SlideShare a Scribd company logo
1 of 10
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1736
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING
CONSTRUCTION PROJECT
Shreyash D.Desai1, Renuka R.Purohit2
1P.G Student(Construction Management), Department of Civil Engineering, Pimpri Chinchwad College of
Engineering, Nigdi, Pune, India
2 Assistant Professor, Department of Civil Engineering, Pimpri Chinchwad College of Engineering, Pune, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - One of the most frequent issues with residential
construction projects is delay. When work is completed after
the contracted or anticipated time frame, the project issaid to
be delayed. Projects can be delayed for a variety of causes,
including those caused by the client, the contractor, divine
intervention, or a third party. They may happen alone or in
conjunction with other delays, early or late in the project's
development. Only after determining their reason can delays
be minimised. This study's goals were to identify the main
reasons for delays, classify and rank them to discover their
root causes, and then offer a workable remedy. Based on a
literature research and survey, this study was conducted. The
purpose of this work was to identify and assess the relative
importance of the significantfactorsinfluencing delaythrough
a questionnaire survey. To improve project performance and
reduce or eliminate delays, effective project planning,
controlling, and monitoring should be implemented.
Key words : Residential Construction delays, Delay Causes,
Relative Importance Index (R.I.I), Root cause analysis
1.INTRODUCTION
India's construction sector is expanding very quickly. There
are numerous projects underway in India right now with
important clients, but only 1 to 5 percent of them are
finished promptly. The remainder of the projects either lag
behind schedule or haven't been finished at all.
These projects are primarily the result of poor planning or
different circumstances throughout project planning and
implementation. This may be duetothefactthattheworking
environment differs from what the designer or planner had
anticipated, or it may be due to various obstacles,
uncertainties, or risks associated with the current activity
that are unknown to an amateur planner or engineer.
Both economically and politically, delays and cost overruns
have a big impact. The people and the economy must wait
longer than necessary for the provision of public goods and
services as a result of delays in project implementation. As a
result, delays reduce the economy's capacity for growth.
1.1 Problem Statement
Many factors might cause construction projects to be
delayed. On residential construction projects, there are
various sorts and categories of delays. When the causes of
delays are found, they can be minimised.
1.2 Objectives of study
1. To identify the factors that are generating delays in the
residential construction proSject
2. To find the impact of the identified factors on
construction delay.
3. To analyse delays for residential construction project.
4. To make suggestions for corrective measurestoreduce
project delays
1.3 Limitations
The study is restricted to a sample interview for
residential developments; infrastructure projects might
differ. A analysis of infrastructure development initiatives
might present a quite different image. Some restrictions
depend on the site's location in relation to other parts of
India. Additionally, the project's administrators typically
resist disclosing the data. Given the limited quantity of
resources in the city, more samples would provide a clearer
picture. Smaller projects experience less delays than larger
township projects, which would experience more serious
delays.
2. LITERATURE REVIEW
[1] The risk categories in this study by Rao Aamir Khan et al.
were ranked using the RII to identify the most significant
risks that result in project delay and mitigate them as soon
as possible. The study's conclusions were followed by
recommendations.
[2] In order to create prediction models for analysing how
these factors affect delay, Hemanta Doloi et alstudy.'s first
determined the crucial attributes that have the greatest
impact on delay in the Indian construction industry. The
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1737
foundation of this researchwasa questionnaireandin-depth
interviews.
[3] Ahmed El Sayed and colleagues look into the causes of
construction project delays in Bosnia and Herzegovina and
assess their importance. This study examines how
management software is used during the project planning
and execution phases, as well as how precisely inputs are
determined.
[4] The essential elements thatcontributetodelaysandtheir
effects on project completion were identified by M.P.
Venkatesh et al. More emphasisisplacedonresource-related
delays in the construction industry in this study. The
investigation that produced the results was conducted at
several ongoing and completed construction sites in the
context of India. The reasons were elicited from diverse
construction specialistsinvariousfirmsusinga standardised
questionnaire survey.
[5] By using the Relative Importance and Importance Index
technique, Ashish Chandu Pawar et al. identified the main
causes of delays, the effects of delays, and
methods/recommendations of minimising delays in
Residential Construction projects.
[6] From the perspectives of contractors, consultants, and
owners, M. E. Abd El-Razek et al[6] .'s analysis of
construction projects in Egypt foundtheprimary reasonsfor
delays.
[7] The most major causesof constructiondelayswerefound
by Omid Abbasi et al, who then classifiedandrankedthemto
identify the root causes of delays and offered a workable
remedy.
[8] Pei-Yuan Hsu et al.'s investigation of the elements
influencing schedule deviation in building projects helped
them comprehend the causal connections underlying the
delays. Fault Tree Analysis (FTA) is a well-known method
among the many root cause analysis techniques. FTA
investigates the series of circumstances that led to the issue
in-depth in order to determine its root cause.
3. METHODOLOGY
In order to determine the impact of several factors on delay
in the Indian construction sector, a questionnaire survey
approach has been used for this research, based on the
numerous overseas researchers previously mentioned. A
survey of industry experts representing different
stakeholders in construction projects in India was carried
out.
Following methodology was adopted:
Fig-1: Detailed Methodology
3.1 Identification of delay factors and sources
A significant step in ensuring the effectiveness of the
research is the identification of the study's critical qualities
and the creation of the questionnaire. There has already
been a significant amount of research done on the factors
that contribute to constructiondelays,andtheliterature also
has a collection of delay attributes that have undergone
extensive peer review. The important delay attributes
mentioned in the literature have been incorporated into the
questionnaire for this study. Technical staff in the building
industry were sent Google forms. Under five major
headings—manpower related, equipment related, material
related, design related, and authority related—a total of 23
delay features were found. Table 1 contains a list of the
qualities. Respondents were askedtorank thesignificanceof
a certain attribute on delay in one of their chosen projects
using a five point “Likert scale (1 very low, 2 low, 3
moderate, 4 high, and 5 very high).”[1].
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1738
Table -1: Identification of delay factors and sources
Sr.
no
Category Factors
affecting
delays
Source
1 Man power
related delays
1) Shortage of
skilled labours
2) Low
productivity
level of labours
3) Unqualified
Workforce
4) Abseentism
of labours
5) Shortage of
unskilled
labours
Hemanta Doloi
et al.(2012),
Ashish
Chandru
Pawar et
al.(2016)
2 Equipment
related delays
1) Availability
of equipment
2) Maintenance
of equipment
3) Delay in
delivery of
machinery by
suppliers
4) Frequent
failure or
breakdown of
equipments
M.P Venkatesh
et al,(2012)
3 Material related
delays
1) Shortage of
materials
2) Delivery of
materials
3) Quality of
materials
4) Procurement
of materials
5) Damage of
materials in
storage
Ahmed El
Sayed et
al.(2020)
4 Architectural/Str
uctural Design
related delays
1)
Architectural/S
tructural design
not completed
in time
2) Change in
design in
drawings
3) Insufficient
detailing
4) Rework due
to errors in
drawing
5) Delay in
receiving
corrections and
revisions of
design and
instructions.
Rao Aamir
Khan et
al.(2017)
5 Authority
related
delays
1) Obtaining
permission
from local
authorities
2) Changes in
government
regulations and
laws
3) Lack of funds
4) Delay due to
slow decision
making
Hemanta Doloi
et al.(2012),
Ashish
Chandru
Pawar et
al.(2016)
3.2 Respondent’s profile
Respondents are chosen from a diverse group of
professionals working in India's construction industry
(contractors, clients and engineers). All of the identified
respondents have knowledge of reasonably sizable
engineering construction projects in the setting of India.
Project managers, contractadministrators,designmanagers,
and construction managers were among the sample's
owners, architects, structural engineers, service engineers,
and architects. A brief summary of the respondents'
professional roles and experience is provided in Table 2 for
those who took part in the study.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1739
Table-2 : Respondent’s profile
Nature of work Experience ( years) Total
< 5 5-10 10-15
Owner 1 - 1 2
Contractors 3 - - 3
Designers/Architects 2 1 - 3
Engineers 19 8 1 28
Total 25 9 2 36
Due to the respondents' strong knowledge of the
questionnaires and relevant industrial experiences, even if
the sample size is small, the quality of the responses was
thought to be highly reliable for the analysis.
4. ANALYSIS AND RESULTS
4.1 Ranking of delay attributes
The rankings of the various delay factors had been
determined using the Relative Importance Index (RII)
ranking approach. It is able to determinethe mostimportant
delay factors based on the rankings given to each cause of
delays.
The relative importance index for each cause was calculated
using the formula below.
RII = ΣW / (A*N)
W is the weightage given to each factor by the respondents
(ranging from 1 to 5),
A is the highest weight (i.e. 5 in this case), and
N is the total number of respondents.
The attributes are ranked from highest to lowest impact on
delay, with the highest RII or rank 1 having the greatest
impact on delay and the lowest rank having the least impact
on delay time.
Table-3 : R.I.I ranking for Man power related delays
Sr.no Description of
Delay Factor
R.I.I R.I.I
In
(%)
Rank
1 Delays due to
Shortage of skilled
labours
0.65 20.56 1
2 Delays due to low
productivity of
labour
0.65 20.56 1
3 Delays due to
Unqualified
workforce
0.65 20.56 1
4 Delays due to
Absenteeism of
labour
0.63 19.93 2
5 Delays due to
Shortage of
unskilled labours
0.58 18.35 3
Table-4 : R.I.I ranking for Equipment related delays
Sr.no Description of Delay
Factor
R.I.I R.I.I
In
(%)
Rank
1 Delays due to
availability of
equipment
0.73 26.93 1
2 Delays due to Frequent
failure or breakdown
of equipments
0.68 25.09 2
3 Delays due to
Maintenance of
equipment
0.65 23.98 3
4 Delay in delivery of
machinerybysuppliers
0.65 23.98 3
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1740
Table-5 : R.I.I ranking for Material related delays
Sr.no Description of Delay
Factor
R.I.I R.I.I
In
(%)
Rank
1 Delays due to Shortage
of materials
0.73 21.53 1
2 Delays due to delivery of
materials
0.70 20.64 2
3 Delays due to Quality of
materials
0.66 19.46 3
4 Delays due to
Procurement of
materials
0.65 19.17 4
5 Delays due to damage of
materials in Storage
0.65 19.17 5
Table-6 : R.I.I ranking for Architectural/Structural related
delays
Sr.no Description of Delay
Factor
R.I.I R.I.I
In
(%)
Rank
1 Delays due to Change
in design in drawings
0.69 20.59 1
2 Rework due to errors
in drawings
0.68 20.29 2
3 Delays in receiving
corrections and
revisions of design &
instructions
0.68 20.29 3
4 Delays due to
architectural/
structural design not
completed in time
0.66 19.70 4
5 Delays due to
Insufficient detailing in
drawings
0.64 19.10 5
Table-7 : R.I.I ranking for Owner related delays
Sr.no Description of Delay
Factor
R.I.I R.I.I
In
(%)
Rank
1 Delays due to slow
decision making
0.78 25.49 1
2 Delays due to obtaining
permission from local
authorities
0.77 25.16 2
3 Delays due to changes
in government
regulations and laws
0.77 25.16 2
4 Delays due to lack of
funds
0.74 24.18 3
Table-8 : R.I.I ranking of delay categories
Sr.no Categories of Delay R.I.I R.I.I
In
(%)
Rank
1 Owner related delays 0.76 22.28 1
2 Material related
delays
0.68 19.94 2
3 Equipment related
delays
0.67 19.64 3
4 Architectural /
Structural Design
related delays
0.67 19.64 3
5 Manpower related
delays
0.63 18.47 4
4.2 Root cause analysis of identified delay
attributes
Using a tree diagram, the root cause analysis of the 23 delay
attributes was performed. In the Pimpri Chinchwad region,
three study locations were chosen for this purpose. The first
site was chosen for the excavation stage of construction, the
second for the intermediate stage, and the third for the final
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1741
stage of construction activity. By witnessing building
activities at various phases, engaging in brainstorming
sessions, and speaking with construction experts at the
relevant sites, the underlying reasons of delay attributes
were found.
The details of the sites are as follows:
1) Vastu udyog colony, Ajmera (Excavation stage)
Address :- 68, Ajmera Main Rd, Kalewadi Phata, Ajmera
Housing Society, Pimpri Colony, Pimpri-Chinchwad,
Maharashtra 411018
Building type – Residential building (G+6)
2) Shantai Classic, Ravet ( Intermediate stage)
Address - DP Rd, near S.B.Patil Public School, Ravet, Pimpri-
Chinchwad, Maharashtra 412101
Building Type – Residential Building (B+G+6)
3) RKH Pride, Nehrunagar (Finishing stage)
Address - New Telco Rd, Nehru Nagar, Pimpri Colony,
Pimpri-Chinchwad, Maharashtra 411018
Building Type – Residential Building (G+5)
4.2.1 Root cause analysis of Manpower related
delays
Fig. 2 shows three common root causesfoundforthefactors
(shortage of skilled labours, low productivity level of
labours, unqualified workforce, absentism of labours,
shortage of unskilled labours) namely:
i. The contractor's failure to provide decent working
conditions for workers.
ii. Ignoring the project site's distance from the
locations of human resources andtheiraccessibility
throughout the execution phase
iii. Late wage payments
4.2.2 Root cause analysis of Equipment related
delays
From Fig.3 it can be seen that three common root causes
were identified for factors (Delayindeliveryofmachinery by
suppliers and Availability of equipment) namely :
i. Reliance on a single vendor.
ii. Picking the incompetent supplier.
iii. Failure to pay suppliers on time.
Also for factors( Maintenance of equipment and Frequent
failure or breakdown of equipments) three common root
causes were identified namely:
i. Using equipment that is rented.
ii. Using outdated equipment
iii. Improper machine handling and operation.
4.2.3 Root cause analysis of materialrelateddelays
Fig 4. shows root causes for the following factors :
1) Shortage of materials
Following are the root causes:
i. The negligent usage of materials by the contractor.
ii. Poor material storage in the warehouse.
iii. A delay in placing the order.
iv. A delay in estimating
2) Delivery of materials
Following are the root causes:
i. Not paying the supplier in advance for the
materials.
ii. Long travel time between the site and the suppliers
iii. Delay in placing material orders.
iv. A lack of the requested materials.
3) Quality of materials
Following are the root causes:
i. Lack of quality control over materials during
shipping and delivery to the project site.
ii. Giving procurement limited funds.
4) Procurement of materials
Following are the root causes:
i. Not enough storage space is available.
ii. Insufficient funding to purchase materials on
schedule.
iii. Increased material costs and inflation.
5) Damage of materials in storage
Following are the root causes:
i. The contractor's negligent usage of materials
ii. The warehouse's improper material storage
4.2.4 Root cause analysis for Architectural /
Structural related delays
Fig 5. shows root causes for the following factors :
1) Design not completed in time and insufficient detailing
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1742
Following are the root causes:
i. Employing a design team that is unqualified
ii. Insufficient coordination across design units.
iii. Not allotting enough time for design
2) Change in design of drawings
Following are the root causes:
i. Planning and execution occurring at the same time.
ii. The inability of the design units to coordinate.
iii. Providing the project site with an unfinished
drawing.
iv. Utilizing an amateur design team.
3) Rework due to errors in drawing
Following are the root causes:
i. The absence of frequent meetings to enhance
coordination between units.
ii. A lack of supervision and a widerperspectiveonthe
project
4) Delay in receiving corrections and revisions in design
Following are the root causes:
i. Using inexperienced employees based on the
severity of the project.
4.2.5 Owner related delays
Fig 6. shows root causes for the following factors :
1) Obtaining permission from local authorities
Following are the root causes:
i. The local authority's delay in document approval.
ii. At different phases of development, multiple
clearances are needed.
iii. Lack of departmental coordination.
2) Lack of funds
Following are the root causes:
i. The owner's bad financial performance.
ii. Being the owner of several projects.
3) Delay due to slow decision
Following are the root causes:
i. Poor communication between contractors and
owners..
ii. Frequent change in orders
iii. A lack of thorough analysis before providing
instructions
Fig-2: The delay finder tree diagram for manpower
related delays
Fig-3: The delay finder tree diagram for equipment related
delays
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1743
Fig-4: The delay finder tree diagram for material related
delays
Fig-5: The delay finder tree diagram for architectural /
structural related delays
Fig-6: The delay finder tree diagram for owner related
delays
5. CONCLUSIONS AND RECOMMENDATIONS
5.1 Conclusion
From the above results conclusion may be given as follows:
1) After Literature Review, Site visits, and brainstorming,
23 Delay attributes under 5 broad categories namely
(Man power, Equipment, Material,
Architectural/Structural, Owner) have been found as
most common in small residential buildingconstruction
projects.
2) The results received from google survey forms and RII
analysis revealed that owner related delays has
maximum impact among all delays.
3) Root causes of 23 delay attributes were found by root
cause analysis technique usingtreediagrambystudying
3 sites in Pimpri Chinchwad area.
4) Corrective measures were proposedfortheabovefound
23 delay attributes to minimise delays caused by them
in the near future in the building construction field.
5.2 Recommendations to minimize delays
5.2.1 Man power related delays
1) Hiring a enough amount of experts domestic staff.
2) Having effective administration of human resources.
3) Offering competitive pay for available roles.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1744
5.2.2 Equipment related delays
1) Having 2 to 3 standby suppliers .
2) Choosing an appropriatesupplier whoisreadytosupply
machinery on credit.
3) Making use of new and modern equipments.
4) Having an effective system for managing your
machinery.
5.2.3 Material related delays
1) In order to reduce waste and rework, examining and
managing the material quality at the point of entry to
the project site.
2) Keeping an eye on the warehouse and material
organisation.
3) Setting aside enough money and creating an acceptable
purchasing plan to enable timely material purchases.
4) Creating an effective risk plan for funding and risk
estimation.
5.2.4 Architectural/Structural related delays
1) Employing qualified personnel.
2) Organizing regular meetings to strengthen
communication between the technical office and the
design teams.
3) Creating a system that is effective for quick decision-
making and information flow to complete the drawings.
4) Giving the design process enough time.
5) Making use of new tools and software, and techniques
like BIM.
5.2.5 Owner related delays
1) Establishing a financial plan for payments while taking
into account the delivered work at different phases of
the project.
2) Being knowledgeable about emerging project
management tools and techniques like BIM.
3) Choosing a reliable contractor with solid financial and
technical capabilities.
4) Creating a proper risk management strategy and
correctly allocating risks.
REFERENCES
[1] Khan, Rao Aamir, and Warda Gul. "Emperical study of
critical risk factors causing delays in construction
projects." In 2017 9th IEEE International Conference on
Intelligent Data Acquisition and Advanced Computing
Systems: Technology and Applications (IDAACS),
IEEE,,vol. 2, ,pp. 900-906,2017
[2] Doloi, Hemanta, Anil Sawhney, K. C. Iyer, and Sameer
Rentala. "Analysing factors affecting delays in Indian
construction projects." International journal of project
management 30, no. 4 : 479-489, 2012
[3] El Sayed, Ahmed, Emad Mamoua, and Adnan Novalić.
"The Lack of Techniques Used in Management as a
Factor Causing Delays in Construction Projects in B&H
and Other Delay Factors Detected." In International
Conference “New Technologies, Development and
Applications”, pp. 728-735. Springer, Cham, 2019.
[4] M.P.Venkatesh, C.Umarani, S.M.Renuga and
BalasubramanianMalathi“AnalysisandIdentificationof
Critical Factors of Delay in Construction Projects.”
NICMAR-Journal of construction management, Volume-
XXVII, No.2 &3, 2012.
[5] Ashish Chandu Pawar, S.V.Wagh and Nikhil V. Bhalerao
“Factors causing delay and Methodology of Ranking for
Residential Projects.” International Journal of
Engineering Research & Technology (IJERT),Vol.5Issue
8, 2016.
[6] Abd El-Razek, M. E., H. A. Bassioni, and A. M. Mobarak.
"Causes of delay in building construction projects in
Egypt." Journal of construction engineering and
management 134, no. 11 : 831-841,2008
[7] Abbasi, Omid, Esmatullah Noorzai, Kobra Gharouni
Jafari, and Mahmood Golabchi. "Exploring the causes of
delays in construction industry using a cause-and-effect
diagram: case study for Iran." Journal of Architectural
Engineering 26, no. 3, 2020.
[8] Hsu, Pei-Yuan, Marco Aurisicchio, and Panagiotis
Angeloudis. "Investigating schedule deviation in
construction projects through root cause
analysis." Procedia computer science 121 : 732-739,
2017
[9] Yiu, N.S., Sze, N.N. and Chan, D.W.,” Implementation of
safety management systems in Hong Kong construction
industry–A safety practitioner's perspective”. Journal of
safety research, 64, pp.1-9,2018
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1745
[10] Benny, D. and Jaishree, D., “Construction safety
management and accident control
measures”. International Journal of Civil Engineering
and Technology, 8(4), pp.611-617, 2017.
[11] Solís-Carca, R.G. and Franco-Poot, R.J., “Construction
workers’ perceptions of safety practices: A casestudyin
Mexico”. Journal of Building Construction and Planning
Research, 2014.
[12] Hassanein, A.A. and Hanna, R.S., “Safety Programs in
Large-Size Construction Firms Operating in
Egypt”. Journal of SH&E Research, 4(1), ,pp.1-31, 2007
[13] Toole, T.M., “Construction site safety roles”. Journal of
construction engineering and management, 128(3),
,pp.203-210, 2002
[14] Jaselskis, E.J. and Recarte Suazo, G.A., “A survey of
construction site safety in Honduras”. Construction
Management and economics, 12(3), ,pp.245-255, 1994
[15] Winge, S., Albrechtsen,E.and Arnesen, J.,“Acomparative
analysis of safety management and safety performance
in twelve construction projects”. Journal of safety
research, 71, , pp.139-152, 2019

More Related Content

Similar to INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 

Similar to INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT (20)

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
D012261521
D012261521D012261521
D012261521
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
20320140503023
2032014050302320320140503023
20320140503023
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1736 INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT Shreyash D.Desai1, Renuka R.Purohit2 1P.G Student(Construction Management), Department of Civil Engineering, Pimpri Chinchwad College of Engineering, Nigdi, Pune, India 2 Assistant Professor, Department of Civil Engineering, Pimpri Chinchwad College of Engineering, Pune, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - One of the most frequent issues with residential construction projects is delay. When work is completed after the contracted or anticipated time frame, the project issaid to be delayed. Projects can be delayed for a variety of causes, including those caused by the client, the contractor, divine intervention, or a third party. They may happen alone or in conjunction with other delays, early or late in the project's development. Only after determining their reason can delays be minimised. This study's goals were to identify the main reasons for delays, classify and rank them to discover their root causes, and then offer a workable remedy. Based on a literature research and survey, this study was conducted. The purpose of this work was to identify and assess the relative importance of the significantfactorsinfluencing delaythrough a questionnaire survey. To improve project performance and reduce or eliminate delays, effective project planning, controlling, and monitoring should be implemented. Key words : Residential Construction delays, Delay Causes, Relative Importance Index (R.I.I), Root cause analysis 1.INTRODUCTION India's construction sector is expanding very quickly. There are numerous projects underway in India right now with important clients, but only 1 to 5 percent of them are finished promptly. The remainder of the projects either lag behind schedule or haven't been finished at all. These projects are primarily the result of poor planning or different circumstances throughout project planning and implementation. This may be duetothefactthattheworking environment differs from what the designer or planner had anticipated, or it may be due to various obstacles, uncertainties, or risks associated with the current activity that are unknown to an amateur planner or engineer. Both economically and politically, delays and cost overruns have a big impact. The people and the economy must wait longer than necessary for the provision of public goods and services as a result of delays in project implementation. As a result, delays reduce the economy's capacity for growth. 1.1 Problem Statement Many factors might cause construction projects to be delayed. On residential construction projects, there are various sorts and categories of delays. When the causes of delays are found, they can be minimised. 1.2 Objectives of study 1. To identify the factors that are generating delays in the residential construction proSject 2. To find the impact of the identified factors on construction delay. 3. To analyse delays for residential construction project. 4. To make suggestions for corrective measurestoreduce project delays 1.3 Limitations The study is restricted to a sample interview for residential developments; infrastructure projects might differ. A analysis of infrastructure development initiatives might present a quite different image. Some restrictions depend on the site's location in relation to other parts of India. Additionally, the project's administrators typically resist disclosing the data. Given the limited quantity of resources in the city, more samples would provide a clearer picture. Smaller projects experience less delays than larger township projects, which would experience more serious delays. 2. LITERATURE REVIEW [1] The risk categories in this study by Rao Aamir Khan et al. were ranked using the RII to identify the most significant risks that result in project delay and mitigate them as soon as possible. The study's conclusions were followed by recommendations. [2] In order to create prediction models for analysing how these factors affect delay, Hemanta Doloi et alstudy.'s first determined the crucial attributes that have the greatest impact on delay in the Indian construction industry. The
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1737 foundation of this researchwasa questionnaireandin-depth interviews. [3] Ahmed El Sayed and colleagues look into the causes of construction project delays in Bosnia and Herzegovina and assess their importance. This study examines how management software is used during the project planning and execution phases, as well as how precisely inputs are determined. [4] The essential elements thatcontributetodelaysandtheir effects on project completion were identified by M.P. Venkatesh et al. More emphasisisplacedonresource-related delays in the construction industry in this study. The investigation that produced the results was conducted at several ongoing and completed construction sites in the context of India. The reasons were elicited from diverse construction specialistsinvariousfirmsusinga standardised questionnaire survey. [5] By using the Relative Importance and Importance Index technique, Ashish Chandu Pawar et al. identified the main causes of delays, the effects of delays, and methods/recommendations of minimising delays in Residential Construction projects. [6] From the perspectives of contractors, consultants, and owners, M. E. Abd El-Razek et al[6] .'s analysis of construction projects in Egypt foundtheprimary reasonsfor delays. [7] The most major causesof constructiondelayswerefound by Omid Abbasi et al, who then classifiedandrankedthemto identify the root causes of delays and offered a workable remedy. [8] Pei-Yuan Hsu et al.'s investigation of the elements influencing schedule deviation in building projects helped them comprehend the causal connections underlying the delays. Fault Tree Analysis (FTA) is a well-known method among the many root cause analysis techniques. FTA investigates the series of circumstances that led to the issue in-depth in order to determine its root cause. 3. METHODOLOGY In order to determine the impact of several factors on delay in the Indian construction sector, a questionnaire survey approach has been used for this research, based on the numerous overseas researchers previously mentioned. A survey of industry experts representing different stakeholders in construction projects in India was carried out. Following methodology was adopted: Fig-1: Detailed Methodology 3.1 Identification of delay factors and sources A significant step in ensuring the effectiveness of the research is the identification of the study's critical qualities and the creation of the questionnaire. There has already been a significant amount of research done on the factors that contribute to constructiondelays,andtheliterature also has a collection of delay attributes that have undergone extensive peer review. The important delay attributes mentioned in the literature have been incorporated into the questionnaire for this study. Technical staff in the building industry were sent Google forms. Under five major headings—manpower related, equipment related, material related, design related, and authority related—a total of 23 delay features were found. Table 1 contains a list of the qualities. Respondents were askedtorank thesignificanceof a certain attribute on delay in one of their chosen projects using a five point “Likert scale (1 very low, 2 low, 3 moderate, 4 high, and 5 very high).”[1].
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1738 Table -1: Identification of delay factors and sources Sr. no Category Factors affecting delays Source 1 Man power related delays 1) Shortage of skilled labours 2) Low productivity level of labours 3) Unqualified Workforce 4) Abseentism of labours 5) Shortage of unskilled labours Hemanta Doloi et al.(2012), Ashish Chandru Pawar et al.(2016) 2 Equipment related delays 1) Availability of equipment 2) Maintenance of equipment 3) Delay in delivery of machinery by suppliers 4) Frequent failure or breakdown of equipments M.P Venkatesh et al,(2012) 3 Material related delays 1) Shortage of materials 2) Delivery of materials 3) Quality of materials 4) Procurement of materials 5) Damage of materials in storage Ahmed El Sayed et al.(2020) 4 Architectural/Str uctural Design related delays 1) Architectural/S tructural design not completed in time 2) Change in design in drawings 3) Insufficient detailing 4) Rework due to errors in drawing 5) Delay in receiving corrections and revisions of design and instructions. Rao Aamir Khan et al.(2017) 5 Authority related delays 1) Obtaining permission from local authorities 2) Changes in government regulations and laws 3) Lack of funds 4) Delay due to slow decision making Hemanta Doloi et al.(2012), Ashish Chandru Pawar et al.(2016) 3.2 Respondent’s profile Respondents are chosen from a diverse group of professionals working in India's construction industry (contractors, clients and engineers). All of the identified respondents have knowledge of reasonably sizable engineering construction projects in the setting of India. Project managers, contractadministrators,designmanagers, and construction managers were among the sample's owners, architects, structural engineers, service engineers, and architects. A brief summary of the respondents' professional roles and experience is provided in Table 2 for those who took part in the study.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1739 Table-2 : Respondent’s profile Nature of work Experience ( years) Total < 5 5-10 10-15 Owner 1 - 1 2 Contractors 3 - - 3 Designers/Architects 2 1 - 3 Engineers 19 8 1 28 Total 25 9 2 36 Due to the respondents' strong knowledge of the questionnaires and relevant industrial experiences, even if the sample size is small, the quality of the responses was thought to be highly reliable for the analysis. 4. ANALYSIS AND RESULTS 4.1 Ranking of delay attributes The rankings of the various delay factors had been determined using the Relative Importance Index (RII) ranking approach. It is able to determinethe mostimportant delay factors based on the rankings given to each cause of delays. The relative importance index for each cause was calculated using the formula below. RII = ΣW / (A*N) W is the weightage given to each factor by the respondents (ranging from 1 to 5), A is the highest weight (i.e. 5 in this case), and N is the total number of respondents. The attributes are ranked from highest to lowest impact on delay, with the highest RII or rank 1 having the greatest impact on delay and the lowest rank having the least impact on delay time. Table-3 : R.I.I ranking for Man power related delays Sr.no Description of Delay Factor R.I.I R.I.I In (%) Rank 1 Delays due to Shortage of skilled labours 0.65 20.56 1 2 Delays due to low productivity of labour 0.65 20.56 1 3 Delays due to Unqualified workforce 0.65 20.56 1 4 Delays due to Absenteeism of labour 0.63 19.93 2 5 Delays due to Shortage of unskilled labours 0.58 18.35 3 Table-4 : R.I.I ranking for Equipment related delays Sr.no Description of Delay Factor R.I.I R.I.I In (%) Rank 1 Delays due to availability of equipment 0.73 26.93 1 2 Delays due to Frequent failure or breakdown of equipments 0.68 25.09 2 3 Delays due to Maintenance of equipment 0.65 23.98 3 4 Delay in delivery of machinerybysuppliers 0.65 23.98 3
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1740 Table-5 : R.I.I ranking for Material related delays Sr.no Description of Delay Factor R.I.I R.I.I In (%) Rank 1 Delays due to Shortage of materials 0.73 21.53 1 2 Delays due to delivery of materials 0.70 20.64 2 3 Delays due to Quality of materials 0.66 19.46 3 4 Delays due to Procurement of materials 0.65 19.17 4 5 Delays due to damage of materials in Storage 0.65 19.17 5 Table-6 : R.I.I ranking for Architectural/Structural related delays Sr.no Description of Delay Factor R.I.I R.I.I In (%) Rank 1 Delays due to Change in design in drawings 0.69 20.59 1 2 Rework due to errors in drawings 0.68 20.29 2 3 Delays in receiving corrections and revisions of design & instructions 0.68 20.29 3 4 Delays due to architectural/ structural design not completed in time 0.66 19.70 4 5 Delays due to Insufficient detailing in drawings 0.64 19.10 5 Table-7 : R.I.I ranking for Owner related delays Sr.no Description of Delay Factor R.I.I R.I.I In (%) Rank 1 Delays due to slow decision making 0.78 25.49 1 2 Delays due to obtaining permission from local authorities 0.77 25.16 2 3 Delays due to changes in government regulations and laws 0.77 25.16 2 4 Delays due to lack of funds 0.74 24.18 3 Table-8 : R.I.I ranking of delay categories Sr.no Categories of Delay R.I.I R.I.I In (%) Rank 1 Owner related delays 0.76 22.28 1 2 Material related delays 0.68 19.94 2 3 Equipment related delays 0.67 19.64 3 4 Architectural / Structural Design related delays 0.67 19.64 3 5 Manpower related delays 0.63 18.47 4 4.2 Root cause analysis of identified delay attributes Using a tree diagram, the root cause analysis of the 23 delay attributes was performed. In the Pimpri Chinchwad region, three study locations were chosen for this purpose. The first site was chosen for the excavation stage of construction, the second for the intermediate stage, and the third for the final
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1741 stage of construction activity. By witnessing building activities at various phases, engaging in brainstorming sessions, and speaking with construction experts at the relevant sites, the underlying reasons of delay attributes were found. The details of the sites are as follows: 1) Vastu udyog colony, Ajmera (Excavation stage) Address :- 68, Ajmera Main Rd, Kalewadi Phata, Ajmera Housing Society, Pimpri Colony, Pimpri-Chinchwad, Maharashtra 411018 Building type – Residential building (G+6) 2) Shantai Classic, Ravet ( Intermediate stage) Address - DP Rd, near S.B.Patil Public School, Ravet, Pimpri- Chinchwad, Maharashtra 412101 Building Type – Residential Building (B+G+6) 3) RKH Pride, Nehrunagar (Finishing stage) Address - New Telco Rd, Nehru Nagar, Pimpri Colony, Pimpri-Chinchwad, Maharashtra 411018 Building Type – Residential Building (G+5) 4.2.1 Root cause analysis of Manpower related delays Fig. 2 shows three common root causesfoundforthefactors (shortage of skilled labours, low productivity level of labours, unqualified workforce, absentism of labours, shortage of unskilled labours) namely: i. The contractor's failure to provide decent working conditions for workers. ii. Ignoring the project site's distance from the locations of human resources andtheiraccessibility throughout the execution phase iii. Late wage payments 4.2.2 Root cause analysis of Equipment related delays From Fig.3 it can be seen that three common root causes were identified for factors (Delayindeliveryofmachinery by suppliers and Availability of equipment) namely : i. Reliance on a single vendor. ii. Picking the incompetent supplier. iii. Failure to pay suppliers on time. Also for factors( Maintenance of equipment and Frequent failure or breakdown of equipments) three common root causes were identified namely: i. Using equipment that is rented. ii. Using outdated equipment iii. Improper machine handling and operation. 4.2.3 Root cause analysis of materialrelateddelays Fig 4. shows root causes for the following factors : 1) Shortage of materials Following are the root causes: i. The negligent usage of materials by the contractor. ii. Poor material storage in the warehouse. iii. A delay in placing the order. iv. A delay in estimating 2) Delivery of materials Following are the root causes: i. Not paying the supplier in advance for the materials. ii. Long travel time between the site and the suppliers iii. Delay in placing material orders. iv. A lack of the requested materials. 3) Quality of materials Following are the root causes: i. Lack of quality control over materials during shipping and delivery to the project site. ii. Giving procurement limited funds. 4) Procurement of materials Following are the root causes: i. Not enough storage space is available. ii. Insufficient funding to purchase materials on schedule. iii. Increased material costs and inflation. 5) Damage of materials in storage Following are the root causes: i. The contractor's negligent usage of materials ii. The warehouse's improper material storage 4.2.4 Root cause analysis for Architectural / Structural related delays Fig 5. shows root causes for the following factors : 1) Design not completed in time and insufficient detailing
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1742 Following are the root causes: i. Employing a design team that is unqualified ii. Insufficient coordination across design units. iii. Not allotting enough time for design 2) Change in design of drawings Following are the root causes: i. Planning and execution occurring at the same time. ii. The inability of the design units to coordinate. iii. Providing the project site with an unfinished drawing. iv. Utilizing an amateur design team. 3) Rework due to errors in drawing Following are the root causes: i. The absence of frequent meetings to enhance coordination between units. ii. A lack of supervision and a widerperspectiveonthe project 4) Delay in receiving corrections and revisions in design Following are the root causes: i. Using inexperienced employees based on the severity of the project. 4.2.5 Owner related delays Fig 6. shows root causes for the following factors : 1) Obtaining permission from local authorities Following are the root causes: i. The local authority's delay in document approval. ii. At different phases of development, multiple clearances are needed. iii. Lack of departmental coordination. 2) Lack of funds Following are the root causes: i. The owner's bad financial performance. ii. Being the owner of several projects. 3) Delay due to slow decision Following are the root causes: i. Poor communication between contractors and owners.. ii. Frequent change in orders iii. A lack of thorough analysis before providing instructions Fig-2: The delay finder tree diagram for manpower related delays Fig-3: The delay finder tree diagram for equipment related delays
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1743 Fig-4: The delay finder tree diagram for material related delays Fig-5: The delay finder tree diagram for architectural / structural related delays Fig-6: The delay finder tree diagram for owner related delays 5. CONCLUSIONS AND RECOMMENDATIONS 5.1 Conclusion From the above results conclusion may be given as follows: 1) After Literature Review, Site visits, and brainstorming, 23 Delay attributes under 5 broad categories namely (Man power, Equipment, Material, Architectural/Structural, Owner) have been found as most common in small residential buildingconstruction projects. 2) The results received from google survey forms and RII analysis revealed that owner related delays has maximum impact among all delays. 3) Root causes of 23 delay attributes were found by root cause analysis technique usingtreediagrambystudying 3 sites in Pimpri Chinchwad area. 4) Corrective measures were proposedfortheabovefound 23 delay attributes to minimise delays caused by them in the near future in the building construction field. 5.2 Recommendations to minimize delays 5.2.1 Man power related delays 1) Hiring a enough amount of experts domestic staff. 2) Having effective administration of human resources. 3) Offering competitive pay for available roles.
  • 9. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1744 5.2.2 Equipment related delays 1) Having 2 to 3 standby suppliers . 2) Choosing an appropriatesupplier whoisreadytosupply machinery on credit. 3) Making use of new and modern equipments. 4) Having an effective system for managing your machinery. 5.2.3 Material related delays 1) In order to reduce waste and rework, examining and managing the material quality at the point of entry to the project site. 2) Keeping an eye on the warehouse and material organisation. 3) Setting aside enough money and creating an acceptable purchasing plan to enable timely material purchases. 4) Creating an effective risk plan for funding and risk estimation. 5.2.4 Architectural/Structural related delays 1) Employing qualified personnel. 2) Organizing regular meetings to strengthen communication between the technical office and the design teams. 3) Creating a system that is effective for quick decision- making and information flow to complete the drawings. 4) Giving the design process enough time. 5) Making use of new tools and software, and techniques like BIM. 5.2.5 Owner related delays 1) Establishing a financial plan for payments while taking into account the delivered work at different phases of the project. 2) Being knowledgeable about emerging project management tools and techniques like BIM. 3) Choosing a reliable contractor with solid financial and technical capabilities. 4) Creating a proper risk management strategy and correctly allocating risks. REFERENCES [1] Khan, Rao Aamir, and Warda Gul. "Emperical study of critical risk factors causing delays in construction projects." In 2017 9th IEEE International Conference on Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications (IDAACS), IEEE,,vol. 2, ,pp. 900-906,2017 [2] Doloi, Hemanta, Anil Sawhney, K. C. Iyer, and Sameer Rentala. "Analysing factors affecting delays in Indian construction projects." International journal of project management 30, no. 4 : 479-489, 2012 [3] El Sayed, Ahmed, Emad Mamoua, and Adnan Novalić. "The Lack of Techniques Used in Management as a Factor Causing Delays in Construction Projects in B&H and Other Delay Factors Detected." In International Conference “New Technologies, Development and Applications”, pp. 728-735. Springer, Cham, 2019. [4] M.P.Venkatesh, C.Umarani, S.M.Renuga and BalasubramanianMalathi“AnalysisandIdentificationof Critical Factors of Delay in Construction Projects.” NICMAR-Journal of construction management, Volume- XXVII, No.2 &3, 2012. [5] Ashish Chandu Pawar, S.V.Wagh and Nikhil V. Bhalerao “Factors causing delay and Methodology of Ranking for Residential Projects.” International Journal of Engineering Research & Technology (IJERT),Vol.5Issue 8, 2016. [6] Abd El-Razek, M. E., H. A. Bassioni, and A. M. Mobarak. "Causes of delay in building construction projects in Egypt." Journal of construction engineering and management 134, no. 11 : 831-841,2008 [7] Abbasi, Omid, Esmatullah Noorzai, Kobra Gharouni Jafari, and Mahmood Golabchi. "Exploring the causes of delays in construction industry using a cause-and-effect diagram: case study for Iran." Journal of Architectural Engineering 26, no. 3, 2020. [8] Hsu, Pei-Yuan, Marco Aurisicchio, and Panagiotis Angeloudis. "Investigating schedule deviation in construction projects through root cause analysis." Procedia computer science 121 : 732-739, 2017 [9] Yiu, N.S., Sze, N.N. and Chan, D.W.,” Implementation of safety management systems in Hong Kong construction industry–A safety practitioner's perspective”. Journal of safety research, 64, pp.1-9,2018
  • 10. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1745 [10] Benny, D. and Jaishree, D., “Construction safety management and accident control measures”. International Journal of Civil Engineering and Technology, 8(4), pp.611-617, 2017. [11] Solís-Carca, R.G. and Franco-Poot, R.J., “Construction workers’ perceptions of safety practices: A casestudyin Mexico”. Journal of Building Construction and Planning Research, 2014. [12] Hassanein, A.A. and Hanna, R.S., “Safety Programs in Large-Size Construction Firms Operating in Egypt”. Journal of SH&E Research, 4(1), ,pp.1-31, 2007 [13] Toole, T.M., “Construction site safety roles”. Journal of construction engineering and management, 128(3), ,pp.203-210, 2002 [14] Jaselskis, E.J. and Recarte Suazo, G.A., “A survey of construction site safety in Honduras”. Construction Management and economics, 12(3), ,pp.245-255, 1994 [15] Winge, S., Albrechtsen,E.and Arnesen, J.,“Acomparative analysis of safety management and safety performance in twelve construction projects”. Journal of safety research, 71, , pp.139-152, 2019