SlideShare a Scribd company logo
GOVT. WOMEN ENGINEERING COLLEGE, AJMER
Presentation On:
NATIONAL AND REGIONAL PLANNING
PRESENTED TO: PRESENTED BY:
Mr. Anant Gupta Jyoti Garg
Khushi Lohia
Monika Tailor
Nisha Dangi
CONTENT:
 INTRODUCTION
 POWER SYSTEM PLANNING
 TRANSMISSION VERSUS DISTRIBUTION PLANNING
 LONG TERM VERSUS SHORT TERM PLANNING
 ISSUES IN TRANSMISSION PLANNING
 GENERATION PLANNING
 CAPACITY RESOURCE PLANNING
 TRANSMISSION PLANNING
 NATIONAL AND REGIONAL PLANNING
INTRODUCTION:
 Planning is the process of selecting vision, values, mission and objectives and
deciding what should be done to attain them.
 The elements may be:
 • Generation facilities
 • Substations
 • Transmission lines and/or cables
 • Capacitors/Reactors
 Planning is the process of taking a careful decision.
The decision should be:
 Where to allocate the element (for instance, thesending and receiving end
of a line).
 When to install the element (for instance, 2018).
 What to select, in terms of the element specifications (for instance, number
of bundles and conductor type).
Transmission Versus Distribution Planning :
 Three main levels for a power system structure, namely, transmission, sub-
transmission and distribution.
 Distribution level is often planned or at least operated, radially.
Long-term Versus Short-term Planning:
Power system planning issues may cover a period of 1–10 years, or even more.
For the peak loading condition of the coming year, a power system utility
expert notices that from the two lines, feeding a substation, one would be
overloaded by 10% of its rating, while, the other would be loaded by 60% of its
rating.
If a control device is installed on one line, the load distribution may be
balanced on both lines.
Once decided, the installation process of this device can be performed in such
a way that no problem arises for the coming year.
This is a typical short term transmission planning decision.
The load forecasting for the coming years shows that with all already available and
planned generations, there would be a shortfall of generation in 9 years from now,
onward.
After a careful study, the planner decides on adding a new 500 MW steam power
plant at a specific bus in that year.
Its construction should start well in advance so that it would be available at the
required time.
His or her decision is a typical long-term (9-year) transmission planning decision.
Basic Issues in Transmission Planning:
 Load Forecasting
The first crucial step for any planning study is to predict the consumption for the study
period (say 2015–2020), as all subsequent studies will be based on that.
However, it is understood that a short-term load forecasting, used for operational studies,
is significantly different from the long-term one used in planning studies.
In a short-term load forecasting, for predicting the load for instance, of the next week,
we come across predicting the load for each hour of the coming week.
It is obvious that the determining factors may be weather conditions, special TV programs
and similar.
Obviously, the determining factors are different here i.e. Population rate increase, GDP
(Gross Domestic Product) and similar terms have dominant effects.
 Generation Expansion Planning:
After predicting the load, the next step is to determine the generation
requirements to satisfy the load.
An obvious simple solution is to assume a generation increase equal to load
increase.
If, for instance, in year 2015, the peak load would be 40,000 MW and at that
time, the available generation is 35,000 MW, an extra generation of 5,000 MW
would be required.
 Substation Expansion Planning:
Once the load is predicted and the generation requirements are known, the next step is to determine
the substation requirements, both, in terms of
Expanding the existing ones
Installing some new ones
This is referred to as Substation Expansion Planning (SEP).
SEP is a difficult task as many factors are involved such as
Those constraints due to the upward grid, feeding the substations,
Those constraints due to the downward grid, through which the substation supplies the loads,
Those constraints due to the factors to be observed for the substation itself.
 Network Expansion Planning:
Network Expansion Planning (NEP) is a process in which the network
(transmission lines, cables, etc.) specifications are determined.
In fact, the network is a media for transmitting the power, efficiently and in
a reliable manner from generation resources to the load centers.
Generator planning:
Load Forecasting
In the short term, load can be forecast with great accuracy, and this is
performed daily to determine generation units’ commitment.
Load forecasting for the purpose of generation planning, however, requires a
substantially longer time horizon, because system expansion projects require
long lead times, often between 2 and 10 years.
The outputs from a load forecast are a forecast of annual energy sales (in
kilowatt-hours), and the annual peak demand (in kilowatts).
There are two widely used methods in energy sales forecasting, econometric
regression analysis, and end- use electricity models.
 The usefulness of each method depends on data availability, customer
segmentation, and the degree of detail required.
 End-use electricity models are physical, engineering based methods that
often are used in forecasting the residential load, and sometimes for
commercial and industrial loads.
 Forecasting the peak demand is done based on forecasted energy sales
by multiplying forecasted energy with an empirically determined load factor
coefficient.
 Peak load is extremely sensitive to weather, and both the historic data
and the forecast must be adjusted consistently to normalize them relative to
the weather.
 Peak load forecasting is important because it directly influences the
required generation capacity—on every day of the year there must be enough
available generation to feed the peak load.
Reactive Power Planning:
In running NEP, the voltages are assumed to be flat (i.e. 1 p.u.) and reactive power flows
are ignored.
The main reason is the fact that constructing a line is not considered as a main tool for
voltage improvement.
Moreover, the running time of NEP can be exceptionally high or even the solution may
not be possible if AC Load Flow (ACLF) is employed. That is why in practice, NEP is
normally based on using Direct Current Load Flow (DCLF).
Upon running GEP, SEP and NEP, the network topology is determined.
However, it may perform unsatisfactorily, if a detailed AC Load Flow (ACLF) is
performed, based on existing algorithms.
To solve such a difficulty, static reactive power compensators, such as capacitors and
reactors may be used. Moreover, some more flexible reactive power resources are
required. The problem is, however
Where to install these devices?
What capacities do we have to employ?
What types do we have to use?
Capacity Resource Planning:
The question of what type of generating station (hydroelectric, nuclear, coal,
gas turbine, or other) would be the most economical addition to the system is
answered by combining a production cost analysis with an investment cost
analysis.
The evaluation begins by preparing a set of expansion scenarios.
An expansion scenario includes additions of multiple units and the planners are
required to hypothesize the type and the number of units that should be
considered.
The scenarios then are evaluated one at a time, beginning with a multiyear
reliability simulation to determine the LOLP index for each year of study.
If the reliability requirements are not met they often can be improved either
by advancing the installation dates of some units, or by delaying retirement
dates of others.
Transmission Planning:
• A transmission system makes it possible to supply loads from the most
economical sources of power, and operate generating stations flexibly and thus
improve overall system reliability.
• Transmission planning therefore ensures that the transmission infrastructure
can deliver power from the generators to the loads, and that all the equipment
will remain within its operating limits in both normal operation and during
system contingencies.
• Contingencies in this context mean unexpected failures of any system element;
for example a generator or a transmission line could have an unexpected outage,
which would force the remainder of the system to transition to a new operating
point.
NATIONAL AND REGIONAL PLANNING:
 There is a lot of diversity in the country in topography, daily peak due
to date and difference in annual peak load timing( winter or summer)
and resources in various regions.
 Hence, the five electricity regions have been established.
 The economic Arguments in support of regional coordination are:
A. Such coordination allow join planning and operation of facilities.
B. It makes exchange of economical energy easier.
C. It prevents construction of unneccessary facilities by isolated
system.
 More specifically, as a result of transmission, coordination offers distinct
economic and the none –coincidental occurrence of the peaks of participation
system.
 It might be possible to reduce the total generating capacity requirements
capacity that would otherwise applied if each utility system were fully meet
its need.
 By combining the existing capacity of different utility, it is possible to reduce
the required reserve capacity of generation in the region and to make
economic use of the generation resources such as hydro and fossil fuel.
 One of the problems in regional planning relates to coordination among the
various utility in the region with respect to tariff and backing down of
generating units in merit order.
 HVDC links for transfer of power between various regions is desirable in order
to utilize surplus power in some regions and for stable grid operation.
FIVE ELECTRICITY REGIONS ARE:
 A. Northern Region
 B. Western Region
 C. Southern Region
 D. Eastern Region
 E. North Eastern Region
ELECTRICITY REGIONS OF INDIA
 Integrated resources planning:
 Least cost utility planning:
 There are two fundamental problems inherent in traditional planning.
 The first is – the demand forecasting and investment planning are treated as
sequential steps in planning.
 The second is – that planning efforts are inadequately directed at the main
constraints facing the sector like the serious shortage of resources.
 Least cost planning is least cost utility planning strategy to provide reliable
electrical services at the lowest overall cost with a mix of supply side and
demand side resources.
POWER SYSTEM PLANNING

More Related Content

What's hot

Demand side management: Demand response
Demand side management: Demand response Demand side management: Demand response
Demand side management: Demand response
Siksha 'O' Anusandhan (Deemed to be University )
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
Leonardo ENERGY
 
demand side management
demand side managementdemand side management
demand side management
Komal Nigam
 
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINEFAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
Dr. Babasaheb Ambedkar Technological University
 
An introduction to FACTS
An introduction to FACTSAn introduction to FACTS
An introduction to FACTSAyyarao T S L V
 
Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of Microgrid
Amarjeet S Pandey
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
akkshay kharwade
 
Load forecasting
Load forecastingLoad forecasting
Load forecastingsushrut p
 
Power system interconnection presentation
Power system interconnection presentationPower system interconnection presentation
Power system interconnection presentation
Aneeque Qaiser
 
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
thanigaivelraja1
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issues
Rohil Kumar
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard Design
Living Online
 
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY pptFACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
Mamta Bagoria
 
Load Forecasting II
Load Forecasting IILoad Forecasting II
Load Forecasting II
linsstalex
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
Pritesh Priyadarshi
 
Electrical power system management
Electrical power system managementElectrical power system management
Electrical power system management
Akshay Awadhani
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
priyanka1432
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIAArun Muraleedharan
 
Distributed generation b 3
Distributed generation b 3Distributed generation b 3
Distributed generation b 3
Naresh Thakur
 
Integration of Renewable Distributed Generators in Distribution System
Integration of Renewable Distributed Generators in Distribution System Integration of Renewable Distributed Generators in Distribution System
Integration of Renewable Distributed Generators in Distribution System
Siksha 'O' Anusandhan (Deemed to be University )
 

What's hot (20)

Demand side management: Demand response
Demand side management: Demand response Demand side management: Demand response
Demand side management: Demand response
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
 
demand side management
demand side managementdemand side management
demand side management
 
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINEFAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALISIS IN HVDC & HVAC TRANSMISSION LINE
 
An introduction to FACTS
An introduction to FACTSAn introduction to FACTS
An introduction to FACTS
 
Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of Microgrid
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
Power system interconnection presentation
Power system interconnection presentationPower system interconnection presentation
Power system interconnection presentation
 
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issues
 
Electrical Substations and Switchyard Design
Electrical Substations and Switchyard DesignElectrical Substations and Switchyard Design
Electrical Substations and Switchyard Design
 
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY pptFACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
 
Load Forecasting II
Load Forecasting IILoad Forecasting II
Load Forecasting II
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
Electrical power system management
Electrical power system managementElectrical power system management
Electrical power system management
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIA
 
Distributed generation b 3
Distributed generation b 3Distributed generation b 3
Distributed generation b 3
 
Integration of Renewable Distributed Generators in Distribution System
Integration of Renewable Distributed Generators in Distribution System Integration of Renewable Distributed Generators in Distribution System
Integration of Renewable Distributed Generators in Distribution System
 

Similar to POWER SYSTEM PLANNING

The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...
arvindsinghrathore6
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
Sifan Welisa
 
Lecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdfLecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdf
ssuser5feb82
 
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
swapnamansani123
 
Power system Planning - Basic Techniques
Power system Planning - Basic TechniquesPower system Planning - Basic Techniques
Power system Planning - Basic Techniques
ChithraM26
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curves
Azfar Rasool
 
Renewable energy integration and energy storage
Renewable energy integration and energy storage Renewable energy integration and energy storage
Renewable energy integration and energy storage
Bushveld Energy
 
EE6603 - Power System Operation & Control
EE6603 - Power System Operation & ControlEE6603 - Power System Operation & Control
EE6603 - Power System Operation & Control
Vel Tech High Tech Dr. Rangarajan Dr. Sakunthala Engg. College
 
Uncertainty model for rate of change of frequency analysis with high renewab...
Uncertainty model for rate of change of frequency analysis with  high renewab...Uncertainty model for rate of change of frequency analysis with  high renewab...
Uncertainty model for rate of change of frequency analysis with high renewab...
IJECEIAES
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Resurgent India
 
Dr.pptx1
Dr.pptx1Dr.pptx1
Two-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network MethodsTwo-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
IRJET Journal
 
Load forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCBLoad forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCB
Suryakant Morey
 
Eskom - Grid Connectivity
Eskom - Grid ConnectivityEskom - Grid Connectivity
Eskom - Grid Connectivity
Wind Energy Update
 
Load forcasting in rajasthan
Load forcasting in rajasthanLoad forcasting in rajasthan
Load forcasting in rajasthan
ShubhamKashyap125
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
smsksolar
 
ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6ladan ghods
 
Alemante research method presentation ppt
Alemante research method presentation pptAlemante research method presentation ppt
Alemante research method presentation ppt
GetahunShankoKefeni
 
Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...
IJECEIAES
 

Similar to POWER SYSTEM PLANNING (20)

The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
 
Lecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdfLecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdf
 
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
 
Power system Planning - Basic Techniques
Power system Planning - Basic TechniquesPower system Planning - Basic Techniques
Power system Planning - Basic Techniques
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curves
 
Renewable energy integration and energy storage
Renewable energy integration and energy storage Renewable energy integration and energy storage
Renewable energy integration and energy storage
 
PP_lect1.pptx
PP_lect1.pptxPP_lect1.pptx
PP_lect1.pptx
 
EE6603 - Power System Operation & Control
EE6603 - Power System Operation & ControlEE6603 - Power System Operation & Control
EE6603 - Power System Operation & Control
 
Uncertainty model for rate of change of frequency analysis with high renewab...
Uncertainty model for rate of change of frequency analysis with  high renewab...Uncertainty model for rate of change of frequency analysis with  high renewab...
Uncertainty model for rate of change of frequency analysis with high renewab...
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
 
Dr.pptx1
Dr.pptx1Dr.pptx1
Dr.pptx1
 
Two-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network MethodsTwo-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
 
Load forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCBLoad forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCB
 
Eskom - Grid Connectivity
Eskom - Grid ConnectivityEskom - Grid Connectivity
Eskom - Grid Connectivity
 
Load forcasting in rajasthan
Load forcasting in rajasthanLoad forcasting in rajasthan
Load forcasting in rajasthan
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6
 
Alemante research method presentation ppt
Alemante research method presentation pptAlemante research method presentation ppt
Alemante research method presentation ppt
 
Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...
 

Recently uploaded

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

POWER SYSTEM PLANNING

  • 1. GOVT. WOMEN ENGINEERING COLLEGE, AJMER Presentation On: NATIONAL AND REGIONAL PLANNING PRESENTED TO: PRESENTED BY: Mr. Anant Gupta Jyoti Garg Khushi Lohia Monika Tailor Nisha Dangi
  • 2. CONTENT:  INTRODUCTION  POWER SYSTEM PLANNING  TRANSMISSION VERSUS DISTRIBUTION PLANNING  LONG TERM VERSUS SHORT TERM PLANNING  ISSUES IN TRANSMISSION PLANNING  GENERATION PLANNING  CAPACITY RESOURCE PLANNING  TRANSMISSION PLANNING  NATIONAL AND REGIONAL PLANNING
  • 3. INTRODUCTION:  Planning is the process of selecting vision, values, mission and objectives and deciding what should be done to attain them.  The elements may be:  • Generation facilities  • Substations  • Transmission lines and/or cables  • Capacitors/Reactors  Planning is the process of taking a careful decision.
  • 4. The decision should be:  Where to allocate the element (for instance, thesending and receiving end of a line).  When to install the element (for instance, 2018).  What to select, in terms of the element specifications (for instance, number of bundles and conductor type).
  • 5. Transmission Versus Distribution Planning :  Three main levels for a power system structure, namely, transmission, sub- transmission and distribution.  Distribution level is often planned or at least operated, radially.
  • 6. Long-term Versus Short-term Planning: Power system planning issues may cover a period of 1–10 years, or even more. For the peak loading condition of the coming year, a power system utility expert notices that from the two lines, feeding a substation, one would be overloaded by 10% of its rating, while, the other would be loaded by 60% of its rating. If a control device is installed on one line, the load distribution may be balanced on both lines. Once decided, the installation process of this device can be performed in such a way that no problem arises for the coming year.
  • 7. This is a typical short term transmission planning decision. The load forecasting for the coming years shows that with all already available and planned generations, there would be a shortfall of generation in 9 years from now, onward. After a careful study, the planner decides on adding a new 500 MW steam power plant at a specific bus in that year. Its construction should start well in advance so that it would be available at the required time. His or her decision is a typical long-term (9-year) transmission planning decision.
  • 8. Basic Issues in Transmission Planning:  Load Forecasting The first crucial step for any planning study is to predict the consumption for the study period (say 2015–2020), as all subsequent studies will be based on that. However, it is understood that a short-term load forecasting, used for operational studies, is significantly different from the long-term one used in planning studies. In a short-term load forecasting, for predicting the load for instance, of the next week, we come across predicting the load for each hour of the coming week. It is obvious that the determining factors may be weather conditions, special TV programs and similar. Obviously, the determining factors are different here i.e. Population rate increase, GDP (Gross Domestic Product) and similar terms have dominant effects.
  • 9.  Generation Expansion Planning: After predicting the load, the next step is to determine the generation requirements to satisfy the load. An obvious simple solution is to assume a generation increase equal to load increase. If, for instance, in year 2015, the peak load would be 40,000 MW and at that time, the available generation is 35,000 MW, an extra generation of 5,000 MW would be required.
  • 10.  Substation Expansion Planning: Once the load is predicted and the generation requirements are known, the next step is to determine the substation requirements, both, in terms of Expanding the existing ones Installing some new ones This is referred to as Substation Expansion Planning (SEP). SEP is a difficult task as many factors are involved such as Those constraints due to the upward grid, feeding the substations, Those constraints due to the downward grid, through which the substation supplies the loads, Those constraints due to the factors to be observed for the substation itself.
  • 11.  Network Expansion Planning: Network Expansion Planning (NEP) is a process in which the network (transmission lines, cables, etc.) specifications are determined. In fact, the network is a media for transmitting the power, efficiently and in a reliable manner from generation resources to the load centers.
  • 12. Generator planning: Load Forecasting In the short term, load can be forecast with great accuracy, and this is performed daily to determine generation units’ commitment. Load forecasting for the purpose of generation planning, however, requires a substantially longer time horizon, because system expansion projects require long lead times, often between 2 and 10 years. The outputs from a load forecast are a forecast of annual energy sales (in kilowatt-hours), and the annual peak demand (in kilowatts). There are two widely used methods in energy sales forecasting, econometric regression analysis, and end- use electricity models.
  • 13.  The usefulness of each method depends on data availability, customer segmentation, and the degree of detail required.  End-use electricity models are physical, engineering based methods that often are used in forecasting the residential load, and sometimes for commercial and industrial loads.  Forecasting the peak demand is done based on forecasted energy sales by multiplying forecasted energy with an empirically determined load factor coefficient.  Peak load is extremely sensitive to weather, and both the historic data and the forecast must be adjusted consistently to normalize them relative to the weather.  Peak load forecasting is important because it directly influences the required generation capacity—on every day of the year there must be enough available generation to feed the peak load.
  • 14. Reactive Power Planning: In running NEP, the voltages are assumed to be flat (i.e. 1 p.u.) and reactive power flows are ignored. The main reason is the fact that constructing a line is not considered as a main tool for voltage improvement. Moreover, the running time of NEP can be exceptionally high or even the solution may not be possible if AC Load Flow (ACLF) is employed. That is why in practice, NEP is normally based on using Direct Current Load Flow (DCLF). Upon running GEP, SEP and NEP, the network topology is determined. However, it may perform unsatisfactorily, if a detailed AC Load Flow (ACLF) is performed, based on existing algorithms.
  • 15. To solve such a difficulty, static reactive power compensators, such as capacitors and reactors may be used. Moreover, some more flexible reactive power resources are required. The problem is, however Where to install these devices? What capacities do we have to employ? What types do we have to use?
  • 16. Capacity Resource Planning: The question of what type of generating station (hydroelectric, nuclear, coal, gas turbine, or other) would be the most economical addition to the system is answered by combining a production cost analysis with an investment cost analysis. The evaluation begins by preparing a set of expansion scenarios. An expansion scenario includes additions of multiple units and the planners are required to hypothesize the type and the number of units that should be considered. The scenarios then are evaluated one at a time, beginning with a multiyear reliability simulation to determine the LOLP index for each year of study. If the reliability requirements are not met they often can be improved either by advancing the installation dates of some units, or by delaying retirement dates of others.
  • 17. Transmission Planning: • A transmission system makes it possible to supply loads from the most economical sources of power, and operate generating stations flexibly and thus improve overall system reliability. • Transmission planning therefore ensures that the transmission infrastructure can deliver power from the generators to the loads, and that all the equipment will remain within its operating limits in both normal operation and during system contingencies. • Contingencies in this context mean unexpected failures of any system element; for example a generator or a transmission line could have an unexpected outage, which would force the remainder of the system to transition to a new operating point.
  • 18. NATIONAL AND REGIONAL PLANNING:  There is a lot of diversity in the country in topography, daily peak due to date and difference in annual peak load timing( winter or summer) and resources in various regions.  Hence, the five electricity regions have been established.  The economic Arguments in support of regional coordination are: A. Such coordination allow join planning and operation of facilities. B. It makes exchange of economical energy easier. C. It prevents construction of unneccessary facilities by isolated system.
  • 19.  More specifically, as a result of transmission, coordination offers distinct economic and the none –coincidental occurrence of the peaks of participation system.  It might be possible to reduce the total generating capacity requirements capacity that would otherwise applied if each utility system were fully meet its need.  By combining the existing capacity of different utility, it is possible to reduce the required reserve capacity of generation in the region and to make economic use of the generation resources such as hydro and fossil fuel.  One of the problems in regional planning relates to coordination among the various utility in the region with respect to tariff and backing down of generating units in merit order.  HVDC links for transfer of power between various regions is desirable in order to utilize surplus power in some regions and for stable grid operation.
  • 20.
  • 21.
  • 22. FIVE ELECTRICITY REGIONS ARE:  A. Northern Region  B. Western Region  C. Southern Region  D. Eastern Region  E. North Eastern Region
  • 25.  Least cost utility planning:  There are two fundamental problems inherent in traditional planning.  The first is – the demand forecasting and investment planning are treated as sequential steps in planning.  The second is – that planning efforts are inadequately directed at the main constraints facing the sector like the serious shortage of resources.  Least cost planning is least cost utility planning strategy to provide reliable electrical services at the lowest overall cost with a mix of supply side and demand side resources.