Study on the analysis and evaluation of delays in public sector
construction projects in Kerala.
Ashiq K M1, Shrinath Rao K2, Dr. Ramakrishna Hegde3
1 M.Tech (Construction Management) Student, Dept of Civil Engineering,
Srinivas University Institute of Engineering and Technology. Mukka, Mangalore
2 Associate Professor, Dept of Civil Engineering,
Srinivas University Institute of Engineering and Technology. Mukka, Mangalore
3 Professor and HOD, Dept of Civil Engineering,
Srinivas University Institute of Engineering and Technology. Mukka, Mangalore
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - The Indian construction sector is the country’s
economic engine. Because strong infrastructure provides the
foundation for all other initiatives, the Indian construction
industry is responsible for accelerating the country’s overall
growth, and it receives top priority from the government.
However, due to the geographical, social, political and
financial situation many construction projects in the country
are prone to delays. These delays can be avoidedby identifying
factors and their sources. The main objectivesofthispaperare
to find out the main causes of delays in public construction
projects in Kerala. The research design was quantitative
where data was collected from owners, contractors, and
designers. The questionnaire is prepared using Google form,
added a list of reasons for delays factor’s, each of which
respondents were asked to rank on a 5-point scale. Acquired
data were checked using the statistical program for social
scientists, SPSS. Questionnaire survey was conducted in order
to find the delays occurred in public projects in Kerala.
Recommendations are suggested to avoid delays in public
sector construction projects.
Key Words: Construction Management, Construction,
Delays, Construction Industry, Civil Engineering.
1. INTRODUCTION
The construction industry quite often encourages a
significant part of a country’s GDP, reflecting of the impact it
has on its economy as well as working as a strong indicator
for its growth. So it is one of the most economic sectors.
However, delays frequently take place in the construction
industry. Construction delay is time exceeds eitherafterthe
contract date, that thecomponentsinvolvedandhaveagreed
upon for the delivery of the project. In both case delay is
always usually a costly situation. Construction projects are
complex activities, associated with large costs and long
period. A large number of interconnected activities are
carried out by different project participantsaretobecarried
out during execution of a construction project. Even when
the plans are prepared with due, uncertainties and
unexpected events appear on project execution. Often, such
events lead to delays that have an adverse effect upon the
execution and performance of the project, all construction
project stakeholders (final users also included) may suffer
when a delay occurs.
Delays occur due to a variety of reasons (have various
origins); con be compensated or not; and they may appear
concurrently or subsequently. The impact caused on the
project condition may be direct or else indirect. Their
appearance direct to additional cost generation, conflicts
among project peoples and in worst-case scenario, litigation
where extra costs may be generated. Often, delays may
appear already in the initial stages of the construction, such
as the stage of the preparation of the plans, or design,
obtaining the building permit etc. As a outcome, the
construction itself is often delayed already at its start,due to
this happening of delays in previous stages of the project.
Special notice should be always taken to the preparation
stage and ensure that enough detailed documentation is
available at the starting stage of the project. When dealing
with the delays, it is not only significant to identify delays
and quantify the delay impacts on project condition but also
to identify and quantify the impacts of delays already done
upon further project development. In order to determine
responsibility, enable to learning from undesirable events,
the primary causes as well as origin of delays should be
identified as well.
The responsibility for thehappeningofa particulardelaycan
be allocated to one project stakeholders. If those
responsibilities are not identified before starting of the
particular project, there can be risk of conflicts among
project stakeholders regarding the responsibility allocation
that can lead even to litigation. Responsibility allocation
matrix is defined prior to the project condition that can
therefore be an very useful in conflict management tool as it
implies the roles and responsibilities of all the stakeholders
therefore related to the construction projects. On this basis,
the financial reward for harmful events can be identified
before.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 57
1.1 TYPES OF DELAYS
Type of delays generally comes under four categories.
Delay is measured a major cause of construction claim. The
four types of delay namely:
1.11 Excusable delays
1.12 Non-excusable
1.13 Delays compensable delays
1.14 Concurrent delays
1.11 Excusable Delays
Excusable delays are those attributable to the contractor's
actions or inactions, and typically include a unforeseen
events. It allows the contractor to obtain a time extension to
complete the project without being penalized
1.12 Non-Excusable Delays
This type of delay presents no supports to a time extension
or delay damages for the contractor if the delay can be
proved to have affected the whole contract. The owner
however could be the enforcer to the damages
1.13 Compensable Delays
Compensable delay is when the contractor will get a
payment due to the additional cost of delay and as well as to
a time extension for contract performance if there is any
change in scope of work, late supply of owner materials or
information, delayed siteaccess,differingsiteconditions and
letdown to provide timely and review shop drawings
1.14 Concurrent Delay
Concurrent delays mention to delay situations when two or
more delays occur at the same time or join to some degree.
For example, if an owner denies access to a project site for
two weeks, and a severe tempest prevents the contractor
from working on the contract for one of those two weeks as
well, there will be a parallel delay of one week.
1.2 Effects of Delay
The common effects of delays in construction projects are
 Time overruns
 Cost overruns
 Dispute
 Arbitration
 Total abandonment
 Litigation
 Poor coordination (e.g. within site &
with subcontractors)
 Fatigue/morale problems
 Mistakes due to overwork
 lost opportunities for work elsewhere
 Indirect effects can cause costs, further delays.
2. OBJECTIVES
The purpose of this study is to find the various factors that
cause delays in construction projects, their impact, and
solutions to delays. This research aims to identify the main
causes of delays.
To achieve the goal, it is identified as:
1. Effect of delay
2. Determine the root cause of a project.
3. Recommendations for minimizing and controlling
construction projects.
3. LITERATURE REVIEW
[1] Aleksander Srdić et al (2015) conducted research and
results showed that delays are a part of the daily routine
during construction project execution. It can be concluded
that more attention should be paid to the processes that are
taking place prior to construction, such as producing
adequate design drawings and documents.Theresultsofthe
presented research identify the needs of the construction
industry from the viewpoint of timemanagementanddelays
that occur in projects, and could be used as the base for the
preparation strategy for time managing for all construction
stakeholders.
[2] Jesper Kranker Larsen et al (2015) concluded in their
research that project schedule, budget, quality level are
affected in considerably different ways. Therefore, a project
manager cannot switch such critical issues by focusing only
on agenda or budget complications; nor can he or she
assume that time, cost, and quality are equally affected.
[3] Sadi A. Assaf et al (2006) conducted study on delays in
construction projects in Saudi Arabia. Clients specified that
causes of delay are related to contractor and labors. Study
indicated that owners and consultants realize thatawarding
to the lowest bidder is the highest frequent factor of delay,
while, contractors considered severe causes of delay are
related to owners.
Based on literature review, it has identified that delay inany
construction project is inevitable. The contractor under the
construction project or contract is required to carry out and
complete the project within a specific time period and cost.
This requirement is often accompanied by a requirement to
produce an effective program schedule and cash flow
analysis in the entire project which have to be strictly
followed, to ensure a minimum variation connecting critical
activities unless changes are inescapable which is however
covered with proper contingencies as a normal practice of
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 58
agreeing a percentage of the project cost as contingencies
allowance. Importance is thus laid on timely delivery of
project within the budget and to the level of standard
specified by the owner is an index of successful project
delivery. Failure to accomplish the targeted cost will
however effect in various unexpected negativeeffectson the
projects. One of such effects is the cost overruns, which are
attributed to finance, and payment arrangement, materials
shortages, poor contractmanagement,inaccurate estimating
and overall price fluctuations. Bottlenecks in the execution
of the projects can also reduced by the need for a clear
intention and understanding of the technical specifications
4. METHODOLOGY
First, a literature review was conducted in order to find the
factors causing construction project delays. This helped to
conduct a survey to collect information and to find out the
causes related to the delays in public sector projects in
Kerala.
Following are the main stages of conducting this study:
1. Identifying the problems
2. Specifying research objectives
3. Specifying research scope
4. Data collection
5. Literature research
6. Questionnaire
7. Data analysis
8. Results
4.1 Designing and collecting data through a
questionnaire survey
A questionnaire survey was conducted as a source of
primary data. There are two ways to collect data from
surveys. One is called cross elevation and other one is called
longitudinal elevation. Cross-sectional studies are designed
to collect data over a short period of time, while longitudinal
studies are designed to collect data over a long period of
time. A cross-sectional survey method waschosendueto the
time limitation of this study.
4.2 Data collection
The survey was sent to 40 people, 30 peoples are responded
within three weeks of time, so the response rate is 75%,
these 30 people’s response was used for the analysis.Hence,
completed the data collection with 75% validity rate.
4.3 Rating scale
Each statement in these questions should be rated ona scale
from strongly agree to strongly disagree, starting with the
rating system was given as follow:
Strongly agree – 5 , Agree – 4 , Satisfactory – 3 , Disagree –
2 , Strongly disagree – 1
4.4 Questionnaires for causes of delay
CATEGORY FACTORS CAUSING DELAYS
OWNER
1) Delay in decision making
2) Suspension of work
3) Delay in revising and approving
documentsby owner
4) Delay in delivering construction site
tocontractor
5) Delay of financing and payments by
owner
6) Changes to the project by owner
7) Type of project bidding and award
8) Unrealistic enforced contract
duration
9) Lack of experience of owner in
construction project
10) Delay by owner in handing over
process or approval of completed work
CONTRACTOR
11) Difficulties in financing the project
by Contractor
12) Poor site management and
supervision
13) Deficiency in scheduling and
planning of project
14) Rework due to errors during
construction
15) Delays related to sub-contractors
work
16) Lack of experience of contractor
17) Inappropriate construction method
18) Poor communication and
coordination with other parties
19) Unsafe practice at site
CONSULTANTS
20) Lack of experience of consultants
22) Drawing, shopdrawingsandsample
materials etc
23) Mistakes or discrepancies in
documents or specifications issued by
consultants
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 59
24) Poor communication and
coordination with other parties
25) Delay in inspection
27) Unqualified workforce
28) Low productivity of labour
MATERIALS
29) Shortage of construction materials
30) Delays due to material delivery
31) Changes in material types and
32) Specifications during construction
33) Inflation and escalation of material
prices
EQUIPMENT
34) Shortage of equipment and or
equipment Failure
35) Unforeseen site conditions
36)Restriction at job site (poor site
access,traffic congestion)
37)Lack of site utilities or services such
as water, electricity, etc.
38) Accident during construction
39) Problem with nearby structure or
facilities
EXTERNAL
FACTORS
40) Weather effect (heat, rain, etc.)
41) Changes in government regulation
and laws
42) Delay in performing finalinspection
and certification by a third party
43)Global financial crisis
44)Force majeure (earthquake ,etc.)
45) changes in the govt regulations and
laws
46. Weather effect (heat, rain, etc.)
47. Changes in government regulation
and laws
48. Dispute between Govt agencies or
departments
49. Legal disputed of the project owner
(client) and others (relatives or
partners)
Table-1: Questionnaire Survey
5. RESULT AND ANALYSIS
5.1 Result analysis chart
Question
No.
Number of
companies
responded
4&5, Agree
Number of
companies
responded 3,
Satisfactory
Number of
companies
responded
1&2,
Disagree
1 5 10 15
2 11 7 12
3 4 14 12
4 10 8 12
5 3 12 15
6 3 12 15
7 5 12 13
8 5 7 18
9 11 7 12
10 4 14 12
11 4 13 13
12 12 6 12
13 2 11 17
14 5 5 20
15 14 5 11
16 8 9 13
17 11 3 16
18 11 8 11
19 4 6 20
20 4 6 20
21 2 16 12
22 7 13 10
23 5 8 17
24 10 13 7
25 6 15 9
26 6 4 20
27 6 12 12
28 6 12 12
29 7 14 9
30 8 16 6
31 5 4 21
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 60
32 10 6 14
33 4 5 21
34 4 6 20
35 5 6 19
36 3 8 19
37 3 7 20
38 3 7 20
39 7 7 16
40 6 7 17
41 7 14 9
42 5 16 9
43 5 14 11
44 1 7 22
45 6 9 15
46 4 11 15
47 4 11 15
48 5 11 14
49 3 10 17
Table-2: Result Analysis Chart
Graph 1 - Number of companies with positive response
Graph 2 - Number of companies responded Satisfactory
Graph 3 - Number of companies responded Disagree
Graph 4 - Overall Result Analysis
6. CONCLUSION AND RECOMMENDATION
The purpose of this study was to identify the factors
responsible for delays in public sector construction projects
in the state of Kerala and their effects and solution. The
study identified the factors causing delays in construction
projects across various skateholders and categories. These
categories are owner, contractor, designer, labor, materials,
equipment and external factors.
Based on the research in the Kerala public construction
industry, the following top 6 common causes of delays were
identified:
1) Suspension of work
2) Unrealistic enforced contract duration
3) Delay in handing over the site for mobilization
4) Difficulties in financing the project by contractor
5) Poor site management and supervision
6) Deficiency in planning and scheduling of project.
Following 6 common impacts of delays in the public sector
construction industry in Kerala were identified:
1) Time overruns
2) 2ost overruns
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 61
3) Dispute
4) Arbitration
5) Total abandonment
6) Litigation.
6.1 RECOMMENDATION
Construction delays are an unavoidable phenomenon that
occurs in almost every country due to the combination of
factors considered above. However, construction delays are
very common in most developing countries. Therefore,
considering all the above and in order to reduce or mitigate
these factors, the following measures may be implemented
in Kerala:
 Sufficient planning and the establishment of quality
control mechanisms should be put in place to avoid
design changes. appropriate time should be made to
careful production of design , complete the tender
documents, so as to get better the quality of contract
documents with minimum numbers of errors and
inconsistencies and reduce delay during several
construction stages.
 Design related problems such as changes in drawings,
incomplete and wrong specification; clients initiated
changes and general change can have very bad effect on
project delivery which always leads to delay and cost
overruns. These are reasons that should be controlled
by a good design process and excellent decisionmaking.
 The govt, in collaboration with other stake holders,
should invest in human capital development by training
construction workers in appropriate technical skills to
make them good. By this country can construct quality
infrastructure.
 Govt should also make sure that project tenders are
based on experience and expertise in a particular
construction field and not full of cronyism. If this made
sure, it means that the best company will get theproject
and complete it without delay.
 Client to reject low bids have not been taken proper
account of the risks involved and make sure suitable
provisions have been permitted for in the tender prices
for the completion of statutory and contractual
responsibilities
 Client to exercise healthy change control withparticular
importance on comprehensiveprojectplanningandrisk
assessment at project .
 Clients to make sure appropriate allocation of
responsibilities among project clients and to enforce a
clear responsibility structure within their own
organization.
 To bring in past performance as one of the main quality
criteria for prequalification and bid assessment for
public works consultancy, and expand a quantitative
means for checking the past performance ofconsultants
 To improve the "Contractor system" for public projects
and the Works Bureau to consider allowing those with
consistently good performance to take part in the pre-
qualification exercise for major public works projects.
 Client organization should provide wider use of direct
labour by contractual requirements.
 To develop an effectivedisciplinarymechanismtotackle
non-performance by sharing informationamongClients
on the performance of theirconsultantsandcontractors.
 Client and project team to safe teamwork, good practice
and good commitment from all parties at a project level
through a joint developed project pact.
 Client to ensure more developed input from different
disciplines.
 Client to avoid total sub-letting and exercise good
control over the performance and management of sub
contractors.
 To think again the recommendation of the consultancy
study on the General form of Contract for Public Works
Projects with the objective of resulting a more equitable
allocation of risks between contracting parties.
REFERENCES
[1] Sebghatullah Karimi and Poorang Piroozfar, “
Exploring Causes of Delays in National Road and
Highway Projects in Developing Construction
Economy”Journal of Engineering, Project, and
Production Management 2022, 12(2), 137-148.
[2] Shabir Hussain Khahro, Tauha Hussain Ali “
Causes leading to conflicts in construction projects:
A viewpoint of pakistani construction industry”
International Conference on challenges in IT,
Engineering and Technology (ICCIET’2018)July,17-
18.
[3] Yulia Panova, Per Hilletofth “Managingsupplychain
risks and delays in construction project” Industrial
Management & Data Systems 118(2) 2018
DOI:10.1108/IMDS-09-2017-0422.
[4] Mr. Kartik bagrecha Ms. Ayushibais“ studyondelay
construction project in india” [ijiert] issn: 2394-
3696 volume 4, issue 11, nov.-2017.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 62
[5] Raj Kapur Shah “an exploration of causes for delay
and cost overruns in construction projects: case
study of australia, malaysia & ghana” Journal of
Advanced College of Engineering and Management,
Vol. 2, 2016
[6] Aleksander Srdić , Jana Šelih“DelaysinConstruction
Projects: Causes and Mitigation” DOI
10.5592/otmcj.2015.3.5
[7] Jesper Kranker Larsen,GeoffreyQipingShen,Søren
Munch Lindhard ,Thomas Ditlev Brunoe “Factors
Affecting Schedule Delay, Cost Overrun, andQuality
Level in Public Construction Projects” DOI:
10.1061/(ASCE)ME.1943-5479.0000391.
[8] M. E. Abd El-Razek, H. A. Bassioni, and A. M.
Mobarak “Causes of Delay in Building Construction
Projects in Egypt” DOI: 10.1061/(ASCE)0733-9364
2008 (134:11)831
BIOGRAPHIES
Ashiq K. M. is pursuing M.Tech
Construction Management at
Srinivas University Institute of
Engineering & Technology, Mukka,
Mangaluru. After Bachelor Degree
in Civil Engineering, Ashiq K. M.
has worked as Manager at Century
Park, Kasaragod, Kerala for 2
years.
Shrinath Rao K is working as
Associate Professor in the Dept of
Civil Engg at Srinivas University
Institute of Engineering &
Technology,Mukka,Mangaluru.He
has 7 years of work experience at
Abroad and 14 years at India
including Teaching, Review & Re-
Design of Syllabus, Quality
Assurance in Higher Educational
Institutions and Construction
Industry.

More Related Content

Similar to Study on the analysis and evaluation of delays in public sector construction projects in Kerala

IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET Journal
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
IRJET Journal
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
IJERA Editor
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Associate Professor in VSB Coimbatore
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET Journal
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
B012140812
B012140812B012140812
B012140812
IOSR Journals
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
IRJET Journal
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET Journal
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
IRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET Journal
 

Similar to Study on the analysis and evaluation of delays in public sector construction projects in Kerala (20)

IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 

Recently uploaded (20)

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 

Study on the analysis and evaluation of delays in public sector construction projects in Kerala

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 56 Study on the analysis and evaluation of delays in public sector construction projects in Kerala. Ashiq K M1, Shrinath Rao K2, Dr. Ramakrishna Hegde3 1 M.Tech (Construction Management) Student, Dept of Civil Engineering, Srinivas University Institute of Engineering and Technology. Mukka, Mangalore 2 Associate Professor, Dept of Civil Engineering, Srinivas University Institute of Engineering and Technology. Mukka, Mangalore 3 Professor and HOD, Dept of Civil Engineering, Srinivas University Institute of Engineering and Technology. Mukka, Mangalore ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - The Indian construction sector is the country’s economic engine. Because strong infrastructure provides the foundation for all other initiatives, the Indian construction industry is responsible for accelerating the country’s overall growth, and it receives top priority from the government. However, due to the geographical, social, political and financial situation many construction projects in the country are prone to delays. These delays can be avoidedby identifying factors and their sources. The main objectivesofthispaperare to find out the main causes of delays in public construction projects in Kerala. The research design was quantitative where data was collected from owners, contractors, and designers. The questionnaire is prepared using Google form, added a list of reasons for delays factor’s, each of which respondents were asked to rank on a 5-point scale. Acquired data were checked using the statistical program for social scientists, SPSS. Questionnaire survey was conducted in order to find the delays occurred in public projects in Kerala. Recommendations are suggested to avoid delays in public sector construction projects. Key Words: Construction Management, Construction, Delays, Construction Industry, Civil Engineering. 1. INTRODUCTION The construction industry quite often encourages a significant part of a country’s GDP, reflecting of the impact it has on its economy as well as working as a strong indicator for its growth. So it is one of the most economic sectors. However, delays frequently take place in the construction industry. Construction delay is time exceeds eitherafterthe contract date, that thecomponentsinvolvedandhaveagreed upon for the delivery of the project. In both case delay is always usually a costly situation. Construction projects are complex activities, associated with large costs and long period. A large number of interconnected activities are carried out by different project participantsaretobecarried out during execution of a construction project. Even when the plans are prepared with due, uncertainties and unexpected events appear on project execution. Often, such events lead to delays that have an adverse effect upon the execution and performance of the project, all construction project stakeholders (final users also included) may suffer when a delay occurs. Delays occur due to a variety of reasons (have various origins); con be compensated or not; and they may appear concurrently or subsequently. The impact caused on the project condition may be direct or else indirect. Their appearance direct to additional cost generation, conflicts among project peoples and in worst-case scenario, litigation where extra costs may be generated. Often, delays may appear already in the initial stages of the construction, such as the stage of the preparation of the plans, or design, obtaining the building permit etc. As a outcome, the construction itself is often delayed already at its start,due to this happening of delays in previous stages of the project. Special notice should be always taken to the preparation stage and ensure that enough detailed documentation is available at the starting stage of the project. When dealing with the delays, it is not only significant to identify delays and quantify the delay impacts on project condition but also to identify and quantify the impacts of delays already done upon further project development. In order to determine responsibility, enable to learning from undesirable events, the primary causes as well as origin of delays should be identified as well. The responsibility for thehappeningofa particulardelaycan be allocated to one project stakeholders. If those responsibilities are not identified before starting of the particular project, there can be risk of conflicts among project stakeholders regarding the responsibility allocation that can lead even to litigation. Responsibility allocation matrix is defined prior to the project condition that can therefore be an very useful in conflict management tool as it implies the roles and responsibilities of all the stakeholders therefore related to the construction projects. On this basis, the financial reward for harmful events can be identified before.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 57 1.1 TYPES OF DELAYS Type of delays generally comes under four categories. Delay is measured a major cause of construction claim. The four types of delay namely: 1.11 Excusable delays 1.12 Non-excusable 1.13 Delays compensable delays 1.14 Concurrent delays 1.11 Excusable Delays Excusable delays are those attributable to the contractor's actions or inactions, and typically include a unforeseen events. It allows the contractor to obtain a time extension to complete the project without being penalized 1.12 Non-Excusable Delays This type of delay presents no supports to a time extension or delay damages for the contractor if the delay can be proved to have affected the whole contract. The owner however could be the enforcer to the damages 1.13 Compensable Delays Compensable delay is when the contractor will get a payment due to the additional cost of delay and as well as to a time extension for contract performance if there is any change in scope of work, late supply of owner materials or information, delayed siteaccess,differingsiteconditions and letdown to provide timely and review shop drawings 1.14 Concurrent Delay Concurrent delays mention to delay situations when two or more delays occur at the same time or join to some degree. For example, if an owner denies access to a project site for two weeks, and a severe tempest prevents the contractor from working on the contract for one of those two weeks as well, there will be a parallel delay of one week. 1.2 Effects of Delay The common effects of delays in construction projects are  Time overruns  Cost overruns  Dispute  Arbitration  Total abandonment  Litigation  Poor coordination (e.g. within site & with subcontractors)  Fatigue/morale problems  Mistakes due to overwork  lost opportunities for work elsewhere  Indirect effects can cause costs, further delays. 2. OBJECTIVES The purpose of this study is to find the various factors that cause delays in construction projects, their impact, and solutions to delays. This research aims to identify the main causes of delays. To achieve the goal, it is identified as: 1. Effect of delay 2. Determine the root cause of a project. 3. Recommendations for minimizing and controlling construction projects. 3. LITERATURE REVIEW [1] Aleksander Srdić et al (2015) conducted research and results showed that delays are a part of the daily routine during construction project execution. It can be concluded that more attention should be paid to the processes that are taking place prior to construction, such as producing adequate design drawings and documents.Theresultsofthe presented research identify the needs of the construction industry from the viewpoint of timemanagementanddelays that occur in projects, and could be used as the base for the preparation strategy for time managing for all construction stakeholders. [2] Jesper Kranker Larsen et al (2015) concluded in their research that project schedule, budget, quality level are affected in considerably different ways. Therefore, a project manager cannot switch such critical issues by focusing only on agenda or budget complications; nor can he or she assume that time, cost, and quality are equally affected. [3] Sadi A. Assaf et al (2006) conducted study on delays in construction projects in Saudi Arabia. Clients specified that causes of delay are related to contractor and labors. Study indicated that owners and consultants realize thatawarding to the lowest bidder is the highest frequent factor of delay, while, contractors considered severe causes of delay are related to owners. Based on literature review, it has identified that delay inany construction project is inevitable. The contractor under the construction project or contract is required to carry out and complete the project within a specific time period and cost. This requirement is often accompanied by a requirement to produce an effective program schedule and cash flow analysis in the entire project which have to be strictly followed, to ensure a minimum variation connecting critical activities unless changes are inescapable which is however covered with proper contingencies as a normal practice of
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 58 agreeing a percentage of the project cost as contingencies allowance. Importance is thus laid on timely delivery of project within the budget and to the level of standard specified by the owner is an index of successful project delivery. Failure to accomplish the targeted cost will however effect in various unexpected negativeeffectson the projects. One of such effects is the cost overruns, which are attributed to finance, and payment arrangement, materials shortages, poor contractmanagement,inaccurate estimating and overall price fluctuations. Bottlenecks in the execution of the projects can also reduced by the need for a clear intention and understanding of the technical specifications 4. METHODOLOGY First, a literature review was conducted in order to find the factors causing construction project delays. This helped to conduct a survey to collect information and to find out the causes related to the delays in public sector projects in Kerala. Following are the main stages of conducting this study: 1. Identifying the problems 2. Specifying research objectives 3. Specifying research scope 4. Data collection 5. Literature research 6. Questionnaire 7. Data analysis 8. Results 4.1 Designing and collecting data through a questionnaire survey A questionnaire survey was conducted as a source of primary data. There are two ways to collect data from surveys. One is called cross elevation and other one is called longitudinal elevation. Cross-sectional studies are designed to collect data over a short period of time, while longitudinal studies are designed to collect data over a long period of time. A cross-sectional survey method waschosendueto the time limitation of this study. 4.2 Data collection The survey was sent to 40 people, 30 peoples are responded within three weeks of time, so the response rate is 75%, these 30 people’s response was used for the analysis.Hence, completed the data collection with 75% validity rate. 4.3 Rating scale Each statement in these questions should be rated ona scale from strongly agree to strongly disagree, starting with the rating system was given as follow: Strongly agree – 5 , Agree – 4 , Satisfactory – 3 , Disagree – 2 , Strongly disagree – 1 4.4 Questionnaires for causes of delay CATEGORY FACTORS CAUSING DELAYS OWNER 1) Delay in decision making 2) Suspension of work 3) Delay in revising and approving documentsby owner 4) Delay in delivering construction site tocontractor 5) Delay of financing and payments by owner 6) Changes to the project by owner 7) Type of project bidding and award 8) Unrealistic enforced contract duration 9) Lack of experience of owner in construction project 10) Delay by owner in handing over process or approval of completed work CONTRACTOR 11) Difficulties in financing the project by Contractor 12) Poor site management and supervision 13) Deficiency in scheduling and planning of project 14) Rework due to errors during construction 15) Delays related to sub-contractors work 16) Lack of experience of contractor 17) Inappropriate construction method 18) Poor communication and coordination with other parties 19) Unsafe practice at site CONSULTANTS 20) Lack of experience of consultants 22) Drawing, shopdrawingsandsample materials etc 23) Mistakes or discrepancies in documents or specifications issued by consultants
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 59 24) Poor communication and coordination with other parties 25) Delay in inspection 27) Unqualified workforce 28) Low productivity of labour MATERIALS 29) Shortage of construction materials 30) Delays due to material delivery 31) Changes in material types and 32) Specifications during construction 33) Inflation and escalation of material prices EQUIPMENT 34) Shortage of equipment and or equipment Failure 35) Unforeseen site conditions 36)Restriction at job site (poor site access,traffic congestion) 37)Lack of site utilities or services such as water, electricity, etc. 38) Accident during construction 39) Problem with nearby structure or facilities EXTERNAL FACTORS 40) Weather effect (heat, rain, etc.) 41) Changes in government regulation and laws 42) Delay in performing finalinspection and certification by a third party 43)Global financial crisis 44)Force majeure (earthquake ,etc.) 45) changes in the govt regulations and laws 46. Weather effect (heat, rain, etc.) 47. Changes in government regulation and laws 48. Dispute between Govt agencies or departments 49. Legal disputed of the project owner (client) and others (relatives or partners) Table-1: Questionnaire Survey 5. RESULT AND ANALYSIS 5.1 Result analysis chart Question No. Number of companies responded 4&5, Agree Number of companies responded 3, Satisfactory Number of companies responded 1&2, Disagree 1 5 10 15 2 11 7 12 3 4 14 12 4 10 8 12 5 3 12 15 6 3 12 15 7 5 12 13 8 5 7 18 9 11 7 12 10 4 14 12 11 4 13 13 12 12 6 12 13 2 11 17 14 5 5 20 15 14 5 11 16 8 9 13 17 11 3 16 18 11 8 11 19 4 6 20 20 4 6 20 21 2 16 12 22 7 13 10 23 5 8 17 24 10 13 7 25 6 15 9 26 6 4 20 27 6 12 12 28 6 12 12 29 7 14 9 30 8 16 6 31 5 4 21
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 60 32 10 6 14 33 4 5 21 34 4 6 20 35 5 6 19 36 3 8 19 37 3 7 20 38 3 7 20 39 7 7 16 40 6 7 17 41 7 14 9 42 5 16 9 43 5 14 11 44 1 7 22 45 6 9 15 46 4 11 15 47 4 11 15 48 5 11 14 49 3 10 17 Table-2: Result Analysis Chart Graph 1 - Number of companies with positive response Graph 2 - Number of companies responded Satisfactory Graph 3 - Number of companies responded Disagree Graph 4 - Overall Result Analysis 6. CONCLUSION AND RECOMMENDATION The purpose of this study was to identify the factors responsible for delays in public sector construction projects in the state of Kerala and their effects and solution. The study identified the factors causing delays in construction projects across various skateholders and categories. These categories are owner, contractor, designer, labor, materials, equipment and external factors. Based on the research in the Kerala public construction industry, the following top 6 common causes of delays were identified: 1) Suspension of work 2) Unrealistic enforced contract duration 3) Delay in handing over the site for mobilization 4) Difficulties in financing the project by contractor 5) Poor site management and supervision 6) Deficiency in planning and scheduling of project. Following 6 common impacts of delays in the public sector construction industry in Kerala were identified: 1) Time overruns 2) 2ost overruns
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 61 3) Dispute 4) Arbitration 5) Total abandonment 6) Litigation. 6.1 RECOMMENDATION Construction delays are an unavoidable phenomenon that occurs in almost every country due to the combination of factors considered above. However, construction delays are very common in most developing countries. Therefore, considering all the above and in order to reduce or mitigate these factors, the following measures may be implemented in Kerala:  Sufficient planning and the establishment of quality control mechanisms should be put in place to avoid design changes. appropriate time should be made to careful production of design , complete the tender documents, so as to get better the quality of contract documents with minimum numbers of errors and inconsistencies and reduce delay during several construction stages.  Design related problems such as changes in drawings, incomplete and wrong specification; clients initiated changes and general change can have very bad effect on project delivery which always leads to delay and cost overruns. These are reasons that should be controlled by a good design process and excellent decisionmaking.  The govt, in collaboration with other stake holders, should invest in human capital development by training construction workers in appropriate technical skills to make them good. By this country can construct quality infrastructure.  Govt should also make sure that project tenders are based on experience and expertise in a particular construction field and not full of cronyism. If this made sure, it means that the best company will get theproject and complete it without delay.  Client to reject low bids have not been taken proper account of the risks involved and make sure suitable provisions have been permitted for in the tender prices for the completion of statutory and contractual responsibilities  Client to exercise healthy change control withparticular importance on comprehensiveprojectplanningandrisk assessment at project .  Clients to make sure appropriate allocation of responsibilities among project clients and to enforce a clear responsibility structure within their own organization.  To bring in past performance as one of the main quality criteria for prequalification and bid assessment for public works consultancy, and expand a quantitative means for checking the past performance ofconsultants  To improve the "Contractor system" for public projects and the Works Bureau to consider allowing those with consistently good performance to take part in the pre- qualification exercise for major public works projects.  Client organization should provide wider use of direct labour by contractual requirements.  To develop an effectivedisciplinarymechanismtotackle non-performance by sharing informationamongClients on the performance of theirconsultantsandcontractors.  Client and project team to safe teamwork, good practice and good commitment from all parties at a project level through a joint developed project pact.  Client to ensure more developed input from different disciplines.  Client to avoid total sub-letting and exercise good control over the performance and management of sub contractors.  To think again the recommendation of the consultancy study on the General form of Contract for Public Works Projects with the objective of resulting a more equitable allocation of risks between contracting parties. REFERENCES [1] Sebghatullah Karimi and Poorang Piroozfar, “ Exploring Causes of Delays in National Road and Highway Projects in Developing Construction Economy”Journal of Engineering, Project, and Production Management 2022, 12(2), 137-148. [2] Shabir Hussain Khahro, Tauha Hussain Ali “ Causes leading to conflicts in construction projects: A viewpoint of pakistani construction industry” International Conference on challenges in IT, Engineering and Technology (ICCIET’2018)July,17- 18. [3] Yulia Panova, Per Hilletofth “Managingsupplychain risks and delays in construction project” Industrial Management & Data Systems 118(2) 2018 DOI:10.1108/IMDS-09-2017-0422. [4] Mr. Kartik bagrecha Ms. Ayushibais“ studyondelay construction project in india” [ijiert] issn: 2394- 3696 volume 4, issue 11, nov.-2017.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 62 [5] Raj Kapur Shah “an exploration of causes for delay and cost overruns in construction projects: case study of australia, malaysia & ghana” Journal of Advanced College of Engineering and Management, Vol. 2, 2016 [6] Aleksander Srdić , Jana Šelih“DelaysinConstruction Projects: Causes and Mitigation” DOI 10.5592/otmcj.2015.3.5 [7] Jesper Kranker Larsen,GeoffreyQipingShen,Søren Munch Lindhard ,Thomas Ditlev Brunoe “Factors Affecting Schedule Delay, Cost Overrun, andQuality Level in Public Construction Projects” DOI: 10.1061/(ASCE)ME.1943-5479.0000391. [8] M. E. Abd El-Razek, H. A. Bassioni, and A. M. Mobarak “Causes of Delay in Building Construction Projects in Egypt” DOI: 10.1061/(ASCE)0733-9364 2008 (134:11)831 BIOGRAPHIES Ashiq K. M. is pursuing M.Tech Construction Management at Srinivas University Institute of Engineering & Technology, Mukka, Mangaluru. After Bachelor Degree in Civil Engineering, Ashiq K. M. has worked as Manager at Century Park, Kasaragod, Kerala for 2 years. Shrinath Rao K is working as Associate Professor in the Dept of Civil Engg at Srinivas University Institute of Engineering & Technology,Mukka,Mangaluru.He has 7 years of work experience at Abroad and 14 years at India including Teaching, Review & Re- Design of Syllabus, Quality Assurance in Higher Educational Institutions and Construction Industry.