This document discusses optimizing the time and cost of building construction projects using fast tracking scheduling methods. It analyzes a case study of constructing linemen quarters using Microsoft Project software. The study found that using fast tracking and project management tools like MSP reduced the planned project duration from 381 to 328 days, a 53 day reduction. The total estimated cost remained nearly the same between traditional and MSP scheduling methods. Thus fast tracking can help complete construction projects faster while maintaining budget.