Optimization of Time and Cost of Building Construction using Fast
Tracking Method of Scheduling
Pooja Kamble1, Nadeem Sanadi2
1Post Graduate Student, Department of Civil Engineering, Jain College of Engineering Belagavi.
2Assistant Professor, Department of Civil Engineering, Jain College of Engineering Belagavi.
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - The purpose of this study is to assess causes and
effects of cost and time overruns in construction projects. An
effective project management tool is introduced in the form
of Microsoft Project (MSP). In this project, Fast tracking
method is adopted for planning and scheduling for the
construction of Linemen Quarters using Microsoft Project
(MSP) software. Various activities involved in the
construction of linemen quarters are scheduled. A
comparison between planned duration and cost in
traditional method and by using project management tool
such as Microsoft project is carried out.
Key Words: Planning, Scheduling, Fast Tracking, Time
Overrun, Cost Overrun.
1. INTRODUCTION
The project management team should plan a project in
such a way that completion of the project should be as on
date with planned budget and resources. The project
should meet all the set standards without compromising
with the quality of work, budgeted cost and planned
duration. A project which fulfills the abovementioned
requirements is called a successful project. For the study,
the case study considered involved construction of
Linemen quarter for the staff in the town of Kanakapura,
the details of which are mentioned below.
1.1Brief details of the project
 Name of project: LM Quarters
 Contractor: Sri Shivkumar S.M
 Type: Residential building
 Number of stories: G+2
 Project Estimation Cost : Rs.18,417,844.79
The lineman Quarter is a G+2 building. Total area
of the building is 989.64SQM. The linemen quarters are
designed with bedroom, kitchen, balcony, living room, and
bathroom. It is a 2BHK. And the ground floor is designed
as the parking area.
2. OBJECTIVES OF PROJECT
 To estimate the cost required to complete the
project.
 Estimating then duration required to complete the
project along with individual activities.
 Comparison of traditional method of planning to
Planning using project Management Software.
 Detailed Analysis of the dependency between the
tasks.
 Estimation of the cost using productivity details.
 To fast track the project for early completion.
3. RESEARCH METHODOLOGY
I. Literature study: A set of research papers,
journal articles, project reports were studied to
know the importance of Time, Cost and Qualityiin
a constructioniproject. Efforts were made to
understand the need of proper planning and
management of Time, Cost andnQuality for
successfulicompletioniof any project.
II. Formulating problem statement: After the
literature study and knowing the current needs of
the industry, a problem statement was formed to
conduct detailed study of a construction project
and bring out a solution for efficient
managementnof Time, Costiand Quality within the
project.
III. Fixing of Objectives: After conducting a brief
literature review of various research articles,
journals, project reports etc. based on the
problem statement formulated a set of objectives
were framed stick to which entire flow of the
project will be worked on.
IV. Data collection: The requiredidata was collected
with respect to the research objective. Details of a
project such as BOQ, Plans, Schedule, cost
estimate, Detailed Project Report etc. were
collected and studied.
V. Analysis: The collected data is studied to
understand status of the project, causes of delays,
risks involved etc. A new project schedule for the
same project is prepared using Microsoft Project
Software which could guide the project in proper
way for its successful completion.
VI. Results: After analysing the project and preparing
a detailed schedule of the project using Microsoft
project (MSP) we could derive various details
such as duration required for completion of
project, total cost required, resource allocation
plan etc.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1243
4. INVESTIGATION AND ANALYSIS
4.1 Estimation of the Project
The estimation of the project was obtained and
studied. The quantities were calculated in Microsoft Excel
for each and every material and task such as earthwork
excavation, reinforcement etc. The total budgeted cost
after conducting estimation was Rs.18,417,844.
4.2 Planning and scheduling in Microsoft Project
(MSP)
All the activities in sequence were listed and a Work
Breakdown Sequence was prepared in Microsoft Project
(MSP). In the next step resource and duration were
allotted for each and every activity. The activities later
were linked with the one another by giving the
predecessors. Budgeting was done after allocating the
resources like manpower, material, and machinery used
for the specified activity. The resources allocated were
given with rate per unit so that when we allocate the
number of resources required for the specified activity the
software will automatically compute the total cost of the
activity. Then the overall cost of the activities will give the
overall cost of project.
Fig.1.Planning of Project in MSP
5. RESULTS AND DISCUSSION
Planning scheduling of the project is carried out in
order to calculate the total duration of the project by
creating work breakdown Structure (WBS) and allocating
resources. In this duration was reduced by using Microsoft
Project (MSP) which includes the finding of critical Path
where the duration of the project can be changed by Fast
tracking method.
5.1 Comparison of duration
The actual planned duration using Microsoft excel
was 381days, after using project management tool -
Microsoft project (MSP) duration was found to be 328
days. The total time required was reduced by 53days
after fast tracking.
Fig.2. Comparision of duration
5.2 Project cost
The budgeted cost of project by using Microsoft
excel was Rs.18,417,844.79 Whereas, the estimated
cost of project after fast tracking by using Microsoft
project software (MSP) was Rs.18,417,707.22. The
difference between conventional and modern method
of estimation was 137.57 which deficits the estimate
carried out the estimation cost appropriate.
Table 5.2 Project Cost
6. CONCLUSIONS
1. By using a computer application like Microsoft project
(MSP) to schedule gives the best results in construction
projects.
2. The chronological planning of the construction activities
and graphical representation on the Gantt chart is useful
for superior understanding of the project.
3. Planning and scheduling in Microsoft project (MSP)
proved to be more effective than in Microsoft Excel.
Project In traditional
method
In MSP
Linemen
Quarters
Rs.18,417,844.79 Rs.18,417,844.79
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1244
4. Reduction in duration was carried out for the project
by fast tracking method.
5. Generally if the duration of the project is to be reduced,
there will be a need to increase the amount of resources
i.e. increase in the cost of the project.
6. In the current study the total budgeted cost of the
project has been kept the same whereas reduction in the
duration of construction is achieved.
7. Initially the duration of the project was 381 days after
reduction the duration of project became 328 days. A
Reduction of 53 days in the project schedule is achieved
using project management tools and techniques.
7. REFERENCES
[1] Anant Narayan Shete, Vaibhav Durwas Kothawade.
(2016). An Analysis of Cost Overruns and Time Overruns
of Construction Projects in India. International of
Engineering Trends and Technology, 4(1),33- 36
[2] Erande, S. S., & Pimplikar, S. S. (2016). Total Quality
Management in Indian construction
industry. International Research Journal of Engineering
and Technology, 3(6), 685-691.
[3] Chidambaram, R., & Potty, N. S. (2014). Qualitative
analysis of Time delay and Cost overrun in Multiple Design
and Build Projects. Civil and Mechanical Engineering.
[4] Sai Murali Krishna Reddy,Raya and S.S Bhanu
Prakash(2016). Cost and time overruns in Indian
construction industry. Industrial Science, 2(4), 1-9
[5] Chin-Keng, T. (2011). Study of quality management in
construction projects. Chinese Business Review, 10(7).
[6] Serpell, A., & Alarcon, L. F. (1998). Construction
process improvement methodology for construction
projects. International journal of project
management, 16(4), 215-221.
[7] Stasiak-Betlejewska, R., & Potkány, M. (2015).
Construction costs analysis and its importance to the
economy. Procedia Economics and Finance, 34, 35-42.
[8] Mallawaarachchi, H., & Senaratne, S. (2015, December).
Importance of quality for construction project success.
In 6th International conference on structural engineering
and construction management.
[9] Shah, M. R., Pitroda, J., & Patel, C. G. Quality Control
Management in Building Construction.
[10] Monish Kumar K, Maheshwar S Maregowdru, Sparsha
B.P. (2017).Construction Project scheduling of MK
Apartment Using MS Project 2013. International Research
Journal of Engineering and Technology 4(7) ,2275-2279
[11] Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012).
Analysing factors affecting delays in Indian construction
projects. International journal of project
management, 30(4), 479-489.
[12] Ashokkumar, D. (2014). Study of quality management
in construction industry. International Journal of
Innovative Research in Science, Engineering and
Technology, 3(1), 36-43.
BIOGRAPHIES
POOJA V KAMBLE, is a Final Year
Post Graduate student in
Construction Technology in the
Department of Civil Engineering
of Jain College of Engineering
Belagavi.
NADEEM SANADI, is Assistant
Professor in in the Department of
Civil Engineering of Jain College
of Engineering Belagavi. He has 1
Year of Teaching and over 2 years
of experience in execution of
Major Bridges.

More Related Content

What's hot

IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET Journal
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...IRJET Journal
 
Engineering process flow
Engineering process flowEngineering process flow
Engineering process flowPurnendu Jha
 
ASHWIN A_Senior planning Engineer_
ASHWIN A_Senior planning Engineer_ASHWIN A_Senior planning Engineer_
ASHWIN A_Senior planning Engineer_#win(ashwin) Work
 
Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualSummerfieldTBL
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner SystemIRJET Journal
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2Narayan Mane
 
NgaiChung Lau, Portfolio
NgaiChung Lau, PortfolioNgaiChung Lau, Portfolio
NgaiChung Lau, PortfolioNgai Chung Lau
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
Software Project Management Plan
Software Project Management PlanSoftware Project Management Plan
Software Project Management PlanSeval Çapraz
 
A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...
A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...
A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...Andy McNamara
 

What's hot (19)

IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...
 
Engineering process flow
Engineering process flowEngineering process flow
Engineering process flow
 
ASHWIN A_Senior planning Engineer_
ASHWIN A_Senior planning Engineer_ASHWIN A_Senior planning Engineer_
ASHWIN A_Senior planning Engineer_
 
Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manual
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
prof. in eng. proj. mngt., const. mngt.
prof. in eng. proj. mngt., const. mngt.prof. in eng. proj. mngt., const. mngt.
prof. in eng. proj. mngt., const. mngt.
 
Use of network scheduling technique
Use of network scheduling technique Use of network scheduling technique
Use of network scheduling technique
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner System
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
NgaiChung Lau, Portfolio
NgaiChung Lau, PortfolioNgaiChung Lau, Portfolio
NgaiChung Lau, Portfolio
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Software Project Management Plan
Software Project Management PlanSoftware Project Management Plan
Software Project Management Plan
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...
A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...
A METHODOLOGICAL APPROACH TO SUPPORT BUILDING LIFE CYCLE ANALYSIS - Andy McNa...
 
Outage planning
Outage planningOutage planning
Outage planning
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 

Similar to IRJET- Optimization of Time and Cost of Building Construction using Fast Tracking Method of Scheduling

IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...IRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERACOMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERAIRJET Journal
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013IRJET Journal
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...IRJET Journal
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraIRJET Journal
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...IRJET Journal
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPIRJET Journal
 
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLINGREAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLINGIRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...IRJET Journal
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6IRJET Journal
 

Similar to IRJET- Optimization of Time and Cost of Building Construction using Fast Tracking Method of Scheduling (20)

IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERACOMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using Primavera
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLINGREAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
 
76 s201905
76 s20190576 s201905
76 s201905
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

IRJET- Optimization of Time and Cost of Building Construction using Fast Tracking Method of Scheduling

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1242 Optimization of Time and Cost of Building Construction using Fast Tracking Method of Scheduling Pooja Kamble1, Nadeem Sanadi2 1Post Graduate Student, Department of Civil Engineering, Jain College of Engineering Belagavi. 2Assistant Professor, Department of Civil Engineering, Jain College of Engineering Belagavi. ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - The purpose of this study is to assess causes and effects of cost and time overruns in construction projects. An effective project management tool is introduced in the form of Microsoft Project (MSP). In this project, Fast tracking method is adopted for planning and scheduling for the construction of Linemen Quarters using Microsoft Project (MSP) software. Various activities involved in the construction of linemen quarters are scheduled. A comparison between planned duration and cost in traditional method and by using project management tool such as Microsoft project is carried out. Key Words: Planning, Scheduling, Fast Tracking, Time Overrun, Cost Overrun. 1. INTRODUCTION The project management team should plan a project in such a way that completion of the project should be as on date with planned budget and resources. The project should meet all the set standards without compromising with the quality of work, budgeted cost and planned duration. A project which fulfills the abovementioned requirements is called a successful project. For the study, the case study considered involved construction of Linemen quarter for the staff in the town of Kanakapura, the details of which are mentioned below. 1.1Brief details of the project  Name of project: LM Quarters  Contractor: Sri Shivkumar S.M  Type: Residential building  Number of stories: G+2  Project Estimation Cost : Rs.18,417,844.79 The lineman Quarter is a G+2 building. Total area of the building is 989.64SQM. The linemen quarters are designed with bedroom, kitchen, balcony, living room, and bathroom. It is a 2BHK. And the ground floor is designed as the parking area. 2. OBJECTIVES OF PROJECT  To estimate the cost required to complete the project.  Estimating then duration required to complete the project along with individual activities.  Comparison of traditional method of planning to Planning using project Management Software.  Detailed Analysis of the dependency between the tasks.  Estimation of the cost using productivity details.  To fast track the project for early completion. 3. RESEARCH METHODOLOGY I. Literature study: A set of research papers, journal articles, project reports were studied to know the importance of Time, Cost and Qualityiin a constructioniproject. Efforts were made to understand the need of proper planning and management of Time, Cost andnQuality for successfulicompletioniof any project. II. Formulating problem statement: After the literature study and knowing the current needs of the industry, a problem statement was formed to conduct detailed study of a construction project and bring out a solution for efficient managementnof Time, Costiand Quality within the project. III. Fixing of Objectives: After conducting a brief literature review of various research articles, journals, project reports etc. based on the problem statement formulated a set of objectives were framed stick to which entire flow of the project will be worked on. IV. Data collection: The requiredidata was collected with respect to the research objective. Details of a project such as BOQ, Plans, Schedule, cost estimate, Detailed Project Report etc. were collected and studied. V. Analysis: The collected data is studied to understand status of the project, causes of delays, risks involved etc. A new project schedule for the same project is prepared using Microsoft Project Software which could guide the project in proper way for its successful completion. VI. Results: After analysing the project and preparing a detailed schedule of the project using Microsoft project (MSP) we could derive various details such as duration required for completion of project, total cost required, resource allocation plan etc.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1243 4. INVESTIGATION AND ANALYSIS 4.1 Estimation of the Project The estimation of the project was obtained and studied. The quantities were calculated in Microsoft Excel for each and every material and task such as earthwork excavation, reinforcement etc. The total budgeted cost after conducting estimation was Rs.18,417,844. 4.2 Planning and scheduling in Microsoft Project (MSP) All the activities in sequence were listed and a Work Breakdown Sequence was prepared in Microsoft Project (MSP). In the next step resource and duration were allotted for each and every activity. The activities later were linked with the one another by giving the predecessors. Budgeting was done after allocating the resources like manpower, material, and machinery used for the specified activity. The resources allocated were given with rate per unit so that when we allocate the number of resources required for the specified activity the software will automatically compute the total cost of the activity. Then the overall cost of the activities will give the overall cost of project. Fig.1.Planning of Project in MSP 5. RESULTS AND DISCUSSION Planning scheduling of the project is carried out in order to calculate the total duration of the project by creating work breakdown Structure (WBS) and allocating resources. In this duration was reduced by using Microsoft Project (MSP) which includes the finding of critical Path where the duration of the project can be changed by Fast tracking method. 5.1 Comparison of duration The actual planned duration using Microsoft excel was 381days, after using project management tool - Microsoft project (MSP) duration was found to be 328 days. The total time required was reduced by 53days after fast tracking. Fig.2. Comparision of duration 5.2 Project cost The budgeted cost of project by using Microsoft excel was Rs.18,417,844.79 Whereas, the estimated cost of project after fast tracking by using Microsoft project software (MSP) was Rs.18,417,707.22. The difference between conventional and modern method of estimation was 137.57 which deficits the estimate carried out the estimation cost appropriate. Table 5.2 Project Cost 6. CONCLUSIONS 1. By using a computer application like Microsoft project (MSP) to schedule gives the best results in construction projects. 2. The chronological planning of the construction activities and graphical representation on the Gantt chart is useful for superior understanding of the project. 3. Planning and scheduling in Microsoft project (MSP) proved to be more effective than in Microsoft Excel. Project In traditional method In MSP Linemen Quarters Rs.18,417,844.79 Rs.18,417,844.79
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1244 4. Reduction in duration was carried out for the project by fast tracking method. 5. Generally if the duration of the project is to be reduced, there will be a need to increase the amount of resources i.e. increase in the cost of the project. 6. In the current study the total budgeted cost of the project has been kept the same whereas reduction in the duration of construction is achieved. 7. Initially the duration of the project was 381 days after reduction the duration of project became 328 days. A Reduction of 53 days in the project schedule is achieved using project management tools and techniques. 7. REFERENCES [1] Anant Narayan Shete, Vaibhav Durwas Kothawade. (2016). An Analysis of Cost Overruns and Time Overruns of Construction Projects in India. International of Engineering Trends and Technology, 4(1),33- 36 [2] Erande, S. S., & Pimplikar, S. S. (2016). Total Quality Management in Indian construction industry. International Research Journal of Engineering and Technology, 3(6), 685-691. [3] Chidambaram, R., & Potty, N. S. (2014). Qualitative analysis of Time delay and Cost overrun in Multiple Design and Build Projects. Civil and Mechanical Engineering. [4] Sai Murali Krishna Reddy,Raya and S.S Bhanu Prakash(2016). Cost and time overruns in Indian construction industry. Industrial Science, 2(4), 1-9 [5] Chin-Keng, T. (2011). Study of quality management in construction projects. Chinese Business Review, 10(7). [6] Serpell, A., & Alarcon, L. F. (1998). Construction process improvement methodology for construction projects. International journal of project management, 16(4), 215-221. [7] Stasiak-Betlejewska, R., & Potkány, M. (2015). Construction costs analysis and its importance to the economy. Procedia Economics and Finance, 34, 35-42. [8] Mallawaarachchi, H., & Senaratne, S. (2015, December). Importance of quality for construction project success. In 6th International conference on structural engineering and construction management. [9] Shah, M. R., Pitroda, J., & Patel, C. G. Quality Control Management in Building Construction. [10] Monish Kumar K, Maheshwar S Maregowdru, Sparsha B.P. (2017).Construction Project scheduling of MK Apartment Using MS Project 2013. International Research Journal of Engineering and Technology 4(7) ,2275-2279 [11] Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International journal of project management, 30(4), 479-489. [12] Ashokkumar, D. (2014). Study of quality management in construction industry. International Journal of Innovative Research in Science, Engineering and Technology, 3(1), 36-43. BIOGRAPHIES POOJA V KAMBLE, is a Final Year Post Graduate student in Construction Technology in the Department of Civil Engineering of Jain College of Engineering Belagavi. NADEEM SANADI, is Assistant Professor in in the Department of Civil Engineering of Jain College of Engineering Belagavi. He has 1 Year of Teaching and over 2 years of experience in execution of Major Bridges.