DELAY ANALYSIS OF A CONSTRUCTION PROJECT- A CASE STUDY
Mr. Nagarjun Gowda B.S1, Ms. Chethana K.N2
1Assistant Professor, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India
2Student, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Construction technology has become an essential
part of any of the project, for timely and economical
completion of the project. A proper construction planning
and schedule acts as a main role ford different purposes. By
using the schedule, we can know the merely completion of
the project, contractors can recruit the necessary
manpower; can demand shifts or equipments to speed up
the project. The most important function of the project
management is to plan and control the project objective like
time, budget and setting out of resource productivity
standards to achieve the objectives of the project. Delay
happens in all construction projects. Where construction
project will vary in size, some will be in small. In vast
projects, analysis should be done for the purpose on making
right decisions on time and cost compensation claims. Many
type of software’s are available to plan, execute and control
the project; with the help of these software’s the project
management has become easier to evolve the construction
project. Large quantities of different kind of resources are
required for execution and the risk is more in case of big
projects. So, planning and scheduling in big projects is
essential. In this study, an effort is made in planning,
scheduling and delay analysis and updating of various
activities which is done using MS project.
Key Words: Construction Management, Planning,
Delay, Labour Productivity, Scheduling, Tracking.
1. INTRODUCTION
Construction industry plays an important role in the
economic growth of a country. It is the process of
implementing the plans, ideas, standards, specifications
and assigning the resources into a physical facility to meet
the specific requirements of owner.
Construction management can be defined as the
accomplishment of results through the combined effort of
the consultant, client and designer. Construction is a very
unique and creative practice which coverts four M’s of the
construction-Material, Manpower, Machinery and Money
into a systematic structure. Thus construction management
contains Planning, Executing and monitoring the
construction activities in a specific project.
1.1 Project Planning, Scheduling and Controlling
The main aim of the construction management is to plan
and schedule the resources within the frame work of a
project. The guidelines and procedures of the construction
management direct the managers how to utilize the
resources during the construction process. Before
execution of the work on the site all kinds of office works
such as planning, designing, estimating, negotiating,
purchasing, scheduling, controlling etc. should be done
carefully.
1.2 Construction Delay Analysis
Delay is one of the common problems in the construction
project. Delay of a construction project is defined as late
completion of the project as compared to the planned
schedule. Construction delays are often resulting of
miscommunication between contractors, subcontractors,
owners and suppliers.
These types of unrealistic exceptions are usually avoided
by clean and efficient planning mechanism, which clearly
specifies the work and timetable to be used. Delays in
construction project are quite expensive; sometimes they
may result in severe damages to the involved parties.
1.3 Objective of the Study
 Detailed literature study to define the various causes
of delay in construction projects
 Study on ongoing Project site to observe the activities
and to identify delay factors
 Determination of Critical Path using MS Projects
 The analysis also involves the process of scheduling
and tracking of a construction project activities in
software and related catch up programs due to delays.
2. METHODOLOGY
 Site Investigation.
 Studying Of BOQ & Drawings.
 Study On Labor Productivity.
 Scheduling.
 Tracking & updating of project.
 Delay Analysis.
 Results & conclusions.
2.1 Brief Details of Project
Nature Walk is a Villa project consisting of 14 Villas of
3BHK and 4 BHK.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1729
 Name of the project: Nature Walk Project.
 Location: KR Puram, Bengaluru.
 Contractor: Sri Laxmi Constructions.
 Client: Renaissance Holdings.
 Built up Area: 8400 sq-ft-9880 sq-ft.
 Super Built-up Area: 9450 sq-ft – 11115 sq-ft.
 Site area: 14 Acres.
 Building Type: Villas.
 Number of floors: G+2.
 Total number of Villas: 147.
2.2 Project Specification
 Structure
- Villas are Reinforced Cement Concrete with G+2
Floor.
 Concrete
- M10 grade for PCC, M25 grade for Footing, Columns,
Beams & Slabs.
 Steel
- High Yield Strength Deformed bars Fe-500 is used.
 Masonry Work
- 4” & 6” Internal and External Concrete block walls.
 Plastering
- External sand faced plaster.
- Internal plaster with putty.
 Painting
- External Walls-Cement texturing with Apex/Ace
emulsion.
 Windows
- UPVC.
 Flooring
- Balcony -Anti Skid Tiles, Kitchen- Vitrified Tiles,
Living/Dining- Marble, Granite.
2.3 Labor Productivity and Manpower Requirement
The required manpower for each activity for carrying out
that particular activity efficiently without compromising
on the quality is allocated and calculated based on labor
productivity.
Table: 2.1 Duration delay table
Task Name Duration Baseline
Duration
Nature Walk Project B-
08
472 days 406 days
VILLA 99 & 100 439 days 360 days
Nature Walk Project B-08
Sub Structure 106 days 88 days
Earthwork 6 days 5 days
Plain cement concrete 59 days 50 days
Footing 37 days 30 days
Plinth Beam 48 days 40 days
Ground Floor 63 days 59 days
1st floor 62 days 52 days
2nd Floor 36 days 28 days
Staircase 13 days 10 days
Block Work 99 days 75 days
Wall Tiling 21 days 15 days
Plastering 132 days 101 days
Internal Plastering 53 days 37 days
Ceiling Plastering 24 days 19 days
Wall Plastering 40 days 28 days
External Plastering 76 days 59 days
Painting 50 days 46 days
Internal Painting 42 days 32 days
External Painting 20 days 39 days
3. CONCLUSIONS
On analyzing it’s been found there is a delay of 66 days in
the completion of the project. The critical activities of the
project are foundation, casting the floor slab, block work,
external plastering, painting and doors. Inspire of critical
activities, there are some additional activities where the
project experienced difficulties in execution and delay in
completion.
From the delay analysis an amount of Rs. 620200/- has
been incurred to the project which is an additional loss to
the project and simultaneously over shoots the budget
allocated to the project. The main causes of the delay in
the project are both excusable and non-excusable delays,
which are identified by the occurrence and experience.
The main delays were recorded and the loss of
productivity and cost loss has been calculated.
In this study, the main causes of the delay occurrence are
rain, unskilled labors, shortage of skilled labor, poor
workmanship, shortage of labors, inadequate of
availability of materials, non-availability of materials,
delay in payment to the contractor by client, partial
payments to labor by contractors. These delays imply that
contract related delays require adequate attention,
because these delays topped with huge loss to the
company and project duration overrun. Time overrun and
cost overrun effects are more in this project. So, necessary
action should be adopted to avoid the delays which lead to
project loss.
REFERENCES
[1] Megha Desai and Rajiv Bhatt (April 2013). “Critical
Causes of Delay in Residential Construction Projects: Case
Study of Central Gujarat Region of India”, International
Journal of Engineering Trends and Technology, Vol. 4,
Issue 4, pp 767-768.
[2] Siddesh K. Pai and J. Raj Bharath (March 2013).
“Analysis of Critical Causes of Delays in Indian
Infrastructure Projects”, International Journal of
Innovative Research and Development, Vol. 2, Issue 3, pp
251-263.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1730
[3] Enas Fathi Taher and R. K. Pandey (Feb 2013). “Study
of Delay in Project Planning and Design Stage of Civil
Engineering Projects”, International Journal of
Engineering and Advanced Technology, Vol. 2, Issue 3, pp
456-461.
[4] M. Haseeb, Xinhai-Lu, Aneesa Bibi, Maloof-ud-Dyian
and Wahab Rabbani (Sept 2011). “Problems of Projects
and Effects of Delays in the Construction Industry of
Pakistan”, Australian Journal of Business and Management
Research, Vol. 1, No. 5, pp 41-50.
[5] Abedi M., Fathi M. S. and Mohammad M. F. (2011).
“Effects of Construction Delays on Construction Project
Objectives”, Scientific Conference Malaysia.
[6] Aswathi R and Ciby Thomas (December 2013).
“Development of a Delay Analysis System for a Railway
Construction Project”, International Journal of Innovative
Research in Science, Engineering and Technology, ICEE,
Vol. 2, Special Issue 1, pp 531-541.
[7] Murali Sambasivan and Yau Wen Soon (2007). “Causes
and Effects of Delays in Malaysian construction industry”,
International Journal of Project Management, 25, pp 517-
526.
[8] Sadi A. Assaf and Sadiq Al-Hejji (2006). “Causes of
delay in large construction projects”, International Journal
of Project Management, ELSEVIER, 24, pp 349-357.
[9] Abdalla M. Odeh and Hussaien T. Battaineh (2002).
“Causes of Construction delay: traditional contracts”,
International Journal of Project Management, PERGAMON,
20, pp 67-73.

More Related Content

What's hot

Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan TemplateSimplilearn
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Project management-plan
Project management-planProject management-plan
Project management-planTran Tien
 
project plan document(ppd)
project plan document(ppd)project plan document(ppd)
project plan document(ppd)maamir farooq
 
Project management plan_template
Project management plan_templateProject management plan_template
Project management plan_templateRaquel Shirazi
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan templateMichelle Joja
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresIRJESJOURNAL
 

What's hot (17)

KAIA Project Management Plan[1]
KAIA Project Management Plan[1]KAIA Project Management Plan[1]
KAIA Project Management Plan[1]
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
 
RESUME.1
RESUME.1RESUME.1
RESUME.1
 
APM_AEB_FINAL
APM_AEB_FINALAPM_AEB_FINAL
APM_AEB_FINAL
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Project management-plan
Project management-planProject management-plan
Project management-plan
 
Swapnil Resume
Swapnil ResumeSwapnil Resume
Swapnil Resume
 
project plan document(ppd)
project plan document(ppd)project plan document(ppd)
project plan document(ppd)
 
8 Project Plan
8 Project Plan8 Project Plan
8 Project Plan
 
Project management plan_template
Project management plan_templateProject management plan_template
Project management plan_template
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Brijesh
BrijeshBrijesh
Brijesh
 
Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan template
 
Resume_VRGOLI_BTECH_CHEMICAL
Resume_VRGOLI_BTECH_CHEMICALResume_VRGOLI_BTECH_CHEMICAL
Resume_VRGOLI_BTECH_CHEMICAL
 
Henry CV
Henry CVHenry CV
Henry CV
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential Structures
 
CV ,VK JHA
CV ,VK JHACV ,VK JHA
CV ,VK JHA
 

Similar to IRJET - Delay Analysis of a Construction Project- A Case Study

IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...IRJET Journal
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...IRJET Journal
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...IRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projectsIRJET Journal
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...IRJET Journal
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPIRJET Journal
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERACOMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERAIRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”IRJET Journal
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey BuildingIRJET Journal
 

Similar to IRJET - Delay Analysis of a Construction Project- A Case Study (20)

IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERACOMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

IRJET - Delay Analysis of a Construction Project- A Case Study

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1728 DELAY ANALYSIS OF A CONSTRUCTION PROJECT- A CASE STUDY Mr. Nagarjun Gowda B.S1, Ms. Chethana K.N2 1Assistant Professor, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India 2Student, Department of CTM, Dayananda Sagar College of Engineering, Karnataka, India ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Construction technology has become an essential part of any of the project, for timely and economical completion of the project. A proper construction planning and schedule acts as a main role ford different purposes. By using the schedule, we can know the merely completion of the project, contractors can recruit the necessary manpower; can demand shifts or equipments to speed up the project. The most important function of the project management is to plan and control the project objective like time, budget and setting out of resource productivity standards to achieve the objectives of the project. Delay happens in all construction projects. Where construction project will vary in size, some will be in small. In vast projects, analysis should be done for the purpose on making right decisions on time and cost compensation claims. Many type of software’s are available to plan, execute and control the project; with the help of these software’s the project management has become easier to evolve the construction project. Large quantities of different kind of resources are required for execution and the risk is more in case of big projects. So, planning and scheduling in big projects is essential. In this study, an effort is made in planning, scheduling and delay analysis and updating of various activities which is done using MS project. Key Words: Construction Management, Planning, Delay, Labour Productivity, Scheduling, Tracking. 1. INTRODUCTION Construction industry plays an important role in the economic growth of a country. It is the process of implementing the plans, ideas, standards, specifications and assigning the resources into a physical facility to meet the specific requirements of owner. Construction management can be defined as the accomplishment of results through the combined effort of the consultant, client and designer. Construction is a very unique and creative practice which coverts four M’s of the construction-Material, Manpower, Machinery and Money into a systematic structure. Thus construction management contains Planning, Executing and monitoring the construction activities in a specific project. 1.1 Project Planning, Scheduling and Controlling The main aim of the construction management is to plan and schedule the resources within the frame work of a project. The guidelines and procedures of the construction management direct the managers how to utilize the resources during the construction process. Before execution of the work on the site all kinds of office works such as planning, designing, estimating, negotiating, purchasing, scheduling, controlling etc. should be done carefully. 1.2 Construction Delay Analysis Delay is one of the common problems in the construction project. Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often resulting of miscommunication between contractors, subcontractors, owners and suppliers. These types of unrealistic exceptions are usually avoided by clean and efficient planning mechanism, which clearly specifies the work and timetable to be used. Delays in construction project are quite expensive; sometimes they may result in severe damages to the involved parties. 1.3 Objective of the Study  Detailed literature study to define the various causes of delay in construction projects  Study on ongoing Project site to observe the activities and to identify delay factors  Determination of Critical Path using MS Projects  The analysis also involves the process of scheduling and tracking of a construction project activities in software and related catch up programs due to delays. 2. METHODOLOGY  Site Investigation.  Studying Of BOQ & Drawings.  Study On Labor Productivity.  Scheduling.  Tracking & updating of project.  Delay Analysis.  Results & conclusions. 2.1 Brief Details of Project Nature Walk is a Villa project consisting of 14 Villas of 3BHK and 4 BHK.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1729  Name of the project: Nature Walk Project.  Location: KR Puram, Bengaluru.  Contractor: Sri Laxmi Constructions.  Client: Renaissance Holdings.  Built up Area: 8400 sq-ft-9880 sq-ft.  Super Built-up Area: 9450 sq-ft – 11115 sq-ft.  Site area: 14 Acres.  Building Type: Villas.  Number of floors: G+2.  Total number of Villas: 147. 2.2 Project Specification  Structure - Villas are Reinforced Cement Concrete with G+2 Floor.  Concrete - M10 grade for PCC, M25 grade for Footing, Columns, Beams & Slabs.  Steel - High Yield Strength Deformed bars Fe-500 is used.  Masonry Work - 4” & 6” Internal and External Concrete block walls.  Plastering - External sand faced plaster. - Internal plaster with putty.  Painting - External Walls-Cement texturing with Apex/Ace emulsion.  Windows - UPVC.  Flooring - Balcony -Anti Skid Tiles, Kitchen- Vitrified Tiles, Living/Dining- Marble, Granite. 2.3 Labor Productivity and Manpower Requirement The required manpower for each activity for carrying out that particular activity efficiently without compromising on the quality is allocated and calculated based on labor productivity. Table: 2.1 Duration delay table Task Name Duration Baseline Duration Nature Walk Project B- 08 472 days 406 days VILLA 99 & 100 439 days 360 days Nature Walk Project B-08 Sub Structure 106 days 88 days Earthwork 6 days 5 days Plain cement concrete 59 days 50 days Footing 37 days 30 days Plinth Beam 48 days 40 days Ground Floor 63 days 59 days 1st floor 62 days 52 days 2nd Floor 36 days 28 days Staircase 13 days 10 days Block Work 99 days 75 days Wall Tiling 21 days 15 days Plastering 132 days 101 days Internal Plastering 53 days 37 days Ceiling Plastering 24 days 19 days Wall Plastering 40 days 28 days External Plastering 76 days 59 days Painting 50 days 46 days Internal Painting 42 days 32 days External Painting 20 days 39 days 3. CONCLUSIONS On analyzing it’s been found there is a delay of 66 days in the completion of the project. The critical activities of the project are foundation, casting the floor slab, block work, external plastering, painting and doors. Inspire of critical activities, there are some additional activities where the project experienced difficulties in execution and delay in completion. From the delay analysis an amount of Rs. 620200/- has been incurred to the project which is an additional loss to the project and simultaneously over shoots the budget allocated to the project. The main causes of the delay in the project are both excusable and non-excusable delays, which are identified by the occurrence and experience. The main delays were recorded and the loss of productivity and cost loss has been calculated. In this study, the main causes of the delay occurrence are rain, unskilled labors, shortage of skilled labor, poor workmanship, shortage of labors, inadequate of availability of materials, non-availability of materials, delay in payment to the contractor by client, partial payments to labor by contractors. These delays imply that contract related delays require adequate attention, because these delays topped with huge loss to the company and project duration overrun. Time overrun and cost overrun effects are more in this project. So, necessary action should be adopted to avoid the delays which lead to project loss. REFERENCES [1] Megha Desai and Rajiv Bhatt (April 2013). “Critical Causes of Delay in Residential Construction Projects: Case Study of Central Gujarat Region of India”, International Journal of Engineering Trends and Technology, Vol. 4, Issue 4, pp 767-768. [2] Siddesh K. Pai and J. Raj Bharath (March 2013). “Analysis of Critical Causes of Delays in Indian Infrastructure Projects”, International Journal of Innovative Research and Development, Vol. 2, Issue 3, pp 251-263.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 02 | Feb 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value (2018): 0.28 | SJIF (2018): 7.426 | Page 1730 [3] Enas Fathi Taher and R. K. Pandey (Feb 2013). “Study of Delay in Project Planning and Design Stage of Civil Engineering Projects”, International Journal of Engineering and Advanced Technology, Vol. 2, Issue 3, pp 456-461. [4] M. Haseeb, Xinhai-Lu, Aneesa Bibi, Maloof-ud-Dyian and Wahab Rabbani (Sept 2011). “Problems of Projects and Effects of Delays in the Construction Industry of Pakistan”, Australian Journal of Business and Management Research, Vol. 1, No. 5, pp 41-50. [5] Abedi M., Fathi M. S. and Mohammad M. F. (2011). “Effects of Construction Delays on Construction Project Objectives”, Scientific Conference Malaysia. [6] Aswathi R and Ciby Thomas (December 2013). “Development of a Delay Analysis System for a Railway Construction Project”, International Journal of Innovative Research in Science, Engineering and Technology, ICEE, Vol. 2, Special Issue 1, pp 531-541. [7] Murali Sambasivan and Yau Wen Soon (2007). “Causes and Effects of Delays in Malaysian construction industry”, International Journal of Project Management, 25, pp 517- 526. [8] Sadi A. Assaf and Sadiq Al-Hejji (2006). “Causes of delay in large construction projects”, International Journal of Project Management, ELSEVIER, 24, pp 349-357. [9] Abdalla M. Odeh and Hussaien T. Battaineh (2002). “Causes of Construction delay: traditional contracts”, International Journal of Project Management, PERGAMON, 20, pp 67-73.