Distribution System Voltage Drop and Power Loss CalculationAmeen San
Distribution System Voltage Drop and Power Loss
Calculation
Comparison of Overhead Versus Underground System
Power Loss Calculation,Voltage Drop Calculation
Distribution System Voltage Drop and Power Loss CalculationAmeen San
Distribution System Voltage Drop and Power Loss
Calculation
Comparison of Overhead Versus Underground System
Power Loss Calculation,Voltage Drop Calculation
Summary of Modern power system planning part one
"The Forecasting of Growth of Demand for Electrical Energy"
the main topic of this chapter is the analysis of the various techniques required for utility planning engineers to optimally plan the expansion of the electrical power system.
We had made a working model on static VAR compensator which is made by power electronic switch and mechanically switched. We had chosen mechanically switched capacitor method to improved receiving end voltage as well as power factor.
Long & Short Interruptions: Interruptions – Definition – Difference between failures,
outage, Interruptions – causes of Long Interruptions – Origin of Interruptions – Limits for the
Interruption frequency – Limits for the interruption duration – costs of Interruption –
Overview of Reliability evaluation to power quality, comparison of observations and
reliability evaluation.Short interruptions: definition, origin of short interruptions, basic principle, fuse saving,
voltage magnitude events due to re-closing, voltage during the interruption, monitoring of
short interruptions, difference between medium and low voltage systems. Multiple events,
single phase tripping – voltage and current during fault period, voltage and current at post
fault period
Disadvantages of corona, radio interference, inductive interference between p...vishalgohel12195
Disadvantages of corona, radio interference, inductive interference between power and communication lines
Introduction
Disadvantages of corona.
Radio interference.
Inductive interference between power and communication lines
Generation of High D.C. Voltage (HVDC generation)RP6997
Generation of high dc voltage using different methods like half wave and full wave rectifier, voltage doubler circuits, voltage multiplier circuits, cockcroft-walton circuits and van de graaff generators.
Summary of Modern power system planning part one
"The Forecasting of Growth of Demand for Electrical Energy"
the main topic of this chapter is the analysis of the various techniques required for utility planning engineers to optimally plan the expansion of the electrical power system.
We had made a working model on static VAR compensator which is made by power electronic switch and mechanically switched. We had chosen mechanically switched capacitor method to improved receiving end voltage as well as power factor.
Long & Short Interruptions: Interruptions – Definition – Difference between failures,
outage, Interruptions – causes of Long Interruptions – Origin of Interruptions – Limits for the
Interruption frequency – Limits for the interruption duration – costs of Interruption –
Overview of Reliability evaluation to power quality, comparison of observations and
reliability evaluation.Short interruptions: definition, origin of short interruptions, basic principle, fuse saving,
voltage magnitude events due to re-closing, voltage during the interruption, monitoring of
short interruptions, difference between medium and low voltage systems. Multiple events,
single phase tripping – voltage and current during fault period, voltage and current at post
fault period
Disadvantages of corona, radio interference, inductive interference between p...vishalgohel12195
Disadvantages of corona, radio interference, inductive interference between power and communication lines
Introduction
Disadvantages of corona.
Radio interference.
Inductive interference between power and communication lines
Generation of High D.C. Voltage (HVDC generation)RP6997
Generation of high dc voltage using different methods like half wave and full wave rectifier, voltage doubler circuits, voltage multiplier circuits, cockcroft-walton circuits and van de graaff generators.
Load types, estimation, grwoth, forecasting and duration curvesAzfar Rasool
It includes the detail analysis of the various types electrical load, how to estimatate the load, methods of load forecasting and explanation of the load duration curves.
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
Application of Capacitors to
Distribution System and Voltage
Regulation
POWER FACTOR IMPROVEMENT,
System Harmonics
Voltage Regulation
Methods of Voltage Control
The function of a power station is to de-
liver power to a large number of consum
ers. However, the power demands of dif-
ferent consumers vary in accordance with their
activities. The result of this variation in demand
is that load on a power station is never constant,
rather it varies from time to time. Most of the
complexities of modern power plant operation
arise from the inherent variability of the load de-
manded by the users. Unfortunately, electrical
power cannot be stored and, therefore, the power
station must produce power as and when de-
manded to meet the requirements of the consum-
ers. On one hand, the power engineer would like
that the alternators in the power station should
run at their rated capacity for maximum efficiency
and on the other hand, the demands of the con-
sumers have wide variations. This makes the
design of a power station highly complex. In this
chapter, we shall focus our attention on the prob-
lems of variable load on power stations.
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
POWER SYSTEM PROTECTION
Protection Devices and the Lightning,. protection,
Lightning protection, Introduction
Air Break Switches
Disconnect switches
Grounding switches
Current limiting reactors
Grounding transformers
Co-ordination of protective devices
Grounding of electrical installations
Electric shock
Lightning protection
Lightning Arrestor
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Courier management system project report.pdfKamal Acharya
It is now-a-days very important for the people to send or receive articles like imported furniture, electronic items, gifts, business goods and the like. People depend vastly on different transport systems which mostly use the manual way of receiving and delivering the articles. There is no way to track the articles till they are received and there is no way to let the customer know what happened in transit, once he booked some articles. In such a situation, we need a system which completely computerizes the cargo activities including time to time tracking of the articles sent. This need is fulfilled by Courier Management System software which is online software for the cargo management people that enables them to receive the goods from a source and send them to a required destination and track their status from time to time.
Vaccine management system project report documentation..pdfKamal Acharya
The Division of Vaccine and Immunization is facing increasing difficulty monitoring vaccines and other commodities distribution once they have been distributed from the national stores. With the introduction of new vaccines, more challenges have been anticipated with this additions posing serious threat to the already over strained vaccine supply chain system in Kenya.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
Load Characteristics
1. 2/26/2013
1
CHAPTER 2
Load Characteristics
1Dr.A.Arunagiri
2
The load characteristic plays an important role in
determiningthe totalpowerand energyrequirementsof the system
planningthe installedcapacityof a powerplant
selectionof suitablegeneratingcapacityfor eachunit of the plant..
Load Characteristics
Someof the termsin connectionwith the load characteristicsare explained
below
Demand
The demand of a system is the load at the receiving terminals
(usually in kW or kVA) averaged over a suitable specific interval
of time of shortduration. Dr.A.Arunagiri
2. 2/26/2013
2
3
Demand Interval
It is the periodover whichthe load is averaged.
Load Curves of a Generating Station
The totalpowerrequirementof a generationstationcan be estimatedusingthis
curves
Load Curve (or Chronological Load
Curve)
It represents the load in its time sequence. As shown this curve is obtained by
plotting the station load along Y-axis and the time when it occurs along X-axis.
Usually, it is plotted for one day by taking average load based on the time
interval t, which is usually an hour. The area under the curve represents the
totalenergyconsumedby the load in one day.
Dr.A.Arunagiri
4
6AM 12N 6PM 11PM 6AM
15kW
20kW
10kW
5kW
2kW
Time
0 5 11 17 24
15kW
20kW
10kW
5kW
2kW
Time in hr
Load curve Load-duration curve
Load-Duration Curve
It represents the same data (i.e. load versus time) but the ordinates are
rearranged in magnitude sequence (not time sequence). Here, the greatest
load is plotted on the left, lesser load towards the right and the least load
on the extremeright,as Shown.Dr.A.Arunagiri
3. 2/26/2013
3
5
The areas under the load curve and load duration curve are equal and each
represents the total units consumed during a day of 24 hours. The load –
duration curves can be daily, weekly, monthly and annual. Sometimes the
plotsare done in per unit values.
The total load supplied by a generating station is normally divided into
threeparts:
Base load
Intermediateload
Peak load
The base load is the load below which the demand never falls and is
supplied 100% of the time. The peak load occurs for about 15% of the
time. The intermediate load represents the remaining load region in the
load curve.These typesof loadsare shownin the next figure.Dr.A.Arunagiri
6
Base load Base load
Intermediate load
Intermediate load
Peak loadPeak load
Time Time
Load-duration curve
Load curve
Dr.A.Arunagiri
5. 2/26/2013
5
It is the sum of continuous ratings of all the
equipments connected to supply system.
Connected load
9Dr.A.Arunagiri
Maximum Demand
It is the greatest demand of load on the power
station during a given period.
10Dr.A.Arunagiri
6. 2/26/2013
6
Demand Factor
It is the ratio of maximum demand on the power station to
its connected load
Demand Factor = Maximum Demand
Connected Load
11Dr.A.Arunagiri
The value of demand factor is usually less than 1. It
is expected because maximum demand on the power
station is generally less than the connected load. If
the maximum demand on the power station is 80 MW
and the connected load is 100 MW,
then demand factor = 80/100 = 0.8. The knowledge
of demand factor is vital in determining the capacity
of the plant equipment.
12Dr.A.Arunagiri
7. 2/26/2013
7
Average Load
It is the average of loads occurring on the power
station in a given period (day or month or year) is
known as average load or average demand.
13Dr.A.Arunagiri
14Dr.A.Arunagiri
8. 2/26/2013
8
Load Factor
The ratio of average load to the maximum
demand during a given period is known as
Load Factor
15Dr.A.Arunagiri
Diversity Factor
It is the ratio of sum of individual maximumIt is the ratio of sum of individual maximum
demands to the maximum demand on the powerdemands to the maximum demand on the power
stationstation
16Dr.A.Arunagiri
9. 2/26/2013
9
Capacity Factor
It is the ratio of actual energy produced to the
maximum possible energy that could have been
produced during a given period.
17Dr.A.Arunagiri
18Dr.A.Arunagiri
10. 2/26/2013
10
Plant Use Factor
It is the ratio of KWhr generated to the product of
plant capacity and the number of hours for which the
plant was in operation
19Dr.A.Arunagiri
Load Duration Curve
When the load elements of a load curve are
arranged in the order of descending magnitudes,
the curve thus obtained is called a load duration
curve
20Dr.A.Arunagiri
12. 2/26/2013
12
2 A generating station has a connected load of
43MW and a maximum demand of 20 MW, the units
generated being 61500000KWhr per annum. Caculate the
(i) the demand factor (0.465)
(ii) the load factor(35.1%)
23Dr.A.Arunagiri
Time Consumer1 Consumer2 Consumer3
12 midnight
to
8 A.M
No load 200W No load
8 A.M to 2 P.M 600W No load 200W
2 P.M to 4
P.M
200W 1000W 1200W
4 P.M to 10
P.M
800W No load No load
10 P.M to
midnight
No load 200W 200W
Thedaily demands of three consumers are given below
24Dr.A.Arunagiri
13. 2/26/2013
13
Plot the load curve and find
(i) load factor of individual consumer
45.8%,16.7%13.8%
(ii) diversity factor(1.25)
(iii) load factor of the station (29.1%)
25Dr.A.Arunagiri
The power station has the following daily load cycle:
Time in
Hours
6 - 8 8-12 12-16 16-20 20-24 24-6
Load in
MW
20 40 60 20 50 20
Plot the load curve and load duration curve also calculate
the energy generated perday (840000kwhr)
26Dr.A.Arunagiri
14. 2/26/2013
14
27
High value of diversity factor means that more consumers
can be supplied for a given station maximum demand and
so lower prices can be offered to consumer. Usually,
domestic load gives higher value of diversity factor than
industrial load.
Example 1
Assume that there are 6 residential consumers
connected to a distribution transformer. The connected
load per consumer is 9.0 kW. The demand factor and
diversity factor of the group of 6 residential consumers
are 0.65 and 1.1 respectively. Calculate the (coincident)
maximum demand on the transformer.
Dr.A.Arunagiri
28
Therefore, maximum demand of each consumer is 9xDFi
= 9x0.65 = 5.85 kW
loadconnectedtotal
consumereachofdemandmaximum
Solution
Demand factor of each consumer, DFi =
loadwholetheofdemandmaximum
demandsmaximumindividualofsum
factorDiversity
loadwholetheofdemandmaximum
685.5
1.1
Therefore, the maximum demand on the transformer is
5.86x6/1.1 = 31.9 kW
Dr.A.Arunagiri
15. 2/26/2013
15
29
Significance of Load Factor
Load factor is, in fact, an index to the proportion of the
whole time a generator plant or system is being worked to
its full capacity. The generating equipment has to be
selected on the basis of the maximum power demand that
is likely to be imposed on it. However, it seldom happens
that the generating equipment is loaded to its maximum
load during all the 8,760 hours of a year. But whether the
equipment is being worked to its full capacity or not, there
are certain charges (like interest, depreciation, taxes,
insurance, part of staff salaries etc.) which are adding up
continuously. In other word, the equipment is costing
money to its owner whether working or idle. The equipment
earns profit only during those hours when it is fully loaded
and the more it is fully loaded the more is the profit to the
owner. Dr.A.Arunagiri
30
Hence, from the point view of economics it is desirable
to obtain high load factors. If the load factor is poor i.e.
kWh of electrical energy produced is small, then charge
per kWh would obviously be high. But if load factor is
high i.e. the number of kWh generated is large, then cost
of production and hence charge per kWh are reduced
because now the fixed charges are distributed over a
large number of units of energy.
Dr.A.Arunagiri
16. 2/26/2013
16
31
Connected load Factor
This factor relates only to the receiving equipment and
is defined as the ratio of the average power input to the
connected load.
loadconnected
inputpoweraverage
factorloadConnected
factor)Demand(factor)(Load
loadconnected
demandmax.
demandmax.
inputpoweraverage
factorloadConnected
Dr.A.Arunagiri
32
Example 3
A consumer has the following load-schedule for a day:
From midnight to 6.00a.m. = 200W
From 6.00a.m to 12.00 noon = 3000W
From 12.00 noon to 1.00p.m = 100W
From 1.00p.m to 4.00p.m = 4000W
From 4.00p.m to 9.00p.m = 2000W
From 9.00p.m to midnight = 1000W
Find the load factor.
Solution
17. 2/26/2013
17
33
Example 4
A generating station has a connected load of 43 MW and
a maximum demand of 20 MW. The total annual energy
generated by the station is 61,500,000 kWh (Units).
Calculate the load factor, demand factor and connected
load factor.
Solution
Dr.A.Arunagiri
34
Example 5
A power station has a load cycle as under::
260MW for 6hr; 200MW for 8hr; 160MW for 4hr; 100MW
for 6hr.
If the power station is equipped with 4 generating sets of
75MW each, calculate the load factor and the capacity
factor from the above data.
Solution
Dr.A.Arunagiri
19. 2/26/2013
19
The economics of power generation has
assumed a great importance in this fast
developing power plant engineering. A
consumer will use electric power only if it is
supplied at reasonable rate. Therefore, power
engineers have to find convenient methods to
produce electric power as cheap as possible so
that consumers are tempted to use electrical
methods
37Dr.A.Arunagiri
Definition Of Terms
(i) Interest. The Cost Of Use of money is
known as interest
A power station is constructed by investing
a. huge capital. This money is generally
borrowed from banks or other financial
institutions and the supply company has to
pay the annual interest .
38Dr.A.Arunagiri
20. 2/26/2013
20
Therefore, while calculating the cost of
production of electrical energy, the interest
payable on the capital investment must be
included. The rate of interest depends upon
market position and other factors, and may
vary from 4% to 8% per annum.
39Dr.A.Arunagiri
(ii) Depreciation
The decrease in the value of the power plant
equipment and building due to constant use is
known as depreciation.
40Dr.A.Arunagiri
21. 2/26/2013
21
In actual practice, every power station has a useful
life ranging from fifty to sixty years. From the time
the power station is installed, its equipment steadily
deteriorates due to wear and tear so that there is a
gradual reduction in the value of the plant. This
reduction in the value of plant every year is known as
annual depreciation. Due to depreciation, the plant has
to be replaced by the new one after its useful life.
Therefore, suitable amount must be set aside every
year so that by the time the plant retires, the
collected amount by way of depreciation equals the
cost of replacement.
41Dr.A.Arunagiri
Cost of Electrical Energy
The total cost of electrical energy
generated can be divided into three
parts, namely;
(i) Fixed cost;
(ii) Semi-fixed cost;
(iii) Running or operating cost.
42Dr.A.Arunagiri
22. 2/26/2013
22
Fixed Cost
It is the cost which is independent of maximum
demand and units generated.
43Dr.A.Arunagiri
The fixed cost is due to the annual cost of central
organization, interest on capital cost of land and
salaries of high officials. The annual expenditure on
the central organization and salaries of high officials
is fixed since it has to be met whether the plant has
high or low maximum demand or it generates less or
more units. Further, the capital investment on the
land is fixed and hence the amount of interest is
also fixed.
44Dr.A.Arunagiri
23. 2/26/2013
23
Semi-fixed cost
It is the cost which depends upon maximum demand,
but is independent of units generated.
45Dr.A.Arunagiri
Running cost
It is the cost which depends only upon the
number of units generated.
46Dr.A.Arunagiri
24. 2/26/2013
24
The running cost is on account of annual cost
of fuel, lubricating oil, maintenance, repairs
and salaries of operating staff. Since these
charges depend upon the energy output, the
running cost is directly proportional to the
number of units generated by the station. In
other words, if the power station generates
more units, it will have higher running cost
47Dr.A.Arunagiri
Expressions for Cost of
Electrical Energy
The overall annual cost of electrical energy generated
by a power station can be expressed in two forms ie
three part form and two part form.
48Dr.A.Arunagiri
25. 2/26/2013
25
Three part form
In this method, the overall annual costof
electrical energy generated is divided into
three
parts ie fixed cost, semi-fixed cost and
running cost
49Dr.A.Arunagiri
Total annual cost of energy =
Fixed cost+Semi fixed cost+Running cost
Constant+Proportional to max. demand+Proportional to
kWh generated.
RM(a+b kW+c kWh)
50Dr.A.Arunagiri
26. 2/26/2013
26
wherea = annual fixed cost independent of maximum
demand and energy output
b = a constant which when multiplied by maximum
demand on the station gives annual semi fixed cost
c= a constant which when multiplied by KWhr
output per annum gives the annual running cost
51Dr.A.Arunagiri
Two part form
It is sometimes convenient to give the
annual cost of energy in two part form. In this case,
the annual cost of energy is divided into two parts ie a
fixed sum per kW of maximum demand plus a running
charge per unit of energy. The expression for the
annual cost of
energy then becomes
Total annual cost of energy
= RM(A kW+B kWh)
52Dr.A.Arunagiri
27. 2/26/2013
27
where A = a constant which when multiplied by maximum
kW, demand on the station gives the annual cost
of the first part.
B =
53Dr.A.Arunagiri
a constant which when multiplied by KWhr
output per annum gives the annual running cost
PROBLEM
54
A generating station has a maximum demand of 50,000 kW. Calculate the
cost per unit generated from the following data :
Capital cost = SR 95 * 106;
Annual load factor = 40%
Annual cost of fuel and oil = SR 9 ×*106
Taxes, wages and salaries etc. = SR 7·5*× 106
Interest and depreciation = 12% (16 Halala)
Dr.A.Arunagiri
28. 2/26/2013
28
Problem
Dr.A.Arunagiri 55
A generating station has an installed capacity of
50,000 kW and delivers 220 ×10^6units per annum. If
the annual fixed charges are SR 160 per kW installed
capacity and running charges are 4 halala per kWh,
determine the cost per unit generated.(7.64)
Dr.A.Arunagiri 56
29. 2/26/2013
29
Problem
Dr.A.Arunagiri 57
A generating plant has a maximum capacity of 100 kW and costs
SR 1,60,000. The annual fixed charges are 12% consisting of 5%
intererst, 5% depreciation and 2% taxes. Find the fixed charges
per kWh if the load factor is
(i) 100% and (ii) 50%.( HALALA 2.19,4.38)
Problem
Dr.A.Arunagiri 58
Estimate the generating cost per kWh delivered from a
generating station from the following data :
Plant capacity = 50 MW ;Annual load factor = 40%
Capital cost = 12 millions;
annual cost of wages, taxation etc. = Rs 0.4 lmillion;
cost of fuel,lubrication, maintenance etc. = 1·0
halala/kWh generated.
Interest 5% per annum, depreciation 6%per annum of
initial value. (2)
31. 2/26/2013
31
Load and Loss Factor Relationship
61
While calculating the energy cost the cost of power loss also
must be taken into account.
THERE are two type of losses:
•Fixed Loss ( No load loss)
•Variable loss (Load losses)
Dr.A.Arunagiri
62
No load losses:
Since these are essentially constant , extra generating
equipments must be provided to supply the additional
demand at peak hours. Efficient base –load units(from
hydro capacity , thermal or nuclear) can supply these
losses most of the time. Hence the perunit
demand/energy cost for these is low.
Load Losses:
These losses constitute two losses
Demand loss
Energy loss
Dr.A.Arunagiri
32. 2/26/2013
32
63
Load diversity complicates the evaluation of the demand based
cost of peak load losses. The distribution system peak loading
may not coincide with the total system(generation) peak.
In these losses, the demand cost depends upon peak
responsibility factor(k) which is the ratio of distribution systems
load at the time of total system peak to its peak load. It generally
varies between 0.2 and 0.8 for distribution system and 0.8 and
0.95 for transmission systems.
Dr.A.Arunagiri
Dr.A.Arunagiri 64
If a distribution has P kw loss at its peak load, then k2P
will be the loss at the time of total system peak, the
cost of which is demand based. Therefore k2P kw
losses demand must be provided by the generating
equipments.
33. 2/26/2013
33
Dr.A.Arunagiri 65
For energy based losses the loss factor is important.
It is the ratio of the energy loss in the system during
a given time period to the energy loss that would
result if the system peak loss had persisted
throughout that period.
Load and losses factors relationship:
66
Loss factor = (Load factor)1.732
Or another thumb rule isOne empirical formula is
Loss factor = c (Load factor) + (1-c) (Load factor)2
Where c= 0.3 for transmission system and 0.15 for distribution systems. These two
relations are considered accurate if the minimum demand during the period does
not fall below 0.2 pu of the peak demand.
Dr.A.Arunagiri
One empirical formula is
34. 2/26/2013
34
Dr.A.Arunagiri 67
In case the system load factor Lf Is below 0.8 the following
relation is more accurate:
22
)(273.0 KLLL ffs
K is the minimum demand in pu of peak demand
Ls is loss factor
Lf is load factor
Total losses per annum = Loss factor* Maximum losses
based on continuous peak current
68
2
8.02.0 ffs LLL
2
7.03.0 ffs LLL
2
84.016.0 ffs LLL
2
8.02.0 ffs LLL
•In terms of British experience , this the Losses factor fits relationship:
•The Americanexperience gives:
For urban areas
For rural areas
•The Australians use:
Dr.A.Arunagiri
35. 2/26/2013
35
Example
Dr.A.Arunagiri 69
In a power utility the energy consumption per year
is 5000 GWhr with the maximum and minimum
demands of 1000 and 100 MW respectively. Find the
loss factor and the typical empirical relation.
Solution
Dr.A.Arunagiri 70
Yearly load factor = AD/MD = 0.57
K is the minimum demand in pu of peak demand
K = 100/1000=0.10
3852.0
)(273.0 22
KLLL ffs
Loss factor = c (Load factor) + (1-c) (Load factor)2
0.3852= c (Load factor) + (1-c) (Load factor)2
C=0.25
The empirical relation will be
Loss factor = 0.25(Load factor) + (0.75) (Load factor)2
36. 2/26/2013
36
Load Growth
Dr.A.Arunagiri 71
.
The demand estimation is the starting point for planning
the future electric power supply. The consistency of
demand growth over the years has led to numerous
attempts to fit mathematical curves to this trend. One of
the simplest method is
where a is the average per unit growth rate, P is the
demand in year t, and P0 is
the given demand at year t0.
Definition of some basic concepts in statistics:
Dr.A.Arunagiri 72
n
yi
n
yii
'
n
yi
2
2
)(
2
exp
)(
]/
2
1
[ 22
y
yf
•Mean value
•Weighted mean
•Variance (standard deviation)
•Normaldistribution
37. 2/26/2013
37
Problem
Dr.A.Arunagiri 73
A 2.5MVAR, 11KV, capacitor bank has been commissioned at a
33/11KV, 10MVA transformersubstationhaving the following data:
33KV line length is 35 KM and conductor resistance is 0.584Ω/KM,
Load factor = 0.65.
Find saving in losses and sparing of system capacity after installation
of the capacitors
Without Capacitors With Capacitors
Peak load 8000KW 8000KW
Voltage 10.4KV 11.4KV
Power Factor 0.846 0.99
Peak current on
11KV
525A 409A
Peak current on
33KV
175A 136.3A
Solution
Dr.A.Arunagiri 74