SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7463
“EFFECT OF PRE-PLANNING IN HIGH RISE BUILDING FOR TIME
MANAGEMENT”
Mr. Akash D. Mundaware1, Prof. Dr. Arunkumar Dwivedi2, Prof. Harshita Ambre3
1M. Tech Research Scholar, Department of Civil Engineering (Construction Management),
Sandip University, SOET, Nashik, Maharashtra, India
2Prof.Dr.Arunkumar Dwivedi, Dean, Department of Civil Engineering (Construction Management),
Sandip University, SOET, Nashik, Maharashtra, India
3 Prof.Harshita Ambre, Assistant Professor, Department of Civil Engineering (Construction Management),
Sandip University, SOET, Nashik, Maharashtra, India
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - In India the Construction industryisonethemost
integral industry and it also forms a vital roleincontributing
toithe economy growth of the country. People of wideirange
ranging from skilled , unskilled to semi skilled are provided
employment by this industry as this industry is very labor
intensive .Despite this thereihas been
manyireportediaccidents , iill health problems and damage
cause to the Environment during theexecutionphasesiof the
constructioniworks . Knowledge however for the
management Plan for the Health , Safety. And the
Environment Management Plan is limitediin the Industry.
Theiaimiof the study is therefore aimed at finding the plans
to be followed in real life at the sites , to find and analyze the
deficiencies and also to suggest ways to mitigate them in the
context of the Indian Industry.
While meeting the objective of the study for my case study
two metro projects were studied onetheDelhimetroproject
and the other one being the Mumbai Metro project . Boththe
projects were studied for their environment management
plans which is being followed and the mitigation methods
adapted by the authorities .The studyiaims at going through
the literature reviews and to understand and see that
whether the facts mentioned are being followediat the site
and what are theithings which is beingilacked.
Keyword’s: PPP, BOT, COJiiiii
1. INTRODUCTION
Studies have shown that planning have an important role in
both initial phase of construction project & during execution
phase also. All construction projects are unique in nature so
we have to plan for uncertainties that are part of
construction projects. Pre-planning have become very
crucial as construction projects have become more complex
in nature and the sector have become more dynamic (Laufer
et al 1994). The growth in research and development have
given architects, structural consultants the freedomtocome
with very unique and astonishing and marvelous
construction models that catch the eyes of every individual.
The architects and consultants have transformed their
canvassed ideas into real time feasible construction models
converging into lifestyle habitat for people. iiiiiiiii
Common pattern that is observed in all high rise building
projects is cost overrun, time overrun, delayed clearance of
running account bills, failure to meet deadlines and
milestones. Many researches claim to address solving of
these problems by having a proper and detailed planning of
construction projects prior to beginning with execution of
construction work. Many projects have failed to see thelight
that they have been crafted by the stakeholders since they
failed to look at the pre-planning aspect before starting of
project work.
Globally various types of public-private partnerships(PPPs)
have been practiced in infrastructure development in order
to achieve the best results. The private funding in the BOT
arrangement not only reduces the strain on the
government/public pocket but also facilitates more
innovations by harnessing the skills, technologies, and
operational efficiency of the private sector. This
arrangement also reduces the risks and responsibilities of
the public sector as most of these are transferred to the
private sector. Many projects in a broad range of sectors
have been successfully developed through BOT with
significantly increased value to the outputs. These include
roads, bridges, ports, airports, and railways; power, water
supply, and waste disposal systems; telecommunication
networks and other services of information technology;
schools, hotels, hospitals, prisons, and even military
facilities. Though the BOT model for financing of the
infrastructure has been a boomfortheconstructionindustry
and the developing countries lacking funds, various
problems have been encountered in worldwide
infrastructure development through BOT. One major
problem that has been encountered is the slow progress in
the execution of BOT. There are other serious problems like
legal, political, environmental, etc. that have even led to
failures of BOT projects worldwide.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7464
1.1 .CAUSES AND EFFECTS OF DELAYS
20 causes of delays categorized into 2 different groups were
found in order to make a questionnaire survey with the
respective participants (contractors, owners, consultants
and others) of Indian constructionindustryandalso8effects
of delays were observed. The number of causes and effects
are given below. iiii
1.1.1. Causes of Delayii
Group-A Owner Contributed Factors
1. Delay in progress payments
2. Delay to furnish and deliver the site
3. Change orders (plan/design) & extra orders by owner
during construction
4. Late in revising and approving design documents
5. Delay in approving shop drawings and sample materials
6. Slowness in decision-making process
7. Conflicts between joint-ownership of the project
8. Suspension of work by owner
9. Owners lack of experience and involvement
10. Bureaucracy in client's organization
11. Unavailability of professional construction management
(i.e. consultant)
Group-B Contractor Contributed Factorsii
12. Difficulties in financing project/insolvency
13. Conflicts in sub-contractor’s schedule during execution
14. Rework due to errors during construction
15. Conflicts between contractor and other participants
16. Ineffective & inadequate earlyplanningandschedulingof
project
17. Implementing improper & obsolete construction
methods
18. Fraudulent practices and kickbacks
19. Negotiations and obtaining of contracts
20. Inadequate contractor's work & experience & also poor
risk management and ignorance.
1.2. Effects of Delay
1. Time overrun
2. Much reduction in profit for the contractor due to cost
overrun
3. Non-productivity loss for the owner due to extended stay
of construction phase
4. Distrust with contractor and damage for the company’s
reputation
5. Distrust insists the owner to delay the progress payment
which leads to contractor’s cash-flow
Problem
6. Dispute, Arbitration or Litigation b/w the participants of
the project
7. Abandonment of project
8. Difficult in improving the market value of the contractor’s
company.
1.3 Objective
The purpose of the study is to describe importance of pre-
planning for high rise buildings& toidentifyparametersthat
require major focus for successful completion of Project. To
identify possible remedial solution for the most influencing
factor and the major factors for time overrun.
2. Literature Review
Planning for a construction project is very unique, complex
and challenging process that requires a detailed
considerations of all the parameters that are part and parcel
of a project lifecycle. Meaning of planning as per different
stakeholders is different and correct. For example; material
flow plan, logistics plan, weekly meetingplanning,resources
planning, communication flow plan and others (Friblick,
Olsson, & Reslow, 2009). However planning for a project can
be referred to as process of identifying all the processes and
activities that are required to be performed correctly in a
certain pattern or sequential manner to meet the end
desired result (Hammadi & Nawab, 2016). The client and
contractor in their own approach first of all visualize what
the end product or project delivery would look like,
consisting of different features and uses and facilities,
leading to a chalk out plan to identify all activities and tasks
that would be performed or followedinsequential fashionto
reach the final outcome, the desired end project or goal. It
also includes working out the timerequirementforactivities
along with their resource estimates for same (Friblick et al.,
2009).
3. METHODOLOGYi
Initially literature review and live project case study helped
to find out factors causing delayofconstructionprojects(pre
planning). Thisstudyhelped inipreparationofquestionnaire
survey with the help of experts and other industry guides.
The category of people approached for the survey were
Project managers, Senior Engineers, Project Engineers,
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7465
Planning engineers, General managers, owners and
contractors with goodi work experience. Relative
importance of these identified causes with respect to Indian
construction scenario was found out. ii
4. Data collection
4.1Case Study 1:
Name of Project: City of Joy (COJ)
Project Description: 16 Towers of 36 story each with high
end amenities.
Cost of Project: 1250 crore
Name of Client: A JV between Neptune, Nirmal & Lifestyle
Group
Name of Contractor: ABC
Consultants: Hafeez Contractor, Sterling, Buro Happold
Start Date of Project: March 1998
Current Status: work is halted (Construction of 2 towers
Triumph & Thrill with Built up Area of 3.2 lac sqft with
Mivan Formwork began in 2008, reached 28th floor till date)
Causes of Delay:
a) Financial problems of the Client.
b) Delay in statutory approvals.
c) Frequent changes in design.
d) Delay and Error in issuing of drawings.
e) Faulty drawings documentation.
f) Termination of main contractor and its due
litigation. i
g) Logistics error (7 wastage’s occurring).
h) Modification in shutter design.
i) Delay due to non-compliance of Govt. Norms.
j) Shortage of labor.
k) Shortage of Equipment’s and Machineries.
l) Shortage of Material.
m) Rework due to design changes.
4.2Case Study 2:
Name of Project: US Open Apartments
Project Description: 5 Towers of 40 story each with high
end amenities.
Cost of Project: 450 Cr.
Name of Client: XYZ Group
Name of Contractor: ABC
Consultants: Hafeez Contractor, J+W Constultant, Buro
Happold and others
Start Date of Project: Feburary 2011
Current Status: Towers yet to be completed (work for 2 in
progress and 3 yet to start). Causes of Delay:
a) Financial problems of the Client.
b) Delay in statutory approvals.
c) Slow decision making.
d) Frequent changes in design.
e) Error in drawings.
f) Delay in design and delivery of shuttering
formwork.
g) Theft of shuttering material.
h) Incompatible client team.
i) Failure of QC system (delay in closure of NCRs)
j) Logistics error (7 wastage’s occurring)
k) Modification in shutter design.
l) Delay due to non-compliance of Govt. Norms.
m) Shortage of labor.
n) Inefficient use of tower crane.
o) Shortage of equipment’s and machineries.
p) Shortage of material.
q) Rework due to design changes.
4.3. Case Study 3:
Name of Project: ABC Future X.
Project Description: 3 Tower of 60 (2 basement +3
podium) story each
Cost of Project: 500 crore
Name of Client: MACE Developers
Name of Contractor: XYZ
Consultants: Naik & Associates, Rahimtulla Constultant,
Arup, Kapadia Architects.
Start Date of Project: January 2010
Current Status: Current status work is halted (reached 45th
Floor).
Causes of Delay:
a) Frequent changes in Scope.
b) Financial problems of the contractor.
c) Delay in statutory approvals (delay in CC, Tree
Authority).
d) Delay in approvals of GFC Drawings.
e) Poorly maintained Project Schedule.
f) Slow decision making (Approvals of formwork
design, RFIs).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7466
g) Frequent changes in design (swimming pool being
introduced @ 8th Floor).
h) Error in drawings (in complete detailing).
i) Incompatible contractor team.
j) Modification in shutter design.
k) Delay due to non-compliance of Govt. Norms.
l) Shortage of labor.
m) Shortage of Equipment’s and Machineries.
n) Shortage of Material (Reebol shuttering oil, MS
nails, Hessian cloth and others).
o) Rework due to design changes.
Of the three cases studied, it was found that the financial
condition of client and contractor, delayinissueofdrawings,
design changes, Frequent changes in scope of work, delay in
statutory approvals, slow decision making process by client
as well as contractor, poorly drafted project schedule, error
in drawings, Modification of shutter scheme, changes in due
non-compliance of Govt. Norms, shortage of material,
equipment’s and machines, weakly drafted Quality
Assurance and Quality Control policy,inefficientuseoftower
crane, wrong estimate of cost of construction and time,
improper site planning, weather conditions, other external
influences, lack of experience of contractor, low bidding by
contractor, irregular supply of water and electricity,
equipment breakdown, rework duechangesindesignor bad
quality work, inefficient client andcontractorteam,shortage
of labor and others as major problems.
From the list of number of factors for delay, few were
identified as reasons due failure of pre-planning as per
discussions with industry experts and professionals. They
were as follows:
Client related factors
a) Design changes (changing scope)
b) Site Handover
c) Type of Contract
d) Logistics and Traffic Mgmt.
e) Delay in issue of drawings
f) Risk Identification
g) Statutory approvals
h) Coordination with and between consultants
i) Inefficient resources planning
j) Cash flow of Client
Contractor related factors
a) Locating temporary facilities
b) Process of Supply chain and Material mgmt.
c) Inefficient resources planning
d) Cash flow of contractor
e) Ineffective use of Tower crane
f) QA/QC plan
g) Safety plan
h) Availability of raw material
i) Risk identification
j) Process of execution
4.4. Questionnaire Survey
The survey carried out was divided into two sections. One
being about respondent’s demographic information, which
consisted of name, experience and location. Second being
responses for 20 questions that were classified into two
major factors causing time overrun. The question were
based on literature review and study of live projects. The
common factors were included in the survey questionnaire.
The various factors affecting the time for completion of
construction projects were rated on scale of five points.
Where 1 expressed Very Low Impact and 5 expressed Very
High Impact. The likert scale is being used as it is easy to
construct, makes collection of data easier to collect and
interpret. The respondents weresupposedtoratetheirscore
on this range. By random sampling statistical techniques,50
questionnaires were sent to industry professionals through
mail and other means. Only 36 number of respondents
responded to the survey. Though the sample size is small,
but the quality of responses is considered to be high due
feedback from experienced professionals with clear
understandings of the survey questions.
4.4.1. Demographic Information
The demographic profile of respondents is as follow in
below.
Table 1: Demographic Profile of Respondents
Position in
organization
Number
of sample
received
Number
of sample
for this
position
Percentage
of sample
for this
position
General
Manager
36 5 13.89 %
Project
Manager
36 10 27.78 %
Planning
Engineer
36 4 11.11 %
Project
Engineer
36 7 19.44 %
Senior
Engineer
36 4 11.11 %
Site Engineer 36 6 16.67 %
A total of 36 responses were received, that represented
about 72 % as the response rate. According to survey the
demographic characteristics showed about 13.89% (n=5)
responses were received from General Manager, 27.78%
(n=10) were PM, 11.11% (n=4) were Planning Engineer,
19.44% (n=7) were Project Engineer, 11.11% (n=4) were
Senior Engineer, 16.67% (n=6) were Site Engineer.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7467
5. Data Analysis
5.1.1Reliability Test
To calculate reliability for the five perspective of
balanced questionnaire responses, we used the internal
consistency method by Nunnally 1978. It is used to calculate
cronbach alpha co-efficient. Cronbach’s alpha is the most
sort out measure to internal consistency that is reliability. It
is widely used in questionnaire survey where likert scale is
used and one needs to find whether the scale is reliable.
Since the cronbach alpha value for the questionnaire survey
done is 0.815.
5.1.2. Relative Importance Index (RII)
We have used relative importance index to
determine the relative importance of the various causes of
delays. The RII method is used to determineintheresponses
which factors where used more frequently duringformation
of Project.
RII for various factors are calculated as per the standard
formula:
RII= (∑ W) / (A*N)
Where RII = relative importance index
∑ W= weighting given to each factor by respondents (1-5
here)
A= highest weight (5 in this case)
N= Total number of respondents (36 in this case)
Table 2: Impact of Client on Timely Completion of Project
Impact of Client on
Timely Completion of
Project
RII RANK
Delay in issuing of
drawings
0.783 3
Site Handover 0.583 8
Type of Contract 0.444 10
Logistics and Traffic Mgmt. 0.711 6
Design changes 0.788 2
Risk Identification 0.561 9
Statutory approvals 0.778 4
Coordination with and
between consultants
0.678 7
Inefficient resources
planning
0.744 5
Table 3: Impact of Contractor on Timely completion of
project
Impact of Contractor on
Timely Completion of
Project
RII RANK
Availability of Raw
Material and Labor
0.757 4
Locating Temporary
Facilities
0.711 6
QA/QC Plan 0.65 7
Process of Supply Chain&
Material Mgmt.
0.567 9
Safety Plan 0.512 10
Inefficient Resource
Planning
0.750 5
Risk Identification 0.568 8
Cash Flow of Contractor 0.810 1
Process of Execution 0.785 3
Effective use of Tower
Crane
0.794 2
6. CONCLUSION
This study tried to identify the impact ofpreplanninginhigh
rise building for time management. A semi structured
questionnaire survey was made with help of literature
review. The study tried to fill in gaps for critical preplanning
factors that affect the timely completionofhigh rise building.
These factors would help the strategist to make policies and
contracts which will help to curb the time overrun for
projects, thereby improving the quality of construction
business by improved performances.
7. Recommendation
Recommendations for Client and Contractor related
Impact factor are suggested.
i) Pre-Construction planning should be given due
importance and proper timeframework should
be assigned to it in a project. It helps in
covering all the uncertainties that the project
could face and proper mitigation plan can be
put in place. Depending on the scale of project,
even industry experts or construction
professional’s guidance can be taken. i
ii) Procurement schedule of different consultants
should be asked in advanced and timely follow
up should be practiced religiously. Scope of
project and required deliverables should
finalized before execution starts. Lean practice
of Integrated Project Deliveryshouldbeusedin
project. i
iii) Drawings should be issued on time as per
procurement schedule. Documentation of such
vital data should be kept in a central data
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7468
processing unit. Data management system can
be used as latest technology. It will help tokeep
track of all documentation process which
include submittals, transmittals, RFI’s and
others.
iv) Effective and efficient management of
equipment should be there in system. Daily
schedule of use of the lifting equipment’s
should be kept in place and to be followed and
each personnel involvedinprojectshouldknow
the schedule. Spare parts of important
equipment should be ordered along with
procurement of equipment. Even extra standby
equipment along with operator should be on
project site. The time which is wasted by
keeping machine idle during lunch break, can
be utilized fruitfully should be worked out
keeping all stakeholders in confidence.
v)Proper logistics plan along withtraffic management
which includes its timely up gradation as
project passes through different execution
phase should be planned in advance. It is
helpful in avoiding wastages onsite.
vi) Main contractor should appoint efficient sub-
contractor which is financially secured. He
should be capable both technically and
financially. Also government should facilitate
affordable loan to client, contractor and others
to give a boost to the construction sector.
vii) Client should have a clear cut orientation with
contractors, consultants so that changes in
scope can be avoided. Design provided by
consultants should be feasible as per site
parameters. Scheduling of project progress
should be such that all uncertainties and actual
progress that will be achieved should be the
basis of Scheduling for finalization of time
duration.
viii)Fortnightly meeting with all project coordinators
should be conducted where all design related
issues, RFI’s, design submittals and design
feasible issues to be discussed and decision to
taken. It will help in increasing the speed of
decision making thereby saving crucial project
time which is wasted due idle resources.
Last planner system should be used after
agreement between stakeholders so that
maximum output can be achieved with existing
set of resources, avoiding conflict.
ix) Flaws in drawings issued should tackled with
high priority. Sketch drawings to be issued, so
that time taken to revise and send the GFC
drawings won’t affect the project activities on
site. Idle time would be avoided.
x) If the project has lot of complexity like unique
design, then designing team to taken on board
should be suitable for it. The design contracts
should be awarded to experienced consultants
who can make design independently.
xi) On regular basis contractor should submit up-
dated schedule of material supply and should
be keep follow up with vendorstoknowcorrect
status of delivery of material so that effective
resource planning can be made.
xii) Client and contractor should have a strong
liaison team so that statutory approvals can be
obtained on time.
REFERENCES
i) Divakar, K., & Subramanian, K. (2009). Critical Success
Factors in the Real-Time Monitoring of Construction
Projects. ResearchJournalof AppliedScience, Engineering
and Technology, 1(2), 35–39.
ii) Eriksson, P. E. (2010). Partnering: what is it, when
should it be used, and how should it be implemented?
Construction Management and Economics, 28(9), 905–
917. https://doi.org/10.1080/01446190903536422.
iii) Friblick, F., Olsson, V., & Reslow, J. (2009). Prospects for
implementing Last Planner in the constructionindustry.
Proc. 17th Ann. Conf. of the Int’l. Group for Lean
Construction, 197–206.
iv) Gibson, GE, & Cho, C. (2001). Building project scope
definition using definition rating index. Journal of
Architectural Engineering, 7(7), 115–125.
v) Gibson, GE, Wang, YR, Cho, CS & Pappas, M. (2006).
“What is preproject planning, anyway?” Journal of
Management in Engineering, 22(1), 35–42.
vi) Hammadi, S. Al, & Nawab, M. S. (2016). Project Time
Overruns in Saudi Arabian Con-struction Industry, 7(2),
555–560.
vii) Hendrickson, Chris, and T. A. (1998). Project
Management for Construction.
viii) Kerzner, H. (2007). Achieving Project Management
Excellence.
ix) Larsen, J. K. (2015). Streamlining Publicly Funded
Construction Projects.
https://doi.org/10.5278/VBN.PHD.ENGSCI.00020.
x) Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D.
(2016). Factors Affecting Schedule Delay, Cost Overrun,
and Quality Level in Public Construction Projects.
Journal of Management in Engineering, 32(1), 4015032.
https://doi.org/10.1061/(ASCE)ME.1943-
5479.0000391
xi) Laufer, A. & Tucker, R. (1987). Is construction planning
really doing its job? Construction Management and
Economics, London.
xii) Laufer et al 1994.
xiii) PMI. (2013). A Guide to the Project Management Body of
Knowledge. In (5a ed.). Pennsylvania: Project
Management Institute, Inc. (Vol. 13).
https://doi.org/10.1016/02637863(95)00006-C

More Related Content

What's hot

Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
IRJET Journal
 
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET Journal
 
Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...
Mohammad Lemar ZALMAİ
 
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Charles
 
Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...
Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...
Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...
Project Controls Expo
 
Barriers to Implement Lean Principles in the Indian Construction Industry
Barriers to Implement Lean Principles in the Indian Construction IndustryBarriers to Implement Lean Principles in the Indian Construction Industry
Barriers to Implement Lean Principles in the Indian Construction Industry
AM Publications
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
SANJEEV Wazir
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
vivatechijri
 
Quy trình BIM
Quy trình BIMQuy trình BIM
Quy trình BIM
Nguyen Manh Tuan
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in Iraq
Dr. Amarjeet Singh
 
The impact of ict in quantity surveying
The impact of ict in quantity surveyingThe impact of ict in quantity surveying
The impact of ict in quantity surveying
Solomon Rex Borchers
 
S7 p5 milindcaneus
S7 p5 milindcaneusS7 p5 milindcaneus
S7 p5 milindcaneustough587
 
Safety implementation in BIM
Safety implementation in BIMSafety implementation in BIM
Safety implementation in BIM
Zain Juratli
 
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...Tim Christ Executive Leadership
 
BIM Presentation Germany R3
BIM Presentation Germany R3BIM Presentation Germany R3
BIM Presentation Germany R3Clive Walsh
 
Salah Yousif, module 1, introduction to bim and the business case of bim
Salah Yousif, module 1, introduction to bim and the business case of bimSalah Yousif, module 1, introduction to bim and the business case of bim
Salah Yousif, module 1, introduction to bim and the business case of bim
Salah Yousif
 
Process Modeling with IDEF 0
Process Modeling with IDEF 0Process Modeling with IDEF 0
Process Modeling with IDEF 0
Mandar Trivedi
 
Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...
Ionel GRECESCU
 
CAD and BIM Outsourcing Services
CAD and BIM Outsourcing ServicesCAD and BIM Outsourcing Services
CAD and BIM Outsourcing Services
theaecassociates1
 

What's hot (20)

Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
 
Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...Implementation of-building-information-modeling-in-turkish-government-sector-...
Implementation of-building-information-modeling-in-turkish-government-sector-...
 
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
Adeoye Preye charles qsv/12/0227 term paper on Risk involved in highway const...
 
Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...
Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...
Project Controls Expo, 18th Nov 2014 - "From Cost Plan To Bid Evaluation To C...
 
Barriers to Implement Lean Principles in the Indian Construction Industry
Barriers to Implement Lean Principles in the Indian Construction IndustryBarriers to Implement Lean Principles in the Indian Construction Industry
Barriers to Implement Lean Principles in the Indian Construction Industry
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
 
Quy trình BIM
Quy trình BIMQuy trình BIM
Quy trình BIM
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in Iraq
 
The impact of ict in quantity surveying
The impact of ict in quantity surveyingThe impact of ict in quantity surveying
The impact of ict in quantity surveying
 
S7 p5 milindcaneus
S7 p5 milindcaneusS7 p5 milindcaneus
S7 p5 milindcaneus
 
Safety implementation in BIM
Safety implementation in BIMSafety implementation in BIM
Safety implementation in BIM
 
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
Christ_Santos_LiquidatedDamagesThePenaltyForFailingToAchieveTheImpossible_201...
 
BIM Presentation Germany R3
BIM Presentation Germany R3BIM Presentation Germany R3
BIM Presentation Germany R3
 
Salah Yousif, module 1, introduction to bim and the business case of bim
Salah Yousif, module 1, introduction to bim and the business case of bimSalah Yousif, module 1, introduction to bim and the business case of bim
Salah Yousif, module 1, introduction to bim and the business case of bim
 
BIM Report 3
BIM Report 3BIM Report 3
BIM Report 3
 
Process Modeling with IDEF 0
Process Modeling with IDEF 0Process Modeling with IDEF 0
Process Modeling with IDEF 0
 
Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...Lean Construction – Construction Process Integration framework, London Novemb...
Lean Construction – Construction Process Integration framework, London Novemb...
 
CAD and BIM Outsourcing Services
CAD and BIM Outsourcing ServicesCAD and BIM Outsourcing Services
CAD and BIM Outsourcing Services
 

Similar to IRJET- Effect of Pre-Planning in High Rise Building for Time Management

IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET Journal
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A Review
IRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
ijtsrd
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Sankalp Swarnkar
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET Journal
 

Similar to IRJET- Effect of Pre-Planning in High Rise Building for Time Management (20)

IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
20320140503023
2032014050302320320140503023
20320140503023
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A Review
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 

Recently uploaded (20)

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 

IRJET- Effect of Pre-Planning in High Rise Building for Time Management

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7463 “EFFECT OF PRE-PLANNING IN HIGH RISE BUILDING FOR TIME MANAGEMENT” Mr. Akash D. Mundaware1, Prof. Dr. Arunkumar Dwivedi2, Prof. Harshita Ambre3 1M. Tech Research Scholar, Department of Civil Engineering (Construction Management), Sandip University, SOET, Nashik, Maharashtra, India 2Prof.Dr.Arunkumar Dwivedi, Dean, Department of Civil Engineering (Construction Management), Sandip University, SOET, Nashik, Maharashtra, India 3 Prof.Harshita Ambre, Assistant Professor, Department of Civil Engineering (Construction Management), Sandip University, SOET, Nashik, Maharashtra, India ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - In India the Construction industryisonethemost integral industry and it also forms a vital roleincontributing toithe economy growth of the country. People of wideirange ranging from skilled , unskilled to semi skilled are provided employment by this industry as this industry is very labor intensive .Despite this thereihas been manyireportediaccidents , iill health problems and damage cause to the Environment during theexecutionphasesiof the constructioniworks . Knowledge however for the management Plan for the Health , Safety. And the Environment Management Plan is limitediin the Industry. Theiaimiof the study is therefore aimed at finding the plans to be followed in real life at the sites , to find and analyze the deficiencies and also to suggest ways to mitigate them in the context of the Indian Industry. While meeting the objective of the study for my case study two metro projects were studied onetheDelhimetroproject and the other one being the Mumbai Metro project . Boththe projects were studied for their environment management plans which is being followed and the mitigation methods adapted by the authorities .The studyiaims at going through the literature reviews and to understand and see that whether the facts mentioned are being followediat the site and what are theithings which is beingilacked. Keyword’s: PPP, BOT, COJiiiii 1. INTRODUCTION Studies have shown that planning have an important role in both initial phase of construction project & during execution phase also. All construction projects are unique in nature so we have to plan for uncertainties that are part of construction projects. Pre-planning have become very crucial as construction projects have become more complex in nature and the sector have become more dynamic (Laufer et al 1994). The growth in research and development have given architects, structural consultants the freedomtocome with very unique and astonishing and marvelous construction models that catch the eyes of every individual. The architects and consultants have transformed their canvassed ideas into real time feasible construction models converging into lifestyle habitat for people. iiiiiiiii Common pattern that is observed in all high rise building projects is cost overrun, time overrun, delayed clearance of running account bills, failure to meet deadlines and milestones. Many researches claim to address solving of these problems by having a proper and detailed planning of construction projects prior to beginning with execution of construction work. Many projects have failed to see thelight that they have been crafted by the stakeholders since they failed to look at the pre-planning aspect before starting of project work. Globally various types of public-private partnerships(PPPs) have been practiced in infrastructure development in order to achieve the best results. The private funding in the BOT arrangement not only reduces the strain on the government/public pocket but also facilitates more innovations by harnessing the skills, technologies, and operational efficiency of the private sector. This arrangement also reduces the risks and responsibilities of the public sector as most of these are transferred to the private sector. Many projects in a broad range of sectors have been successfully developed through BOT with significantly increased value to the outputs. These include roads, bridges, ports, airports, and railways; power, water supply, and waste disposal systems; telecommunication networks and other services of information technology; schools, hotels, hospitals, prisons, and even military facilities. Though the BOT model for financing of the infrastructure has been a boomfortheconstructionindustry and the developing countries lacking funds, various problems have been encountered in worldwide infrastructure development through BOT. One major problem that has been encountered is the slow progress in the execution of BOT. There are other serious problems like legal, political, environmental, etc. that have even led to failures of BOT projects worldwide.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7464 1.1 .CAUSES AND EFFECTS OF DELAYS 20 causes of delays categorized into 2 different groups were found in order to make a questionnaire survey with the respective participants (contractors, owners, consultants and others) of Indian constructionindustryandalso8effects of delays were observed. The number of causes and effects are given below. iiii 1.1.1. Causes of Delayii Group-A Owner Contributed Factors 1. Delay in progress payments 2. Delay to furnish and deliver the site 3. Change orders (plan/design) & extra orders by owner during construction 4. Late in revising and approving design documents 5. Delay in approving shop drawings and sample materials 6. Slowness in decision-making process 7. Conflicts between joint-ownership of the project 8. Suspension of work by owner 9. Owners lack of experience and involvement 10. Bureaucracy in client's organization 11. Unavailability of professional construction management (i.e. consultant) Group-B Contractor Contributed Factorsii 12. Difficulties in financing project/insolvency 13. Conflicts in sub-contractor’s schedule during execution 14. Rework due to errors during construction 15. Conflicts between contractor and other participants 16. Ineffective & inadequate earlyplanningandschedulingof project 17. Implementing improper & obsolete construction methods 18. Fraudulent practices and kickbacks 19. Negotiations and obtaining of contracts 20. Inadequate contractor's work & experience & also poor risk management and ignorance. 1.2. Effects of Delay 1. Time overrun 2. Much reduction in profit for the contractor due to cost overrun 3. Non-productivity loss for the owner due to extended stay of construction phase 4. Distrust with contractor and damage for the company’s reputation 5. Distrust insists the owner to delay the progress payment which leads to contractor’s cash-flow Problem 6. Dispute, Arbitration or Litigation b/w the participants of the project 7. Abandonment of project 8. Difficult in improving the market value of the contractor’s company. 1.3 Objective The purpose of the study is to describe importance of pre- planning for high rise buildings& toidentifyparametersthat require major focus for successful completion of Project. To identify possible remedial solution for the most influencing factor and the major factors for time overrun. 2. Literature Review Planning for a construction project is very unique, complex and challenging process that requires a detailed considerations of all the parameters that are part and parcel of a project lifecycle. Meaning of planning as per different stakeholders is different and correct. For example; material flow plan, logistics plan, weekly meetingplanning,resources planning, communication flow plan and others (Friblick, Olsson, & Reslow, 2009). However planning for a project can be referred to as process of identifying all the processes and activities that are required to be performed correctly in a certain pattern or sequential manner to meet the end desired result (Hammadi & Nawab, 2016). The client and contractor in their own approach first of all visualize what the end product or project delivery would look like, consisting of different features and uses and facilities, leading to a chalk out plan to identify all activities and tasks that would be performed or followedinsequential fashionto reach the final outcome, the desired end project or goal. It also includes working out the timerequirementforactivities along with their resource estimates for same (Friblick et al., 2009). 3. METHODOLOGYi Initially literature review and live project case study helped to find out factors causing delayofconstructionprojects(pre planning). Thisstudyhelped inipreparationofquestionnaire survey with the help of experts and other industry guides. The category of people approached for the survey were Project managers, Senior Engineers, Project Engineers,
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7465 Planning engineers, General managers, owners and contractors with goodi work experience. Relative importance of these identified causes with respect to Indian construction scenario was found out. ii 4. Data collection 4.1Case Study 1: Name of Project: City of Joy (COJ) Project Description: 16 Towers of 36 story each with high end amenities. Cost of Project: 1250 crore Name of Client: A JV between Neptune, Nirmal & Lifestyle Group Name of Contractor: ABC Consultants: Hafeez Contractor, Sterling, Buro Happold Start Date of Project: March 1998 Current Status: work is halted (Construction of 2 towers Triumph & Thrill with Built up Area of 3.2 lac sqft with Mivan Formwork began in 2008, reached 28th floor till date) Causes of Delay: a) Financial problems of the Client. b) Delay in statutory approvals. c) Frequent changes in design. d) Delay and Error in issuing of drawings. e) Faulty drawings documentation. f) Termination of main contractor and its due litigation. i g) Logistics error (7 wastage’s occurring). h) Modification in shutter design. i) Delay due to non-compliance of Govt. Norms. j) Shortage of labor. k) Shortage of Equipment’s and Machineries. l) Shortage of Material. m) Rework due to design changes. 4.2Case Study 2: Name of Project: US Open Apartments Project Description: 5 Towers of 40 story each with high end amenities. Cost of Project: 450 Cr. Name of Client: XYZ Group Name of Contractor: ABC Consultants: Hafeez Contractor, J+W Constultant, Buro Happold and others Start Date of Project: Feburary 2011 Current Status: Towers yet to be completed (work for 2 in progress and 3 yet to start). Causes of Delay: a) Financial problems of the Client. b) Delay in statutory approvals. c) Slow decision making. d) Frequent changes in design. e) Error in drawings. f) Delay in design and delivery of shuttering formwork. g) Theft of shuttering material. h) Incompatible client team. i) Failure of QC system (delay in closure of NCRs) j) Logistics error (7 wastage’s occurring) k) Modification in shutter design. l) Delay due to non-compliance of Govt. Norms. m) Shortage of labor. n) Inefficient use of tower crane. o) Shortage of equipment’s and machineries. p) Shortage of material. q) Rework due to design changes. 4.3. Case Study 3: Name of Project: ABC Future X. Project Description: 3 Tower of 60 (2 basement +3 podium) story each Cost of Project: 500 crore Name of Client: MACE Developers Name of Contractor: XYZ Consultants: Naik & Associates, Rahimtulla Constultant, Arup, Kapadia Architects. Start Date of Project: January 2010 Current Status: Current status work is halted (reached 45th Floor). Causes of Delay: a) Frequent changes in Scope. b) Financial problems of the contractor. c) Delay in statutory approvals (delay in CC, Tree Authority). d) Delay in approvals of GFC Drawings. e) Poorly maintained Project Schedule. f) Slow decision making (Approvals of formwork design, RFIs).
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7466 g) Frequent changes in design (swimming pool being introduced @ 8th Floor). h) Error in drawings (in complete detailing). i) Incompatible contractor team. j) Modification in shutter design. k) Delay due to non-compliance of Govt. Norms. l) Shortage of labor. m) Shortage of Equipment’s and Machineries. n) Shortage of Material (Reebol shuttering oil, MS nails, Hessian cloth and others). o) Rework due to design changes. Of the three cases studied, it was found that the financial condition of client and contractor, delayinissueofdrawings, design changes, Frequent changes in scope of work, delay in statutory approvals, slow decision making process by client as well as contractor, poorly drafted project schedule, error in drawings, Modification of shutter scheme, changes in due non-compliance of Govt. Norms, shortage of material, equipment’s and machines, weakly drafted Quality Assurance and Quality Control policy,inefficientuseoftower crane, wrong estimate of cost of construction and time, improper site planning, weather conditions, other external influences, lack of experience of contractor, low bidding by contractor, irregular supply of water and electricity, equipment breakdown, rework duechangesindesignor bad quality work, inefficient client andcontractorteam,shortage of labor and others as major problems. From the list of number of factors for delay, few were identified as reasons due failure of pre-planning as per discussions with industry experts and professionals. They were as follows: Client related factors a) Design changes (changing scope) b) Site Handover c) Type of Contract d) Logistics and Traffic Mgmt. e) Delay in issue of drawings f) Risk Identification g) Statutory approvals h) Coordination with and between consultants i) Inefficient resources planning j) Cash flow of Client Contractor related factors a) Locating temporary facilities b) Process of Supply chain and Material mgmt. c) Inefficient resources planning d) Cash flow of contractor e) Ineffective use of Tower crane f) QA/QC plan g) Safety plan h) Availability of raw material i) Risk identification j) Process of execution 4.4. Questionnaire Survey The survey carried out was divided into two sections. One being about respondent’s demographic information, which consisted of name, experience and location. Second being responses for 20 questions that were classified into two major factors causing time overrun. The question were based on literature review and study of live projects. The common factors were included in the survey questionnaire. The various factors affecting the time for completion of construction projects were rated on scale of five points. Where 1 expressed Very Low Impact and 5 expressed Very High Impact. The likert scale is being used as it is easy to construct, makes collection of data easier to collect and interpret. The respondents weresupposedtoratetheirscore on this range. By random sampling statistical techniques,50 questionnaires were sent to industry professionals through mail and other means. Only 36 number of respondents responded to the survey. Though the sample size is small, but the quality of responses is considered to be high due feedback from experienced professionals with clear understandings of the survey questions. 4.4.1. Demographic Information The demographic profile of respondents is as follow in below. Table 1: Demographic Profile of Respondents Position in organization Number of sample received Number of sample for this position Percentage of sample for this position General Manager 36 5 13.89 % Project Manager 36 10 27.78 % Planning Engineer 36 4 11.11 % Project Engineer 36 7 19.44 % Senior Engineer 36 4 11.11 % Site Engineer 36 6 16.67 % A total of 36 responses were received, that represented about 72 % as the response rate. According to survey the demographic characteristics showed about 13.89% (n=5) responses were received from General Manager, 27.78% (n=10) were PM, 11.11% (n=4) were Planning Engineer, 19.44% (n=7) were Project Engineer, 11.11% (n=4) were Senior Engineer, 16.67% (n=6) were Site Engineer.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7467 5. Data Analysis 5.1.1Reliability Test To calculate reliability for the five perspective of balanced questionnaire responses, we used the internal consistency method by Nunnally 1978. It is used to calculate cronbach alpha co-efficient. Cronbach’s alpha is the most sort out measure to internal consistency that is reliability. It is widely used in questionnaire survey where likert scale is used and one needs to find whether the scale is reliable. Since the cronbach alpha value for the questionnaire survey done is 0.815. 5.1.2. Relative Importance Index (RII) We have used relative importance index to determine the relative importance of the various causes of delays. The RII method is used to determineintheresponses which factors where used more frequently duringformation of Project. RII for various factors are calculated as per the standard formula: RII= (∑ W) / (A*N) Where RII = relative importance index ∑ W= weighting given to each factor by respondents (1-5 here) A= highest weight (5 in this case) N= Total number of respondents (36 in this case) Table 2: Impact of Client on Timely Completion of Project Impact of Client on Timely Completion of Project RII RANK Delay in issuing of drawings 0.783 3 Site Handover 0.583 8 Type of Contract 0.444 10 Logistics and Traffic Mgmt. 0.711 6 Design changes 0.788 2 Risk Identification 0.561 9 Statutory approvals 0.778 4 Coordination with and between consultants 0.678 7 Inefficient resources planning 0.744 5 Table 3: Impact of Contractor on Timely completion of project Impact of Contractor on Timely Completion of Project RII RANK Availability of Raw Material and Labor 0.757 4 Locating Temporary Facilities 0.711 6 QA/QC Plan 0.65 7 Process of Supply Chain& Material Mgmt. 0.567 9 Safety Plan 0.512 10 Inefficient Resource Planning 0.750 5 Risk Identification 0.568 8 Cash Flow of Contractor 0.810 1 Process of Execution 0.785 3 Effective use of Tower Crane 0.794 2 6. CONCLUSION This study tried to identify the impact ofpreplanninginhigh rise building for time management. A semi structured questionnaire survey was made with help of literature review. The study tried to fill in gaps for critical preplanning factors that affect the timely completionofhigh rise building. These factors would help the strategist to make policies and contracts which will help to curb the time overrun for projects, thereby improving the quality of construction business by improved performances. 7. Recommendation Recommendations for Client and Contractor related Impact factor are suggested. i) Pre-Construction planning should be given due importance and proper timeframework should be assigned to it in a project. It helps in covering all the uncertainties that the project could face and proper mitigation plan can be put in place. Depending on the scale of project, even industry experts or construction professional’s guidance can be taken. i ii) Procurement schedule of different consultants should be asked in advanced and timely follow up should be practiced religiously. Scope of project and required deliverables should finalized before execution starts. Lean practice of Integrated Project Deliveryshouldbeusedin project. i iii) Drawings should be issued on time as per procurement schedule. Documentation of such vital data should be kept in a central data
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7468 processing unit. Data management system can be used as latest technology. It will help tokeep track of all documentation process which include submittals, transmittals, RFI’s and others. iv) Effective and efficient management of equipment should be there in system. Daily schedule of use of the lifting equipment’s should be kept in place and to be followed and each personnel involvedinprojectshouldknow the schedule. Spare parts of important equipment should be ordered along with procurement of equipment. Even extra standby equipment along with operator should be on project site. The time which is wasted by keeping machine idle during lunch break, can be utilized fruitfully should be worked out keeping all stakeholders in confidence. v)Proper logistics plan along withtraffic management which includes its timely up gradation as project passes through different execution phase should be planned in advance. It is helpful in avoiding wastages onsite. vi) Main contractor should appoint efficient sub- contractor which is financially secured. He should be capable both technically and financially. Also government should facilitate affordable loan to client, contractor and others to give a boost to the construction sector. vii) Client should have a clear cut orientation with contractors, consultants so that changes in scope can be avoided. Design provided by consultants should be feasible as per site parameters. Scheduling of project progress should be such that all uncertainties and actual progress that will be achieved should be the basis of Scheduling for finalization of time duration. viii)Fortnightly meeting with all project coordinators should be conducted where all design related issues, RFI’s, design submittals and design feasible issues to be discussed and decision to taken. It will help in increasing the speed of decision making thereby saving crucial project time which is wasted due idle resources. Last planner system should be used after agreement between stakeholders so that maximum output can be achieved with existing set of resources, avoiding conflict. ix) Flaws in drawings issued should tackled with high priority. Sketch drawings to be issued, so that time taken to revise and send the GFC drawings won’t affect the project activities on site. Idle time would be avoided. x) If the project has lot of complexity like unique design, then designing team to taken on board should be suitable for it. The design contracts should be awarded to experienced consultants who can make design independently. xi) On regular basis contractor should submit up- dated schedule of material supply and should be keep follow up with vendorstoknowcorrect status of delivery of material so that effective resource planning can be made. xii) Client and contractor should have a strong liaison team so that statutory approvals can be obtained on time. REFERENCES i) Divakar, K., & Subramanian, K. (2009). Critical Success Factors in the Real-Time Monitoring of Construction Projects. ResearchJournalof AppliedScience, Engineering and Technology, 1(2), 35–39. ii) Eriksson, P. E. (2010). Partnering: what is it, when should it be used, and how should it be implemented? Construction Management and Economics, 28(9), 905– 917. https://doi.org/10.1080/01446190903536422. iii) Friblick, F., Olsson, V., & Reslow, J. (2009). Prospects for implementing Last Planner in the constructionindustry. Proc. 17th Ann. Conf. of the Int’l. Group for Lean Construction, 197–206. iv) Gibson, GE, & Cho, C. (2001). Building project scope definition using definition rating index. Journal of Architectural Engineering, 7(7), 115–125. v) Gibson, GE, Wang, YR, Cho, CS & Pappas, M. (2006). “What is preproject planning, anyway?” Journal of Management in Engineering, 22(1), 35–42. vi) Hammadi, S. Al, & Nawab, M. S. (2016). Project Time Overruns in Saudi Arabian Con-struction Industry, 7(2), 555–560. vii) Hendrickson, Chris, and T. A. (1998). Project Management for Construction. viii) Kerzner, H. (2007). Achieving Project Management Excellence. ix) Larsen, J. K. (2015). Streamlining Publicly Funded Construction Projects. https://doi.org/10.5278/VBN.PHD.ENGSCI.00020. x) Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), 4015032. https://doi.org/10.1061/(ASCE)ME.1943- 5479.0000391 xi) Laufer, A. & Tucker, R. (1987). Is construction planning really doing its job? Construction Management and Economics, London. xii) Laufer et al 1994. xiii) PMI. (2013). A Guide to the Project Management Body of Knowledge. In (5a ed.). Pennsylvania: Project Management Institute, Inc. (Vol. 13). https://doi.org/10.1016/02637863(95)00006-C