SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1208
TO STUDY THE CAUSES AND EFFECTS OF DELAYS IN
CONSTRUCTION PROJECT
Jayashree Bhangale1, Dr. Pankaj Bhangale2
1M.Tech, Student (Construction Technology & Management), Department of Civil Engineering, Shri Sant Gadge
Baba College of Engineering, Bhusawal, Maharashtra, India
2Head of Department, Civil Engineering Department, Shri Sant Gadge Baba College of Engineering, Bhusawal,
Maharashtra, India
----------------------------------------------------------------------***---------------------------------------------------------------------
Abstract – A construction project is basically a temporary
endeavor with specified time & cost, initiated to create a
unique product, service or result, tend to be limited edition. If
we didn't use time properly, it also can be the one cause for
failure of a project. So, in Construction Project cycle delay is
one of the greatest common problems. When the real project
work duration is more than planned project duration, it is
referred to as project time delay. Construction delays are
considered as time lag in completion of activities from its
specified time as per contract. It can also be defined as late
completion or late start of activities to the baseline schedule,
directly affecting specified cost. The main aim of this review
will be to study the causes of delays in constructionprojects. In
this review, the basic causes of delays in construction projects
are reviewed on basis of past literature review.
Key Words: Delays, Reasons, Effects, Causes,
Construction Project.
1. INTRODUCTION
The construction industry in any country is of great
importance. It makes quite sure that people have access to
homes, roads, and other important structures that are
essential for the survival of humanity. Hence construction
management as a whole is as an important factor in any
country, which requires a certain degree of emphasis and
approach. Physical development is achieved totally through
the construction industry, and it is truly the engine of the
national economy. Nowadays there is increase incomplexity
of Infrastructure projects as well as the environment in
which it is to be constructed and therefore this has a greater
demand on construction managers to complete the projects
on scheduled time with planned budgets and with utmost
quality. In various projects,authoritieslikeprojectmanagers
and contractors face difficulties regarding shortage of
equipments, poor quality as well as increase in price of
materials, wastage of material, improperplanningofproject,
shortage of labor class and also material, climate change,
improper management, etc. As a result of these issues, it
leads to time delays. Construction delays are often result of
some mismanaged events and can arise as a risk for the
projects, which if identified, analyzed and managed in a
systematic process at inception, could be managed,
minimized, shared, mitigated or accepted to give some good
results and minimize chances of further delay. Delay in
construction project has a negative effect on clients,
contractors, and consultants in terms of growth in
adversarial relationships, mistrust, litigation, arbitration,
and cash-flow problems. According to the point of view of
contractors, delay results in a lot of financial loss as the
project takes long time duration for its overall completion.
Usually delay in the construction industry bymanyfactorsis
linked with the performance of time, quality, and cost. The
construction project is universally approved as successful
when it finished on time, within budget, according to
specifications and to stakeholder's satisfaction.
2. LITERATURE REVIEW
Construction delays in residential construction are often the
result of miscommunication between contractors,
subcontractors, and property owners. These types of
misunderstandings and unrealistic expectations are usually
avoided through the use of detailed critical path schedules,
which specify the work, and timetable to be used, but most
importantly, the logical sequence of eventswhichmustoccur
fora project to be completed. Delays in construction projects
are frequently expensive,sincethereisusuallyaconstruction
loan involved which charges interest, management staff
dedicated to the project whose costs aretimedependent,and
ongoing inflation in wage and material prices.
Many of researches and studies have completed to explore
the reasons why delay happensinconstructionprojects;both
nearby and globally research have been reviewed.
Dinesh Kumar R (2016) have studied on the Causes and
Effects of Delays in Indian Construction Projects. This paper
has the main aim to look out for the most significant factors
causing delays in Indian construction projects. They carried
out this process through literaturereviewand questionnaire
survey. After studying theliteraturereview,theycategorized
different causes of delays into 8 different groups.
Questionnaire was conducted with the three parties i.e.
contractors, owners, consultants so as to shortlist thetop 20
significant factors of delays in Indian construction industry
and at last recommendations are given to avoid delays in
construction project. They came to the conclusion that the
major reason behind all these causes is lack of commitment
and coordination within the project participants.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1209
Dr. Jayeshkumar Pitroda and Desalegn Disasa Daba(2018)
conducted a review work on main causes of delays in
construction projects. In constructionprojectcontextwe can
explain the delay of time as postponement of time to finish
the project progress. This review work attempts to find and
investigate the main factors perceived to affect delays in
projects. On this review, the basic delay causes in
construction project reviewed on the past literature review.
The researcher achieves their aims to get the main cause of
delay on building constructions by inviting the construction
stakeholders specifically contractor, developers, designer,
and client. The most conducted method to find the main
cause of delays is Relative Important Index (RII) and
Importance index based onthedegreeofseverityanddegree
of frequency.
Shruthi Sivaprakasam, S.Dinesh, J. Jayashree(2017) studied
the reviews on causes of delays in construction projects.
One of the major difficulty faced in the Construction Project
is Delay. Time overrun beyond the specified date in contract
are known as the Construction Delays. Causes of delay
should be recognized and analyzed in order to minimize
them. In this study, the past literature review are studied to
know about the different causes of delay in projects. Along
with identifying the causes of delay, the other important
objective of this study is also to identify the effect of delays
and also methods to minimize these delays. It also aims to
study about the perspectives of the three major parties in
construction industry i.e. owners, contractors and
consultants.
Abhijit Warudkar, Leena Mali(2016) studied the causes of
delay in Pune city. Construction delay is a time exceeds
either after the contract date or after the date that the
components involved have agreed upon for the delivery of
the project. In both cases, a delay is usually a costly situation
or the period of amount of time during which something is
delayed. This paper has intended to identify the causes of
delays, the effects of delays and methods of minimizing
construction delays. This paper study has carried out based
on literature review and a questionnaire survey. Theeighty-
three questionnaire has been made on the basis of pilot
study, which has been distributed on various construction
site. Interview has been taken on each construction sites,
also took photos of any ongoing activity on thatsiteandthen
ranked on their importance index by the data collection in
Pune city. For major factor analysis has used to reduce all
factors divided into nine groups:project,clients,consultants,
contractors, designer, equipment, labour, external and
material. The result of this paper should help construction
practitioners, policy makers and researchers inconstruction
field.
Md Aftab Uddin, Dr. Syed Khursheed Ahmad, Mohd (2017)
studied the types and causes in construction projects. The
main objective of this research is to seek solution of
problems which make obstacles in completionoftheproject.
To satisfy this objective, various actions are carried out like
conducting survey using questionnaireatdifferentsites,find
the causes of delays in construction projects, etc.
Considering the methodology, theyhavefabricated effortsto
minimize delays generally faced by all persons. The main
aspect of this research is to accelerate the reduction in
delays in the upcoming days. As per the study we got to
know that one should always schedule and manage
construction industrieswith a veryhighqualitymanagement
technique to avoid day by day arising problems at site.
3. CONCLUSION
Different researchers from different area studied the causes
and factors of delay in a construction project. So, based on
different literature study many delay causeswereidentified.
Construction contracts tend to provide for three categories
of delay which are as follows:
1. DELAYS RESULTING FROM NEUTRAL CAUSES.
Neutral events are those which are not the result of either
party which might entitle the contractor to an extension of
time. Typically these includes factors like adverse weather
conditions, civil commotion orterrorism,specifiedperil such
as flood, national strikes, change in statutory requirements,
war or an epidemic. One of the factors which also results in
delay is in receiving permissionthatthecontractorhastaken
reasonable steps to avoid. This cause does not necessarily
entitle the contractors to claim loss and expenses.
2. DELAYS THAT ARE THE FAULT OF THE CLIENT.
When the work progress is materiallyaffectedbymatters for
which the client is responsible, then the contractor would
not be entitled to claim loss and expenses incurred. Such
factors for which client is responsible canbe thattheclientis
instructing variations in the works, poor coordination and
communication, client’s failure to supply the materials or
goods, lack of motivations for contractor to finish ahead of
schedule, interruption of work, slow document approval,
consultant team failure to provideproperinformation,delay
on part of nominated sub-contractor, causing delay in
handing over the possession of side to the contractor. All
these above factors enables the contractor to claim an
extension of time for the completion of the project.
3. DELAYS THAT ARE THE FAULT OF THE
CONTRACTOR
These delays are also referred as culpable delay or
contractor delay. The factors which causethisdelayarepoor
experience of the contractor, late approving design
documents, delay in site arrangement, problems in funding
by contractor, revise due to mistakes during work,
ineffective site supervision, delay in procurement of
materials, unskilled project crew, slow decision-making,
conflict between labor and client, ineffective scheduling,
poor methods of construction, lack of labour, shortage of
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1210
equipment, improper equipment, frequent equipment
breakdowns, delay in payment of executed work for a
contractor by the owner, unskilled sub-contractors,
ineffective economic control on site. When a delay occurs
which impacts on the completion date of project caused by
the contractor, the contractor will be liable to pay liquidated
and ascertained damages to the client.
REFERENCES
[1] Dinesh Kumar R, “Causes and Effects of Delays in Indian
Construction Projects”, IRJET, Volume 3, Issue 4, April
16, ISSN: 2395 -0056.
[2] Dr. Jayeshkumar Pitroda, Desalegn Disasa Daba, “A
Critical Literature Review on Main Cause of Delay in
Construction Projects”, IRJET, Volume: 05Issue:01,Jan-
2018, ISSN: 2395-0056.
[3] Shruthi Sivaprakasam, S.Dinesh, J. Jayashree, “A Review
on Causes of Delay in Construction Projects”, IJSRD,
Volume 5, Issue 02, 2017, ISSN (online): 2321-0613.
[4] Leena Mali, Abhijit Warudkar, “Analysis on Causes of
Delay in Construction Industry in Pune City”, IJIRSET,
Volume 5, Issue 8, August 2016, ISSN: 2319-8753.
[5] Md Aftab Uddin, Dr. Syed Khursheed Ahmad, Mohd
Danish, “Types and causes in construction delays”,
IRJET, Volume 4, Issue 7, July-2017, ISSN: 2395-0056.

More Related Content

What's hot

IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Sankalp Swarnkar
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
ijsrd.com
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
IRJET Journal
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
Dr.Madhav Prasad Koirala
 
Time overruns
Time overrunsTime overruns
Time overruns
Bhalchandra Tankkar
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
Harish Rajmane
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
World-Academic Journal
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
IJERA Editor
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
Charles Abraham Scheck
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET Journal
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
IJERA Editor
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
Engr_Emad Khan
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
HASHIM HANIF
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
Twana Ahmad
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Associate Professor in VSB Coimbatore
 

What's hot (19)

IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Time overruns
Time overrunsTime overruns
Time overruns
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 

Similar to IRJET- To Study the Causes and Effects of Delays in Construction Project

Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET Journal
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
IRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
ijtsrd
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
IAEME Publication
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
IRJET Journal
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
IRJET Journal
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET Journal
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
EbrahimJemal4
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET Journal
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
eSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
eSAT Journals
 

Similar to IRJET- To Study the Causes and Effects of Delays in Construction Project (20)

Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 

Recently uploaded (20)

road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 

IRJET- To Study the Causes and Effects of Delays in Construction Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1208 TO STUDY THE CAUSES AND EFFECTS OF DELAYS IN CONSTRUCTION PROJECT Jayashree Bhangale1, Dr. Pankaj Bhangale2 1M.Tech, Student (Construction Technology & Management), Department of Civil Engineering, Shri Sant Gadge Baba College of Engineering, Bhusawal, Maharashtra, India 2Head of Department, Civil Engineering Department, Shri Sant Gadge Baba College of Engineering, Bhusawal, Maharashtra, India ----------------------------------------------------------------------***--------------------------------------------------------------------- Abstract – A construction project is basically a temporary endeavor with specified time & cost, initiated to create a unique product, service or result, tend to be limited edition. If we didn't use time properly, it also can be the one cause for failure of a project. So, in Construction Project cycle delay is one of the greatest common problems. When the real project work duration is more than planned project duration, it is referred to as project time delay. Construction delays are considered as time lag in completion of activities from its specified time as per contract. It can also be defined as late completion or late start of activities to the baseline schedule, directly affecting specified cost. The main aim of this review will be to study the causes of delays in constructionprojects. In this review, the basic causes of delays in construction projects are reviewed on basis of past literature review. Key Words: Delays, Reasons, Effects, Causes, Construction Project. 1. INTRODUCTION The construction industry in any country is of great importance. It makes quite sure that people have access to homes, roads, and other important structures that are essential for the survival of humanity. Hence construction management as a whole is as an important factor in any country, which requires a certain degree of emphasis and approach. Physical development is achieved totally through the construction industry, and it is truly the engine of the national economy. Nowadays there is increase incomplexity of Infrastructure projects as well as the environment in which it is to be constructed and therefore this has a greater demand on construction managers to complete the projects on scheduled time with planned budgets and with utmost quality. In various projects,authoritieslikeprojectmanagers and contractors face difficulties regarding shortage of equipments, poor quality as well as increase in price of materials, wastage of material, improperplanningofproject, shortage of labor class and also material, climate change, improper management, etc. As a result of these issues, it leads to time delays. Construction delays are often result of some mismanaged events and can arise as a risk for the projects, which if identified, analyzed and managed in a systematic process at inception, could be managed, minimized, shared, mitigated or accepted to give some good results and minimize chances of further delay. Delay in construction project has a negative effect on clients, contractors, and consultants in terms of growth in adversarial relationships, mistrust, litigation, arbitration, and cash-flow problems. According to the point of view of contractors, delay results in a lot of financial loss as the project takes long time duration for its overall completion. Usually delay in the construction industry bymanyfactorsis linked with the performance of time, quality, and cost. The construction project is universally approved as successful when it finished on time, within budget, according to specifications and to stakeholder's satisfaction. 2. LITERATURE REVIEW Construction delays in residential construction are often the result of miscommunication between contractors, subcontractors, and property owners. These types of misunderstandings and unrealistic expectations are usually avoided through the use of detailed critical path schedules, which specify the work, and timetable to be used, but most importantly, the logical sequence of eventswhichmustoccur fora project to be completed. Delays in construction projects are frequently expensive,sincethereisusuallyaconstruction loan involved which charges interest, management staff dedicated to the project whose costs aretimedependent,and ongoing inflation in wage and material prices. Many of researches and studies have completed to explore the reasons why delay happensinconstructionprojects;both nearby and globally research have been reviewed. Dinesh Kumar R (2016) have studied on the Causes and Effects of Delays in Indian Construction Projects. This paper has the main aim to look out for the most significant factors causing delays in Indian construction projects. They carried out this process through literaturereviewand questionnaire survey. After studying theliteraturereview,theycategorized different causes of delays into 8 different groups. Questionnaire was conducted with the three parties i.e. contractors, owners, consultants so as to shortlist thetop 20 significant factors of delays in Indian construction industry and at last recommendations are given to avoid delays in construction project. They came to the conclusion that the major reason behind all these causes is lack of commitment and coordination within the project participants.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1209 Dr. Jayeshkumar Pitroda and Desalegn Disasa Daba(2018) conducted a review work on main causes of delays in construction projects. In constructionprojectcontextwe can explain the delay of time as postponement of time to finish the project progress. This review work attempts to find and investigate the main factors perceived to affect delays in projects. On this review, the basic delay causes in construction project reviewed on the past literature review. The researcher achieves their aims to get the main cause of delay on building constructions by inviting the construction stakeholders specifically contractor, developers, designer, and client. The most conducted method to find the main cause of delays is Relative Important Index (RII) and Importance index based onthedegreeofseverityanddegree of frequency. Shruthi Sivaprakasam, S.Dinesh, J. Jayashree(2017) studied the reviews on causes of delays in construction projects. One of the major difficulty faced in the Construction Project is Delay. Time overrun beyond the specified date in contract are known as the Construction Delays. Causes of delay should be recognized and analyzed in order to minimize them. In this study, the past literature review are studied to know about the different causes of delay in projects. Along with identifying the causes of delay, the other important objective of this study is also to identify the effect of delays and also methods to minimize these delays. It also aims to study about the perspectives of the three major parties in construction industry i.e. owners, contractors and consultants. Abhijit Warudkar, Leena Mali(2016) studied the causes of delay in Pune city. Construction delay is a time exceeds either after the contract date or after the date that the components involved have agreed upon for the delivery of the project. In both cases, a delay is usually a costly situation or the period of amount of time during which something is delayed. This paper has intended to identify the causes of delays, the effects of delays and methods of minimizing construction delays. This paper study has carried out based on literature review and a questionnaire survey. Theeighty- three questionnaire has been made on the basis of pilot study, which has been distributed on various construction site. Interview has been taken on each construction sites, also took photos of any ongoing activity on thatsiteandthen ranked on their importance index by the data collection in Pune city. For major factor analysis has used to reduce all factors divided into nine groups:project,clients,consultants, contractors, designer, equipment, labour, external and material. The result of this paper should help construction practitioners, policy makers and researchers inconstruction field. Md Aftab Uddin, Dr. Syed Khursheed Ahmad, Mohd (2017) studied the types and causes in construction projects. The main objective of this research is to seek solution of problems which make obstacles in completionoftheproject. To satisfy this objective, various actions are carried out like conducting survey using questionnaireatdifferentsites,find the causes of delays in construction projects, etc. Considering the methodology, theyhavefabricated effortsto minimize delays generally faced by all persons. The main aspect of this research is to accelerate the reduction in delays in the upcoming days. As per the study we got to know that one should always schedule and manage construction industrieswith a veryhighqualitymanagement technique to avoid day by day arising problems at site. 3. CONCLUSION Different researchers from different area studied the causes and factors of delay in a construction project. So, based on different literature study many delay causeswereidentified. Construction contracts tend to provide for three categories of delay which are as follows: 1. DELAYS RESULTING FROM NEUTRAL CAUSES. Neutral events are those which are not the result of either party which might entitle the contractor to an extension of time. Typically these includes factors like adverse weather conditions, civil commotion orterrorism,specifiedperil such as flood, national strikes, change in statutory requirements, war or an epidemic. One of the factors which also results in delay is in receiving permissionthatthecontractorhastaken reasonable steps to avoid. This cause does not necessarily entitle the contractors to claim loss and expenses. 2. DELAYS THAT ARE THE FAULT OF THE CLIENT. When the work progress is materiallyaffectedbymatters for which the client is responsible, then the contractor would not be entitled to claim loss and expenses incurred. Such factors for which client is responsible canbe thattheclientis instructing variations in the works, poor coordination and communication, client’s failure to supply the materials or goods, lack of motivations for contractor to finish ahead of schedule, interruption of work, slow document approval, consultant team failure to provideproperinformation,delay on part of nominated sub-contractor, causing delay in handing over the possession of side to the contractor. All these above factors enables the contractor to claim an extension of time for the completion of the project. 3. DELAYS THAT ARE THE FAULT OF THE CONTRACTOR These delays are also referred as culpable delay or contractor delay. The factors which causethisdelayarepoor experience of the contractor, late approving design documents, delay in site arrangement, problems in funding by contractor, revise due to mistakes during work, ineffective site supervision, delay in procurement of materials, unskilled project crew, slow decision-making, conflict between labor and client, ineffective scheduling, poor methods of construction, lack of labour, shortage of
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 12 | Dec 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1210 equipment, improper equipment, frequent equipment breakdowns, delay in payment of executed work for a contractor by the owner, unskilled sub-contractors, ineffective economic control on site. When a delay occurs which impacts on the completion date of project caused by the contractor, the contractor will be liable to pay liquidated and ascertained damages to the client. REFERENCES [1] Dinesh Kumar R, “Causes and Effects of Delays in Indian Construction Projects”, IRJET, Volume 3, Issue 4, April 16, ISSN: 2395 -0056. [2] Dr. Jayeshkumar Pitroda, Desalegn Disasa Daba, “A Critical Literature Review on Main Cause of Delay in Construction Projects”, IRJET, Volume: 05Issue:01,Jan- 2018, ISSN: 2395-0056. [3] Shruthi Sivaprakasam, S.Dinesh, J. Jayashree, “A Review on Causes of Delay in Construction Projects”, IJSRD, Volume 5, Issue 02, 2017, ISSN (online): 2321-0613. [4] Leena Mali, Abhijit Warudkar, “Analysis on Causes of Delay in Construction Industry in Pune City”, IJIRSET, Volume 5, Issue 8, August 2016, ISSN: 2319-8753. [5] Md Aftab Uddin, Dr. Syed Khursheed Ahmad, Mohd Danish, “Types and causes in construction delays”, IRJET, Volume 4, Issue 7, July-2017, ISSN: 2395-0056.