SlideShare a Scribd company logo
Unit Commitment
A comparison of Optimization techniques applied on 10 unit systems for Unit
Commitment Problem
Contents
 Introduction
 Unit Commitment Problem Formulation
 Objective Function
 Constraints
 A Brief Overview of Some Optimization Techniques
 Cost Comparison of different Optimization Techniques applied to UCP
 10 Unit Standard Test System
 Load profile of 24 hour (Tabular and Graphical)
 Tabular Summary of Results from Research Papers
 Graphical Summary of Results from Research Papers
 Binary Unit Commitment and Unit Allocation data
 Conclusion
 References
Introduction
• Steps of Power System Operation
• Load Forecasting
• Hydrothermal Coordination
• Unit Commitment
• Economic Dispatch
• Unit Commitment Overview
• Determination of Generation mix to achieve estimated output
level to meet the demand of electricity for a specified time
interval while satisfying all constraints.
Objective Function
 Minimization of Total Cost including:
 Fuel Cost
𝐹𝐶𝑖 𝑃𝑖 𝑡 = 𝐴𝑖 + 𝐵𝑖 𝑃𝑖 𝑡 + 𝐶𝑖 𝑃𝑖
2
(𝑡)
 Startup Cost
 Shutdown Cost
 Shutdown Cost is Constant and is zero in Typical Systems
 Total Cost
Constraints
Definition:
Constraint is limitations in power system avoiding it cause serious
problem.
This limitation can be technical for unit or technical limitation for power
system or can be environmental limitations.
We can classified into
 Unit constraints.
 System constraints.
 Environmental constraints.
 Network constraints.
 Cost constraints.
Unit commitment constraints
 Unit constraint :
1. Maximum generating capacity.
2. Minimum stable generation.
3. Minimum up time.
4. Minimum down time.
5. Ramp rates.
1. Ramp up rate.
2. Ramp down rate.
3. Start-up ramp rate.
4. Shut down ramp rate
5. Running-up ramp rate
6. Running down ramp rate.
Unit commitment constraints
 System constraints:
1- Load / generation balance / system power balance.
2- Spinning reserve constraint.
 Network constraint:
 Environmental constraint:
 Cost constrain:
1- Start-up cost.
2- Running cost.
Unit commitment constraints
 Maximum generating capacity:
That constraint state that the power generated from the unit must not exceed
specific value because of thermal stability of the unit exceeding this constraint cause damage to the unit.
Mathematical formula.
X (i,t) < P max
X (i,t) is the output power of the unit i, in the time t.
 Minimum stable generation:
As the above constraint the power outage from the unit must not fall down
specific value because of technical limitation like flame stability in the gas and steam units.
Mathematical formula.
X (i,t) > P min
The maximum and minimum generated power of each scheduled unit must not be exceeded
p min < X (i, t) < p max
Unit commitment constraints
 Minimum up time:
This constraint state that once the unit is running must not shunt down
immediately due technical limitation and mechanical characteristic of the unit.
Mathematical formula:
Where
u(i, t) : status of unit i at period t.
u(i, t) = 1 unit i is ON during period t.
u(i, t) = 0 unit i is Off during period t.
Unit commitment constraints
Ramp rates:
Definition:
To avoid damaging the turbine, the electrical output of a unit cannot
change by more than a certain amount over a period of time.
Minimum down time:
This constrain state that once the unit is running must not shunt
down immediately due technical limitation and mechanical characteristic of the unit.
Unit commitment constraints
 Ramp-up rate:
 Start-up ramp rate:
According to this constraint the unit cannot start immediately but taking
time this time called start up time.
 Running-up ramp rate:
According to this constraint the unit cannot immediate changing the power
up without taking time called ramp rate running up time. The change here means
increasing outage power.
Mathematical formula:
x(i, t+1) x(i, t)
Unit commitment constraints
 Ramp down rate:
 Shut down ramp rate:
Look like previse constraint the unit take time to shut down.
 Running down ramp rate:
According to this one in case of running condition. The unit cannot
immediate changing the power down without taking time called ramp rate running
down time. The change here means decreasing outage power.
Mathematical formula:
x (i, t) x (i, t+1)
Unit commitment constraints
 System constraints:
State as the power generated from all unit must be equal the load and
the losses.
Mathematical formula:
u(i,t) * x(i,t) = l(t)
Where l(t) is the load power at time t.
 Spinning reserve constraint:
 Spinning reserve:
Spinning reserve is the on-line reserve capacity that is synchronized to
the grid system and ready to meet electric demand within 10 minutes of a dispatch
instruction by the ISO (International Standards Organization) . Spinning reserve is
needed to maintain system frequency stability during emergency operating conditions
and unforeseen load swings.
Unit commitment constraints
 Reason to keep reserve power.
1- Sudden unexpected increase in the load demand.
2- Underestimating the load due to error in load forecasting.
3- Local shortage in the generated power
4- Force outage of some generating units.
5- Force outage of supplementary equipment’s due to stability problem.
In Electrical engineering, Force outage is the shutdown condition of a power station, transmission
line or distribution line when the generating unit is unavailable to produce power due to unexpected
breakdown.
 Condition of reserve.
1- Reserve must be higher than largest unit.
2- Should be spread around the network.
3- The unit must operate at 80-85% of its rated.
Unit commitment constraints
 Network constraint:
Transmission network may have effect on the commitment of units because of
Some units must run to provide voltage support.
The output of some units may be limited because their output would exceed the
transmission capacity of the network.
 Environmental constraint:
Unit commitment study is effected by environmental constrains because of
Constraints on pollutants such SO2, NOx various forms:
1- Limit on each plant at each hour.
2- Limit on plant over a year.
3- Limit on a group of plants over a year.
Unit commitment constraints
 Constraints on hydro generation:
1- Protection of wildlife.
2- Navigation, recreation.
 Cost constraints:
Cost constrain taking two type of cost in consideration.
1- Start-up cost:
Start up cost depends on varicose factor like
 Warming up because the unit cannot bring on line immediately.
Start up cost depends on time unit has been off.
Unit commitment constraints
 Running cost:
A balance between start-up costs and running costs is important
because of
1- How long should a unit run to “ recover” its start up cost ?
Example:
Diesel generator : Low start-up cost, High running cost.
Coal plant : High start-up cost, Low running cost.
 Spinning Reserve:
“Spinning” means the generator is running and may have be synchronized, so it is
ready to provide the desired power in short time.
 when some sudden load demand is there we increase steam input and delta increases a little
bit and sudden requirement is supplied. This capacity of generators is called "Spinning
Reserve".
A Brief Overview of Some
Optimization Techniques
Algorithms used in UC
 Solving Unit Commitment Problem
Using Modified Sub-gradient
Method Combined with Simulated
Annealing Algorithm
 A New Heuristic Algorithm for Unit
Commitment Problem (Modified
Harmonic Search)
 Solving Unit Commitment Problem
Using Multi-agent Evolutionary
Programming Incorporating Priority
List
 Solution to Unit Commitment
Problem using La-Grangian
Relaxation and Mendel’s GA Method
 A New Priority List Unit
Commitment Method for Large-
Scale Power Systems
 Three meta heuristic techniques:
 Charged Search System
 Particle Swarm Optimization
 Ant Colony Search
Simulated Annealing
 Strong technique for solving hard combinatorial optimization problems without specific structure
 Inspired by Annealing in Metallurgy which involves:
 Heating and Controlled cooling of a material to increase the size of its crystals and reduce their effect
(Wikipedia)
 Basic Working Steps:
 Random Selection of a solution close to current solution
 Decision on the basis of two probabilities:
 Probability of finding a better solution (kept 1)
 Probability of finding a worse solution (kept 0)
 Main Features:
 Lesser Memory Requirements (Advantage)
 Ability to escape Local Minima
 Large Computation Time Required (Disadvantage)
Simulated Annealing Algorithm Steps
Harmony Search (HS) Algorithm
 Population based metaheuristic Algorithm
 Based on natural musical performance processes that occur when a musician
searches for a better state of Harmony
 Algorithm Steps
 Initialization of Harmony Memory
 Improvisation of new Harmony vector
 Harmony Memory Updating
Multi-agent Evolutionary Programming
Incorporating Priority List
 Multi-agent Evolutionary Programming incorporating Priority List optimization
technique (MAEP-PL) is proposed to solve the unit commitment problem
 Combination of three techniques:
 The Multi-agent system (MAS)
 Multiple Interacting Intelligent Agents working together to achieve common goal
 The Evolutionary Programming (EP) optimization technique
 The Priority List optimization Technique (PL)
 Rule 1: based on Maximum Power Generation Rate
 Rule 2: based on Maximum Generation Rate and Capacity
Cost Comparison of different Optimization
Techniques applied to UCP
Standard 10 Unit Test System
Load Profile of 24 hr (Tabular)
Load Profile of 24 hr (Graphical)
0
200
400
600
800
1000
1200
1400
1600
0 5 10 15 20 25 30
LOADINMW
HOURS
LOAD PROFILE OF 24 HR
Tabular Summary of Results from
Research Papers (1/3)
Ref. # Technique used Abbreviation Year Best Cost ($)
1 GA Genetic Algorithm 2012 565,825.00
2 EP Evolutionary Programming 2012 564,551.00
3 SA Simulated Annealing 2012 565,828.00
4 DE Differential Evolution 2012 563,977.00
5 IPSO Improved Particle Swarm Optimization 2012 563,954.00
6 IQEA Improved Quantum Evolutionary Algorithm 2012 563,977.00
7 QBPSO Quantum-Inspired binary PSO 2012 563,977.00
8 BNFO Binary Neighbourhood field Optimization 2012 563,938.00
9 SPL Stochastic Priority list 2013 564,950.00
10 EP Evolutionary Programming 2013 565,352.00
11 PSO Particle Swarm Optimization 2013 574,153.00
12 BPSO Binary Neighbourhood field Optimization 2013 565,804.00
13 PSO-LR PSO Combined with Lagrangian relaxation 2013 565,869.00
14 LR Lagrangian relaxation 2013 566,107.00
15 LRGA Lagrangian relaxation combined with Genetic Algorithm 2013 564,800.00
16 ALR Augmented Lagrangian relaxation 2013 565,508.00
17 GA Genetic Algorithm 2013 565,825.00
18 BCGA Binary Coded Genetic Algorithm 2013 567,367.00
19 ICGA Integer Coded Genetic Algorithm 2013 566,404.00
20 DP Dynamic Programming 2013 565,825.00
21 MA Memetic Algorithm 2013 565,827.00
22 PM Prposed method 2013 564,703.00
Tabular Summary of Results from
Research Papers (2/3)
23 MIP Mexed Integer Programming 2014 564,647.00
24 QEA Quantum-Inspired Evolutionary Algorithm 2014 563,938.00
25 IBPSO Improved Binary Particle Swarm Optimization 2014 563,977.00
26 BGSO Binary Glowwarm Swarm Optimization 2014 563,938.00
27 SDPSP Semi Definite Programming combined with selective Pruning 2016 563,977.00
28 GA Genetic Algorithm 2016 565,825.00
29 EP Evolutionary Programming 2016 564,551.00
30 ICA Imperialist Competitive Algorithm 2016 563,938.00
31 BRABC Binary Real Coded Artificial Bee Colony 2016 563,937.72
32 QIEA Quantum-Inspired Evolutionary Algorithm 2016 563,938.00
33 GHS-JGT Guassian Harmony Search and Jumping Gene Transposition Algorithm 2016 563,937.68
34 QOTLOB Quasi-oppositional Teaching Learning Based Optimization 2016 563,937.69
35 ELRPSO Langrangian Relaxation and Particle Swarm Optimization 2016 563,938.00
36 LR Lagragian Relaxation 2016 565,673.13
37 GA Genetic Algorithm 2016 564,217.08
38 LRGA Lagrangian Relaxation & Genetic Algorithm 2016 564,800.00
39 BFA Bacteria Foraging Algorithm 2016 564,842.00
40 IBPSO Improved Binary PSO 2016 563,977.00
41 Mendel's GA Mendel's Genetic Algorithm 2016 563,937.00
42 LRMGA Lagrangian Relaxation & Mendel's Genetic Algorithm 2016 562,587.00
43 SPL Stochastic Priority list 2017 564,950.00
44 EP Evolutionary Programming 2017 565,352.00
Tabular Summary of Results from
Research Papers (3/3)
45 EPL Extended Priority List 2017 563,977.00
46 PLEA Priority List Based Evolutionary Algorithm 2017 563,977.00
47 PSO Particle Swarm Optimization 2017 574,153.00
48 BPSO Binary Neighbourhood field Optimization 2017 565,804.00
49 PSO-LR Particle Swarm Optimization- Langrangian Relaxation 2017 565,869.00
50 LR Langrangian Relaxation 2017 566,107.00
51 LRGA Lagrangian Relaxation & Genetic Algorithm 2017 564,800.00
52 ALR Augmented Lagrangian relaxation 2017 565,508.00
53 GA Genetic Algorithm 2017 565,825.00
54 FPGA Floating Point Genetic Algorithm 2017 564,094.00
55 BCGA Binary Coded Genetic Algorithm 2017 567,367.00
56 ICGA Integer Coded Genetic Algorithm 2017 566,404.00
57 UCC-GA Unit Characteristic Classification-Genetic Algorithm 2017 563,977.00
58 ACSA Ant Colony search Algorithm 2017 564,049.00
59 DP Dynamic Programming 2017 565,825.00
60 DPLR Dynamic Programming and Langrangian Relaxation 2017 564,049.00
61 TS-RP Tabu Search based Hybrid Algorithm 2017 564,551.00
62 MA Memetic Algorithm 2017 565,827.00
63 MRCGA Modified Real Coded Genetic Algorithm 2017 564,244.00
64 CSS Charge Search Algorithm 2017 563,938.00
65 PSO Particle Swarm Optimization 2017 563,938.00
66 ACS Ant Colony search 2017 563,938.00
Graphical Summary of Results from
Research Papers
574,153.00
562,587.00
574,153.00
562,000.00
564,000.00
566,000.00
568,000.00
570,000.00
572,000.00
574,000.00
576,000.00
0 10 20 30 40 50 60 70
BESTCOSTACHEIVED
REFERENCE NUMBER OF TECHNIQUE USED TO SOLVE UC PROBLEM
COST COMPARISON W.R.T DIFFERENT
TECHNIQUES
Some Binaries extracted from
Research Papers
Conclusion
 In this Presentation, we have learned
 Unit Commitment Problem Formulation
 Objective Function
 Constraints
 Some Algorithms Applied to UCP
 Results and Comparison from recent Research Papers
References
 Wu, Zhou, and Tommy WS Chow. "Binary neighbourhood field optimisation for
unit commitment problems." IET Generation, Transmission & Distribution 7.3
(2013): 298-308.
 Najafi, S. "A new heuristic algorithm for unit commitment problem." Energy
Procedia 14 (2012): 2005-2011.
 Sharma, Deepak, et al. "Multi-agent modeling for solving profit based unit
commitment problem." Applied Soft Computing 13.8 (2013): 3751-3761.
 Roy, Provas Kumar, and Ranadhir Sarkar. "Solution of unit commitment
problem using quasi-oppositional teaching learning based algorithm."
International Journal of Electrical Power & Energy Systems 60 (2014): 96-106.
 Mingwei, L. I., et al. "Binary glowworm swarm optimization for unit
commitment." Journal of Modern Power Systems and Clean Energy 2.4 (2014):
357-365.
References
 Arora, Vinay, and Saurabh Chanana. "Solution to unit commitment problem using
Lagrangian relaxation and Mendel's GA method." Emerging Trends in Electrical
Electronics & Sustainable Energy Systems (ICETEESES), International Conference
on. IEEE, 2016.
 Othman, M. N. C., et al. "Solving unit commitment problem using multi-agent
evolutionary programming incorporating priority list." Arabian Journal for Science
and Engineering 40.11 (2015): 3247-3261.
 Elsayed, Abdullah M., Ahmed M. Maklad, and Sobhy M. Farrag. "A new priority list
unit commitment method for large-scale power systems." Power Systems
Conference (MEPCON), 2017 Nineteenth International Middle East. IEEE, 2017.
 Arora, Vinay, and Saurabh Chanana. "Solution to unit commitment problem using
Lagrangian relaxation and Mendel's GA method." Emerging Trends in Electrical
Electronics & Sustainable Energy Systems (ICETEESES), International Conference
on. IEEE, 2016.
References
 Wu, Yuan-Kang, Hong-Yi Chang, and Shih Ming Chang. "Analysis and Comparison for
the Unit Commitment Problem in a Large-Scale Power System by Using Three Meta-
Heuristic Algorithms." Energy Procedia 141 (2017): 423-427.
 Ghadi, M. Jabbari, A. Baghramian, and M. Hosseini Imani. "An ICA based approach
for solving profit based unit commitment problem market." Applied Soft
Computing 38 (2016): 487-500.
 Shahbazitabar, Maryam, and Hamdi Abdi. "A Solution to the Unit Commitment
Problem Applying a Hierarchical Combination Algorithm." Journal of Energy
Management and Technology 1.2 (2017): 12-19.
 Saber, Navid Abdolhoseyni, Mahdi Salimi, and Davar Mirabbasi. "A priority list based
approach for solving thermal unit commitment problem with novel hybrid genetic-
imperialist competitive algorithm." Energy 117 (2016): 272-280.
Unit commitment

More Related Content

What's hot

Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
Balaram Das
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
Pritesh Priyadarshi
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
Birju Besra
 
Load / Frequency balancing Control systems study
Load / Frequency balancing Control systems studyLoad / Frequency balancing Control systems study
Load / Frequency balancing Control systems study
CAL
 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental cost
Eklavya Sharma
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability
SANTOSH GADEKAR
 
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY pptFACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
Mamta Bagoria
 
Combined operation of power plants
Combined operation of power plantsCombined operation of power plants
Combined operation of power plants
Nishkam Dhiman
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curve
CraZzy Shubh
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
Mayank Sharma
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
Niraj Solanki
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysis
Revathi Subramaniam
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
khemraj298
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
Nitish NIT
 
Economic Dispatch
Economic DispatchEconomic Dispatch
Economic Dispatch
Power System Operation
 
Load Forecasting
Load ForecastingLoad Forecasting
Load Forecasting
linsstalex
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
Power System Operation
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission Lines
Raja Adapa
 
Solution to ELD problem
Solution to ELD problemSolution to ELD problem
Solution to ELD problem
Naveena Navi
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
Ahmed M. Elkholy
 

What's hot (20)

Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment Economic operation of Power systems by Unit commitment
Economic operation of Power systems by Unit commitment
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
 
Load / Frequency balancing Control systems study
Load / Frequency balancing Control systems studyLoad / Frequency balancing Control systems study
Load / Frequency balancing Control systems study
 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental cost
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability
 
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY pptFACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
 
Combined operation of power plants
Combined operation of power plantsCombined operation of power plants
Combined operation of power plants
 
Ppt on diff. load curve
Ppt on diff. load curvePpt on diff. load curve
Ppt on diff. load curve
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysis
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
 
Economic Dispatch
Economic DispatchEconomic Dispatch
Economic Dispatch
 
Load Forecasting
Load ForecastingLoad Forecasting
Load Forecasting
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission Lines
 
Solution to ELD problem
Solution to ELD problemSolution to ELD problem
Solution to ELD problem
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 

Similar to Unit commitment

Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
paperpublications3
 
Economic dipatch
Economic dipatch Economic dipatch
Economic dipatch
Doni Wahyudi
 
F43022431
F43022431F43022431
F43022431
IJERA Editor
 
IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...
IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...
IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...
IRJET Journal
 
A Genetic Algorithm Approach to Solve Unit Commitment Problem
A Genetic Algorithm Approach to Solve Unit Commitment ProblemA Genetic Algorithm Approach to Solve Unit Commitment Problem
A Genetic Algorithm Approach to Solve Unit Commitment Problem
IOSR Journals
 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
Karthik Kathan
 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytemshawon1981
 
A039101011
A039101011A039101011
A039101011
inventionjournals
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
Universidad Naacional de Loja
 
The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...
IJECEIAES
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET Journal
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET Journal
 
Power station
Power stationPower station
Power station
Sirat Mahmood
 
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMA MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
AEIJjournal2
 
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMA MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
AEIJjournal2
 
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMA MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
aeijjournal
 
Advanced Energy: An International Journal (AEIJ)
Advanced Energy: An International Journal (AEIJ)Advanced Energy: An International Journal (AEIJ)
Advanced Energy: An International Journal (AEIJ)
AEIJjournal2
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
inventionjournals
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
IJAPEJOURNAL
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
Adama Science and Technology University
 

Similar to Unit commitment (20)

Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...
 
Economic dipatch
Economic dipatch Economic dipatch
Economic dipatch
 
F43022431
F43022431F43022431
F43022431
 
IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...
IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...
IRJET- A Genetic based Stochastic Approach for Solving Thermal Unit Commitmen...
 
A Genetic Algorithm Approach to Solve Unit Commitment Problem
A Genetic Algorithm Approach to Solve Unit Commitment ProblemA Genetic Algorithm Approach to Solve Unit Commitment Problem
A Genetic Algorithm Approach to Solve Unit Commitment Problem
 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytem
 
A039101011
A039101011A039101011
A039101011
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
Power station
Power stationPower station
Power station
 
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMA MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
 
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMA MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
 
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMA MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEM
 
Advanced Energy: An International Journal (AEIJ)
Advanced Energy: An International Journal (AEIJ)Advanced Energy: An International Journal (AEIJ)
Advanced Energy: An International Journal (AEIJ)
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
 

Recently uploaded

Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 

Recently uploaded (20)

Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 

Unit commitment

  • 1. Unit Commitment A comparison of Optimization techniques applied on 10 unit systems for Unit Commitment Problem
  • 2. Contents  Introduction  Unit Commitment Problem Formulation  Objective Function  Constraints  A Brief Overview of Some Optimization Techniques  Cost Comparison of different Optimization Techniques applied to UCP  10 Unit Standard Test System  Load profile of 24 hour (Tabular and Graphical)  Tabular Summary of Results from Research Papers  Graphical Summary of Results from Research Papers  Binary Unit Commitment and Unit Allocation data  Conclusion  References
  • 3. Introduction • Steps of Power System Operation • Load Forecasting • Hydrothermal Coordination • Unit Commitment • Economic Dispatch • Unit Commitment Overview • Determination of Generation mix to achieve estimated output level to meet the demand of electricity for a specified time interval while satisfying all constraints.
  • 4. Objective Function  Minimization of Total Cost including:  Fuel Cost 𝐹𝐶𝑖 𝑃𝑖 𝑡 = 𝐴𝑖 + 𝐵𝑖 𝑃𝑖 𝑡 + 𝐶𝑖 𝑃𝑖 2 (𝑡)  Startup Cost  Shutdown Cost  Shutdown Cost is Constant and is zero in Typical Systems  Total Cost
  • 5. Constraints Definition: Constraint is limitations in power system avoiding it cause serious problem. This limitation can be technical for unit or technical limitation for power system or can be environmental limitations. We can classified into  Unit constraints.  System constraints.  Environmental constraints.  Network constraints.  Cost constraints.
  • 6. Unit commitment constraints  Unit constraint : 1. Maximum generating capacity. 2. Minimum stable generation. 3. Minimum up time. 4. Minimum down time. 5. Ramp rates. 1. Ramp up rate. 2. Ramp down rate. 3. Start-up ramp rate. 4. Shut down ramp rate 5. Running-up ramp rate 6. Running down ramp rate.
  • 7. Unit commitment constraints  System constraints: 1- Load / generation balance / system power balance. 2- Spinning reserve constraint.  Network constraint:  Environmental constraint:  Cost constrain: 1- Start-up cost. 2- Running cost.
  • 8. Unit commitment constraints  Maximum generating capacity: That constraint state that the power generated from the unit must not exceed specific value because of thermal stability of the unit exceeding this constraint cause damage to the unit. Mathematical formula. X (i,t) < P max X (i,t) is the output power of the unit i, in the time t.  Minimum stable generation: As the above constraint the power outage from the unit must not fall down specific value because of technical limitation like flame stability in the gas and steam units. Mathematical formula. X (i,t) > P min The maximum and minimum generated power of each scheduled unit must not be exceeded p min < X (i, t) < p max
  • 9. Unit commitment constraints  Minimum up time: This constraint state that once the unit is running must not shunt down immediately due technical limitation and mechanical characteristic of the unit. Mathematical formula: Where u(i, t) : status of unit i at period t. u(i, t) = 1 unit i is ON during period t. u(i, t) = 0 unit i is Off during period t.
  • 10. Unit commitment constraints Ramp rates: Definition: To avoid damaging the turbine, the electrical output of a unit cannot change by more than a certain amount over a period of time. Minimum down time: This constrain state that once the unit is running must not shunt down immediately due technical limitation and mechanical characteristic of the unit.
  • 11. Unit commitment constraints  Ramp-up rate:  Start-up ramp rate: According to this constraint the unit cannot start immediately but taking time this time called start up time.  Running-up ramp rate: According to this constraint the unit cannot immediate changing the power up without taking time called ramp rate running up time. The change here means increasing outage power. Mathematical formula: x(i, t+1) x(i, t)
  • 12. Unit commitment constraints  Ramp down rate:  Shut down ramp rate: Look like previse constraint the unit take time to shut down.  Running down ramp rate: According to this one in case of running condition. The unit cannot immediate changing the power down without taking time called ramp rate running down time. The change here means decreasing outage power. Mathematical formula: x (i, t) x (i, t+1)
  • 13. Unit commitment constraints  System constraints: State as the power generated from all unit must be equal the load and the losses. Mathematical formula: u(i,t) * x(i,t) = l(t) Where l(t) is the load power at time t.  Spinning reserve constraint:  Spinning reserve: Spinning reserve is the on-line reserve capacity that is synchronized to the grid system and ready to meet electric demand within 10 minutes of a dispatch instruction by the ISO (International Standards Organization) . Spinning reserve is needed to maintain system frequency stability during emergency operating conditions and unforeseen load swings.
  • 14. Unit commitment constraints  Reason to keep reserve power. 1- Sudden unexpected increase in the load demand. 2- Underestimating the load due to error in load forecasting. 3- Local shortage in the generated power 4- Force outage of some generating units. 5- Force outage of supplementary equipment’s due to stability problem. In Electrical engineering, Force outage is the shutdown condition of a power station, transmission line or distribution line when the generating unit is unavailable to produce power due to unexpected breakdown.  Condition of reserve. 1- Reserve must be higher than largest unit. 2- Should be spread around the network. 3- The unit must operate at 80-85% of its rated.
  • 15. Unit commitment constraints  Network constraint: Transmission network may have effect on the commitment of units because of Some units must run to provide voltage support. The output of some units may be limited because their output would exceed the transmission capacity of the network.  Environmental constraint: Unit commitment study is effected by environmental constrains because of Constraints on pollutants such SO2, NOx various forms: 1- Limit on each plant at each hour. 2- Limit on plant over a year. 3- Limit on a group of plants over a year.
  • 16. Unit commitment constraints  Constraints on hydro generation: 1- Protection of wildlife. 2- Navigation, recreation.  Cost constraints: Cost constrain taking two type of cost in consideration. 1- Start-up cost: Start up cost depends on varicose factor like  Warming up because the unit cannot bring on line immediately. Start up cost depends on time unit has been off.
  • 17. Unit commitment constraints  Running cost: A balance between start-up costs and running costs is important because of 1- How long should a unit run to “ recover” its start up cost ? Example: Diesel generator : Low start-up cost, High running cost. Coal plant : High start-up cost, Low running cost.  Spinning Reserve: “Spinning” means the generator is running and may have be synchronized, so it is ready to provide the desired power in short time.  when some sudden load demand is there we increase steam input and delta increases a little bit and sudden requirement is supplied. This capacity of generators is called "Spinning Reserve".
  • 18. A Brief Overview of Some Optimization Techniques
  • 19. Algorithms used in UC  Solving Unit Commitment Problem Using Modified Sub-gradient Method Combined with Simulated Annealing Algorithm  A New Heuristic Algorithm for Unit Commitment Problem (Modified Harmonic Search)  Solving Unit Commitment Problem Using Multi-agent Evolutionary Programming Incorporating Priority List  Solution to Unit Commitment Problem using La-Grangian Relaxation and Mendel’s GA Method  A New Priority List Unit Commitment Method for Large- Scale Power Systems  Three meta heuristic techniques:  Charged Search System  Particle Swarm Optimization  Ant Colony Search
  • 20. Simulated Annealing  Strong technique for solving hard combinatorial optimization problems without specific structure  Inspired by Annealing in Metallurgy which involves:  Heating and Controlled cooling of a material to increase the size of its crystals and reduce their effect (Wikipedia)  Basic Working Steps:  Random Selection of a solution close to current solution  Decision on the basis of two probabilities:  Probability of finding a better solution (kept 1)  Probability of finding a worse solution (kept 0)  Main Features:  Lesser Memory Requirements (Advantage)  Ability to escape Local Minima  Large Computation Time Required (Disadvantage)
  • 22. Harmony Search (HS) Algorithm  Population based metaheuristic Algorithm  Based on natural musical performance processes that occur when a musician searches for a better state of Harmony  Algorithm Steps  Initialization of Harmony Memory  Improvisation of new Harmony vector  Harmony Memory Updating
  • 23. Multi-agent Evolutionary Programming Incorporating Priority List  Multi-agent Evolutionary Programming incorporating Priority List optimization technique (MAEP-PL) is proposed to solve the unit commitment problem  Combination of three techniques:  The Multi-agent system (MAS)  Multiple Interacting Intelligent Agents working together to achieve common goal  The Evolutionary Programming (EP) optimization technique  The Priority List optimization Technique (PL)  Rule 1: based on Maximum Power Generation Rate  Rule 2: based on Maximum Generation Rate and Capacity
  • 24.
  • 25. Cost Comparison of different Optimization Techniques applied to UCP
  • 26. Standard 10 Unit Test System
  • 27. Load Profile of 24 hr (Tabular)
  • 28. Load Profile of 24 hr (Graphical) 0 200 400 600 800 1000 1200 1400 1600 0 5 10 15 20 25 30 LOADINMW HOURS LOAD PROFILE OF 24 HR
  • 29. Tabular Summary of Results from Research Papers (1/3) Ref. # Technique used Abbreviation Year Best Cost ($) 1 GA Genetic Algorithm 2012 565,825.00 2 EP Evolutionary Programming 2012 564,551.00 3 SA Simulated Annealing 2012 565,828.00 4 DE Differential Evolution 2012 563,977.00 5 IPSO Improved Particle Swarm Optimization 2012 563,954.00 6 IQEA Improved Quantum Evolutionary Algorithm 2012 563,977.00 7 QBPSO Quantum-Inspired binary PSO 2012 563,977.00 8 BNFO Binary Neighbourhood field Optimization 2012 563,938.00 9 SPL Stochastic Priority list 2013 564,950.00 10 EP Evolutionary Programming 2013 565,352.00 11 PSO Particle Swarm Optimization 2013 574,153.00 12 BPSO Binary Neighbourhood field Optimization 2013 565,804.00 13 PSO-LR PSO Combined with Lagrangian relaxation 2013 565,869.00 14 LR Lagrangian relaxation 2013 566,107.00 15 LRGA Lagrangian relaxation combined with Genetic Algorithm 2013 564,800.00 16 ALR Augmented Lagrangian relaxation 2013 565,508.00 17 GA Genetic Algorithm 2013 565,825.00 18 BCGA Binary Coded Genetic Algorithm 2013 567,367.00 19 ICGA Integer Coded Genetic Algorithm 2013 566,404.00 20 DP Dynamic Programming 2013 565,825.00 21 MA Memetic Algorithm 2013 565,827.00 22 PM Prposed method 2013 564,703.00
  • 30. Tabular Summary of Results from Research Papers (2/3) 23 MIP Mexed Integer Programming 2014 564,647.00 24 QEA Quantum-Inspired Evolutionary Algorithm 2014 563,938.00 25 IBPSO Improved Binary Particle Swarm Optimization 2014 563,977.00 26 BGSO Binary Glowwarm Swarm Optimization 2014 563,938.00 27 SDPSP Semi Definite Programming combined with selective Pruning 2016 563,977.00 28 GA Genetic Algorithm 2016 565,825.00 29 EP Evolutionary Programming 2016 564,551.00 30 ICA Imperialist Competitive Algorithm 2016 563,938.00 31 BRABC Binary Real Coded Artificial Bee Colony 2016 563,937.72 32 QIEA Quantum-Inspired Evolutionary Algorithm 2016 563,938.00 33 GHS-JGT Guassian Harmony Search and Jumping Gene Transposition Algorithm 2016 563,937.68 34 QOTLOB Quasi-oppositional Teaching Learning Based Optimization 2016 563,937.69 35 ELRPSO Langrangian Relaxation and Particle Swarm Optimization 2016 563,938.00 36 LR Lagragian Relaxation 2016 565,673.13 37 GA Genetic Algorithm 2016 564,217.08 38 LRGA Lagrangian Relaxation & Genetic Algorithm 2016 564,800.00 39 BFA Bacteria Foraging Algorithm 2016 564,842.00 40 IBPSO Improved Binary PSO 2016 563,977.00 41 Mendel's GA Mendel's Genetic Algorithm 2016 563,937.00 42 LRMGA Lagrangian Relaxation & Mendel's Genetic Algorithm 2016 562,587.00 43 SPL Stochastic Priority list 2017 564,950.00 44 EP Evolutionary Programming 2017 565,352.00
  • 31. Tabular Summary of Results from Research Papers (3/3) 45 EPL Extended Priority List 2017 563,977.00 46 PLEA Priority List Based Evolutionary Algorithm 2017 563,977.00 47 PSO Particle Swarm Optimization 2017 574,153.00 48 BPSO Binary Neighbourhood field Optimization 2017 565,804.00 49 PSO-LR Particle Swarm Optimization- Langrangian Relaxation 2017 565,869.00 50 LR Langrangian Relaxation 2017 566,107.00 51 LRGA Lagrangian Relaxation & Genetic Algorithm 2017 564,800.00 52 ALR Augmented Lagrangian relaxation 2017 565,508.00 53 GA Genetic Algorithm 2017 565,825.00 54 FPGA Floating Point Genetic Algorithm 2017 564,094.00 55 BCGA Binary Coded Genetic Algorithm 2017 567,367.00 56 ICGA Integer Coded Genetic Algorithm 2017 566,404.00 57 UCC-GA Unit Characteristic Classification-Genetic Algorithm 2017 563,977.00 58 ACSA Ant Colony search Algorithm 2017 564,049.00 59 DP Dynamic Programming 2017 565,825.00 60 DPLR Dynamic Programming and Langrangian Relaxation 2017 564,049.00 61 TS-RP Tabu Search based Hybrid Algorithm 2017 564,551.00 62 MA Memetic Algorithm 2017 565,827.00 63 MRCGA Modified Real Coded Genetic Algorithm 2017 564,244.00 64 CSS Charge Search Algorithm 2017 563,938.00 65 PSO Particle Swarm Optimization 2017 563,938.00 66 ACS Ant Colony search 2017 563,938.00
  • 32. Graphical Summary of Results from Research Papers 574,153.00 562,587.00 574,153.00 562,000.00 564,000.00 566,000.00 568,000.00 570,000.00 572,000.00 574,000.00 576,000.00 0 10 20 30 40 50 60 70 BESTCOSTACHEIVED REFERENCE NUMBER OF TECHNIQUE USED TO SOLVE UC PROBLEM COST COMPARISON W.R.T DIFFERENT TECHNIQUES
  • 33. Some Binaries extracted from Research Papers
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41. Conclusion  In this Presentation, we have learned  Unit Commitment Problem Formulation  Objective Function  Constraints  Some Algorithms Applied to UCP  Results and Comparison from recent Research Papers
  • 42. References  Wu, Zhou, and Tommy WS Chow. "Binary neighbourhood field optimisation for unit commitment problems." IET Generation, Transmission & Distribution 7.3 (2013): 298-308.  Najafi, S. "A new heuristic algorithm for unit commitment problem." Energy Procedia 14 (2012): 2005-2011.  Sharma, Deepak, et al. "Multi-agent modeling for solving profit based unit commitment problem." Applied Soft Computing 13.8 (2013): 3751-3761.  Roy, Provas Kumar, and Ranadhir Sarkar. "Solution of unit commitment problem using quasi-oppositional teaching learning based algorithm." International Journal of Electrical Power & Energy Systems 60 (2014): 96-106.  Mingwei, L. I., et al. "Binary glowworm swarm optimization for unit commitment." Journal of Modern Power Systems and Clean Energy 2.4 (2014): 357-365.
  • 43. References  Arora, Vinay, and Saurabh Chanana. "Solution to unit commitment problem using Lagrangian relaxation and Mendel's GA method." Emerging Trends in Electrical Electronics & Sustainable Energy Systems (ICETEESES), International Conference on. IEEE, 2016.  Othman, M. N. C., et al. "Solving unit commitment problem using multi-agent evolutionary programming incorporating priority list." Arabian Journal for Science and Engineering 40.11 (2015): 3247-3261.  Elsayed, Abdullah M., Ahmed M. Maklad, and Sobhy M. Farrag. "A new priority list unit commitment method for large-scale power systems." Power Systems Conference (MEPCON), 2017 Nineteenth International Middle East. IEEE, 2017.  Arora, Vinay, and Saurabh Chanana. "Solution to unit commitment problem using Lagrangian relaxation and Mendel's GA method." Emerging Trends in Electrical Electronics & Sustainable Energy Systems (ICETEESES), International Conference on. IEEE, 2016.
  • 44. References  Wu, Yuan-Kang, Hong-Yi Chang, and Shih Ming Chang. "Analysis and Comparison for the Unit Commitment Problem in a Large-Scale Power System by Using Three Meta- Heuristic Algorithms." Energy Procedia 141 (2017): 423-427.  Ghadi, M. Jabbari, A. Baghramian, and M. Hosseini Imani. "An ICA based approach for solving profit based unit commitment problem market." Applied Soft Computing 38 (2016): 487-500.  Shahbazitabar, Maryam, and Hamdi Abdi. "A Solution to the Unit Commitment Problem Applying a Hierarchical Combination Algorithm." Journal of Energy Management and Technology 1.2 (2017): 12-19.  Saber, Navid Abdolhoseyni, Mahdi Salimi, and Davar Mirabbasi. "A priority list based approach for solving thermal unit commitment problem with novel hybrid genetic- imperialist competitive algorithm." Energy 117 (2016): 272-280.