SlideShare a Scribd company logo
1 of 36
To Minimize The Time And Cost Overrun Of The
Similar Projects
Syed Jabir Hussain 13CE12
Arshad Khan 13CE41
Israfel Bangash 13CE53
Mohammad Emad 13CE70
Department of Civil Engineering Sweedish College Wah cantt Taxila
3Department of Civil Engineering Sweedish College Wah cantt Taxila
4
1
• Introduction, Problem Statement
2
• Literature Review & Research Objectives
3
• Methodology
4
• Results & Discussion
5
• Conclusions and Recommendation
6
• Future Scope
SEQUENCE OF PRESENTATION
Department of Civil Engineering Swedish College Wah cantt Taxila
5
Over view Of Our Project
2) Structural Drawing
1) Specification
4) BOQ
Standard And Non
Standard
7) Primavera P6
3) Architectural
Drawing
6) Estimation
5) MRS and CSR
7)Result
Department of Civil Engineering Sweedish College Wah cantt Taxila
INTRODUCTION
INTRODUCTION
6
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Recommendation
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
What is a Project?
A project is a temporary endeavor undertaken to create a unique product,
service, or result. The temporary nature of projects indicates that a project
has a definite beginning and end
What is Project Management?
Project management is the application of knowledge, skills, tools, and
techniques to project activities to meet the project requirements.
7
The Triple Constraint of Projects
• On Time, Budget, Quality = Required Scope
SCOPE
Time
Cost Quality
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Recommendation
Introduction & Problem
Statement
INTRODUCTION
Department of Civil Engineering Sweedish College Wah cantt Taxila
Planning Engineer Roles and
Responsibilities
8
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
Prepare and update project schedule based on the contract. Set
work program and target milestones for each phase based on the
project plan....
USING PRIMAVERA P6
INTRODUCTION
Conclusions &
Recommendation
 Prepare and update project schedule based on the contract.
 Set work program and target milestones for each phase based on the project
plan.
 Monitor critical activities based on the project schedule and advise project
management.
 Prepare look ahead plan for the Execution team.
 Monitor day to day work progress and prepare the weekly and monthly
program and report.
 Prepares monthly report reflecting work progress summary.
 Performs other duties and responsibilities as may be assigned from time to
time.
9
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Recommendation
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
INTRODUCTION
 Appropriately skilled & experience Project Manager
 Clear authority for the PM to act
 Commitment to the PM methodology
 A skilled PM team agreed to the project goals
 A complete project plan that is understood by all participants
 Objectives that contribute to the larger goals of the organization
10
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
Success Factors In Project Management:
INTRODUCTION
Conclusions &
Recommendation
The project management process accomplished through the Following five
groups.
1. Initiating,
2. Planning,
3. Executing,
4. Monitoring and Controlling, and
5. Closing.
11
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Recommendation
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
12
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Recommendation
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
13
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
Common Types of Construction Contracts
1) Lump Sum or Fixed Price
Contract Type
2) Item Rate Contract
3) Measurement contract
4) Percentage Rate Contract
Cost are basically two types
14
COST
Indirect
Cost
Direct
Cost
Cost of (Material )
Gravel, Sand , Cement
etc.
 Accounting and legal expenses
 Administrative Salaries
 Office Expenses
 Rent
 Telephone Expenses
 Utilities
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
INTRODUCTION
15
COST
Indirect
Cost
Direct
Cost
TOTAL COST =
RS: 1017002.47/-
TOTAL COST =
RS: 10164000/-
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
INTRODUCTION
Department of Civil Engineering Sweedish College Wah cantt TaxilaDepartment of Civil Engineering Sweedish College Wah cantt Taxila
TOTAL COST (DIRECT + INDIRECT)
= RS: 11181002.47/-
16
Department of Civil Engineering Sweedish College Wah cantt TaxilaDepartment of Civil Engineering Sweedish College Wah cantt Taxila
INTRODUCTION Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Duration
1) Similarity to other
activities
2) Historical data
3) Expert advice
4) Delphi technique
5) Three-point technique
Expert
Advice
Qamar Rohal Hasan
(Project manager of
Telenor head Islamabad)
Naveed Nawaz
(Project manager of
Paradise city center
bahria town )
Habib Rafiq
(Project Manager of
District Complex
Rawalakot)
Productivity Base
Experience Base
171717
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
PROBLEM STATEMENT
1818
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Introduction & Problem
Statement
Conclusions &
Contribution
A cost overrun, also known as
a cost
increase, underrated or budget
overrun, involves
unexpected costs incurred in
excess of budgeted amounts due
to an underestimation of the
actual cost during budgeting
A time overrun, also known as a
time increase is an unexpected
time incurred in excess of a
estimated/ allocated time
Time Over-Run Cost Over-Run
Department of Civil Engineering Sweedish College Wah cantt Taxila
PROBLEM STATEMENT
INTRODUCTION
19
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
CostOverrunPOORDECISION
MAKING
COMMUNICATIONGAP
INACCURATE
ESTIMATION
PROCUREMENT
DELAYS
Discussing causes of cost overrun is a step in enhancing the professional practice through trying to
avoiding the occurrence or the impact of these causes
Department of Civil Engineering Sweedish College Wah cantt Taxila
BOQ(MISSING DATA)
Scope Change(Material
changes)
20
Time
OverrunContractor‟spoor
sitemanagement
Poor estimateproject
duration
Incompetent
designers
Shortageofsite
workers
Late Decision for
approval of materials
Changes in scope of projects
Unforeseen problems
(adverseweathercondition)
INTRODUCTION
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
PROBLEM STATEMENT
OBJECTIVIES
To minimize the Cost over Budget
To minimize the Time over Run
21
LITERATUREREVIEW Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
REVIEW OF PAST STUDIES
LITERATUREREVIEW
Study Year of Study Research Findings
Mohammadreza Emadi
Andani & Golsa Moshayedi 2016 Cost Control in Construction Project Using Primavera Project Planner
Oko John Ameh, Department
of Building, University of
Lagos, Nigeria
Number 2011
STUDY OF RELATIONSHIP BETWEEN TIME OVERRUN AND
PRODUCTIVITY ON CONSTRUCTION SITES
U.Sindhu Vaardini
S.Karthiyayini
2016 STUDY ON COST OVERRUNS IN CONSTRUCTION PROJECTS.
Sindhu Vaardini September 2015
IDENTIFICATION OF CAUSES AND IMPACTS OF TIME
OVERRUN IN CONSTRUCTION PROJECTS
Nabil Al-Hazim, Zaydoun Abu
Salem, Hesham Ahmad*
2008 Delay and Cost Overrun in Infrastructure Projects in Jordan
22
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
COST
SENIOR DOCTOR
BUILDING PHASE (2)
FACTORS WHICH EFFECT BUILIDING
ANALYSIS
1) SCOPE Change
2) BOQ ( MISSING DATA )
3) PROCUREMENT DELAYS
1) Changes in scope of projects
2) Unforeseen problems
3) Late Decision for approval
of materials
TIME
1) BOQ VARIENCES
2) POOR MANAGEMENT
3) POOR PLANNING
4) DELAYED AND FUNDING
BOQ
NON
STANDARD
STANDARD
GOVT OF PUNJAB
(MRS)
CONTRACTOR
(BIDDING)
SENIOR DOCTOR BUILDING
Department of Civil Engineering Sweedish College Wah cantt Taxila
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
METHODOLOGY
24
RESEARCHOBJECTIVES
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
25
PRIMAVERA (P6)
(EPS)
ENTERPRISE
STRUCTURE
OBS
(ORGATIONAL
BREAK DOWN
STRUCTURE)
Department of Civil Engineering Sweedish College Wah cantt Taxila
26
OBS (Organizational Break Down Structure)
Department of Civil Engineering Sweedish College Wah cantt Taxila
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
27
(EPS)
ENTERPRISE
STRUCTURE
OBS
(ORGATIONAL
BREAK DOWN
STRUCTURE)
PRIMAVERA (P6)
CALENDAR
RESOURCES
GLOBAL
PROJECT
METHODOLOGY
Department of Civil Engineering Sweedish College Wah cantt Taxila
28
METHODOLOGY
CALENDAR
GLOBAL PROJECTRESOURCES
Department of Civil Engineering Sweedish College Wah cantt Taxila
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
METHODOLOGY
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
29
Work Break Down Structure (WBS)
Department of Civil Engineering Sweedish College Wah cantt Taxila
30
METHODOLOGY
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
RESOURCES SHEET
Department of Civil Engineering Sweedish College Wah cantt Taxila
31
METHODOLOGY
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
Activities
32
METHODOLOGY
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
Gantt Chart
33
METHODOLOGY
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
S CURVE ( RESOURCES)
– Time and cost overrun DIFFERNECE:
 COST OVERRUN:
• Previous project completed RS 90821925.3/- while
our project will be completed in RS 80640922.56/-
 TIME COMPARISON:
• Previous project completed in 24 month while our
project planning is completing in 12 months.
34
METHODOLOGY
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila
RESULTS&ANALYSES
35
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
Introduction & Problem
Statement
Department of Civil Engineering Sweedish College Wah cantt Taxila35
Company required to complete their project with
specific TIME and COST and to maintain a
required SCOPE and QUALITY
• On Time, Budget, Quality = Required Scope
SCOPE
Time
Cost Quality
Research Objectives &
Literature Review
Research
Methodology
Results &
Analyses
Conclusions &
Recommendation
Introduction & Problem
Statement
LABORATORY CHARACTERIZATION OF ASPHALT MIXTURES USING DYNAMIC
MODULUS TEST
Department of Transportation Engineering, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National
University of Sciences and Technology (NUST), Islamabad, Pakistan.
Research
Methodology
Results &
Analyses
Conclusions &
Contribution
7/6
Research Objectives &
Literature Review
Introduction & Problem
Statement
Date 36
QUESTIONS

More Related Content

What's hot

Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility studyMars Mfyam
 
Statement of work (SOW) for project
Statement of work (SOW) for projectStatement of work (SOW) for project
Statement of work (SOW) for projectSk Habib
 
Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Hari Krishna Shrestha
 
Project scope management
Project scope managementProject scope management
Project scope managementAnit Roy
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
Project Management Notes 5
Project Management Notes 5Project Management Notes 5
Project Management Notes 5Golam Bitonsir
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTSAJJAD KHUDHUR ABBAS
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.pptMohammedAbdu46
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay AnalysisChris Carson
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 

What's hot (20)

Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility study
 
Statement of work (SOW) for project
Statement of work (SOW) for projectStatement of work (SOW) for project
Statement of work (SOW) for project
 
Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10Construction Management in Developing Countries, Lecture 10
Construction Management in Developing Countries, Lecture 10
 
fidic , jct and nec contracts
fidic , jct and nec contractsfidic , jct and nec contracts
fidic , jct and nec contracts
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
How to close a project
How to close a projectHow to close a project
How to close a project
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Project Management Notes 5
Project Management Notes 5Project Management Notes 5
Project Management Notes 5
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXT
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Construction Contract PPT.ppt
Construction Contract PPT.pptConstruction Contract PPT.ppt
Construction Contract PPT.ppt
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Project termination, reporting and project closure
Project termination, reporting and project closureProject termination, reporting and project closure
Project termination, reporting and project closure
 
Construction contract
Construction contract Construction contract
Construction contract
 
3 project life cycle
3   project life cycle3   project life cycle
3 project life cycle
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 

Similar to To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )

IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...IRJET Journal
 
Impact of Rework on Cost and Schedule
Impact of Rework on Cost and ScheduleImpact of Rework on Cost and Schedule
Impact of Rework on Cost and Scheduleskalema34
 
Project Defense
Project DefenseProject Defense
Project DefenseAli Zannah
 
deddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdf
deddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdfdeddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdf
deddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdfvishnu. R
 
Outcome Based Education - Comsats Abbottabad - Civil Engineering.pptx
Outcome Based Education - Comsats Abbottabad - Civil Engineering.pptxOutcome Based Education - Comsats Abbottabad - Civil Engineering.pptx
Outcome Based Education - Comsats Abbottabad - Civil Engineering.pptxAwais Marwat
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptxMd Polash
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
OBE Course Curriculum .pptx
OBE Course Curriculum .pptxOBE Course Curriculum .pptx
OBE Course Curriculum .pptxMsNazninAkter
 
MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...
MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...
MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...cscpconf
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramIJAEMSJORNAL
 
OBE Model-CLO-PLO.pptx
OBE Model-CLO-PLO.pptxOBE Model-CLO-PLO.pptx
OBE Model-CLO-PLO.pptxAdilZohaib2
 
OCCD-PE Training Course Intrdouction
OCCD-PE Training Course IntrdouctionOCCD-PE Training Course Intrdouction
OCCD-PE Training Course IntrdouctionGalala University
 
Process Modeling with IDEF 0
Process Modeling with IDEF 0Process Modeling with IDEF 0
Process Modeling with IDEF 0Mandar Trivedi
 
A) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docx
A) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docxA) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docx
A) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docxbayazid11
 
RD-Project-Proposal-Project-Management-for-Engineering.pdf
RD-Project-Proposal-Project-Management-for-Engineering.pdfRD-Project-Proposal-Project-Management-for-Engineering.pdf
RD-Project-Proposal-Project-Management-for-Engineering.pdfAzeruFelix
 

Similar to To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera ) (20)

IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
Impact of Rework on Cost and Schedule
Impact of Rework on Cost and ScheduleImpact of Rework on Cost and Schedule
Impact of Rework on Cost and Schedule
 
Project Defense
Project DefenseProject Defense
Project Defense
 
deddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdf
deddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdfdeddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdf
deddddddsdfaasdfasdfasdfasdfasdfasdfscriptor.pdf
 
Outcome Based Education - Comsats Abbottabad - Civil Engineering.pptx
Outcome Based Education - Comsats Abbottabad - Civil Engineering.pptxOutcome Based Education - Comsats Abbottabad - Civil Engineering.pptx
Outcome Based Education - Comsats Abbottabad - Civil Engineering.pptx
 
Vivek_Mohanta_QS
Vivek_Mohanta_QSVivek_Mohanta_QS
Vivek_Mohanta_QS
 
BASEEM
BASEEMBASEEM
BASEEM
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
OBE Course Curriculum .pptx
OBE Course Curriculum .pptxOBE Course Curriculum .pptx
OBE Course Curriculum .pptx
 
MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...
MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...
MOVING FROM WATERFALL TO AGILE PROCESS IN SOFTWARE ENGINEERING CAPSTONE PROJE...
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
Project planning: A career path
Project planning: A career pathProject planning: A career path
Project planning: A career path
 
OBE Model-CLO-PLO.pptx
OBE Model-CLO-PLO.pptxOBE Model-CLO-PLO.pptx
OBE Model-CLO-PLO.pptx
 
OCCD-PE Training Course Intrdouction
OCCD-PE Training Course IntrdouctionOCCD-PE Training Course Intrdouction
OCCD-PE Training Course Intrdouction
 
Process Modeling with IDEF 0
Process Modeling with IDEF 0Process Modeling with IDEF 0
Process Modeling with IDEF 0
 
A) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docx
A) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docxA) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docx
A) RUBRIK DGP6152 PROJEK 2 tahun 2024 20252022.docx
 
Sathish-CV.-2Nov16
Sathish-CV.-2Nov16Sathish-CV.-2Nov16
Sathish-CV.-2Nov16
 
RD-Project-Proposal-Project-Management-for-Engineering.pdf
RD-Project-Proposal-Project-Management-for-Engineering.pdfRD-Project-Proposal-Project-Management-for-Engineering.pdf
RD-Project-Proposal-Project-Management-for-Engineering.pdf
 

Recently uploaded

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )

  • 1.
  • 2. To Minimize The Time And Cost Overrun Of The Similar Projects Syed Jabir Hussain 13CE12 Arshad Khan 13CE41 Israfel Bangash 13CE53 Mohammad Emad 13CE70 Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 3. 3Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 4. 4 1 • Introduction, Problem Statement 2 • Literature Review & Research Objectives 3 • Methodology 4 • Results & Discussion 5 • Conclusions and Recommendation 6 • Future Scope SEQUENCE OF PRESENTATION Department of Civil Engineering Swedish College Wah cantt Taxila
  • 5. 5 Over view Of Our Project 2) Structural Drawing 1) Specification 4) BOQ Standard And Non Standard 7) Primavera P6 3) Architectural Drawing 6) Estimation 5) MRS and CSR 7)Result Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 6. INTRODUCTION INTRODUCTION 6 Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Recommendation Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila What is a Project? A project is a temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates that a project has a definite beginning and end What is Project Management? Project management is the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
  • 7. 7 The Triple Constraint of Projects • On Time, Budget, Quality = Required Scope SCOPE Time Cost Quality INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Recommendation Introduction & Problem Statement INTRODUCTION Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 8. Planning Engineer Roles and Responsibilities 8 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila Prepare and update project schedule based on the contract. Set work program and target milestones for each phase based on the project plan.... USING PRIMAVERA P6 INTRODUCTION Conclusions & Recommendation
  • 9.  Prepare and update project schedule based on the contract.  Set work program and target milestones for each phase based on the project plan.  Monitor critical activities based on the project schedule and advise project management.  Prepare look ahead plan for the Execution team.  Monitor day to day work progress and prepare the weekly and monthly program and report.  Prepares monthly report reflecting work progress summary.  Performs other duties and responsibilities as may be assigned from time to time. 9 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Recommendation Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila INTRODUCTION
  • 10.  Appropriately skilled & experience Project Manager  Clear authority for the PM to act  Commitment to the PM methodology  A skilled PM team agreed to the project goals  A complete project plan that is understood by all participants  Objectives that contribute to the larger goals of the organization 10 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila Success Factors In Project Management: INTRODUCTION Conclusions & Recommendation
  • 11. The project management process accomplished through the Following five groups. 1. Initiating, 2. Planning, 3. Executing, 4. Monitoring and Controlling, and 5. Closing. 11 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Recommendation Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 12. 12 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Recommendation Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 13. 13 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila Common Types of Construction Contracts 1) Lump Sum or Fixed Price Contract Type 2) Item Rate Contract 3) Measurement contract 4) Percentage Rate Contract
  • 14. Cost are basically two types 14 COST Indirect Cost Direct Cost Cost of (Material ) Gravel, Sand , Cement etc.  Accounting and legal expenses  Administrative Salaries  Office Expenses  Rent  Telephone Expenses  Utilities INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila INTRODUCTION
  • 15. 15 COST Indirect Cost Direct Cost TOTAL COST = RS: 1017002.47/- TOTAL COST = RS: 10164000/- INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement INTRODUCTION Department of Civil Engineering Sweedish College Wah cantt TaxilaDepartment of Civil Engineering Sweedish College Wah cantt Taxila TOTAL COST (DIRECT + INDIRECT) = RS: 11181002.47/-
  • 16. 16 Department of Civil Engineering Sweedish College Wah cantt TaxilaDepartment of Civil Engineering Sweedish College Wah cantt Taxila INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Duration 1) Similarity to other activities 2) Historical data 3) Expert advice 4) Delphi technique 5) Three-point technique Expert Advice Qamar Rohal Hasan (Project manager of Telenor head Islamabad) Naveed Nawaz (Project manager of Paradise city center bahria town ) Habib Rafiq (Project Manager of District Complex Rawalakot) Productivity Base Experience Base
  • 17. 171717 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila PROBLEM STATEMENT
  • 18. 1818 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Introduction & Problem Statement Conclusions & Contribution A cost overrun, also known as a cost increase, underrated or budget overrun, involves unexpected costs incurred in excess of budgeted amounts due to an underestimation of the actual cost during budgeting A time overrun, also known as a time increase is an unexpected time incurred in excess of a estimated/ allocated time Time Over-Run Cost Over-Run Department of Civil Engineering Sweedish College Wah cantt Taxila PROBLEM STATEMENT
  • 19. INTRODUCTION 19 INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement CostOverrunPOORDECISION MAKING COMMUNICATIONGAP INACCURATE ESTIMATION PROCUREMENT DELAYS Discussing causes of cost overrun is a step in enhancing the professional practice through trying to avoiding the occurrence or the impact of these causes Department of Civil Engineering Sweedish College Wah cantt Taxila BOQ(MISSING DATA) Scope Change(Material changes)
  • 20. 20 Time OverrunContractor‟spoor sitemanagement Poor estimateproject duration Incompetent designers Shortageofsite workers Late Decision for approval of materials Changes in scope of projects Unforeseen problems (adverseweathercondition) INTRODUCTION Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila PROBLEM STATEMENT
  • 21. OBJECTIVIES To minimize the Cost over Budget To minimize the Time over Run 21 LITERATUREREVIEW Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 22. REVIEW OF PAST STUDIES LITERATUREREVIEW Study Year of Study Research Findings Mohammadreza Emadi Andani & Golsa Moshayedi 2016 Cost Control in Construction Project Using Primavera Project Planner Oko John Ameh, Department of Building, University of Lagos, Nigeria Number 2011 STUDY OF RELATIONSHIP BETWEEN TIME OVERRUN AND PRODUCTIVITY ON CONSTRUCTION SITES U.Sindhu Vaardini S.Karthiyayini 2016 STUDY ON COST OVERRUNS IN CONSTRUCTION PROJECTS. Sindhu Vaardini September 2015 IDENTIFICATION OF CAUSES AND IMPACTS OF TIME OVERRUN IN CONSTRUCTION PROJECTS Nabil Al-Hazim, Zaydoun Abu Salem, Hesham Ahmad* 2008 Delay and Cost Overrun in Infrastructure Projects in Jordan 22 Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 23. COST SENIOR DOCTOR BUILDING PHASE (2) FACTORS WHICH EFFECT BUILIDING ANALYSIS 1) SCOPE Change 2) BOQ ( MISSING DATA ) 3) PROCUREMENT DELAYS 1) Changes in scope of projects 2) Unforeseen problems 3) Late Decision for approval of materials TIME 1) BOQ VARIENCES 2) POOR MANAGEMENT 3) POOR PLANNING 4) DELAYED AND FUNDING BOQ NON STANDARD STANDARD GOVT OF PUNJAB (MRS) CONTRACTOR (BIDDING) SENIOR DOCTOR BUILDING Department of Civil Engineering Sweedish College Wah cantt Taxila Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement METHODOLOGY
  • 24. 24 RESEARCHOBJECTIVES Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 26. 26 OBS (Organizational Break Down Structure) Department of Civil Engineering Sweedish College Wah cantt Taxila Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement
  • 28. 28 METHODOLOGY CALENDAR GLOBAL PROJECTRESOURCES Department of Civil Engineering Sweedish College Wah cantt Taxila Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement
  • 29. METHODOLOGY Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement 29 Work Break Down Structure (WBS) Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 30. 30 METHODOLOGY Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila RESOURCES SHEET Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 31. 31 METHODOLOGY Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila Activities
  • 32. 32 METHODOLOGY Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila Gantt Chart
  • 33. 33 METHODOLOGY Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila S CURVE ( RESOURCES)
  • 34. – Time and cost overrun DIFFERNECE:  COST OVERRUN: • Previous project completed RS 90821925.3/- while our project will be completed in RS 80640922.56/-  TIME COMPARISON: • Previous project completed in 24 month while our project planning is completing in 12 months. 34 METHODOLOGY Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila
  • 35. RESULTS&ANALYSES 35 Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Contribution Introduction & Problem Statement Department of Civil Engineering Sweedish College Wah cantt Taxila35 Company required to complete their project with specific TIME and COST and to maintain a required SCOPE and QUALITY • On Time, Budget, Quality = Required Scope SCOPE Time Cost Quality Research Objectives & Literature Review Research Methodology Results & Analyses Conclusions & Recommendation Introduction & Problem Statement
  • 36. LABORATORY CHARACTERIZATION OF ASPHALT MIXTURES USING DYNAMIC MODULUS TEST Department of Transportation Engineering, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Research Methodology Results & Analyses Conclusions & Contribution 7/6 Research Objectives & Literature Review Introduction & Problem Statement Date 36 QUESTIONS

Editor's Notes

  1. Title Slide