International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1326
IMPACT OF DELAYNESS ON CONSTRUCTION PROJECTS
Swadesh Singh Bhadoria,1 Sohit Agrawal,2 Swetank Sharma,2, Dr.Mukesh Kumar Pandey,3
B.Tech+M.tech(INT) P.G student, Construction technology & Management, I.T.M University Madhya Pradesh, India.
Asst.Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh, India.
Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh ,India
-------------------------------------------------------------***------------------------------------------------------------------
Abstract:
This paper deals with the attributes of delay
which extremely effect on the residential and
multi-stories construction projects in Gwalior
City in India. Time delays and cost overruns
have become a challenge for civil engineering
section of India. . This research theme deals
with the analysis of properties of delay &
ranking of attributes by RII (relative
importance index). Which are extremely
effected on construction projects of buildings in
India. This study included analysis of delay
factors, ranking of factors of delays and also
compared among three groups (i.e, Owner,
Contractor & consultant). Total 38 causes are
identified under 8 major groups. An Interview
questionnaire was taken for survey the critical
causes of delays in building area. Total 35
respondents included in this research, i.e., 9
owners, 12 contractors and 14consultants.This
paper suggest the simplest way to find out the
ranking of attributes of delay by RII (Relative
importance technique). After determining
results of all attributes of delays is that
ten factors out of all total are highly effected in
the execution of large building construction.
They are shortage of labour, delay in
delivery of resources on the site, Rework due
to errors on the site, delay current payment by
owner, poor site management at the site
and direction by contractor etc.
Key Words- Analysis of delay’s Factors, Survey,
Relative important index (RII), Effects of delay.
1.INTRODUCTION
The delay in the construction work department
can also be said as the project does not deliver
on the date of completion of the project and
also the expansion in the estimated cost project
as compare to the actual cost of a project, it
means the project is delayed due to delays in
time and values overruns. Toward the owner of
the project delay suggests that price overruns
attributable to lack of production
and rentable area. Toward the contractor
delay implies that higher
overhead price attributable to enlargement in
time of project, high material price, machinery
and labour price increment.. The procedure of
execution of a construction project is subjected
to various and unwanted factors which result
from many sources. These sources contained
availability of resources on site, environment,
condition, the performance of various parties,
Role of other parties and contractual
relationship. Delay means more activities are
pending which mentioned within the contract
duration of the project.
For various parties definition of delayness in
construction project is different such as For
owner delay means low income in more time,
For consultant delay means more work
remaining in less time period etc. so because of
delay project cost, material cost, government
charges and overall cost are increase. All these
factors are related to causes of delay so we
can realize the attributes of delays in
construction to extend the performance of
project. For any construction projects
requirement of work is very high so, owner
needs planning at which time and price of
project is satisfy. This can be listed out by
proper -scheduling and by identification of
causes of delays. So, it is necessary to explain
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1327
the most critical causes of delay which have
great effect on the construction project in order
to minimize and try to avoid the delays in the
construction of multi-stories and residential
building project in India.
1.1 Effect of delays
 Time overrun
 Cost overrun
 Dispute
 Arbitration
 Total abandonment
 Litigation
2. Objectives of study:
The main objectives of this present study are as
follows:
To study and analyse the attributes of delay in
building construction projects from the point of
view of owner, contractor and consultant.
To rank the causes of delay by Relative
importance index technique (RII).
Try to minimize the causes of Delay.
3. LITERATURE REVIEW
Ashraf Samara and Ghanim A. Bekr (2016)
identified the 55 important factors of delay in
Jordan which had hardly effected by Time
overruns and expansion of cost. They were
carried out a survey to identiy the critical
factors of delay which has stopped the
performance of Jordan construction in which
146 respondents are involved. Top ten factors
causing delays for public sector projects in
Jordan are: (1) inadequate management and
supervision by the contractor, (2) client's
changes of the design, (3) inadequate planning
and control by the contractor, (4) using lowest
bid that lead to low performance, (5) changes
in the extent of the project , (6) errors in design
and contract documents , (7) progress
payments are not made in time by the client,
(8) Rework due to mistakes during
construction, (9) Changes in the original design
and (10)Low level productivity.
Mohammad Saiful, Bambang Trigunarsyah
and Sadi Assaf (2015) evaluating the 79
different significant factors of delays in the
construction of multi-stories building and
residential building in construction industry of
Bangladesh. They were conducted a survey to
identifying the causes of delay in large large
building construction projects in which 70
respondents participated i.e, (owner,
consultant, contractor) by using importance
index method. About their results, they
concluded the lack of experience construction
manager ,lowest bidder selection, improper
planning & scheduling ,lack of proper working
management are the most critical causes of
delay which are highly contributed to occur
delay in construction project..
4. RESEARCH METHODOLOGY
 LITERATURE COLLECTION
 REVISION OF LITERATURE
 IDENTIFICATION OF DELAY’S
CAUSES& EFFECTS
 QUESTIONNAIRE PREPRATION
 QUESTIONNAIRE SURVEY
 ANALYSIS OF CAUSES BY (RII)
TECHNIQUE
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1328
4. DATA ANALYSIS APPROCH
(i). Relative Importance Index technique:
By exploitation the Relative Importance Index
technique to the ranking of causes of delay is
easy with compare to alternative. The same
method is taken in this present study within
three groups which are owners, consultants or
contractors. The grading of five-point scale 1
for (very low importance) to 5 for very high
importance) is considered and converted into
relative importance indices (RII) for each factor
as follows:
∑W
RII = (0< RII <1)
A* N
Where:
W – is the response weight given to each
attribute by the personnel and range vary from
1 to 5, (where “1” is “very low importance” and
“5” is “very high importance”);
A – is the highest weight (i.e. 5 in this case) and;
N – is the overall number of stakeholders.
Table -1: significant Causes of delay by RII Method
Figure -1: significant Causes of delay by RII Method
Table 5.2 : Ranking of group of causes of delay
by All three Parties
0.8510.846
0.811
0.7940.7890.7770.7710.7660.7540.743
0.68
0.7
0.72
0.74
0.76
0.78
0.8
0.82
0.84
0.86
Reworkdueto…
Originalcontract…
Shortageoflabor
Inadequate…
Difficultiesin…
Delayinprogress…
Shortageof…
1 2 3 4 5 6 7 8 9 10
RII
RII
No. Critical Cause of delay RII
1 Rework due to errors during
construction 0.851
2 Inadequate planning and scheduling
of project by contractor 0.846
3 Original contract duration is too
short 0.811
4 Delay in material delivery 0.794
5 Shortage of labour 0.789
6 Poor site management and
supervision by the contractor 0.777
7 Inadequate contractor’s work
experience 0.771
8 Difficulties in financing project by
contractor 0.766
9 Delay in progress payment by owner 0.754
10 Shortage of equipment 0.743
S.NO. No.of
Groups
OWNE
R RII
R
A
N
K
Contra
ctor
RII
R
A
N
K
Consul
tant
RII
R
A
N
K
1. contracto
r
0.78 1 0.59 8 0.77 1
2. consultan
t
0.64 5 0.71 4 0.51 8
3. project 0.66 4 0.79 1 0.72 2
4. owner 0.50 7 0.76 2 0.56 7
5. labour 0.68 3 0.72 3 0.68 3
6. Design 0.55 6 0.60 7 0.65 5
7. material 0.71 2 0.61 6 0.62 6
8. equipme
nt
0.48 8 0.65 5 0.66 4
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1329
Figure-2 : Ranking of group of causes of delay
by All three Partie
6. Conclusion
The first step in reducing the delays in
infrastructure construction project is to
understand the root causes of the delay. This
results provide a listing of root causes and
issues that are directly responsible for most
infrastructure construction project delays.
Additionally, it is found that fundamental
principles must be adopted before significant
improvements can be made. The data were
collected from the following construction
Infrastructure companies.
According to results, some factors have found
that which are highly effected on the
construction projects Rework due to mistakes,
Inadequate planning & scheduling of project by
contractor, Original contract duration is too
short, Delay in material delivery on site,
Shortage of labour , Poor site management &
supervision by contractor, Inadequate
contractor’s experience, Difficulties in financing
by contractor, Shortage of equipment, Delay in
progress payment by owner .
7.Recommendation
The following points can be recommended by
all parties in order to minimize and control
delays in construction projects:
7.1. Contractor’s Should Consider The
Following Factors
Shortage and low productivity of labor: enough
number of labors should be assigned and
motivated to improve productivity.
Financial and cash flow problems: contractor
should manage his financial resources and plan
cash flow by utilizing progress payment.
7.2. Consultant’s Should Look To The
Following Factors
Reviewing and approving design documents
any delay caused by the consultant engineer in
checking, reviewing and approving the design
submittals prior to construction phase, could
delay the progress of the work;
Inflexibility: Consultants should be flexible in
evaluating contractor works. Compromising
between the cost and high quality should be
considered.
7.3. Owner’s Should Give Special Attention
To The Following Factors
Pay progress payment to the contractor on
time because it impairs the contractor’s ability
to finance the work.
Reduce the frequent changing in orders during
construction to neglect delays.
8.REFRENCES
1. Hemanta Doloi, Anil Sawhney, K.C.Iyer, Sameer
Rentala (2012).Analysing factors affecting daelays in
Indian construction projects International journal of
project management 30,479-489
2. Mamta Rajgor, Chauhan Paresh, Patel Dhruv, Panchal
Chirag. RII&IMPI: Effective techniques for finding
delay in construction projects. International
Research Journal of
Engineering&TechnologyVolume:03.Issue:01|JAN-
2016.
3.YawFrimpong,JacobOluwoye,LynnCrawford.Causes of
delay and cost overruns in construction of ground
water projects in developing countries in Ghana
International journal of project
management21(2013),321-326.
4.Siddesh K Pai,Mr.J.Raj Bharath. Analysis of critical
causes of Delay in Indian Infrastructure Projects.
0.78
0.64 0.66
0.5
0.68
0.55
0.71
0.48
0.59
0.71
0.790.76
0.72
0.60.61
0.65
0.77
0.51
0.72
0.56
0.680.650.62
0.66
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1 3 5 7 9 11 13 15 17
OWNER RII
Contractor RII
Consultant RII
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1330
International journal of Innovative Research &
Development VOL2:Issue:March-2013.
5.Mega Desai, Rajiv Bhatt. Critical causes of Delay in
Residential Construction Projects: Case Study of
Central Gujarat Region in India. .International
Research Journal of Engineering Trends and
Technology Volume:4.Issue:4|April-2013
6.Murat Gunduj, Yasemin Nielsen, Mustafa Ozdemir.
Quantification of Delay Factors Using the RII Method
for Construction Projects in Turkey. Journal of
Management in Engineering(2013),29(2):133-139.

More Related Content

What's hot

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET Journal
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsIRJET Journal
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
A systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryA systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryeSAT Journals
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...eSAT Journals
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 

What's hot (19)

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Time overruns
Time overrunsTime overruns
Time overruns
 
A systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryA systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industry
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 

Viewers also liked

A review towards various hash algorithms and their comparative analysis
A review towards various hash algorithms and their comparative analysisA review towards various hash algorithms and their comparative analysis
A review towards various hash algorithms and their comparative analysisIRJET Journal
 
An analysis of effect of variable compression ratio in C.I. engine using turb...
An analysis of effect of variable compression ratio in C.I. engine using turb...An analysis of effect of variable compression ratio in C.I. engine using turb...
An analysis of effect of variable compression ratio in C.I. engine using turb...IRJET Journal
 
Color to sound converter for blind people
Color to sound converter for blind peopleColor to sound converter for blind people
Color to sound converter for blind peopleIRJET Journal
 
Free vibration analysis on cantilever beam-A review
Free vibration analysis on cantilever beam-A reviewFree vibration analysis on cantilever beam-A review
Free vibration analysis on cantilever beam-A reviewIRJET Journal
 
IOT Based Water Level Monitoring System For Lake
IOT Based Water Level Monitoring System For LakeIOT Based Water Level Monitoring System For Lake
IOT Based Water Level Monitoring System For LakeIRJET Journal
 
A Distributed Time Triggered Control for a Feedback Control System
A Distributed Time Triggered Control for a Feedback Control SystemA Distributed Time Triggered Control for a Feedback Control System
A Distributed Time Triggered Control for a Feedback Control SystemIRJET Journal
 
Study of Multipurpose Road Cleaning Machine
Study of Multipurpose Road Cleaning MachineStudy of Multipurpose Road Cleaning Machine
Study of Multipurpose Road Cleaning MachineIRJET Journal
 
Strength and geotechnical characterization of copper slag as partial replacem...
Strength and geotechnical characterization of copper slag as partial replacem...Strength and geotechnical characterization of copper slag as partial replacem...
Strength and geotechnical characterization of copper slag as partial replacem...IRJET Journal
 
Sag/Swell Compensation by using BES DVR in Industrial Drives Applications
Sag/Swell Compensation by using BES DVR in Industrial Drives ApplicationsSag/Swell Compensation by using BES DVR in Industrial Drives Applications
Sag/Swell Compensation by using BES DVR in Industrial Drives ApplicationsIRJET Journal
 
Privacy Recommendations and Ranking of User Images on Content Sharing Sites
Privacy Recommendations and Ranking of User Images on Content Sharing SitesPrivacy Recommendations and Ranking of User Images on Content Sharing Sites
Privacy Recommendations and Ranking of User Images on Content Sharing SitesIRJET Journal
 
Localization of wireless sensor network
Localization of wireless sensor networkLocalization of wireless sensor network
Localization of wireless sensor networkIRJET Journal
 
Portable voice communication system on raspberry pi
Portable voice communication system on raspberry piPortable voice communication system on raspberry pi
Portable voice communication system on raspberry piIRJET Journal
 
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...IRJET Journal
 
Automatic pneumatic bumper
Automatic pneumatic bumperAutomatic pneumatic bumper
Automatic pneumatic bumperIRJET Journal
 
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...IRJET Journal
 
A Paper on Study & Design of Multipurpose Riveting Machine
A  Paper on Study & Design of Multipurpose Riveting MachineA  Paper on Study & Design of Multipurpose Riveting Machine
A Paper on Study & Design of Multipurpose Riveting MachineIRJET Journal
 
An Investigation of DAF Protocol in Wireless Communication
An Investigation of DAF Protocol in Wireless CommunicationAn Investigation of DAF Protocol in Wireless Communication
An Investigation of DAF Protocol in Wireless CommunicationIRJET Journal
 
A Review Paper on Pneumatic Operated Collapsable Steering System
A Review Paper on Pneumatic Operated Collapsable Steering SystemA Review Paper on Pneumatic Operated Collapsable Steering System
A Review Paper on Pneumatic Operated Collapsable Steering SystemIRJET Journal
 
Forward and Inverse Kinematic Analysis of Robotic Manipulators
Forward and Inverse Kinematic Analysis of Robotic ManipulatorsForward and Inverse Kinematic Analysis of Robotic Manipulators
Forward and Inverse Kinematic Analysis of Robotic ManipulatorsIRJET Journal
 
A Geo-PFM Model for Point Of Interest Recommendation
A Geo-PFM Model for Point Of Interest RecommendationA Geo-PFM Model for Point Of Interest Recommendation
A Geo-PFM Model for Point Of Interest RecommendationIRJET Journal
 

Viewers also liked (20)

A review towards various hash algorithms and their comparative analysis
A review towards various hash algorithms and their comparative analysisA review towards various hash algorithms and their comparative analysis
A review towards various hash algorithms and their comparative analysis
 
An analysis of effect of variable compression ratio in C.I. engine using turb...
An analysis of effect of variable compression ratio in C.I. engine using turb...An analysis of effect of variable compression ratio in C.I. engine using turb...
An analysis of effect of variable compression ratio in C.I. engine using turb...
 
Color to sound converter for blind people
Color to sound converter for blind peopleColor to sound converter for blind people
Color to sound converter for blind people
 
Free vibration analysis on cantilever beam-A review
Free vibration analysis on cantilever beam-A reviewFree vibration analysis on cantilever beam-A review
Free vibration analysis on cantilever beam-A review
 
IOT Based Water Level Monitoring System For Lake
IOT Based Water Level Monitoring System For LakeIOT Based Water Level Monitoring System For Lake
IOT Based Water Level Monitoring System For Lake
 
A Distributed Time Triggered Control for a Feedback Control System
A Distributed Time Triggered Control for a Feedback Control SystemA Distributed Time Triggered Control for a Feedback Control System
A Distributed Time Triggered Control for a Feedback Control System
 
Study of Multipurpose Road Cleaning Machine
Study of Multipurpose Road Cleaning MachineStudy of Multipurpose Road Cleaning Machine
Study of Multipurpose Road Cleaning Machine
 
Strength and geotechnical characterization of copper slag as partial replacem...
Strength and geotechnical characterization of copper slag as partial replacem...Strength and geotechnical characterization of copper slag as partial replacem...
Strength and geotechnical characterization of copper slag as partial replacem...
 
Sag/Swell Compensation by using BES DVR in Industrial Drives Applications
Sag/Swell Compensation by using BES DVR in Industrial Drives ApplicationsSag/Swell Compensation by using BES DVR in Industrial Drives Applications
Sag/Swell Compensation by using BES DVR in Industrial Drives Applications
 
Privacy Recommendations and Ranking of User Images on Content Sharing Sites
Privacy Recommendations and Ranking of User Images on Content Sharing SitesPrivacy Recommendations and Ranking of User Images on Content Sharing Sites
Privacy Recommendations and Ranking of User Images on Content Sharing Sites
 
Localization of wireless sensor network
Localization of wireless sensor networkLocalization of wireless sensor network
Localization of wireless sensor network
 
Portable voice communication system on raspberry pi
Portable voice communication system on raspberry piPortable voice communication system on raspberry pi
Portable voice communication system on raspberry pi
 
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...
Analysis of 24×7 Water Distribution Network of Gabbur zone in Hubballi city, ...
 
Automatic pneumatic bumper
Automatic pneumatic bumperAutomatic pneumatic bumper
Automatic pneumatic bumper
 
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...
Performance Analysis of DSR, STAR, ZRP Routing Protocols for a Dynamic Ad-Hoc...
 
A Paper on Study & Design of Multipurpose Riveting Machine
A  Paper on Study & Design of Multipurpose Riveting MachineA  Paper on Study & Design of Multipurpose Riveting Machine
A Paper on Study & Design of Multipurpose Riveting Machine
 
An Investigation of DAF Protocol in Wireless Communication
An Investigation of DAF Protocol in Wireless CommunicationAn Investigation of DAF Protocol in Wireless Communication
An Investigation of DAF Protocol in Wireless Communication
 
A Review Paper on Pneumatic Operated Collapsable Steering System
A Review Paper on Pneumatic Operated Collapsable Steering SystemA Review Paper on Pneumatic Operated Collapsable Steering System
A Review Paper on Pneumatic Operated Collapsable Steering System
 
Forward and Inverse Kinematic Analysis of Robotic Manipulators
Forward and Inverse Kinematic Analysis of Robotic ManipulatorsForward and Inverse Kinematic Analysis of Robotic Manipulators
Forward and Inverse Kinematic Analysis of Robotic Manipulators
 
A Geo-PFM Model for Point Of Interest Recommendation
A Geo-PFM Model for Point Of Interest RecommendationA Geo-PFM Model for Point Of Interest Recommendation
A Geo-PFM Model for Point Of Interest Recommendation
 

Similar to Impact of delayness on construction projects

RII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction ProjectRII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction ProjectIRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple ProjectsIRJET Journal
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfKarthikeyanP288430
 
IRJET- Analysis of Change Order in Road Construction Projects
IRJET-  	  Analysis of Change Order in Road Construction ProjectsIRJET-  	  Analysis of Change Order in Road Construction Projects
IRJET- Analysis of Change Order in Road Construction ProjectsIRJET Journal
 
Delay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential ProjectDelay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential ProjectIRJET Journal
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 

Similar to Impact of delayness on construction projects (20)

RII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction ProjectRII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction Project
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
IRJET- Analysis of Change Order in Road Construction Projects
IRJET-  	  Analysis of Change Order in Road Construction ProjectsIRJET-  	  Analysis of Change Order in Road Construction Projects
IRJET- Analysis of Change Order in Road Construction Projects
 
Delay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential ProjectDelay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential Project
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 

Impact of delayness on construction projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1326 IMPACT OF DELAYNESS ON CONSTRUCTION PROJECTS Swadesh Singh Bhadoria,1 Sohit Agrawal,2 Swetank Sharma,2, Dr.Mukesh Kumar Pandey,3 B.Tech+M.tech(INT) P.G student, Construction technology & Management, I.T.M University Madhya Pradesh, India. Asst.Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh, India. Professor DEPT.OF CIVIL ENGINEERING, I.T.M university Madhyapradesh ,India -------------------------------------------------------------***------------------------------------------------------------------ Abstract: This paper deals with the attributes of delay which extremely effect on the residential and multi-stories construction projects in Gwalior City in India. Time delays and cost overruns have become a challenge for civil engineering section of India. . This research theme deals with the analysis of properties of delay & ranking of attributes by RII (relative importance index). Which are extremely effected on construction projects of buildings in India. This study included analysis of delay factors, ranking of factors of delays and also compared among three groups (i.e, Owner, Contractor & consultant). Total 38 causes are identified under 8 major groups. An Interview questionnaire was taken for survey the critical causes of delays in building area. Total 35 respondents included in this research, i.e., 9 owners, 12 contractors and 14consultants.This paper suggest the simplest way to find out the ranking of attributes of delay by RII (Relative importance technique). After determining results of all attributes of delays is that ten factors out of all total are highly effected in the execution of large building construction. They are shortage of labour, delay in delivery of resources on the site, Rework due to errors on the site, delay current payment by owner, poor site management at the site and direction by contractor etc. Key Words- Analysis of delay’s Factors, Survey, Relative important index (RII), Effects of delay. 1.INTRODUCTION The delay in the construction work department can also be said as the project does not deliver on the date of completion of the project and also the expansion in the estimated cost project as compare to the actual cost of a project, it means the project is delayed due to delays in time and values overruns. Toward the owner of the project delay suggests that price overruns attributable to lack of production and rentable area. Toward the contractor delay implies that higher overhead price attributable to enlargement in time of project, high material price, machinery and labour price increment.. The procedure of execution of a construction project is subjected to various and unwanted factors which result from many sources. These sources contained availability of resources on site, environment, condition, the performance of various parties, Role of other parties and contractual relationship. Delay means more activities are pending which mentioned within the contract duration of the project. For various parties definition of delayness in construction project is different such as For owner delay means low income in more time, For consultant delay means more work remaining in less time period etc. so because of delay project cost, material cost, government charges and overall cost are increase. All these factors are related to causes of delay so we can realize the attributes of delays in construction to extend the performance of project. For any construction projects requirement of work is very high so, owner needs planning at which time and price of project is satisfy. This can be listed out by proper -scheduling and by identification of causes of delays. So, it is necessary to explain
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1327 the most critical causes of delay which have great effect on the construction project in order to minimize and try to avoid the delays in the construction of multi-stories and residential building project in India. 1.1 Effect of delays  Time overrun  Cost overrun  Dispute  Arbitration  Total abandonment  Litigation 2. Objectives of study: The main objectives of this present study are as follows: To study and analyse the attributes of delay in building construction projects from the point of view of owner, contractor and consultant. To rank the causes of delay by Relative importance index technique (RII). Try to minimize the causes of Delay. 3. LITERATURE REVIEW Ashraf Samara and Ghanim A. Bekr (2016) identified the 55 important factors of delay in Jordan which had hardly effected by Time overruns and expansion of cost. They were carried out a survey to identiy the critical factors of delay which has stopped the performance of Jordan construction in which 146 respondents are involved. Top ten factors causing delays for public sector projects in Jordan are: (1) inadequate management and supervision by the contractor, (2) client's changes of the design, (3) inadequate planning and control by the contractor, (4) using lowest bid that lead to low performance, (5) changes in the extent of the project , (6) errors in design and contract documents , (7) progress payments are not made in time by the client, (8) Rework due to mistakes during construction, (9) Changes in the original design and (10)Low level productivity. Mohammad Saiful, Bambang Trigunarsyah and Sadi Assaf (2015) evaluating the 79 different significant factors of delays in the construction of multi-stories building and residential building in construction industry of Bangladesh. They were conducted a survey to identifying the causes of delay in large large building construction projects in which 70 respondents participated i.e, (owner, consultant, contractor) by using importance index method. About their results, they concluded the lack of experience construction manager ,lowest bidder selection, improper planning & scheduling ,lack of proper working management are the most critical causes of delay which are highly contributed to occur delay in construction project.. 4. RESEARCH METHODOLOGY  LITERATURE COLLECTION  REVISION OF LITERATURE  IDENTIFICATION OF DELAY’S CAUSES& EFFECTS  QUESTIONNAIRE PREPRATION  QUESTIONNAIRE SURVEY  ANALYSIS OF CAUSES BY (RII) TECHNIQUE
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1328 4. DATA ANALYSIS APPROCH (i). Relative Importance Index technique: By exploitation the Relative Importance Index technique to the ranking of causes of delay is easy with compare to alternative. The same method is taken in this present study within three groups which are owners, consultants or contractors. The grading of five-point scale 1 for (very low importance) to 5 for very high importance) is considered and converted into relative importance indices (RII) for each factor as follows: ∑W RII = (0< RII <1) A* N Where: W – is the response weight given to each attribute by the personnel and range vary from 1 to 5, (where “1” is “very low importance” and “5” is “very high importance”); A – is the highest weight (i.e. 5 in this case) and; N – is the overall number of stakeholders. Table -1: significant Causes of delay by RII Method Figure -1: significant Causes of delay by RII Method Table 5.2 : Ranking of group of causes of delay by All three Parties 0.8510.846 0.811 0.7940.7890.7770.7710.7660.7540.743 0.68 0.7 0.72 0.74 0.76 0.78 0.8 0.82 0.84 0.86 Reworkdueto… Originalcontract… Shortageoflabor Inadequate… Difficultiesin… Delayinprogress… Shortageof… 1 2 3 4 5 6 7 8 9 10 RII RII No. Critical Cause of delay RII 1 Rework due to errors during construction 0.851 2 Inadequate planning and scheduling of project by contractor 0.846 3 Original contract duration is too short 0.811 4 Delay in material delivery 0.794 5 Shortage of labour 0.789 6 Poor site management and supervision by the contractor 0.777 7 Inadequate contractor’s work experience 0.771 8 Difficulties in financing project by contractor 0.766 9 Delay in progress payment by owner 0.754 10 Shortage of equipment 0.743 S.NO. No.of Groups OWNE R RII R A N K Contra ctor RII R A N K Consul tant RII R A N K 1. contracto r 0.78 1 0.59 8 0.77 1 2. consultan t 0.64 5 0.71 4 0.51 8 3. project 0.66 4 0.79 1 0.72 2 4. owner 0.50 7 0.76 2 0.56 7 5. labour 0.68 3 0.72 3 0.68 3 6. Design 0.55 6 0.60 7 0.65 5 7. material 0.71 2 0.61 6 0.62 6 8. equipme nt 0.48 8 0.65 5 0.66 4
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1329 Figure-2 : Ranking of group of causes of delay by All three Partie 6. Conclusion The first step in reducing the delays in infrastructure construction project is to understand the root causes of the delay. This results provide a listing of root causes and issues that are directly responsible for most infrastructure construction project delays. Additionally, it is found that fundamental principles must be adopted before significant improvements can be made. The data were collected from the following construction Infrastructure companies. According to results, some factors have found that which are highly effected on the construction projects Rework due to mistakes, Inadequate planning & scheduling of project by contractor, Original contract duration is too short, Delay in material delivery on site, Shortage of labour , Poor site management & supervision by contractor, Inadequate contractor’s experience, Difficulties in financing by contractor, Shortage of equipment, Delay in progress payment by owner . 7.Recommendation The following points can be recommended by all parties in order to minimize and control delays in construction projects: 7.1. Contractor’s Should Consider The Following Factors Shortage and low productivity of labor: enough number of labors should be assigned and motivated to improve productivity. Financial and cash flow problems: contractor should manage his financial resources and plan cash flow by utilizing progress payment. 7.2. Consultant’s Should Look To The Following Factors Reviewing and approving design documents any delay caused by the consultant engineer in checking, reviewing and approving the design submittals prior to construction phase, could delay the progress of the work; Inflexibility: Consultants should be flexible in evaluating contractor works. Compromising between the cost and high quality should be considered. 7.3. Owner’s Should Give Special Attention To The Following Factors Pay progress payment to the contractor on time because it impairs the contractor’s ability to finance the work. Reduce the frequent changing in orders during construction to neglect delays. 8.REFRENCES 1. Hemanta Doloi, Anil Sawhney, K.C.Iyer, Sameer Rentala (2012).Analysing factors affecting daelays in Indian construction projects International journal of project management 30,479-489 2. Mamta Rajgor, Chauhan Paresh, Patel Dhruv, Panchal Chirag. RII&IMPI: Effective techniques for finding delay in construction projects. International Research Journal of Engineering&TechnologyVolume:03.Issue:01|JAN- 2016. 3.YawFrimpong,JacobOluwoye,LynnCrawford.Causes of delay and cost overruns in construction of ground water projects in developing countries in Ghana International journal of project management21(2013),321-326. 4.Siddesh K Pai,Mr.J.Raj Bharath. Analysis of critical causes of Delay in Indian Infrastructure Projects. 0.78 0.64 0.66 0.5 0.68 0.55 0.71 0.48 0.59 0.71 0.790.76 0.72 0.60.61 0.65 0.77 0.51 0.72 0.56 0.680.650.62 0.66 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 3 5 7 9 11 13 15 17 OWNER RII Contractor RII Consultant RII
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1330 International journal of Innovative Research & Development VOL2:Issue:March-2013. 5.Mega Desai, Rajiv Bhatt. Critical causes of Delay in Residential Construction Projects: Case Study of Central Gujarat Region in India. .International Research Journal of Engineering Trends and Technology Volume:4.Issue:4|April-2013 6.Murat Gunduj, Yasemin Nielsen, Mustafa Ozdemir. Quantification of Delay Factors Using the RII Method for Construction Projects in Turkey. Journal of Management in Engineering(2013),29(2):133-139.