison." The Open
Construction & Building Technology Journal 3.1 (2009).
[9] Trauner, Ted J. Construction delays: Understanding
them clearly, analyzing them correctly. Butterworth-
Heinemann, 2009.
45

More Related Content

Similar to Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case Study

Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodIRJET Journal
ย 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
ย 
IRJET- Analysis of Change Order in Road Construction Projects
IRJET-  	  Analysis of Change Order in Road Construction ProjectsIRJET-  	  Analysis of Change Order in Road Construction Projects
IRJET- Analysis of Change Order in Road Construction ProjectsIRJET Journal
ย 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectseSAT Journals
ย 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportationeSAT Publishing House
ย 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
ย 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
ย 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
ย 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
ย 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
ย 
B1303020508
B1303020508B1303020508
B1303020508IOSR Journals
ย 
IRJET - Investigation of โ€œDelays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of โ€œDelays Occuring in Construction of Commercial B...IRJET -  	  Investigation of โ€œDelays Occuring in Construction of Commercial B...
IRJET - Investigation of โ€œDelays Occuring in Construction of Commercial B...IRJET Journal
ย 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...ijtsrd
ย 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
ย 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
ย 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
ย 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectseSAT Publishing House
ย 
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...IRJET Journal
ย 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projectsijtsrd
ย 

Similar to Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case Study (20)

Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
ย 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
ย 
IRJET- Analysis of Change Order in Road Construction Projects
IRJET-  	  Analysis of Change Order in Road Construction ProjectsIRJET-  	  Analysis of Change Order in Road Construction Projects
IRJET- Analysis of Change Order in Road Construction Projects
ย 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
ย 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
ย 
D012261521
D012261521D012261521
D012261521
ย 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
ย 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
ย 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
ย 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
ย 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
ย 
B1303020508
B1303020508B1303020508
B1303020508
ย 
IRJET - Investigation of โ€œDelays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of โ€œDelays Occuring in Construction of Commercial B...IRJET -  	  Investigation of โ€œDelays Occuring in Construction of Commercial B...
IRJET - Investigation of โ€œDelays Occuring in Construction of Commercial B...
ย 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
ย 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
ย 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
ย 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
ย 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
ย 
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
ย 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
ย 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
ย 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
ย 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
ย 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
ย 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
ย 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
ย 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
ย 
A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
ย 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
ย 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
ย 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
ย 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
ย 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
ย 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
ย 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
ย 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
ย 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
ย 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
ย 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
ย 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
ย 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
ย 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
ย 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
ย 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
ย 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
ย 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
ย 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
ย 
A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of โ€œSeismic Response of RC Structures Having Plan and Vertical Irreg...
ย 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
ย 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
ย 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
ย 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
ย 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
ย 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
ย 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
ย 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
ย 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
ย 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
ย 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
ย 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
ย 

Recently uploaded

Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
ย 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
ย 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
ย 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
ย 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
ย 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
ย 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
ย 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
ย 

Recently uploaded (20)

Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
ย 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
ย 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
ย 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
ย 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
ย 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ย 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
ย 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
ย 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
ย 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
ย 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
ย 

Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case Study

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072 ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 227 Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case Study Kiran Kaneriya1, Gautam Bhadoriya2 1Post Graduation Student, Department of Civil Engineering, MITS Gwalior, Madhya Pradesh, India 2Assistant Professor, Department of Civil Engineering, MITS Gwalior, Madhya Pradesh, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Delays are a common occurrence in construction projects, and they can have a significant impact on the project's cost and schedule. Delay analysis is the process of determining the causes and effects of delays, and it is an essential tool for identifying responsible parties and recovering costs. Comprehensive studies that systematically compare and assess the practical applicability and limitations of various delay analysis methods within the context of Road construction Addressing this research gap is crucial for refining delay analysis practices in Road projects and ensuring that project delays are accurately identified, attributed, and mitigated. Such studies would not only contribute to academic discourse but also provide practical insights that could significantly improve project management and dispute resolution processes in road construction. This research endeavors to enhance understanding and knowledge by evaluating commonly employed Delay Analysis techniques (DATs) through the examination of a real-time road case study project. This study focuses on three specific Delay Analysis Techniques (DATs) within the context of a road project. Primary data sources are utilized to conduct and document the study, enabling the identification of key sources of project delays. The selected DATsโ€”impact as-planned (IAP), Time Impact Analysis (TIA), and Window Analysis (WA)โ€” were endorsed by the SCL protocol, and then employed on the dataset. The implementation of these techniques utilizes Primavera P6 software. Subsequently, a thorough comparative analysis is performed on the obtained results. The assessment of various DATs has led to the conclusion that the window analysis methodology is a more accurate method because it incorporates site progress and is gives reliable results. This knowledge can be invaluable in mitigating the risks associated with delays and disputes during construction. Key Words: Construction Delay, Delay Analysis Techniques (DATs), Road Project, Primavera p6. 1.INTRODUCTION Delays in the construction design phase can arise from various factors, including actions or circumstances involving the project owner, the contractor, unforeseeable natural events, or external third parties. Construction design frequently faces persistent delays. Any task or activity that surpasses its scheduled timeframe can impact on the project's overall pace, potentially causing issues and legal disputes. As a result, it is crucial to explore and understand the factors contributing to construction delays. In the construction industry, Primavera is a widely utilized software tool for project planning, scheduling, and progress tracking. It can also be employed for assessing claims for extensions of time (EOT) and analyzing delays. The aim of this study is to enhance our understanding of Delay Analysis Techniques (DATs) by examining their application in a real-time road case study. To achieve this, we conducted a thorough literature review, critically assessing various DATs and selecting three Techniques for this study. We chose a specific road design project, namely, the Baroda Main Road to Malpura via Chondpur, as our case study. The primary sources of information include insights shared by professionals who were involved in this project and related data on delays. 1.1 Objective of the study 1. Identify the responsible parties and causes of delays. 2. Assigning Responsibility to the Appropriate Party for which action, who is responsible for which act. 3. To track the project progress and analyze the reason for delays. 4. Comparative behavior of different DATs applied. 2. LITERATURE REVIEW SelvaKumar and Manishankar (2020), The paper discusses the use of Primavera software for delay analysis in highway construction projects. A delay analysis is used on Case study of four Laning of Cholapuram โ€“ Thanjavur section of NH-45C highway construction project length is 47.835 kms. Including 184 nos. structure works in the state of Tamil Nadu. A total of 8 types of delays were considered in highway construction projects. The paper concludes by discussing the benefits of using Primavera for delay analysis and the temporary worker has implemented an updated development schedule in compliance with the contract terms, resulting in an extension of the completion time by 364 days.[1]
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072 ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 228 Shubham Ashok Avhad, Satish M. Waysal (2020), According to the contractor, this survey is conducted to determine the timeliness of the road development project and to identify the elements that contribute to delays. It is conducted using the Questionnaire Survey, which was completed with the with Google Forms' aid. According to the study, there are 32 different reasons that can cause a delay or failure of the Road. According to the report, construction-related mishaps, rising material costs, and the main factors that have the greatest impact on road failure are cost and time delays. These elements were used Excel for quantitative analysis and the Severity Index Method for analysis and Google Forms, after which the outcome was computed. There are six government contractors on the panel. Six government contractors and five private contractors will participate in the panel discussion. Based on the survey, the maximum factors' impact level is high (between 60% and 80%), and the limited factors' impact is also high Moderate (40% to 60%) in intensity. [2] Saravanan Karunakaran, M. A. Malek (2019), This paper contributes a deep review on the factors that cause delay in the construction industry, especially in the construction of highway and road projects. The study included 92 factors consisting of various construction phase. The study investigated that topmost significant factor that causes delay in construction projects was poor project planning and scheduling with the highest frequency of occurrences and percentage value which is 25 and 2.5% respectively. Therefore, these findings will be useful for future planning and time management in order to minimize the delay occurrences on the highway and road construction projects.[3] Suroj Ghimire and Anjay Kumar Mishra (2019),Through the case study of an under-construction hydroelectric project and a review of pertinent issues not covered by the techniques, this research has made a comparative study of the limitations and capabilities of different Prospective "DATs," i.e., Impacted as Planned method and Time Impact Analysis method, under the same baseline program and under similar circumstances of delay occurrence. According to the study's findings, the contractor has not complied with any DATs in order to file a request for a time extension. The contractor has requested a 721-day time extension and presented a revised construction schedule in accordance with the FIDIC terms of the contract. The delay to 620 is displayed when the Impacted as intended approach is used. The Time Impact Analysis approach indicated that the employer's delay was 529 days, whereas the contractor's delay was 101 days. [4] Siddesh pai & neeraj anand (2018), A questionnaire survey and personal interviews methodology was used for this research. Most critical variables causing construction delay were analyzed using factor analysis. These results will significantly contribute in controlling the time overruns in Indian road construction industry. The exorbitant costs arising from delays in road constructions results in considerable decline in the entire stretch of roads constructed and repaired yearly or it may lead to substandard quality of construction work.This research provides fresh dimensions in project management of road projects and guides the stakeholders to successfully encounter the challenges that they occur during any road construction project execution in India and to mitigate the delays, handle challenging and problematic matters in a timely way, maintain effective project monitoring, serve as a prior warning system for time and cost overruns, and help project team to take timely decisions and the monitor projects so as to upgrade, continue and/or terminate a project. [5] Diksha Soni, Vijay Kumar Punjabi (2018), this research would analyze and study the Land Acquisition Act of 1894, the various amendments and causes for disputes in land acquisition and intend to achieve this by a thorough understanding of the intricacies of land acquisition act, considering the various causes for disputes and analyzing each reason through a case study. This study explores alternate ways of dispute resolution and see if there is a need to bring about any rectification in the basic dispute resolution process. This study concluded that it is imperative to ensure accurate valuation for compensation calculations. Site selection surveys should prioritize acquiring barren land over fertile land to minimize impact. The use of urgency clauses should be reserved for genuine emergencies. Land surveyors must conduct their work with utmost professionalism, accuracy, and transparency. When compensating for crop damage, rates should align with current market prices and the crop's maturity. [6] Al- Gahtani, Khalid S (2011), This paper examines the delay claim by analyzing current method using a fictional case study. The case study is applied to all current techniques of delay claims that have been identified from previous studies. The comparison uses the delay claim issues as criteria to evaluate all the delay claim techniques from the case study results. It pinpoints the urgent need for standardized approaches and supports the Day-by-Day approach as standard for analyzing project delays. [7] Jyh-Bin Yang, and Chih-Kuei Kao (2009), this study based on Selecting a suitable analysis methodology for resolving the schedule delay claims encountered. This study reviews 18 delay analysis methods, and compares in detail three process-based dynamic analysis methods, namely, the snapshot analysis method, the windows analysis method and the isolated delay type method. A dynamic method is ideal for resolving a delay claim. The
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072 ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 229 differences among the dynamic methods in terms of the capabilities, required documents, timing and analysis process are discussed to help delay analysts to select an appropriate method. Finally, this study attempts to propose six suggestions on developing an ideal analysis method. [8] 2.1 TYPES OF DELAYS Types of Construction Delays are- Prior to starting the schedule delay analysis, it is important to thoroughly understand the general categories of construction delays. Schedule construction delays are categorized in many ways. According to Trauner et al. (2009) identified four categories of construction delay: [9] ๏‚ท Excusable or non-excusable ๏‚ท Compensable or non-compensable ๏‚ท Critical or noncritical ๏‚ท Concurrent or non-concurrent 2.2 CAUSES OF DELAYS From causation perspective delays may be categorized under the following types: 1.Delays caused by the contractor: these include delays caused by parties for whom the contractor is responsible in law. Under most contracts the contractor is neither entitled to extension of time nor recovery of loss and/or expense and may have to pay damages/penalties. 2.Delays caused by the owner: these include delays caused by parties for whom the owner is responsible in law. In most standard forms, the contractor is entitled to extension of time and recovery of loss and/or expense caused by this type of delay. 3.Delays caused by neither party: these include delays for which neither the owner nor the contractor is responsible, e.g. exceptionally adverse weather conditions. Most contracts allow the contractor more time to complete but with no corresponding entitlement to recover any loss and/or expense caused and no damages/penalties assessed. 3.METHODOLOGY Fig.1. Methodology 3.1 About the study Name of work- Construction of rural road under CMGSY Name of Road-Baroda Main Road to Malpura via Chondpur Total length of Road- 3.225 Km Location- Sheopur Head- CMGSY 3.1 COMPARISON A comparative analysis of delay assessment techniques (DATโ€™s) was carried out, and it was observed that each technique gave the same results. i.e., 24 days. This occurred because the selected project had delays from both the client and the contractor, causing all following tasks to be delayed under the same baseline program and under similar circumstances of delay occurrence. Furthermore, the contractor completed all of his tasks within the time frame specified. This explains why each technique produced similar findings.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 11 Issue: 01 | Jan 2024 www.irjet.net p-ISSN: 2395-0072 ยฉ 2024, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 230 Following table provides quick comparative review on the outcomes from the application of Different DATs: Table-1 Comparative Analysis of DATs S. No. DATโ€™s Impacted Completion Date Total Delay EC NN 1. IAP 21-June- 2021 24 days 19 days 5 days 2. TIA 21-June- 2021 24 days 19 days 5 days 3. WA 21-June- 2021 24 days 19 days 5 days Notation DATs Delay Analysis Techniques IAP Impact As-Planned TIA Time Impact Analysis WA Window Analysis EC Client caused delay NN Contractor caused delay 4. CONCLUSION From this research, the following conclusions have been drawn: The delays were caused by the client and the contractor i.e. 19 days and 5 days respectively, the delay due to critical activities extended the project duration by 24 days in totality. It is very important to assign the responsibility of the delay to the particular party to avoid the disputes. Client and contractor both are responsible for excusable and non excusable delays in the study. Project progress is monitored using Primavera P6 and the CPM technique with Different Analysis . The causes of the delayed events can be listed as follows: Delayed procurement of Right of way, Delay in payment, Delay in Excavation, Delay in Material Supply. To find out how delays in events affect the project's completion schedule, three primary DATs are chosen: IAP, TIA, and WA (as advised by SCL Protocol).The windows delay analysis approach is shown to be fairly accurate and appropriate for usage when comparing all of the DATs employed because it accounts for the effects of baseline updates using fragnet. The actual impact of the delay events on the identified actual or as built critical path is determined via a retrospective delay analysis. It needs a skilled and knowledgeable planner. Generally, out of all the commonly utilized delay analysis techniques (DATs) for claiming the Extension of Time (EOT), window analysis (WA) is a better and more reliable technique. REFERENCES [1] SelvaKumar, M., and S. Manishankar. "Delay Analysis of Highway Construction Using Primavera."Emperor Journal of Applied Scientific Research(2020). [2] Avhad, Shubham Ashok, and Satish M.Waysal. "Analysis of Factorโ€™s Causing Delays in RoadProject by Severity Index Method." [3] Karunakaran, Saravanan, M. A. Malek, and M. Z. Ramli. "Causes of delay in construction of highway projects: A review." International Journal of Civil Engineering and Technology 10.2 (2019): 2374-2386. [4] Ghimire, Suroj, and Anjay Kumar Mishra. "Comparative study of prospective delay analysis techniques (DATs)."Saudi J Civ Eng3.5 (2019): 84-95. [5] Pai, Siddesh, et al. "Developing a framework for mitigation of project delays in roads and highways sector projects in India." J Manag Res Anal 5.3 (2020): 357-366. [6] Soni, Diksha, and Vijay Kumar Punjabi. "Delay in Projects due to disputes in land acquisition." International Research Journal of Engineering and Technology (IRJET) e- ISSN (2018): 2395-0056. [7] Al-Gahtani, Khalid S., and Satish B. Mohan. "Delay analysis techniques comparison." Journal of Civil Engineering and Architecture 5.8 (2011): 740-747. [8] Yang, Jyh-Bin, and Chih-Kuei Kao. "Review of delay analysis methods: A process-based comparison." The Open Construction & Building Technology Journal 3.1 (2009). [9] Trauner, Ted J. Construction delays: Understanding them clearly, analyzing them correctly. Butterworth- Heinemann, 2009. 45