SlideShare a Scribd company logo
M.Sc. Thesis
Presented by
Sudina Kuikel
Under the guidance of
Er. Sushil Chandra Tiwari (DDG, DoI)
Transportation Engineering and Management
Nepal Engineering College
Pokhara University
1
Introduction
Study Area
Literature Review
Research Methodology
Results and Discussion
Conclusion and Recommendation
2
Delay- costly, complex & risky problem
-Time overrun beyond completion date
significant implications (economic/social)
 People have to wait for services longer
 Reduce efficiency of available resources
 Limit the growth potential
 Brings drop in building activities
 Bad reputation
 Inability to secure project finance
3
 > 6,000 rivers and rivulets
 More than 50,000 LRN
(DOLIDAR, 2011)
 For all-weather >3,000
bridges required in LRN
 under construction and
design phase-200
 walkover survey-284
 demandlist-more than 2000
(DoLIDAR/LRBP, 2012)
4
-Delay and its effects in
most bridges
-Ranges from short
duration to many years
-Has a frightening
economic problem
- not only wastes
financial resources but
also reduces pace of
development activities
5
1
• What is the present situation of LRB construction?
2
• What are the real causes of delay in the LRB
construction sector?
3
• What are the clients, contractors and consultants
perceptions regarding delay and its effects in LRB
construction?
4
• What are the effects caused by delay in LRB
construction?
6
Analyze the present situation of different LRB of
different types having construction problem
To identify the causes of delays that currently exists in
construction performance and to evaluate their relative
importance
To study the differences in ideas of the three main
stakeholders, including clients, contractors and
consultants regarding delay.
Assess the implications of the delays especially in
terms of project duration and project cost
7
 Bridges being constructed by DoLIDAR
 only with limited number of stakeholders (consultants,
contractors and employer)
 Certain extents of the problems are assumed common
8
S. No.
Implementing
Agency
No. of Bridge
Completed
Under
construction
Total
1 Central (DoLIDAR) 0 7 7
2 DDC 17 48 65
3 JICA 0 32 32
4 RRRSDP 3 22 25
5 RAIDP - 12 12
6 DRILP - 5 5
7 RTI SWAp 9 3 12
Total 20 138 168 9
10
Study Area
 Why the particular site was selected
 Why particular type of bridge is proposed
 Site data and proposal for preparation
drawing
 Soil strata in the form of bore log
 Model study detail
 Salient features and quantities of each items
 Upto date approved structural drawings
 Details of all meetings and decision
 Decision making mechanism in dispute
Dhiman (2009)
11
Literature Review
INPUTDATAANALYSISOUTPUT
, Identification of causes of delay and its consequences
SCOPE
LRB of DoLIDAR
through different
programmes
STRATEGY
- Literature: finding common delay sources and
effects
- Project document: finding specific sources
- Stakeholders: Clarification, validity & finding new
LITERATURE STAKEHOLDERS
Client
Contractor
Consultant
Contracts details, diaries,
meeting record , project
report and schedules
List of causes &
effects (69 causes-11
category & 15 effects)
PROJECT SELECTION
- 16 Projects ( GoN &
donor implemented
including all ecological
region)
Interview DTO , LBS
& LRBSU personnel
Situation of bridges
Discussion with local
Safety measuresRanking causes and
effects
Questionnaire survey
Analysis of data
Statistical tool
(Mean, SD, RII)
Site Observation
- major causes & effects
-Ranking of causes and effects in the view of all
-Ranking category wise and in average
---View analysis
CONCLUSION
- Delay causes
- Delay effects
-Ranking of cause and
effects
Methodology
13
58
34
8
How common is delay %
very
common
common
not so
common
18
40
30
12
0
5
10
15
20
25
30
35
40
45 frequency of schedule revision %
once
twice
thrice
more than
three
Response rate of
Questionnaire
S.N Distributed Return %
1 Client 85.72
2 Contractor 60
4 Consultant 77.4
Total 74.28
Data Analysis
and findings
5.26
6.03
5.22
4.73 4.53
5.06
5.52 5.50 4.93
6.18
4.98
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
Averagemeanscore
Cause category 14
Results &
discussion
15
Name of Bridge Funding Agency
Delay
(%)
Cost Overruns (%)
Cause of Delay (Related
Category)
Phalame Gauda GoN 95 46 Site Condition
Man Nadi GoN 48 5.21 Site Condition
Surahi Nala GoN 31 14 Site Condition
Chauri Khola GoN 55 0 Management
Likhu Khola GoN 29 10 Consultant, Contractor
Ladku khola ADB 20 14 Contractor
Kerunga GoN 10 0 Financial
Roshi JICA 24.1 24.9 Management, Employer
Teli Khola GoN 111 21 Financial
Khani Khola GoN 20 14.5 Site Condition
Roshi 2 JICA 32.8 5.3 Contractor, Management
Marin JICA 19.6 4.3 Management
Thosne ADB 15 0 Site Condition
Siwa Khola ADB 67 10.8 External, consultant
Mulsangu ADB 58 19.6 Site Condition
Dans GoN 78 29 Financial
Results & discussion
Contractor
1. Long time to get permits and
approvals for the employer
2. The employer’s late approvals
3. Slow decision making process of
the employer
4. Strikes, riots and wheel locks
(Bandha)
5. Consultants slowness in giving
instructions
Consultant
1. Frequent changes of government
2. Deficiencies in planning and
scheduling
3. Improper scheduling or problem
in scheduling
4. Inadequate labor force of the
contractor
5. Politically motivated decision of
employer
16
Results &
discussion
S.
N
Cause of Delay
Rank
Group
Employer Contractor Consultant
1 Deficiencies in planning 3 29 2 Management
2 Shortage of power supply 12 6 12 Material
3 Political interference 19 10 7 External
4 Improper scheduling 15 21 3 Management
5 Strikes, riots, wheel locks 16 4 26 External
6 Land/Resettlement problem 25 13 6 Site condition
7
Politically motivated decision of
employer
23 14 5 Employer
8 Frequent changes of government 22 38 1 External
9 Long time to get permits 27 1 29 Employer
10 Selection of improper site 14 8 40 Site condition17
Data Analysis
0
20
40
60
80
100
120
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Overrun%
Cases
Effects of delay
Time
Cost
Findings and
discussion
Donor funded
less time
overrun in
comparison
Problem of
timely budget
unavailability
in GoN funded
1. Time overrun
2. Cost overrun
3. Idling resources
4. Adverse impact on overall national economy
5. Loss reputation of parties
19
Findings
 92% of the respondents agreed that delay problem
is major in bridge construction
 Frequency of original schedule revision in project
period is two and more
 The client’s consultant’s and contractor’s
contribution to causes of delay is of 19.64%, 8.9%
and 12.5% respectively
 Site condition and management category is found
to be the most critical factor
 Time overrun, cost overrun and idling resources
are the major effects identified
 Difference in opinion for causes and similar views
for effects ranking of stakeholders
20
1. Separate site clearance (acquisition) work from
construction work & must be finished before
estimating cost and schedule for construction phase
and bidding work
2. Give high priority to site investigation and site
selection
3. BMIS should be made effective
4. Make clear responsibilities among parties in the
contract document
5. Make planning and scheduling and match with the
resources and time to develop the work
6. Government should run only those projects for
which it can arrange the funds timely and assure
continuity
21
22
23
References
Abbas, M.I., 2006. Causes and Effects of Delays in Aceh Construction Industry, Master's Thesis, Universiti
Teknology, Malaysia
Adhikari, R., 2004. Construction Management, Akshalok Prakasan, Kathmandu, Nepal.
Agaba, E., 2009. Poor Planning Delaying Government Projects (Business News Pullout), The New Vision,
Thursday, 24 (2), pp.16
Agrawal, G. R., 2003. Project management in Nepal, M.K. Publishers, Kathmandu, Nepal
Ahmed, S. M., S. Azhar, P. Kappagantula, & M. Castillo, 2003. Construction Delays in Florida: An Empirical Study,
Florida
Ahuja, H.N., Dozzi, S.P.,& Abourizk,S.M.,1994. Construction Industry Management, J.Wiley, New York, USA.
Aibinu, A. & Jagboro, G., 2002. The effects of construction delays on project delivery in
Nigerian construction industry, International Journal of Project Management, 20, pp.593.
Alaghbari, W., Razali, M., Kadir S. & Ernawati G., 2007. The significant factors causing delay of building
construction projects in Malaysia, Engineering, Construction and
Architectural Management, 14 (2), pp. 192-206.
Al-Gahtani, K. & Mohan S., 2007. Total float management for delay analysis. Journal of Cost Engineering, 49 (2),
pp. 32-37.
24
Alkass, S., Mazerolle, M., & Harris, F., 1996. Construction delay analysis techniques,
Journal of Construction Management and Economics, 14, pp. 375-394
Al-Khalil, M. & Al- Ghafly, M.A., 1999. Important causes of delay in public utility
projects in Saudi Arabia, International Journal of Project Management, 17(2), pp 647-
655
Al-Najjar, J., 2008. Factors Influencing Time and Cost Overruns on Construction
Projects in the Gaza Strip, Master Thesis, The Islamic University of Gaza, Gaza
Arditi, D., Akan, G.T. & Gurdamar, S. 1985. Reasons for delays in public projects n
Turkey, Construction Management and Economics, 3, pp. 171-181
Arshi, S.F., & Sameh, 2006. Significant factors causing delay in UAE construction
industry, Construction Management and Economics 24: pp. 1167-1176
Assaf, S. A. & Al-Hejji, S., 2006. Causes of delay in large construction projects,
International Journal of Project Management, 24(4), pp. 349-57
25

More Related Content

What's hot

Risk management
Risk managementRisk management
Risk management
nashaat algrara
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
1. introduction cm 2014
1. introduction cm 20141. introduction cm 2014
1. introduction cm 2014
dattseg
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Michael Pink
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
Shree Swami atmanand saraswati inst. of technology, surat
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
Hamza Waheed
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
Anupama holla
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
Ary Jamil
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
Md Mohsin Mohsin
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
Manit Agarwal
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
Akshika Mahanama
 
construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
SHAZEBALIKHAN1
 
Construction project management
Construction project managementConstruction project management
Construction project management
saif hasan
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
srinivas2036
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
SivaSubramanian Sakthivel
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
elliotfus
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
katrin enders
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
A Makwana
 

What's hot (20)

Risk management
Risk managementRisk management
Risk management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
1. introduction cm 2014
1. introduction cm 20141. introduction cm 2014
1. introduction cm 2014
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 

Similar to causes and implication of delay in construction

Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
IJERA Editor
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
B012140812
B012140812B012140812
B012140812
IOSR Journals
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
IRJET Journal
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
IOSR Journals
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
IAEME Publication
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential Structures
IRJESJOURNAL
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
IRJET Journal
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
IJRES Journal
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
Est
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
EbrahimJemal4
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
IRJET Journal
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
Doreen Yeo
 

Similar to causes and implication of delay in construction (20)

Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential Structures
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 

Recently uploaded

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 

Recently uploaded (20)

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 

causes and implication of delay in construction

  • 1. M.Sc. Thesis Presented by Sudina Kuikel Under the guidance of Er. Sushil Chandra Tiwari (DDG, DoI) Transportation Engineering and Management Nepal Engineering College Pokhara University 1
  • 2. Introduction Study Area Literature Review Research Methodology Results and Discussion Conclusion and Recommendation 2
  • 3. Delay- costly, complex & risky problem -Time overrun beyond completion date significant implications (economic/social)  People have to wait for services longer  Reduce efficiency of available resources  Limit the growth potential  Brings drop in building activities  Bad reputation  Inability to secure project finance 3
  • 4.  > 6,000 rivers and rivulets  More than 50,000 LRN (DOLIDAR, 2011)  For all-weather >3,000 bridges required in LRN  under construction and design phase-200  walkover survey-284  demandlist-more than 2000 (DoLIDAR/LRBP, 2012) 4
  • 5. -Delay and its effects in most bridges -Ranges from short duration to many years -Has a frightening economic problem - not only wastes financial resources but also reduces pace of development activities 5
  • 6. 1 • What is the present situation of LRB construction? 2 • What are the real causes of delay in the LRB construction sector? 3 • What are the clients, contractors and consultants perceptions regarding delay and its effects in LRB construction? 4 • What are the effects caused by delay in LRB construction? 6
  • 7. Analyze the present situation of different LRB of different types having construction problem To identify the causes of delays that currently exists in construction performance and to evaluate their relative importance To study the differences in ideas of the three main stakeholders, including clients, contractors and consultants regarding delay. Assess the implications of the delays especially in terms of project duration and project cost 7
  • 8.  Bridges being constructed by DoLIDAR  only with limited number of stakeholders (consultants, contractors and employer)  Certain extents of the problems are assumed common 8
  • 9. S. No. Implementing Agency No. of Bridge Completed Under construction Total 1 Central (DoLIDAR) 0 7 7 2 DDC 17 48 65 3 JICA 0 32 32 4 RRRSDP 3 22 25 5 RAIDP - 12 12 6 DRILP - 5 5 7 RTI SWAp 9 3 12 Total 20 138 168 9
  • 11.  Why the particular site was selected  Why particular type of bridge is proposed  Site data and proposal for preparation drawing  Soil strata in the form of bore log  Model study detail  Salient features and quantities of each items  Upto date approved structural drawings  Details of all meetings and decision  Decision making mechanism in dispute Dhiman (2009) 11 Literature Review
  • 12. INPUTDATAANALYSISOUTPUT , Identification of causes of delay and its consequences SCOPE LRB of DoLIDAR through different programmes STRATEGY - Literature: finding common delay sources and effects - Project document: finding specific sources - Stakeholders: Clarification, validity & finding new LITERATURE STAKEHOLDERS Client Contractor Consultant Contracts details, diaries, meeting record , project report and schedules List of causes & effects (69 causes-11 category & 15 effects) PROJECT SELECTION - 16 Projects ( GoN & donor implemented including all ecological region) Interview DTO , LBS & LRBSU personnel Situation of bridges Discussion with local Safety measuresRanking causes and effects Questionnaire survey Analysis of data Statistical tool (Mean, SD, RII) Site Observation - major causes & effects -Ranking of causes and effects in the view of all -Ranking category wise and in average ---View analysis CONCLUSION - Delay causes - Delay effects -Ranking of cause and effects Methodology
  • 13. 13 58 34 8 How common is delay % very common common not so common 18 40 30 12 0 5 10 15 20 25 30 35 40 45 frequency of schedule revision % once twice thrice more than three Response rate of Questionnaire S.N Distributed Return % 1 Client 85.72 2 Contractor 60 4 Consultant 77.4 Total 74.28 Data Analysis and findings
  • 14. 5.26 6.03 5.22 4.73 4.53 5.06 5.52 5.50 4.93 6.18 4.98 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 Averagemeanscore Cause category 14 Results & discussion
  • 15. 15 Name of Bridge Funding Agency Delay (%) Cost Overruns (%) Cause of Delay (Related Category) Phalame Gauda GoN 95 46 Site Condition Man Nadi GoN 48 5.21 Site Condition Surahi Nala GoN 31 14 Site Condition Chauri Khola GoN 55 0 Management Likhu Khola GoN 29 10 Consultant, Contractor Ladku khola ADB 20 14 Contractor Kerunga GoN 10 0 Financial Roshi JICA 24.1 24.9 Management, Employer Teli Khola GoN 111 21 Financial Khani Khola GoN 20 14.5 Site Condition Roshi 2 JICA 32.8 5.3 Contractor, Management Marin JICA 19.6 4.3 Management Thosne ADB 15 0 Site Condition Siwa Khola ADB 67 10.8 External, consultant Mulsangu ADB 58 19.6 Site Condition Dans GoN 78 29 Financial Results & discussion
  • 16. Contractor 1. Long time to get permits and approvals for the employer 2. The employer’s late approvals 3. Slow decision making process of the employer 4. Strikes, riots and wheel locks (Bandha) 5. Consultants slowness in giving instructions Consultant 1. Frequent changes of government 2. Deficiencies in planning and scheduling 3. Improper scheduling or problem in scheduling 4. Inadequate labor force of the contractor 5. Politically motivated decision of employer 16 Results & discussion
  • 17. S. N Cause of Delay Rank Group Employer Contractor Consultant 1 Deficiencies in planning 3 29 2 Management 2 Shortage of power supply 12 6 12 Material 3 Political interference 19 10 7 External 4 Improper scheduling 15 21 3 Management 5 Strikes, riots, wheel locks 16 4 26 External 6 Land/Resettlement problem 25 13 6 Site condition 7 Politically motivated decision of employer 23 14 5 Employer 8 Frequent changes of government 22 38 1 External 9 Long time to get permits 27 1 29 Employer 10 Selection of improper site 14 8 40 Site condition17 Data Analysis
  • 18. 0 20 40 60 80 100 120 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Overrun% Cases Effects of delay Time Cost Findings and discussion Donor funded less time overrun in comparison Problem of timely budget unavailability in GoN funded
  • 19. 1. Time overrun 2. Cost overrun 3. Idling resources 4. Adverse impact on overall national economy 5. Loss reputation of parties 19 Findings
  • 20.  92% of the respondents agreed that delay problem is major in bridge construction  Frequency of original schedule revision in project period is two and more  The client’s consultant’s and contractor’s contribution to causes of delay is of 19.64%, 8.9% and 12.5% respectively  Site condition and management category is found to be the most critical factor  Time overrun, cost overrun and idling resources are the major effects identified  Difference in opinion for causes and similar views for effects ranking of stakeholders 20
  • 21. 1. Separate site clearance (acquisition) work from construction work & must be finished before estimating cost and schedule for construction phase and bidding work 2. Give high priority to site investigation and site selection 3. BMIS should be made effective 4. Make clear responsibilities among parties in the contract document 5. Make planning and scheduling and match with the resources and time to develop the work 6. Government should run only those projects for which it can arrange the funds timely and assure continuity 21
  • 22. 22
  • 23. 23 References Abbas, M.I., 2006. Causes and Effects of Delays in Aceh Construction Industry, Master's Thesis, Universiti Teknology, Malaysia Adhikari, R., 2004. Construction Management, Akshalok Prakasan, Kathmandu, Nepal. Agaba, E., 2009. Poor Planning Delaying Government Projects (Business News Pullout), The New Vision, Thursday, 24 (2), pp.16 Agrawal, G. R., 2003. Project management in Nepal, M.K. Publishers, Kathmandu, Nepal Ahmed, S. M., S. Azhar, P. Kappagantula, & M. Castillo, 2003. Construction Delays in Florida: An Empirical Study, Florida Ahuja, H.N., Dozzi, S.P.,& Abourizk,S.M.,1994. Construction Industry Management, J.Wiley, New York, USA. Aibinu, A. & Jagboro, G., 2002. The effects of construction delays on project delivery in Nigerian construction industry, International Journal of Project Management, 20, pp.593. Alaghbari, W., Razali, M., Kadir S. & Ernawati G., 2007. The significant factors causing delay of building construction projects in Malaysia, Engineering, Construction and Architectural Management, 14 (2), pp. 192-206. Al-Gahtani, K. & Mohan S., 2007. Total float management for delay analysis. Journal of Cost Engineering, 49 (2), pp. 32-37.
  • 24. 24 Alkass, S., Mazerolle, M., & Harris, F., 1996. Construction delay analysis techniques, Journal of Construction Management and Economics, 14, pp. 375-394 Al-Khalil, M. & Al- Ghafly, M.A., 1999. Important causes of delay in public utility projects in Saudi Arabia, International Journal of Project Management, 17(2), pp 647- 655 Al-Najjar, J., 2008. Factors Influencing Time and Cost Overruns on Construction Projects in the Gaza Strip, Master Thesis, The Islamic University of Gaza, Gaza Arditi, D., Akan, G.T. & Gurdamar, S. 1985. Reasons for delays in public projects n Turkey, Construction Management and Economics, 3, pp. 171-181 Arshi, S.F., & Sameh, 2006. Significant factors causing delay in UAE construction industry, Construction Management and Economics 24: pp. 1167-1176 Assaf, S. A. & Al-Hejji, S., 2006. Causes of delay in large construction projects, International Journal of Project Management, 24(4), pp. 349-57
  • 25. 25