SlideShare a Scribd company logo
Unit commitment
Ahmed Mohamed abdel-hakeem Elkholy
Economic operation of power system
March 19, 2016
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 1 of 14
1. Introduction
1.1 Definition
determining the mix of generators and their estimated output
level to meet the expected demand of electricity over a given
time horizon (a day or a week), while satisfying constraints such
as ramp rate limits, up-time and down-time constraints, reserve
and energy requirements. While the load profile is given and also
the unit available to work is given.
Example 1.1
To fully illustrate the uc study the following sample example is
shown. There are three unit with following data.
Unit 1:
PMin = 250 MW, PMax = 600 MW
C1 = 510.0 + 7.9 P1 + 0.00172 P12 $/h
Unit 2:
PMin = 200 MW, PMax = 400 MW
C2 = 310.0 + 7.85 P2 + 0.00194 P22 $/h
Unit 3:
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 2 of 14
PMin = 150 MW, PMax = 500 MW
C3 = 78.0 + 9.56 P3 + 0.00694 P32 $/h
What combination of units 1, 2 and 3 will produce 550 MW at
minimum cost?
How much should each unit in that combination generate?
Solution:
Taking consideration of above given using excel sheet to solve all
possible scenarios of operations for illustration we will solve one
case manual
Case 6
Scenario is
Unit 1 is off
Unit 1 is on
Unit 1 is on
𝜆 =
𝑝 𝑑 + ∑
𝛽𝑖
2 ∗ 𝛾𝑖
𝑛
𝑖=1
∑
1
2 ∗ 𝛾𝑖
𝑛
𝑖=1
=
550 +
7.85
2 ∗ .00194
+
9.56
2 ∗ .00694
1
2 ∗ .00194
+
1
2 ∗ .00694
= 9.891369369
And the power will be
𝑝 =
𝜆 − 𝛽
2 ∗ 𝛾
Power generated from unit 2 =
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 3 of 14
=
9.891369369 − 7.85
2 ∗ .00194
= 526.1261261 𝑀𝑊
To meet constrains the power of unit 2 will be 400 mw
P2=400 mw
The power generated from unit3
=
9.891369369 − 9.56
2 ∗ .00694
= 23.87387387 𝑀𝑊
Also to meet constrains of unit 3 will be 150 mw
P2=150 mw
Also we also cheek constrain of power demand that’s
Pload =p1+p2=400+150=550 mw
The total cost by substituted in cost equation (given)
Total cost will be = 5428.55
This is for one case.
All case in table below
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 4 of 14
in above example for one loading case imagine that we can
consider above example for one hour in a day so we have to
calculate for 24 hour imagine for a week or month
so we find it possible to solve uc problem in that way not just for
long calculation but also considering constrains above example
not taking all constrain as we will illustrate in this report .
But we can learn from example 1.1 that
pmin pmax
U1 U2 U2 250 600 U1 U2 U2
α for units 510 310 78 200 400 510 310 78
β for units 7.9 7.85 9.56 150 500 7.9 7.85 9.56
γ for units 0.0017 0.0019 0.0069 0.002 0.002 0.007
case1 0 0 0 #DIV/0! 0 0 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
case2 0 0 1 17.194 150 500 0 0 0 0 0 0 0 0
case3 0 1 0 9.984 200 400 0 0 0 0 0 0 0 0
case4 1 0 0 9.792 250 600 1 550 0 0 5375.3 0 0 5375.3
case5 0 1 1 9.89136937 350 900 1 0 400 150 0 3760.4 1668.15 5428.55
case6 1 1 0 8.87936612 450 1000 1 284.7 265.3 0 2898.538 2529.155 0 5427.693
case7 1 0 1 9.74592148 400 1100 1 400 0 150 3945.2 0 1668.15 5613.35
case8 1 1 1 8.95839745 600 1500
0 0 0 0 0 0 0 0
cost
cost
Units data
λ opration p1 p2 p3
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 5 of 14
1. When the few units committed then the units can’t meet
the demand.
2. When the units is not enough to be committed then some
units operate above optimum.
3. When the units is many to be committed then some units
below optimum.
4. When the units is too many to be committed then minimum
generation exceeds demand.
5. No-load cost affects choice of optimal combination.
1.2 Type of units or stations.
If we take considerable load profile like
Load
Time
1260 18 24
500
1000
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 6 of 14
And solve for every hour then
LOAD UNIT 1 UNIT 2 UNIT 3
1100 On On On
1000 On On Off
900 On On Off
800 On On Off
700 On On Off
600 On Off Off
500 On Off Off
From solution we find that
1. There is unit will operate all time so we called it base unit.
2. There is unit will operate part time so we called it
intermediate unit
3. There is unit will operate few time so we called it peak unit
As coming figure describe
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 7 of 14
2. Constrains
2.1Definition
Constrain is limitations in power system avoiding it cause serious
problem. This limitation can be technical for unit or technical
limitation for power system or can be environmental limitations.
We can classified into
 Unit constrains
 System constrains
 Environmental constraints
 Network Constraints
Load
Time
1260 18 24
Unit 1 or base unit
Unit 2 or intermediate unit
Unit 3 or peak unit
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 8 of 14
2.2Unit constrains
2.2.1 Maximum generating capacity
That constrain stat that the power generated from the unit
mustn’t exceed specific value because of thermal stability
of the unit exceeding this constrain cause damage to the
unit. Represented in mathematical formula as below.
𝑥( 𝑖, 𝑡) < 𝑝𝑚𝑎𝑥
Where
𝑥( 𝑖, 𝑡) 𝑖𝑠 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓𝑡ℎ𝑒 𝑢𝑛𝑖𝑡 𝑖 𝑖𝑛 𝑡ℎ𝑒 𝑡𝑖𝑚𝑒 𝑡
2.2.2 Minimum stable generation
As above constrain the power outage from the unit
mustn’t fall down specific value because of technical
limitation like flam stability in the gas and steam units.
Represented in mathematical formula as below.
𝑥( 𝑖, 𝑡) > 𝑝𝑚𝑖𝑛
2.2.3 Minimum up time
This constrain stat that once the unit is running mustn’t
shut down immediately due technical limitation and
mechanical characteristic of the unit. This constrain
represented mathematically as:
Where
If u(i,t) =1 and ti
up
< ti
up,min
then u(i,t +1) =1
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 9 of 14
2.2.4 Minimum down time
This constrain stat that once the unit is running
mustn’t shut down immediately due technical
limitation and mechanical characteristic of the unit.
This constrain represented mathematically as:
2.2.5 Ramp rates
2.2.5.1 Definition
To avoid damaging the turbine, the
electrical output of a unit cannot change by
more than a certain amount over a period of
time.
2.2.5.2 Ramp Up rate
2.2.5.2.1 Start-up ramp rate
According to this constrain the unit
can’t start immediately but taking
time this time called start up time.
2.2.5.2.2 Running up ramp rate
According to this one in case of
running condition. the unit can’t
u(i,t): Status of unit i at period t
Unit i is on during period tu(i,t) =1:
Unit i is off during period tu(i,t)= 0:
If u(i,t) = 0 and ti
down
< ti
down,min
then u(i,t +1) = 0
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 10 of 14
immediate changing the power up
without taking time called ramp rate
running up time. The change here
means increasing outage power.
2.2.5.3 Ramp down rate
2.2.5.3.1 Shut down ramp rate
Look like previse constrain the unit take time to
shut down.
2.2.5.3.2 Running down ramp rate
According to this one in case of running condition.
the unit can’t immediate changing the power
down without taking time called ramp rate running
down time. The change here means decreasing
outage power.
2.2.5.4 Mathematical representation
ramp up rate
x i,t +1( )- x i,t( )£ DPi
up,max
ramp down rate
x(i,t)- x(i,t +1) £ DPi
down,max
2.3 Systemconstrains
This constrain that effect more than one unit divide into:
2.3.1 Load / generation balance
Stat as the power generated fromall unit mustbe equal the
load and the losses. Mathematically represented as
∑ 𝑢( 𝑖, 𝑡) ∗ 𝑥( 𝑖, 𝑡) = 𝑙( 𝑡)
𝑛
𝑖=1
𝑤ℎ𝑒𝑟𝑒 𝑙( 𝑡) 𝑖𝑠 𝑡ℎ𝑒 𝑙𝑜𝑎𝑑 𝑝𝑜𝑤𝑒𝑟 𝑎𝑡 𝑡𝑖𝑚𝑒 𝑡
2.3.2 Reserveconstrain
2.3.2.1 Reason to keep reservepower
 Sudden unexpected increasein the load demand
 Forceoutage of some generating units
 Forceoutage of supplementary equipment’s due to stability
problem
 Underestimating the load due to error in load for casting
 Local shortagein the generated power
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 11 of 14
2.3.2.2 Type of reserve
2.3.2.2.1 Cold reserve
Cold reserveis unit kept reserved for servicebut they are
not available in the immediate loading.
2.3.2.2.2 Hot (spinning) reserve
Hot reserverefers to the extra amount of capacity that
unit can provideimmediately when require.
2.3.2.2.3 Operating reserve
Operating reserveis referring to the capacity that already
in service in excess of peak demand.
2.3.2.3 Other sourceof reserve
There is other sourceof reservelike
 Pumped hydro plants
 Demand reduction (e.g. voluntary load shedding)
2.3.2.4 Condition of reserve
 Reservemust be higher than largest unit
 Should be spread around the network
 Must be able to deploy reserveeven if the network
is congested
 The unit mustoperate at 80-85% of its rated
2.4 Network constrain
Transmission network may havean effect on the
commitment of units because of
 Some units mustrun to providevoltage support
 The output of some units may be limited becausetheir
output would exceed the transmission capacity of the
network
2.5Environmental constrain
uc study is effected by environmentalconstrains becauseof
 constraints on pollutants such SO2, NOxvarious forms:
o Limit on each plant at each hour
o Limit on plant over a year
o Limit on a group of plants over a year
 Constraints on hydro generation
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 12 of 14
o Protection of wildlife
o Navigation, recreation
2.6Cost constrains
Cost constrain taking two type of costin consideration
2.6.1 Start-up cost
Start-up cost depends on varicosefactor like
 warming up becausethe unit can’t bring on line immediately
 Start-up cost depends on time unit has been off
2.6.2 Running cost
A balance between start-up costs and running costs is
important becauseof
 How long should a unit run to “recover” its start-up
cost?
 Start-up one more large unit or a diesel generator
to cover the peak?
 Shutdown one moreunit at night or run several
units’ part-loaded?
Example:
 Diesel generator: low start-up cost, high running
cost
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 13 of 14
 Coal plant: high start-up cost, low running cost
3 Summary
The summary of all above that
• Some constraints link periods together
• Minimizing the total cost (start-up + running) mustbe done over the whole
period of study
• Generation scheduling or unit commitment is a more general problem than
economic dispatch
• Economic dispatch is a sub-problemof generation scheduling
4 Type of units according flexibility
4.1Flexible unit
Power output can be adjusting within limits
Example of this unit
– Coal-fired
– Oil-fired
– Open cycle gas turbines
– Combined cycle gas turbines
– Hydro plants with storage
4.2Inflexible unit
Power output cannot be adjusted for technical or commercial reasons
Example of this unit
– Nuclear
– Run-of-the-river hydro
– Renewables (wind, solar,…….)
– Combined heat and power (CHP, cogeneration)
4.2.1.1
4.2.1.2
4.2.2
4.3
4.4
4.4.1.1
4.4.1.2
4.4.1.2.1
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 14 of 14
4.4.1.2.2
4.4.1.3

More Related Content

What's hot

Deregulation in power industry
Deregulation in power industryDeregulation in power industry
Deregulation in power industry
jerry patel
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
Pritesh Priyadarshi
 
Economic dispatch
Economic dispatch  Economic dispatch
Economic dispatch
Hussain Ali
 
Phasor Measurement Unit (PMU)
 Phasor Measurement Unit (PMU) Phasor Measurement Unit (PMU)
Phasor Measurement Unit (PMU)
Siksha 'O' Anusandhan (Deemed to be University )
 
An Overview of Distributed Generation
An Overview of Distributed GenerationAn Overview of Distributed Generation
An Overview of Distributed Generation
IJMER
 
Wind energy ppt
Wind energy pptWind energy ppt
Wind energy ppt
Wendy Legg
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNING
NishaDangi99
 
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLLOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
Preet_patel
 
Computer control of power system.
Computer control of power system.Computer control of power system.
Computer control of power system.
Kausik Bhaumik
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
MINAL RADE
 
Solar pv connected to grid
Solar pv connected to gridSolar pv connected to grid
Solar pv connected to grid
Darshan Prajapati
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
vikram anand
 
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEMISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
Siksha 'O' Anusandhan (Deemed to be University )
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
Deepak John
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
Ministry of New & Renewable Energy, Govt of India
 
Storage In Smart Grids
Storage In Smart GridsStorage In Smart Grids
Storage In Smart Grids
Sudhanshu Sharma
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
Ahmed M. Elkholy
 
Solar photovoltaic system design
Solar photovoltaic system designSolar photovoltaic system design
Solar photovoltaic system design
Jay Ranvir
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
Ahmed M. Elkholy
 

What's hot (20)

Deregulation in power industry
Deregulation in power industryDeregulation in power industry
Deregulation in power industry
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
 
Economic dispatch
Economic dispatch  Economic dispatch
Economic dispatch
 
Phasor Measurement Unit (PMU)
 Phasor Measurement Unit (PMU) Phasor Measurement Unit (PMU)
Phasor Measurement Unit (PMU)
 
An Overview of Distributed Generation
An Overview of Distributed GenerationAn Overview of Distributed Generation
An Overview of Distributed Generation
 
Wind energy ppt
Wind energy pptWind energy ppt
Wind energy ppt
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNING
 
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLLOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
 
Computer control of power system.
Computer control of power system.Computer control of power system.
Computer control of power system.
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
 
Solar pv connected to grid
Solar pv connected to gridSolar pv connected to grid
Solar pv connected to grid
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
 
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEMISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
Class 16 load shedding
 
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
 
Storage In Smart Grids
Storage In Smart GridsStorage In Smart Grids
Storage In Smart Grids
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 
Solar photovoltaic system design
Solar photovoltaic system designSolar photovoltaic system design
Solar photovoltaic system design
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 

Viewers also liked

Power System Operation and Control
Power System Operation and ControlPower System Operation and Control
Power System Operation and Control
Biswajit Pratihari
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatch
ayantudu
 
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
Mln Phaneendra
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
Md. Hasan Al Roktim
 
Minvrom 06 Mul
Minvrom 06 MulMinvrom 06 Mul
Minvrom 06 Mul
aadityaom
 
Ece4762011 lect16
Ece4762011 lect16Ece4762011 lect16
Ece4762011 lect16
miguelmena2013
 
Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48
jiten2k13
 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytem
shawon1981
 
Lecture 16
Lecture 16Lecture 16
Lecture 16
Forward2025
 
Concept kit: PWM Boost Converter Average Model
Concept kit: PWM Boost Converter Average ModelConcept kit: PWM Boost Converter Average Model
Concept kit: PWM Boost Converter Average Model
マルツエレック株式会社 marutsuelec
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
Mayank Sharma
 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
IAEME Publication
 
Economic load dispatch problem solving using "Cuckoo Search"
Economic load dispatch problem solving using "Cuckoo Search"Economic load dispatch problem solving using "Cuckoo Search"
Economic load dispatch problem solving using "Cuckoo Search"
Khulna University of Engineering and Technology
 
Facts controller
Facts controllerFacts controller
Facts controller
Debayon Saha
 
FACTS Controller.
FACTS Controller.FACTS Controller.
FACTS Controller.
Maharshi Pandya
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
Ajay Bhatnagar
 
Load Frequency Control of Two Area System
Load Frequency Control of Two Area SystemLoad Frequency Control of Two Area System
Load Frequency Control of Two Area System
Manash Deka
 
Presentation1
Presentation1Presentation1
Presentation1
Siya Agarwal
 
PLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZINGPLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZING
samsoncj999
 
Commitment management in sap
Commitment management in sapCommitment management in sap
Commitment management in sap
Rajesh Shanbhag
 

Viewers also liked (20)

Power System Operation and Control
Power System Operation and ControlPower System Operation and Control
Power System Operation and Control
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatch
 
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
 
Minvrom 06 Mul
Minvrom 06 MulMinvrom 06 Mul
Minvrom 06 Mul
 
Ece4762011 lect16
Ece4762011 lect16Ece4762011 lect16
Ece4762011 lect16
 
Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48
 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytem
 
Lecture 16
Lecture 16Lecture 16
Lecture 16
 
Concept kit: PWM Boost Converter Average Model
Concept kit: PWM Boost Converter Average ModelConcept kit: PWM Boost Converter Average Model
Concept kit: PWM Boost Converter Average Model
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
 
Economic load dispatch problem solving using "Cuckoo Search"
Economic load dispatch problem solving using "Cuckoo Search"Economic load dispatch problem solving using "Cuckoo Search"
Economic load dispatch problem solving using "Cuckoo Search"
 
Facts controller
Facts controllerFacts controller
Facts controller
 
FACTS Controller.
FACTS Controller.FACTS Controller.
FACTS Controller.
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
 
Load Frequency Control of Two Area System
Load Frequency Control of Two Area SystemLoad Frequency Control of Two Area System
Load Frequency Control of Two Area System
 
Presentation1
Presentation1Presentation1
Presentation1
 
PLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZINGPLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZING
 
Commitment management in sap
Commitment management in sapCommitment management in sap
Commitment management in sap
 

Similar to Unit commitment

Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM Model
IRJET Journal
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
TheBlank5
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
NBoss
 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
Karthik Kathan
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptx
LucasMogaka
 
Understanding generator set ratings
Understanding generator set ratings   Understanding generator set ratings
Understanding generator set ratings
NaveedHussain106
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
Universidad Naacional de Loja
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
ssuserd0df33
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
inventionjournals
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
Balamurugan Subburaj
 
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Instrument Specialties, Inc.
 
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET Journal
 
K045066265
K045066265K045066265
K045066265
IJERA Editor
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load Characteristics
Ameen San
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
Adama Science and Technology University
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET Journal
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET Journal
 
Introducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIntroducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling Framework
IEA-ETSAP
 
Abb technical guide no.08 revb
Abb technical guide no.08 revbAbb technical guide no.08 revb
Abb technical guide no.08 revb
Cesar Enrique Gutierrez Candia
 
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Pieter de Koning, PEng, MBA
 

Similar to Unit commitment (20)

Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM Model
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptx
 
Understanding generator set ratings
Understanding generator set ratings   Understanding generator set ratings
Understanding generator set ratings
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
 
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
 
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
 
K045066265
K045066265K045066265
K045066265
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load Characteristics
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
Introducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIntroducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling Framework
 
Abb technical guide no.08 revb
Abb technical guide no.08 revbAbb technical guide no.08 revb
Abb technical guide no.08 revb
 
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
 

More from Ahmed M. Elkholy

Solar system
Solar systemSolar system
Solar system
Ahmed M. Elkholy
 
Mep pres
Mep presMep pres
Newton raphson
Newton raphsonNewton raphson
Newton raphson
Ahmed M. Elkholy
 
Gauss seidel
Gauss seidelGauss seidel
Gauss seidel
Ahmed M. Elkholy
 
Ybus
YbusYbus
Fuel cell
Fuel cellFuel cell
Fuel cell
Ahmed M. Elkholy
 
Facts
FactsFacts
COMPETITIVE MARKET
COMPETITIVE MARKET COMPETITIVE MARKET
COMPETITIVE MARKET
Ahmed M. Elkholy
 
Optimazation
OptimazationOptimazation
Optimazation
Ahmed M. Elkholy
 

More from Ahmed M. Elkholy (9)

Solar system
Solar systemSolar system
Solar system
 
Mep pres
Mep presMep pres
Mep pres
 
Newton raphson
Newton raphsonNewton raphson
Newton raphson
 
Gauss seidel
Gauss seidelGauss seidel
Gauss seidel
 
Ybus
YbusYbus
Ybus
 
Fuel cell
Fuel cellFuel cell
Fuel cell
 
Facts
FactsFacts
Facts
 
COMPETITIVE MARKET
COMPETITIVE MARKET COMPETITIVE MARKET
COMPETITIVE MARKET
 
Optimazation
OptimazationOptimazation
Optimazation
 

Recently uploaded

DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 

Recently uploaded (20)

DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 

Unit commitment

  • 1. Unit commitment Ahmed Mohamed abdel-hakeem Elkholy Economic operation of power system March 19, 2016
  • 2. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 1 of 14 1. Introduction 1.1 Definition determining the mix of generators and their estimated output level to meet the expected demand of electricity over a given time horizon (a day or a week), while satisfying constraints such as ramp rate limits, up-time and down-time constraints, reserve and energy requirements. While the load profile is given and also the unit available to work is given. Example 1.1 To fully illustrate the uc study the following sample example is shown. There are three unit with following data. Unit 1: PMin = 250 MW, PMax = 600 MW C1 = 510.0 + 7.9 P1 + 0.00172 P12 $/h Unit 2: PMin = 200 MW, PMax = 400 MW C2 = 310.0 + 7.85 P2 + 0.00194 P22 $/h Unit 3:
  • 3. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 2 of 14 PMin = 150 MW, PMax = 500 MW C3 = 78.0 + 9.56 P3 + 0.00694 P32 $/h What combination of units 1, 2 and 3 will produce 550 MW at minimum cost? How much should each unit in that combination generate? Solution: Taking consideration of above given using excel sheet to solve all possible scenarios of operations for illustration we will solve one case manual Case 6 Scenario is Unit 1 is off Unit 1 is on Unit 1 is on 𝜆 = 𝑝 𝑑 + ∑ 𝛽𝑖 2 ∗ 𝛾𝑖 𝑛 𝑖=1 ∑ 1 2 ∗ 𝛾𝑖 𝑛 𝑖=1 = 550 + 7.85 2 ∗ .00194 + 9.56 2 ∗ .00694 1 2 ∗ .00194 + 1 2 ∗ .00694 = 9.891369369 And the power will be 𝑝 = 𝜆 − 𝛽 2 ∗ 𝛾 Power generated from unit 2 =
  • 4. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 3 of 14 = 9.891369369 − 7.85 2 ∗ .00194 = 526.1261261 𝑀𝑊 To meet constrains the power of unit 2 will be 400 mw P2=400 mw The power generated from unit3 = 9.891369369 − 9.56 2 ∗ .00694 = 23.87387387 𝑀𝑊 Also to meet constrains of unit 3 will be 150 mw P2=150 mw Also we also cheek constrain of power demand that’s Pload =p1+p2=400+150=550 mw The total cost by substituted in cost equation (given) Total cost will be = 5428.55 This is for one case. All case in table below
  • 5. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 4 of 14 in above example for one loading case imagine that we can consider above example for one hour in a day so we have to calculate for 24 hour imagine for a week or month so we find it possible to solve uc problem in that way not just for long calculation but also considering constrains above example not taking all constrain as we will illustrate in this report . But we can learn from example 1.1 that pmin pmax U1 U2 U2 250 600 U1 U2 U2 α for units 510 310 78 200 400 510 310 78 β for units 7.9 7.85 9.56 150 500 7.9 7.85 9.56 γ for units 0.0017 0.0019 0.0069 0.002 0.002 0.007 case1 0 0 0 #DIV/0! 0 0 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! case2 0 0 1 17.194 150 500 0 0 0 0 0 0 0 0 case3 0 1 0 9.984 200 400 0 0 0 0 0 0 0 0 case4 1 0 0 9.792 250 600 1 550 0 0 5375.3 0 0 5375.3 case5 0 1 1 9.89136937 350 900 1 0 400 150 0 3760.4 1668.15 5428.55 case6 1 1 0 8.87936612 450 1000 1 284.7 265.3 0 2898.538 2529.155 0 5427.693 case7 1 0 1 9.74592148 400 1100 1 400 0 150 3945.2 0 1668.15 5613.35 case8 1 1 1 8.95839745 600 1500 0 0 0 0 0 0 0 0 cost cost Units data λ opration p1 p2 p3
  • 6. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 5 of 14 1. When the few units committed then the units can’t meet the demand. 2. When the units is not enough to be committed then some units operate above optimum. 3. When the units is many to be committed then some units below optimum. 4. When the units is too many to be committed then minimum generation exceeds demand. 5. No-load cost affects choice of optimal combination. 1.2 Type of units or stations. If we take considerable load profile like Load Time 1260 18 24 500 1000
  • 7. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 6 of 14 And solve for every hour then LOAD UNIT 1 UNIT 2 UNIT 3 1100 On On On 1000 On On Off 900 On On Off 800 On On Off 700 On On Off 600 On Off Off 500 On Off Off From solution we find that 1. There is unit will operate all time so we called it base unit. 2. There is unit will operate part time so we called it intermediate unit 3. There is unit will operate few time so we called it peak unit As coming figure describe
  • 8. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 7 of 14 2. Constrains 2.1Definition Constrain is limitations in power system avoiding it cause serious problem. This limitation can be technical for unit or technical limitation for power system or can be environmental limitations. We can classified into  Unit constrains  System constrains  Environmental constraints  Network Constraints Load Time 1260 18 24 Unit 1 or base unit Unit 2 or intermediate unit Unit 3 or peak unit
  • 9. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 8 of 14 2.2Unit constrains 2.2.1 Maximum generating capacity That constrain stat that the power generated from the unit mustn’t exceed specific value because of thermal stability of the unit exceeding this constrain cause damage to the unit. Represented in mathematical formula as below. 𝑥( 𝑖, 𝑡) < 𝑝𝑚𝑎𝑥 Where 𝑥( 𝑖, 𝑡) 𝑖𝑠 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓𝑡ℎ𝑒 𝑢𝑛𝑖𝑡 𝑖 𝑖𝑛 𝑡ℎ𝑒 𝑡𝑖𝑚𝑒 𝑡 2.2.2 Minimum stable generation As above constrain the power outage from the unit mustn’t fall down specific value because of technical limitation like flam stability in the gas and steam units. Represented in mathematical formula as below. 𝑥( 𝑖, 𝑡) > 𝑝𝑚𝑖𝑛 2.2.3 Minimum up time This constrain stat that once the unit is running mustn’t shut down immediately due technical limitation and mechanical characteristic of the unit. This constrain represented mathematically as: Where If u(i,t) =1 and ti up < ti up,min then u(i,t +1) =1
  • 10. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 9 of 14 2.2.4 Minimum down time This constrain stat that once the unit is running mustn’t shut down immediately due technical limitation and mechanical characteristic of the unit. This constrain represented mathematically as: 2.2.5 Ramp rates 2.2.5.1 Definition To avoid damaging the turbine, the electrical output of a unit cannot change by more than a certain amount over a period of time. 2.2.5.2 Ramp Up rate 2.2.5.2.1 Start-up ramp rate According to this constrain the unit can’t start immediately but taking time this time called start up time. 2.2.5.2.2 Running up ramp rate According to this one in case of running condition. the unit can’t u(i,t): Status of unit i at period t Unit i is on during period tu(i,t) =1: Unit i is off during period tu(i,t)= 0: If u(i,t) = 0 and ti down < ti down,min then u(i,t +1) = 0
  • 11. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 10 of 14 immediate changing the power up without taking time called ramp rate running up time. The change here means increasing outage power. 2.2.5.3 Ramp down rate 2.2.5.3.1 Shut down ramp rate Look like previse constrain the unit take time to shut down. 2.2.5.3.2 Running down ramp rate According to this one in case of running condition. the unit can’t immediate changing the power down without taking time called ramp rate running down time. The change here means decreasing outage power. 2.2.5.4 Mathematical representation ramp up rate x i,t +1( )- x i,t( )£ DPi up,max ramp down rate x(i,t)- x(i,t +1) £ DPi down,max 2.3 Systemconstrains This constrain that effect more than one unit divide into: 2.3.1 Load / generation balance Stat as the power generated fromall unit mustbe equal the load and the losses. Mathematically represented as ∑ 𝑢( 𝑖, 𝑡) ∗ 𝑥( 𝑖, 𝑡) = 𝑙( 𝑡) 𝑛 𝑖=1 𝑤ℎ𝑒𝑟𝑒 𝑙( 𝑡) 𝑖𝑠 𝑡ℎ𝑒 𝑙𝑜𝑎𝑑 𝑝𝑜𝑤𝑒𝑟 𝑎𝑡 𝑡𝑖𝑚𝑒 𝑡 2.3.2 Reserveconstrain 2.3.2.1 Reason to keep reservepower  Sudden unexpected increasein the load demand  Forceoutage of some generating units  Forceoutage of supplementary equipment’s due to stability problem  Underestimating the load due to error in load for casting  Local shortagein the generated power
  • 12. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 11 of 14 2.3.2.2 Type of reserve 2.3.2.2.1 Cold reserve Cold reserveis unit kept reserved for servicebut they are not available in the immediate loading. 2.3.2.2.2 Hot (spinning) reserve Hot reserverefers to the extra amount of capacity that unit can provideimmediately when require. 2.3.2.2.3 Operating reserve Operating reserveis referring to the capacity that already in service in excess of peak demand. 2.3.2.3 Other sourceof reserve There is other sourceof reservelike  Pumped hydro plants  Demand reduction (e.g. voluntary load shedding) 2.3.2.4 Condition of reserve  Reservemust be higher than largest unit  Should be spread around the network  Must be able to deploy reserveeven if the network is congested  The unit mustoperate at 80-85% of its rated 2.4 Network constrain Transmission network may havean effect on the commitment of units because of  Some units mustrun to providevoltage support  The output of some units may be limited becausetheir output would exceed the transmission capacity of the network 2.5Environmental constrain uc study is effected by environmentalconstrains becauseof  constraints on pollutants such SO2, NOxvarious forms: o Limit on each plant at each hour o Limit on plant over a year o Limit on a group of plants over a year  Constraints on hydro generation
  • 13. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 12 of 14 o Protection of wildlife o Navigation, recreation 2.6Cost constrains Cost constrain taking two type of costin consideration 2.6.1 Start-up cost Start-up cost depends on varicosefactor like  warming up becausethe unit can’t bring on line immediately  Start-up cost depends on time unit has been off 2.6.2 Running cost A balance between start-up costs and running costs is important becauseof  How long should a unit run to “recover” its start-up cost?  Start-up one more large unit or a diesel generator to cover the peak?  Shutdown one moreunit at night or run several units’ part-loaded? Example:  Diesel generator: low start-up cost, high running cost
  • 14. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 13 of 14  Coal plant: high start-up cost, low running cost 3 Summary The summary of all above that • Some constraints link periods together • Minimizing the total cost (start-up + running) mustbe done over the whole period of study • Generation scheduling or unit commitment is a more general problem than economic dispatch • Economic dispatch is a sub-problemof generation scheduling 4 Type of units according flexibility 4.1Flexible unit Power output can be adjusting within limits Example of this unit – Coal-fired – Oil-fired – Open cycle gas turbines – Combined cycle gas turbines – Hydro plants with storage 4.2Inflexible unit Power output cannot be adjusted for technical or commercial reasons Example of this unit – Nuclear – Run-of-the-river hydro – Renewables (wind, solar,…….) – Combined heat and power (CHP, cogeneration) 4.2.1.1 4.2.1.2 4.2.2 4.3 4.4 4.4.1.1 4.4.1.2 4.4.1.2.1
  • 15. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 14 of 14 4.4.1.2.2 4.4.1.3