SlideShare a Scribd company logo
2011 
An article presented to The Robert Gordon University in Partial 
Fulfillment of the Award of MSc Project Management 
By Ambsisi Ambituuni 
[ Five Causes of Project Delay and Cost Overrun, and Their Mitigation 
Measures] 
Abstract: Delay and cost overrun are inherent part of most projects despite the 
much acquired knowledge in project management. Although some authors may 
argue that this is negligible (Flyvbjerg 2009), It is important to note that the 
physical and economic scale of most projects is such that it is driven under the 
platform of profit to the parent organization, and of national interest (for 
government projects), by the degree of success defined within the Iron triangle of 
cost, time, and scope. This article looks at five possible causes of project delay and 
cost overrun, and their mitigation measures for the development and advancement 
of the knowledge of project management
Five causes of project delay and cost overrun, and their mitigation 
2 
measures 
Delay and cost overrun are inherent part of most projects despite the much 
acquired knowledge in project management. Although some may argue that this is 
negligible (Flyvbjerg 2009), It is important to note that physical and economic scale 
of projects today is such that it is driven under the platform of profit to the parent 
organization, and of national interest (for government projects) by the degree of 
success defined within the Iron triangle of cost, time, and scope. It is therefore 
much appreciated to look at some reasons of delays and cost overrun in project and 
their mitigation process, so as to increase the perception of project success. 
One major factor that has been identified as reasons for cost overrun in most 
projects is design errors. It is important to note that proper representation of 
client’s requirement and the blue print to achieving good technical input to project 
execution are usually mapped out base on project designs. Thus a design with 
errors practically means wrong or insufficient representation of project deliverables. 
This will lead to wrong application of techniques in achieving result, such that as 
the actual execution phase of the project unfolds these design errors, attempt to 
correct it will lead to delay and cost overrun. Another way design errors could lead 
to cost overrun and delay could be seen in the fact that project estimations are 
done base on the produced designs, as such, having errors in design in a form of 
omission or misrepresentation will mean that the estimation for the project cost will 
also include these omissions, thereby leading to extra works, change order etc, 
thus resulting in delay and cost overrun. Similarly, designs that are done without
extensive investigation of site could contain potential errors. this is because such 
designs could lead to additional work, revision of scope of work, and contract 
revision as the actual site conditions begins to float up at the construction phase of 
the project. These will no doubt affect the overall project delivery time and cost. 
Bordat et al (2004) cited causes of design errors in most projects as inadequate 
field investigation, error in design and specifications, plan errors, design changes 
etc. In controlling project delay and cost overrun due to design errors, the basic 
thing to be considered is the involvement of professional skills and application of 
competent tools throughout the project. Achieving error free design entails good 
communication with the entire design team and integrating a design process that is 
properly planned, giving enough time for corrections, extensive investigation and 
reviews. Similarly, an effective project planning, controlling and monitoring should 
be established to enhance project performance throughout the project life cycle. 
Proper site investigation should be done to ensure that all site conditions are noted 
in the design, and application of value management could be use to obtain the best 
3 
cost effective design options. 
Delay and cost overrun in project could be as a result of scope change. Scope is the 
term that defines the entire deliverables that is expected at the end of a project. 
Therefore, logically, it can be said that all project plans, estimation, schedule, 
quality and base lines are usually designed base in the initial project scope. Thus, 
any change in the project scope during execution will mean that the entire initial 
project plan will have to be reviewed such that a reviewed budget, schedule and 
quality will have to be developed. This means more time and resources will be 
needed as against the initial baseline. “With each scope change, precious project
resources are diverted to activities that were not identified in the original project 
scope, leading to pressure on the project schedule and budget” (Narayan 2010). 
Project scope change could be as a result of wrong initial scope definition, inherent 
risk and uncertainties, sudden change of interest, project funding change, etc. this 
could lead to change request which in turn could lead to change in project 
deliverables, budget and/or even the entire project team. Poor scope change 
management could lead to dispute that may require spending time and money on 
arbitration and litigation for what the contractor or the client believes he is entitle 
to. This will no doubt lead to delay and cost overrun of the project. To achieve a 
proper control for scope change, it is important to first identify the fact that change 
is inevitable in project and could equally be beneficial to the entire project success. 
Thus the most important thing to do is to integrate a proper change management 
plan such that a proactive approach could be adopted involving the project 
stakeholders and incorporating their needs throughout the project lifecycle. During 
the planning phase of the project, it is important to identify the key success factor 
in conjunction with the client and establish KPI in the form of milestone that will 
measure the success for of attaining the project scope. Similarly, to avoid disputes, 
it is important to always seek approval for changes from sponsor and communicate 
changes in a timely way. For highly evolving change in project, the scope could be 
frozen so as to concentrate on the expected deliverable. 
Another major reason for cost overrun and delay in project is inappropriate and 
inadequate procurement and faulty contractual management system (Singh 2009). 
Contracts read out virtually every aspect of a business correlation, including 
payment terms, pricing, and service levels. Therefore a contract that has not 
4
highlighted the entire project scenario may lead to dispute in the contract system. 
For instance, if the initial contract does not completely specify every relevant aspect 
of the project work, this may lead to long chains of negotiations, arbitration and/or 
mitigation due work change orders and the quest for reviewed contractual 
agreement with new budgets and schedule. The result will no doubt be a project 
delay and cost overrun. Similarly, ambiguous contractual agreement with unclear 
clauses can be of potential dispute thus generating delay and cost overrun in 
project. In the same vein, delay and cost overrun could be inherent in terms of 
poor contractor selection and unethical behavior, contract bid amount, difference 
between the winning bid and second bid, difference between the winning bid and 
the engineer’s estimate, etc (Singh 2009), and since majority of projects are 
executed by contractors, it is important to note that procurement process and 
contract management is critical to the successful completion of projects. Thus poor 
selection of contractors due to low bids, with no technical capability to handle the 
project will lead to cost overruns, schedule delays, poor quality, and a final result 
that is not acceptable (PMI 2010). Also, a contract management system with clients 
that have a slow payment schedule could lead to delay and cost overrun. 
To solve these problems, the needful and ethical thing to do is to firstly identify the 
most qualified contractor via an ethical tender system and draft out the most 
suitable contract type as applicable to the conditions of the project and also 
explicitly define the terms and conditions that govern the contract in clear clauses. 
These clauses should spell out the penalties associated to delays and cost overruns 
and the party to bear risk associated to these events. Similarly all important 
potential dispute contract clauses should stated in clear unambiguous terms. The 
5
use of generic contract templates should be avoided and “careful consideration 
should be done when forming the contract, about what might happen during its 
operation, this will ensure that things are included in the contract documents that 
enable effective contract management”(OGC 2010). 
The complexity of project could also be a contributing factor to delay and cost 
overrun. Complexity could be define in terms of the size of the project, most mega 
projects tend to have relatively long implementation period when compared to 
small project. This could be affected by inflation, change in material price and 
changes in exchange rates such that the initial budget may need to be 
supplemented for the project to be completed. The result could be cost overrun and 
long chains of negotiation which will lead to delay. Similarly, projects with high 
degree of complexity usually result in complex plans, schedules and estimations. 
Such that if care is not taken the tendency of omitting certain aspect of the project 
plans and/or estimation could be prominent, thereby leading to change orders. This 
could lead to delay and cost. Also, project complexity could also be defined in term 
of the diversity of stakeholders with different interest and long chain of 
communication channel with slow feedbacks (Cerpa and Verner 2009). Therefore 
integrating their interest could take a lot of time and resources which when 
overlooked could result in conflicts and dispute, thus affecting the project in the 
context of delay and cost overrun. To eliminate or reduce the effect of delay and 
cost overrun due to project complexity, vigorous planning should be done, 
incorporating every important aspect of the project scope, milestones, detailed 
WBS, delivery time, stakeholders, and methodology to be used. According Johnsinit 
(2010), “Managing complex projects needs experience, expertise and exposure”. 
6
Thus Project needs its goals and scope to be defined, based on the client 
requirements. This helps the project to be kept on track and ensures doing only the 
job that is intended. It is therefore important to build a good team with project 
7 
success interest at heart to achieve this. 
Finally, the post execution phase (closure) of a project contains potential factors 
that can lead to delays and cost overrun. Being the very last part of the project 
life-cycle it is often been ignored even by organizations, especially in multi-project 
environments (Athans 2009). Slow closeout could be seen as dragging the various 
handover activities course by unresolved disputes linked with client acceptance, 
contracts and procurement, change order issues not resolved, final change orders 
not issued, poor close out of final account, poor documentation of project success 
and lessons learnt, slow client acceptance and failing to close the work order can 
allow unexpected delay and stray charges to be made to the project. For instance if 
project team is not decommissioned on time after the project work has been 
completed, their exist a tendency of running an idle team that may incur extra 
project expenses due to overhead and this may overrun the project cost. Similarly, 
delay in payment of contractors and suppliers after project completion could lead to 
dispute and delay in signing the certificate of final completion of the project. 
Delay and cost overrun of slow closeout can be avoided when the project closure 
phase is implemented as planned. Anthen (2009) suggested that the following 
steps be adopted. 
 Completion: Ensure that the project is 100% completed to avoid disputes 
and delay in payments.
 Documentation: Detail documentation will ensure that future changes are 
made with little extraordinary effort. 
 Project system closure: this includes closing the financial system ie all 
8 
payments, work termination, etc. 
 Project review: this can help in transfer of tangible knowledge of time and 
cost, know-how and know-why. 
 Disband project team members and complement achievement as soon as 
possible to avoid cost overrun due to extra overhead. 
 Stakeholder satisfaction: provide all the necessary information required by 
stakeholders to avoid conflicts and doubt. “This information can include a 
timeline showing the progress of the project from the beginning until the 
end, the milestones that were met or missed, the problems encountered and 
a brief financial presentation” (Athens 2009) 
In conclusion, although delay and cost overrun may seem very inherent in most 
projects, the good news is that it can be reduce or totally eliminated using a proper 
project performance monitoring and control system that will integrate all the key 
activities of each phase of the project. This system could be designed such that a 
close loop information feedback and feed forward package is obtained from 
definition to close out of the project. The cycle is usually advantageous because 
planning, measuring, monitoring, and taking corrective action are all usually 
included in the control cycle. 
Another additional tactics used to achieving a project with little or no delay and cost 
overrun is in the definition of project success factors and criteria. The integration of
these factors will lead to a better understanding of the issues in which the project 
manager needs to address and design a control system that will monitor these 
issues. The project owner and the project manager should be able to clear define 
the management success and product success so that the project team has clear 
knowledge of its objectives. It is important to note that even dough delay and cost 
overrun course due to “act of God” cannot be prevented; a good monitoring and 
control system can however reduce the effect of such occurrences on project 
9 
performance.
10 
References and Bibliography: 
BORDAT, C et al., 2004. An analysis of cost overrun and time delay of INDOT 
projects. Joint Transport Research Program. Purdue e-pubs. 
CERPA, N. and VERNER, J M., 2009. Why did your project fail. Contributing Article, 
52(12), pp. 131 
FIMPONG, Y JACOB, O and LYNN, C., 2003. Causes of delay and cost overrun in 
construction of ground water project in developing countries: Ghana as a case 
study. Internal Journal of Project Management, 21(2003), pp. 34-326. 
FLYVBJERG, B et al., 2004. What causes cost overrun in transport infrastructure 
project. Transport Review Article, 24(1), pp.3-18. 
FLYVBJERG, B., 2009. Excerpt from the book: mega projects and risk. Available 
from:www.flyubjerg.plan.aau.dk. visited on 12/11/2010. 
ITRM GUIDLINE CPM., 2006. Project management guideline: section 5-project 
closeout phase. ITRM 
JONHSINIT., 2010. Top tips for managing complex projects. Ginny Edwards 
(online). Available from: www.brighthub.com. (Accessed on 6/12/2010). 
KIMBERLY, R. and JAMES, LYNEIS., 1999. Management focus: the dynamics of 
project management: benchmarking the derive of cost and schedule overrun. 
European Management Journal, 17(2), pp. 135-150.
KOUSHKI, P A. AL-RASHID, K. and KARTAM, N., 2005. Construction management 
and economic: Delay and cost increase in the construction of private residential 
11 
projects. Taylor and Francis. 
LARSON, E.W and GRAY, C.F. 2011, Project Management: The Managerial Process, 
5th Edition, McGraw Hill. 
PINTO, J., 2007. Project management: achieving competitive advantages. Pearson. 
SINGH, R., 2009. Delay and cost overrun in infrastructure projects: an enquiry into 
extent causes and remedies. Delhi.

More Related Content

What's hot

Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Construction delays
Construction delaysConstruction delays
Construction delays
Saida Njim
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
Essam Lotffy, PMP®, CCP®
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
Project Management Solutions
 
Time overruns
Time overrunsTime overruns
Time overruns
Bhalchandra Tankkar
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
M Maged Hegazy, LLM, MBA, CCP, P3O
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
Chetan Khanzode
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Project Quality Management | Project Quality Control | Edureka
Project Quality Management | Project Quality Control | EdurekaProject Quality Management | Project Quality Control | Edureka
Project Quality Management | Project Quality Control | Edureka
Edureka!
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
Mohamed Salah Eldien Mohamed Ali
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
TecnicoItca
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
IQPC
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
M Maged Hegazy, LLM, MBA, CCP, P3O
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
tltiede
 
Construction project management
Construction project managementConstruction project management
Construction project management
Senthil Kannan
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims

What's hot (20)

Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
Time overruns
Time overrunsTime overruns
Time overruns
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Project Quality Management | Project Quality Control | Edureka
Project Quality Management | Project Quality Control | EdurekaProject Quality Management | Project Quality Control | Edureka
Project Quality Management | Project Quality Control | Edureka
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 

Similar to Project delay and_cost_overrun-libre

Pp1 final
Pp1 finalPp1 final
Pp1 final
Timun Loh
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultants
bfitzsimons1974
 
D012522433
D012522433D012522433
D012522433
IOSR Journals
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
IRJET Journal
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
Newman Jonathan
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET Journal
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
GhulamQadirWaqar1
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
Y4408131137
Y4408131137Y4408131137
Y4408131137
IJERA Editor
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
IRJET Journal
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract management
Catherine Bendell
 
Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17 Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17
Association for Project Management
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Associate Professor in VSB Coimbatore
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
 
PP1 report
PP1 reportPP1 report
PP1 report
Doreen Yeo
 

Similar to Project delay and_cost_overrun-libre (20)

Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Pp report
Pp reportPp report
Pp report
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultants
 
D012522433
D012522433D012522433
D012522433
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Y4408131137
Y4408131137Y4408131137
Y4408131137
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract management
 
Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17 Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
PP1 report
PP1 reportPP1 report
PP1 report
 

More from UTHM

2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunan2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunan
UTHM
 
Ukur aras-levelling
Ukur aras-levellingUkur aras-levelling
Ukur aras-levelling
UTHM
 
Sistem pencegah kebakaran
Sistem pencegah kebakaranSistem pencegah kebakaran
Sistem pencegah kebakaran
UTHM
 
Bab 11 (b) meminimakan sampah
Bab 11 (b)   meminimakan sampahBab 11 (b)   meminimakan sampah
Bab 11 (b) meminimakan sampah
UTHM
 
K4 banjir
K4 banjirK4 banjir
K4 banjir
UTHM
 
The strategy formulation_framework_10
The strategy formulation_framework_10The strategy formulation_framework_10
The strategy formulation_framework_10
UTHM
 
Sistem bekalan air
Sistem bekalan air Sistem bekalan air
Sistem bekalan air
UTHM
 
Teknologi alam sekitar
Teknologi alam sekitar Teknologi alam sekitar
Teknologi alam sekitar
UTHM
 
Meminimumkan sisa bahan
Meminimumkan sisa bahanMeminimumkan sisa bahan
Meminimumkan sisa bahan
UTHM
 
Kod Etika Kontraktor
Kod Etika Kontraktor Kod Etika Kontraktor
Kod Etika Kontraktor
UTHM
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM
UTHM
 
Drn bm
Drn bmDrn bm
Drn bm
UTHM
 
Planning standard
Planning standardPlanning standard
Planning standard
UTHM
 
Construction materialsconcrete
Construction materialsconcreteConstruction materialsconcrete
Construction materialsconcreteUTHM
 
Applications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gateApplications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gateUTHM
 
Pembinaanjalan w12
Pembinaanjalan w12Pembinaanjalan w12
Pembinaanjalan w12UTHM
 
Lesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin ClassLesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin ClassUTHM
 
Topik 7 kaedah penilaian projek
Topik 7      kaedah penilaian projekTopik 7      kaedah penilaian projek
Topik 7 kaedah penilaian projekUTHM
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibsUTHM
 
Tembok penahan
Tembok penahanTembok penahan
Tembok penahanUTHM
 

More from UTHM (20)

2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunan2014 sistem pengangkutan_dalam_bangunan
2014 sistem pengangkutan_dalam_bangunan
 
Ukur aras-levelling
Ukur aras-levellingUkur aras-levelling
Ukur aras-levelling
 
Sistem pencegah kebakaran
Sistem pencegah kebakaranSistem pencegah kebakaran
Sistem pencegah kebakaran
 
Bab 11 (b) meminimakan sampah
Bab 11 (b)   meminimakan sampahBab 11 (b)   meminimakan sampah
Bab 11 (b) meminimakan sampah
 
K4 banjir
K4 banjirK4 banjir
K4 banjir
 
The strategy formulation_framework_10
The strategy formulation_framework_10The strategy formulation_framework_10
The strategy formulation_framework_10
 
Sistem bekalan air
Sistem bekalan air Sistem bekalan air
Sistem bekalan air
 
Teknologi alam sekitar
Teknologi alam sekitar Teknologi alam sekitar
Teknologi alam sekitar
 
Meminimumkan sisa bahan
Meminimumkan sisa bahanMeminimumkan sisa bahan
Meminimumkan sisa bahan
 
Kod Etika Kontraktor
Kod Etika Kontraktor Kod Etika Kontraktor
Kod Etika Kontraktor
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM
 
Drn bm
Drn bmDrn bm
Drn bm
 
Planning standard
Planning standardPlanning standard
Planning standard
 
Construction materialsconcrete
Construction materialsconcreteConstruction materialsconcrete
Construction materialsconcrete
 
Applications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gateApplications of high performance lightweight concrete in a floating barge gate
Applications of high performance lightweight concrete in a floating barge gate
 
Pembinaanjalan w12
Pembinaanjalan w12Pembinaanjalan w12
Pembinaanjalan w12
 
Lesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin ClassLesson 1-Learning Mandarin Class
Lesson 1-Learning Mandarin Class
 
Topik 7 kaedah penilaian projek
Topik 7      kaedah penilaian projekTopik 7      kaedah penilaian projek
Topik 7 kaedah penilaian projek
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibs
 
Tembok penahan
Tembok penahanTembok penahan
Tembok penahan
 

Project delay and_cost_overrun-libre

  • 1. 2011 An article presented to The Robert Gordon University in Partial Fulfillment of the Award of MSc Project Management By Ambsisi Ambituuni [ Five Causes of Project Delay and Cost Overrun, and Their Mitigation Measures] Abstract: Delay and cost overrun are inherent part of most projects despite the much acquired knowledge in project management. Although some authors may argue that this is negligible (Flyvbjerg 2009), It is important to note that the physical and economic scale of most projects is such that it is driven under the platform of profit to the parent organization, and of national interest (for government projects), by the degree of success defined within the Iron triangle of cost, time, and scope. This article looks at five possible causes of project delay and cost overrun, and their mitigation measures for the development and advancement of the knowledge of project management
  • 2. Five causes of project delay and cost overrun, and their mitigation 2 measures Delay and cost overrun are inherent part of most projects despite the much acquired knowledge in project management. Although some may argue that this is negligible (Flyvbjerg 2009), It is important to note that physical and economic scale of projects today is such that it is driven under the platform of profit to the parent organization, and of national interest (for government projects) by the degree of success defined within the Iron triangle of cost, time, and scope. It is therefore much appreciated to look at some reasons of delays and cost overrun in project and their mitigation process, so as to increase the perception of project success. One major factor that has been identified as reasons for cost overrun in most projects is design errors. It is important to note that proper representation of client’s requirement and the blue print to achieving good technical input to project execution are usually mapped out base on project designs. Thus a design with errors practically means wrong or insufficient representation of project deliverables. This will lead to wrong application of techniques in achieving result, such that as the actual execution phase of the project unfolds these design errors, attempt to correct it will lead to delay and cost overrun. Another way design errors could lead to cost overrun and delay could be seen in the fact that project estimations are done base on the produced designs, as such, having errors in design in a form of omission or misrepresentation will mean that the estimation for the project cost will also include these omissions, thereby leading to extra works, change order etc, thus resulting in delay and cost overrun. Similarly, designs that are done without
  • 3. extensive investigation of site could contain potential errors. this is because such designs could lead to additional work, revision of scope of work, and contract revision as the actual site conditions begins to float up at the construction phase of the project. These will no doubt affect the overall project delivery time and cost. Bordat et al (2004) cited causes of design errors in most projects as inadequate field investigation, error in design and specifications, plan errors, design changes etc. In controlling project delay and cost overrun due to design errors, the basic thing to be considered is the involvement of professional skills and application of competent tools throughout the project. Achieving error free design entails good communication with the entire design team and integrating a design process that is properly planned, giving enough time for corrections, extensive investigation and reviews. Similarly, an effective project planning, controlling and monitoring should be established to enhance project performance throughout the project life cycle. Proper site investigation should be done to ensure that all site conditions are noted in the design, and application of value management could be use to obtain the best 3 cost effective design options. Delay and cost overrun in project could be as a result of scope change. Scope is the term that defines the entire deliverables that is expected at the end of a project. Therefore, logically, it can be said that all project plans, estimation, schedule, quality and base lines are usually designed base in the initial project scope. Thus, any change in the project scope during execution will mean that the entire initial project plan will have to be reviewed such that a reviewed budget, schedule and quality will have to be developed. This means more time and resources will be needed as against the initial baseline. “With each scope change, precious project
  • 4. resources are diverted to activities that were not identified in the original project scope, leading to pressure on the project schedule and budget” (Narayan 2010). Project scope change could be as a result of wrong initial scope definition, inherent risk and uncertainties, sudden change of interest, project funding change, etc. this could lead to change request which in turn could lead to change in project deliverables, budget and/or even the entire project team. Poor scope change management could lead to dispute that may require spending time and money on arbitration and litigation for what the contractor or the client believes he is entitle to. This will no doubt lead to delay and cost overrun of the project. To achieve a proper control for scope change, it is important to first identify the fact that change is inevitable in project and could equally be beneficial to the entire project success. Thus the most important thing to do is to integrate a proper change management plan such that a proactive approach could be adopted involving the project stakeholders and incorporating their needs throughout the project lifecycle. During the planning phase of the project, it is important to identify the key success factor in conjunction with the client and establish KPI in the form of milestone that will measure the success for of attaining the project scope. Similarly, to avoid disputes, it is important to always seek approval for changes from sponsor and communicate changes in a timely way. For highly evolving change in project, the scope could be frozen so as to concentrate on the expected deliverable. Another major reason for cost overrun and delay in project is inappropriate and inadequate procurement and faulty contractual management system (Singh 2009). Contracts read out virtually every aspect of a business correlation, including payment terms, pricing, and service levels. Therefore a contract that has not 4
  • 5. highlighted the entire project scenario may lead to dispute in the contract system. For instance, if the initial contract does not completely specify every relevant aspect of the project work, this may lead to long chains of negotiations, arbitration and/or mitigation due work change orders and the quest for reviewed contractual agreement with new budgets and schedule. The result will no doubt be a project delay and cost overrun. Similarly, ambiguous contractual agreement with unclear clauses can be of potential dispute thus generating delay and cost overrun in project. In the same vein, delay and cost overrun could be inherent in terms of poor contractor selection and unethical behavior, contract bid amount, difference between the winning bid and second bid, difference between the winning bid and the engineer’s estimate, etc (Singh 2009), and since majority of projects are executed by contractors, it is important to note that procurement process and contract management is critical to the successful completion of projects. Thus poor selection of contractors due to low bids, with no technical capability to handle the project will lead to cost overruns, schedule delays, poor quality, and a final result that is not acceptable (PMI 2010). Also, a contract management system with clients that have a slow payment schedule could lead to delay and cost overrun. To solve these problems, the needful and ethical thing to do is to firstly identify the most qualified contractor via an ethical tender system and draft out the most suitable contract type as applicable to the conditions of the project and also explicitly define the terms and conditions that govern the contract in clear clauses. These clauses should spell out the penalties associated to delays and cost overruns and the party to bear risk associated to these events. Similarly all important potential dispute contract clauses should stated in clear unambiguous terms. The 5
  • 6. use of generic contract templates should be avoided and “careful consideration should be done when forming the contract, about what might happen during its operation, this will ensure that things are included in the contract documents that enable effective contract management”(OGC 2010). The complexity of project could also be a contributing factor to delay and cost overrun. Complexity could be define in terms of the size of the project, most mega projects tend to have relatively long implementation period when compared to small project. This could be affected by inflation, change in material price and changes in exchange rates such that the initial budget may need to be supplemented for the project to be completed. The result could be cost overrun and long chains of negotiation which will lead to delay. Similarly, projects with high degree of complexity usually result in complex plans, schedules and estimations. Such that if care is not taken the tendency of omitting certain aspect of the project plans and/or estimation could be prominent, thereby leading to change orders. This could lead to delay and cost. Also, project complexity could also be defined in term of the diversity of stakeholders with different interest and long chain of communication channel with slow feedbacks (Cerpa and Verner 2009). Therefore integrating their interest could take a lot of time and resources which when overlooked could result in conflicts and dispute, thus affecting the project in the context of delay and cost overrun. To eliminate or reduce the effect of delay and cost overrun due to project complexity, vigorous planning should be done, incorporating every important aspect of the project scope, milestones, detailed WBS, delivery time, stakeholders, and methodology to be used. According Johnsinit (2010), “Managing complex projects needs experience, expertise and exposure”. 6
  • 7. Thus Project needs its goals and scope to be defined, based on the client requirements. This helps the project to be kept on track and ensures doing only the job that is intended. It is therefore important to build a good team with project 7 success interest at heart to achieve this. Finally, the post execution phase (closure) of a project contains potential factors that can lead to delays and cost overrun. Being the very last part of the project life-cycle it is often been ignored even by organizations, especially in multi-project environments (Athans 2009). Slow closeout could be seen as dragging the various handover activities course by unresolved disputes linked with client acceptance, contracts and procurement, change order issues not resolved, final change orders not issued, poor close out of final account, poor documentation of project success and lessons learnt, slow client acceptance and failing to close the work order can allow unexpected delay and stray charges to be made to the project. For instance if project team is not decommissioned on time after the project work has been completed, their exist a tendency of running an idle team that may incur extra project expenses due to overhead and this may overrun the project cost. Similarly, delay in payment of contractors and suppliers after project completion could lead to dispute and delay in signing the certificate of final completion of the project. Delay and cost overrun of slow closeout can be avoided when the project closure phase is implemented as planned. Anthen (2009) suggested that the following steps be adopted.  Completion: Ensure that the project is 100% completed to avoid disputes and delay in payments.
  • 8.  Documentation: Detail documentation will ensure that future changes are made with little extraordinary effort.  Project system closure: this includes closing the financial system ie all 8 payments, work termination, etc.  Project review: this can help in transfer of tangible knowledge of time and cost, know-how and know-why.  Disband project team members and complement achievement as soon as possible to avoid cost overrun due to extra overhead.  Stakeholder satisfaction: provide all the necessary information required by stakeholders to avoid conflicts and doubt. “This information can include a timeline showing the progress of the project from the beginning until the end, the milestones that were met or missed, the problems encountered and a brief financial presentation” (Athens 2009) In conclusion, although delay and cost overrun may seem very inherent in most projects, the good news is that it can be reduce or totally eliminated using a proper project performance monitoring and control system that will integrate all the key activities of each phase of the project. This system could be designed such that a close loop information feedback and feed forward package is obtained from definition to close out of the project. The cycle is usually advantageous because planning, measuring, monitoring, and taking corrective action are all usually included in the control cycle. Another additional tactics used to achieving a project with little or no delay and cost overrun is in the definition of project success factors and criteria. The integration of
  • 9. these factors will lead to a better understanding of the issues in which the project manager needs to address and design a control system that will monitor these issues. The project owner and the project manager should be able to clear define the management success and product success so that the project team has clear knowledge of its objectives. It is important to note that even dough delay and cost overrun course due to “act of God” cannot be prevented; a good monitoring and control system can however reduce the effect of such occurrences on project 9 performance.
  • 10. 10 References and Bibliography: BORDAT, C et al., 2004. An analysis of cost overrun and time delay of INDOT projects. Joint Transport Research Program. Purdue e-pubs. CERPA, N. and VERNER, J M., 2009. Why did your project fail. Contributing Article, 52(12), pp. 131 FIMPONG, Y JACOB, O and LYNN, C., 2003. Causes of delay and cost overrun in construction of ground water project in developing countries: Ghana as a case study. Internal Journal of Project Management, 21(2003), pp. 34-326. FLYVBJERG, B et al., 2004. What causes cost overrun in transport infrastructure project. Transport Review Article, 24(1), pp.3-18. FLYVBJERG, B., 2009. Excerpt from the book: mega projects and risk. Available from:www.flyubjerg.plan.aau.dk. visited on 12/11/2010. ITRM GUIDLINE CPM., 2006. Project management guideline: section 5-project closeout phase. ITRM JONHSINIT., 2010. Top tips for managing complex projects. Ginny Edwards (online). Available from: www.brighthub.com. (Accessed on 6/12/2010). KIMBERLY, R. and JAMES, LYNEIS., 1999. Management focus: the dynamics of project management: benchmarking the derive of cost and schedule overrun. European Management Journal, 17(2), pp. 135-150.
  • 11. KOUSHKI, P A. AL-RASHID, K. and KARTAM, N., 2005. Construction management and economic: Delay and cost increase in the construction of private residential 11 projects. Taylor and Francis. LARSON, E.W and GRAY, C.F. 2011, Project Management: The Managerial Process, 5th Edition, McGraw Hill. PINTO, J., 2007. Project management: achieving competitive advantages. Pearson. SINGH, R., 2009. Delay and cost overrun in infrastructure projects: an enquiry into extent causes and remedies. Delhi.