SlideShare a Scribd company logo
Introduction to Electric
Generation Systems
Unit: 5
Economics of Power Generation and
Interconnected Power Station
Terms Commonly Used in System Operation
• connected load
• Firm power: Reserve Capacity of plant used for meeting emergency condition.
• Cold reserve: Reserve Capacity of plant in service but not in operation.
[200MW]
• Spinning reserve: Reserve Capacity of plant connected to the grid ready to
take load. [150MW]
• Hot reserve: Reserve Capacity of plant in operation but not in service. [50MW]
• Operating Reserve: In electricity networks, the operating reserve is the
generating capacity available to the system operator within a short interval of
time to meet demand in case a generator goes down or there is another
disruption to the supply.
Average Demand
• The average of loads occurring on the power station in a given
period (day or month or year) is known as average load or average
demand. The station capacity is so selected that it must meet the
maximum demand.
Maximum demand
• The maximum demand in kVA is nothing but a peak operating load
(maximum load) in kW of the consumer for the specific interval
divided by the operating power factor. The interval will be defined by
your electricity provider. Hence, the maximum demand formula can
be written as,
Maximum demand in kVA = Peak Load in kW / Power factor
Base Load and Peak Load defined
• Base load is the minimum level of
electricity demand required over a
period of 24 hours. It is needed to
provide power to components that
keep running at all times (also
referred as continuous load). Peak
load is the time of high demand.
These peaking demands are often
for only shorter durations.
Load Curve
• Load curve is the variation of load
with time on a Power Station. As
the load on a Power Station never
remain constant rather it varies
time to time, these variations in
load is plotted on half hourly or
hourly basis for the whole day. The
curve thus obtained is known as
Daily Load Curve.
Load Duration Curve
• Definition: The load duration curve is
defined as the curve between the
load and time in which the ordinates
representing the load, plotted in the
order of decreasing magnitude, i.e.,
with the greatest load at the left,
lesser loads towards the rights and
the lowest loads at the time extreme
right. The load duration curve is
shown in the figure below.
Integrated Duration Curve
• Integrated Load Duration Curve:
A plot of number of units
generated (kWh) for a given
demand (kW) is called
integration load duration curve
on Y-axis, load demand in kW or
MW is plotted while on X-axis
corresponding number of units
generated are obtained. Such a
curve corresponding to load
duration curve shown in Fig.
Determine the Average Load From the Load Curve
From load curve load distribution are
(0-6)hours -40MW for 6 hours
(6-10)hours -50MW for 4 hours
(10-12)hours -60MW for 2 hours
(12-16)hours -50MW for 4 hours
(16-20)hours -70MW for 4 hours
(20-24)hours -40MW for 4 hours
Total Load
=(40×6)+(50×4)+(60×2)+(50×4)+(70×4)+(40×4)
=1200MW
Total no of hours =24
Average Load =1200/24=50MW
Mass Curve
• A mass curve gives the total energy consumed by the load up to a
particular time in a day. This curve can be easily plotted from the
chronological load curve by summing up the energy consumed up to
different times starting at the zero time.
Demand factor
It is the ratio of maximum demand on the power station to its
connected load. The value of the demand factor is usually less than 1.
It is because maximum demand is always less than the connected load.
The knowledge of the demand factor is vital in determining the
capacity of the plant equipment.
Load Factor
• Load factor is defined as the ratio of the average load over a given
period to the maximum demand (peak load) occurring in that period.
Diversity Factor
• Diversity factor is defined as the ratio of the sum of the maximum
demands of the various part of a system to the coincident maximum
demand of the whole system.
Plant Capacity Factor
• The capacity factor is defined as the ratio of the total actual energy
produced or supply over a definite period, to the energy that would
have been produced if the plant (generating unit) had operated
continuously at the maximum rating.
Plant Use Factor
• It is defined as the ratio of energy produced in a given time to the
maximum possible energy that could have been produced during the
actual number of hours the plant was in operation.
Tariff
(i) Flat Rate Tariff:
This types of tariff differs from the former one in the sense that the different types of
consumers are charged at different rates i.e. the flat rate for light and fan loads is slightly
higher than that for power load. The rate for each category of consumers is arrived at by
taking into account its load factor and diversity factor.
(ii) Block Rate Tariff:
A block rate tariff, sometimes listed on energy bills as peak, demand or single rate, is a type
of tariff which charges customers a different price depending on how much electricity or
gas they have used.
(iii) Two Part Tariff:
The total energy charge to be made to the consumer is split into two components namely
fixed charge and running charge. This type of tariff is expressed as
Y = Rs a kW + b kWh
Where Rs a is the charge per kw of maximum demand assessed and Rs b is the charge per
kwh of energy consumed. This tariff is mostly applicable to medium industrial consumers.
18
Tariff
(iv)Three Part Tariff:
In this tariff total energy charge is split into three elements namely
fixed charge, semi-fixed charge and variable charge. Such a tariff is
expressed as
y = Rs a + bkW + c kWh.
Where a is a constant charge, b is unit charge in Rs per kw of maximum
demand in kw during billing period (in some case it is also charged in
Rs per kVA instead of Rs per kw) and c is the unit charge for energy in
Rs per kwh of energy consumed. This type of tariff is usually applicable
to bulk supplies.
Advantages of Interconnection
(I) EXCHANGE OF PEAK LOADS
(ii) USE OF OLDER PLANT
(iii) ENSURES ECONOMICAL OPERATION
(iv) INCREASES DIVERSITY FACTOR
(v) REDUCES PLANT RESERVE CAPACITY
(vi) INCREASES RELIABILITY OF SUPPLY
Load Flow Analysis
Load Flow Analysis
How do you choose a size and number of generating units?
• Important Points in the Selection of Units
1. The number and sizes of the units should be so selected that they
approximately fit the annual load curve of the station.
2. The units should be preferably of different capacities to meet the
load requirements.
How load curves help in the selection of size and
number of generating units?
The area under the daily load curve divided by the total number of hours
gives the average load on the station in the day. The ratio of the area under
the load curve to the total area of the rectangle in which it is contained
gives the load factor. The load curve helps in selecting the size and
number of generating
Electrical Grid
• Electrical grid or power grid is defined as the network which
interconnects the generation, transmission and distribution unit.
• Regional Grid – The Regional grid is formed by interconnecting the
different transmission system of a particular area through the
transmission line.
• National Grid – It is formed by interconnecting the different regional
grid.
What are the impact of grid failure?
• Blackout - Cascading failures - Control infrastructures of smart grids
affected
• Delay, blockage or corruption
• Downed wires - Economic and social disruptions
• Line faults
What causes grid failure?
However, the three most common causes are natural causes, human
error, and overload. Basically, any interruption between power
generation and the supply of electricity to homes can cause a power
outage. It can stem from inclement weather conditions, human error,
equipment failure, and even animal interference.
What is a grid fault?
• The grid is faulty when the peaks of voltage and frequency are
severe and exceeds the maximum margins mentioned in the
standards.
7 Major challenges of a power grid and their solutions
1. Growing amount of renewable energy sources. ...
2. Electricity transmission losses. ...
3. Frequent power outages. ...
4. Electro mobility. ...
5. Grid modernization. ...
6. Threat of cyber attacks. ...
7. Threat of terrorist attacks.
What is Brownout?
A brownout is a temporary, partial abrupt drop in voltage level followed by a
quick recovery. It’s the opposite of a power surge in which case some electrical
motors do not work and room lights are dimmer than normal. This indicates
that the demand for power was momentarily greater than the supply, resulting
in reduced voltage, or a condition what is called a brownout. It is caused by
high electricity demand that is close to or above the production capacity of a
power grid system. Simply put, a brownout, sometimes called a sag if it lasts
for less than a second, refers to partial electrical supply failures of the energy
grid system which in turn affects some areas while others remain unaffected.
During a brownout, lights will flicker or become dimmer and unprotected
systems will often turn themselves off or restart. It is a strategy used by the
power grid utilities to prevent the system from a blackout condition.
What is Blackout?
As compared to a brownout, a blackout is a total disruption of electrical services
in an area for a longer period of time. A blackout, also called a power failure or
power cut, is a total crash of the power grid as a result of severe weather
conditions or equipment failure at power plants. It is a large-scale service
disruption which can last from hours to days and days to weeks in case of a
serious emergency or a natural disaster like storm, earthquake, flood, cyclone,
and so on. Blackouts usually happen due to an imbalance between power
generation and power consumption meaning more electricity is consumed than
power companies can supply. When the demand is higher than the supply,
power utilities cut back on the power they release in order to prevent a blackout
from happening, which allow them to save power for the times when it is
needed the most. They do that in two ways – a pre-planned brownout and a
rolling blackout.
Unit-5.pptx

More Related Content

Similar to Unit-5.pptx

EDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxEDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptx
Dr. Rohit Babu
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docx
ArpitaBanik8
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
Dr. Rohit Singh Lather, Ph.D.
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
FelcherLayugan
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
Maharishi Tiwari
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Power System Operation
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
Niraj Solanki
 
Load on Power Station from power sytem engineering
Load on Power Station from power sytem engineeringLoad on Power Station from power sytem engineering
Load on Power Station from power sytem engineering
DIGESHSHAH9
 
Load shedding and load scheduling (ppt)
Load shedding and load scheduling (ppt)Load shedding and load scheduling (ppt)
Load shedding and load scheduling (ppt)
GehlotDarshan1
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
NBoss
 
12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf
NiladreePaul1
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
TheBlank5
 
Module1-Power-System-operation and-control
Module1-Power-System-operation and-controlModule1-Power-System-operation and-control
Module1-Power-System-operation and-control
kvvbapiraju2
 
Power Factor & Utility Rates
Power Factor & Utility RatesPower Factor & Utility Rates
Power Factor & Utility Rates
John Wolfram
 
Copy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdfCopy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdf
ShubhamVerma961456
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
BIJAY NAYAK
 
An Automatic Load Controller for Domestic Applications
An Automatic Load Controller for Domestic ApplicationsAn Automatic Load Controller for Domestic Applications
An Automatic Load Controller for Domestic Applications
ijtsrd
 
Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design
Marcep Inc.
 
PRAYAS.pptx
PRAYAS.pptxPRAYAS.pptx
PRAYAS.pptx
KhushbooMadaan8
 

Similar to Unit-5.pptx (20)

EDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxEDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptx
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docx
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3Principles of Power Systems V.K Mehta Complete Book - Chapter 3
Principles of Power Systems V.K Mehta Complete Book - Chapter 3
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
Class 16 load shedding
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
 
Load on Power Station from power sytem engineering
Load on Power Station from power sytem engineeringLoad on Power Station from power sytem engineering
Load on Power Station from power sytem engineering
 
Load shedding and load scheduling (ppt)
Load shedding and load scheduling (ppt)Load shedding and load scheduling (ppt)
Load shedding and load scheduling (ppt)
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
 
12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Module1-Power-System-operation and-control
Module1-Power-System-operation and-controlModule1-Power-System-operation and-control
Module1-Power-System-operation and-control
 
Power Factor & Utility Rates
Power Factor & Utility RatesPower Factor & Utility Rates
Power Factor & Utility Rates
 
Copy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdfCopy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdf
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
 
An Automatic Load Controller for Domestic Applications
An Automatic Load Controller for Domestic ApplicationsAn Automatic Load Controller for Domestic Applications
An Automatic Load Controller for Domestic Applications
 
Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design
 
PRAYAS.pptx
PRAYAS.pptxPRAYAS.pptx
PRAYAS.pptx
 

Recently uploaded

Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

Unit-5.pptx

  • 2. Economics of Power Generation and Interconnected Power Station
  • 3. Terms Commonly Used in System Operation • connected load • Firm power: Reserve Capacity of plant used for meeting emergency condition. • Cold reserve: Reserve Capacity of plant in service but not in operation. [200MW] • Spinning reserve: Reserve Capacity of plant connected to the grid ready to take load. [150MW] • Hot reserve: Reserve Capacity of plant in operation but not in service. [50MW] • Operating Reserve: In electricity networks, the operating reserve is the generating capacity available to the system operator within a short interval of time to meet demand in case a generator goes down or there is another disruption to the supply.
  • 4. Average Demand • The average of loads occurring on the power station in a given period (day or month or year) is known as average load or average demand. The station capacity is so selected that it must meet the maximum demand.
  • 5. Maximum demand • The maximum demand in kVA is nothing but a peak operating load (maximum load) in kW of the consumer for the specific interval divided by the operating power factor. The interval will be defined by your electricity provider. Hence, the maximum demand formula can be written as, Maximum demand in kVA = Peak Load in kW / Power factor
  • 6. Base Load and Peak Load defined • Base load is the minimum level of electricity demand required over a period of 24 hours. It is needed to provide power to components that keep running at all times (also referred as continuous load). Peak load is the time of high demand. These peaking demands are often for only shorter durations.
  • 7. Load Curve • Load curve is the variation of load with time on a Power Station. As the load on a Power Station never remain constant rather it varies time to time, these variations in load is plotted on half hourly or hourly basis for the whole day. The curve thus obtained is known as Daily Load Curve.
  • 8. Load Duration Curve • Definition: The load duration curve is defined as the curve between the load and time in which the ordinates representing the load, plotted in the order of decreasing magnitude, i.e., with the greatest load at the left, lesser loads towards the rights and the lowest loads at the time extreme right. The load duration curve is shown in the figure below.
  • 9. Integrated Duration Curve • Integrated Load Duration Curve: A plot of number of units generated (kWh) for a given demand (kW) is called integration load duration curve on Y-axis, load demand in kW or MW is plotted while on X-axis corresponding number of units generated are obtained. Such a curve corresponding to load duration curve shown in Fig.
  • 10. Determine the Average Load From the Load Curve From load curve load distribution are (0-6)hours -40MW for 6 hours (6-10)hours -50MW for 4 hours (10-12)hours -60MW for 2 hours (12-16)hours -50MW for 4 hours (16-20)hours -70MW for 4 hours (20-24)hours -40MW for 4 hours Total Load =(40×6)+(50×4)+(60×2)+(50×4)+(70×4)+(40×4) =1200MW Total no of hours =24 Average Load =1200/24=50MW
  • 11. Mass Curve • A mass curve gives the total energy consumed by the load up to a particular time in a day. This curve can be easily plotted from the chronological load curve by summing up the energy consumed up to different times starting at the zero time.
  • 12.
  • 13. Demand factor It is the ratio of maximum demand on the power station to its connected load. The value of the demand factor is usually less than 1. It is because maximum demand is always less than the connected load. The knowledge of the demand factor is vital in determining the capacity of the plant equipment.
  • 14. Load Factor • Load factor is defined as the ratio of the average load over a given period to the maximum demand (peak load) occurring in that period.
  • 15. Diversity Factor • Diversity factor is defined as the ratio of the sum of the maximum demands of the various part of a system to the coincident maximum demand of the whole system.
  • 16. Plant Capacity Factor • The capacity factor is defined as the ratio of the total actual energy produced or supply over a definite period, to the energy that would have been produced if the plant (generating unit) had operated continuously at the maximum rating.
  • 17. Plant Use Factor • It is defined as the ratio of energy produced in a given time to the maximum possible energy that could have been produced during the actual number of hours the plant was in operation.
  • 18. Tariff (i) Flat Rate Tariff: This types of tariff differs from the former one in the sense that the different types of consumers are charged at different rates i.e. the flat rate for light and fan loads is slightly higher than that for power load. The rate for each category of consumers is arrived at by taking into account its load factor and diversity factor. (ii) Block Rate Tariff: A block rate tariff, sometimes listed on energy bills as peak, demand or single rate, is a type of tariff which charges customers a different price depending on how much electricity or gas they have used. (iii) Two Part Tariff: The total energy charge to be made to the consumer is split into two components namely fixed charge and running charge. This type of tariff is expressed as Y = Rs a kW + b kWh Where Rs a is the charge per kw of maximum demand assessed and Rs b is the charge per kwh of energy consumed. This tariff is mostly applicable to medium industrial consumers. 18
  • 19. Tariff (iv)Three Part Tariff: In this tariff total energy charge is split into three elements namely fixed charge, semi-fixed charge and variable charge. Such a tariff is expressed as y = Rs a + bkW + c kWh. Where a is a constant charge, b is unit charge in Rs per kw of maximum demand in kw during billing period (in some case it is also charged in Rs per kVA instead of Rs per kw) and c is the unit charge for energy in Rs per kwh of energy consumed. This type of tariff is usually applicable to bulk supplies.
  • 20. Advantages of Interconnection (I) EXCHANGE OF PEAK LOADS (ii) USE OF OLDER PLANT (iii) ENSURES ECONOMICAL OPERATION (iv) INCREASES DIVERSITY FACTOR (v) REDUCES PLANT RESERVE CAPACITY (vi) INCREASES RELIABILITY OF SUPPLY
  • 23. How do you choose a size and number of generating units? • Important Points in the Selection of Units 1. The number and sizes of the units should be so selected that they approximately fit the annual load curve of the station. 2. The units should be preferably of different capacities to meet the load requirements.
  • 24. How load curves help in the selection of size and number of generating units? The area under the daily load curve divided by the total number of hours gives the average load on the station in the day. The ratio of the area under the load curve to the total area of the rectangle in which it is contained gives the load factor. The load curve helps in selecting the size and number of generating
  • 25. Electrical Grid • Electrical grid or power grid is defined as the network which interconnects the generation, transmission and distribution unit. • Regional Grid – The Regional grid is formed by interconnecting the different transmission system of a particular area through the transmission line. • National Grid – It is formed by interconnecting the different regional grid.
  • 26. What are the impact of grid failure? • Blackout - Cascading failures - Control infrastructures of smart grids affected • Delay, blockage or corruption • Downed wires - Economic and social disruptions • Line faults
  • 27. What causes grid failure? However, the three most common causes are natural causes, human error, and overload. Basically, any interruption between power generation and the supply of electricity to homes can cause a power outage. It can stem from inclement weather conditions, human error, equipment failure, and even animal interference.
  • 28. What is a grid fault? • The grid is faulty when the peaks of voltage and frequency are severe and exceeds the maximum margins mentioned in the standards.
  • 29. 7 Major challenges of a power grid and their solutions 1. Growing amount of renewable energy sources. ... 2. Electricity transmission losses. ... 3. Frequent power outages. ... 4. Electro mobility. ... 5. Grid modernization. ... 6. Threat of cyber attacks. ... 7. Threat of terrorist attacks.
  • 30. What is Brownout? A brownout is a temporary, partial abrupt drop in voltage level followed by a quick recovery. It’s the opposite of a power surge in which case some electrical motors do not work and room lights are dimmer than normal. This indicates that the demand for power was momentarily greater than the supply, resulting in reduced voltage, or a condition what is called a brownout. It is caused by high electricity demand that is close to or above the production capacity of a power grid system. Simply put, a brownout, sometimes called a sag if it lasts for less than a second, refers to partial electrical supply failures of the energy grid system which in turn affects some areas while others remain unaffected. During a brownout, lights will flicker or become dimmer and unprotected systems will often turn themselves off or restart. It is a strategy used by the power grid utilities to prevent the system from a blackout condition.
  • 31. What is Blackout? As compared to a brownout, a blackout is a total disruption of electrical services in an area for a longer period of time. A blackout, also called a power failure or power cut, is a total crash of the power grid as a result of severe weather conditions or equipment failure at power plants. It is a large-scale service disruption which can last from hours to days and days to weeks in case of a serious emergency or a natural disaster like storm, earthquake, flood, cyclone, and so on. Blackouts usually happen due to an imbalance between power generation and power consumption meaning more electricity is consumed than power companies can supply. When the demand is higher than the supply, power utilities cut back on the power they release in order to prevent a blackout from happening, which allow them to save power for the times when it is needed the most. They do that in two ways – a pre-planned brownout and a rolling blackout.