SlideShare a Scribd company logo
Project: Financial feasibility
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 1
Tools for financial feasibility analysis
• Payback period analysis
At what point of time we are making more money than we are spending ?
• Benefit cost ratio analysis
For each rupee how much will be generated?
• Net Present value analysis
How much is future revenue (or expenditure) flow worth in today ?
• Internal rate of return (IRR) analysis
rate of return on our investment for a fixed period, during which time we
are spending money and making money
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 2
Payback Analysis
• A viable project is one that is able to pay back the original investment as early as
possible.
• The payback period is achieved at that point in time when cumulative cash inflows
more than offset cumulative outflows,
or
When we are finally making more money in total than we have spent in total.
• Payback period indicates when, our investment is out of the woods.
• Projects with long payback are less attractive than those with short payback.
- they tie up capital longer, not enabling its use for other productive purposes.
- they are generally riskier than those with short payback periods
as over a long stretch of time, many things can go wrong.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 3
Payback Analysis
• As per payback period, project A is more attractive
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 4
Project A
Year Outflows
Cumulative
out flows
Inflows
Cumulative
In flows
1 200 200 100 100
2 200 400 300 400
3 100 500 300 700
4 500 300 1000
5 500 300 1300
Total 500 1300
Project B
Year Outflows
Cumulative
out flows
Inflows
Cumulative
In flows
1 200 200 100 100
2 200 400 100 200
3 100 500 200 400
4 500 400 800
5 500 500 1300
Total 500 1300
Net Present Value (NPV) Analysis
or Discounted cash flows analysis
• the late 1970s, Americans experienced inflation rates in the 17% per annum range
• Inflation provides one example of what is called the time value of money i.e. A
rupee today has a different value than a rupee one year from now.
• There is more to time value of money than the force of inflation.
• Consider if no inflation, i.e a rupee today has the same purchasing power as a
rupee one year later.
If you have an opportunity to lend Rs 1,000/- to a business at a 10% interest yearly
then at year end you will receive a payment of Rs 1,100/- at the year end when the
loan is paid off.
Your initial investment of Rs 1,000/- has grown by 10% over time.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 5
Net Present Value (NPV) Analysis
or Discounted cash flows analysis
• FV =PV (1+r)n
where r is interest rate fraction and n is number of completed time slots
Inflation provides one example of what is called the time value of money i.e. A rupee
today has a different value than a rupee one year from now.
• There is more to time value of money than the force of inflation.
• Consider if no inflation, i.e a rupee today has the same purchasing power as a
rupee one year later.
If you have an opportunity to lend Rs 1,000/- to a business at a 10% interest yearly
then at year end you will receive a payment of Rs 1,100/- at the year end when the
loan is paid off.
Your initial investment of Rs 1,000/- has grown by 10% over time.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 6
Net Present Value (NPV) Analysis
• Project A is more attractive
than Project B, because its
true, discounted profit (Rs
533.18) is greater than the
discounted profit of Project B
(Rs 485.24).
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 7
Project A
Year Outflows Inflows
Discounting
factor @ 10%
PV of
out flows
PV of
In flows
PV of
Net flows
1 200 100 0.9091 181.82 90.91 -90.91
2 200 300 0.8264 165.28 247.92 82.64
3 100 300 0.7513 75.13 225.39 150.26
4 300 0.683 0 204.9 204.9
5 300 0.6209 0 186.27 186.27
Total 500 1300 422.23 955.39 533.16
Project B
Year OutflowsInflows
Discounting
factor @ 10%
PV of
out flows
PV of
In flows
PV of
Net flows
1 200 100 0.9091 181.82 90.91 -90.91
2 200 100 0.8264 165.28 82.64 -82.64
3 100 200 0.7513 75.13 150.26 75.13
4 400 0.683 0 273.2 273.2
5 500 0.6209 0 310.45 310.45
Total 500 1300 422.23 907.46 485.23
Net Present Value (NPV) Analysis
• Both projects have
same NPV
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 8
Project A
Year Outflows Inflows
Discounting
factor @ 10%
PV of
out flows
PV of
In flows
PV of
Net flows
1 200 0.9091 181.82 0 -181.82
2 200 0.8264 165.28 0 -165.28
3 100 100 0.7513 75.13 75.13 0
4 200 0.683 0 136.6 136.6
5 500 0.6209 0 310.45 310.45
Total 500 800 422.23 522.18 99.95
Project B
Year OutflowsInflows
Discounting
factor @ 10%
PV of
out flows
PV of
In flows
PV of
Net flows
1 50 0.9091 45.455 0 -45.46
2 200 0.8264 165.28 0 -165.28
3 200 100 0.7513 150.26 75.13 -75.13
4 89.65 200 0.683 61.23095 136.6 75.37
5 500 0.6209 0 310.45 310.45
Total 539.65 800 422.226 522.18 99.95
Internal rate of return(IRR) Analysis
• Both projects have same NPV
• By Excel function IRR of project
A is 14 % and Project B is 12 %
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 9
Project A
Year Outflows Inflows
Discounting
factor @ 10%
PV of
out flows
PV of
In flows
PV of
Net flows
1 -200 0.9091 181.82 0 -181.82
2 -200 0.8264 165.28 0 -165.28
3 -100 100 0.7513 75.13 75.13 0
4 200 0.683 0 136.6 136.6
5 500 0.6209 0 310.45 310.45
Total -500 800 422.23 522.18 99.95
Project B
Year Outflows Inflows
Discounting
factor @ 10%
PV of
out flows
PV of
In flows
PV of
Net flows
1 -50 0.9091 45.455 0 -45.46
2 -200 0.8264 165.28 0 -165.28
3 -200 100 0.7513 150.26 75.13 -75.13
4 -89.65 200 0.683 61.23095 136.6 75.37
5 500 0.6209 0 310.45 310.45
Total -539.65 800 422.226 522.18 99.95
Internal rate of return(IRR) Analysis
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 10
Project A discounting @ 15 %
Year Outflows Inflows
Discounting
factor @ 15%
PV of
out flows
PV of
In flows
PV of
Net flows
1 200 0.8696 -173.92 0 -173.92
2 200 0.7561 -151.22 0 -151.22
3 100 100 0.6575 -65.75 65.75 0
4 200 0.5718 0 114.36 114.36
5 500 0.4972 0 248.6 248.6
Total 500 800 -390.89 428.71 37.82
Project B discounting @ 15 %
Year Outflows Inflows
Discounting
factor @ 15%
PV of
out flows
PV of
In flows
PV of
Net flows
1 50 0.8696 -43.48 0 -43.48
2 200 0.7561 -151.22 0 -151.22
3 200 100 0.6575 -131.5 65.75 -65.75
4 89.65 200 0.5718 -51.2619 114.36 63.1
5 500 0.4972 0 248.6 248.6
Total 539.65 800 -377.462 428.71 51.25
Project A discounting @ 20 %
Year Outflows Inflows
Discounting
factor @ 20%
PV of
out flows
PV of
In flows
PV of
Net flows
1 200 0.8333 -166.66 0 -166.66
2 200 0.6944 -138.88 0 -138.88
3 100 100 0.5787 -57.87 57.87 0
4 200 0.4823 0 96.46 96.46
5 500 0.4019 0 200.95 200.95
Total 500 800 -363.41 355.28 -8.13
Project B discounting @ 20 %
Year Outflows Inflows
Discounting
factor @ 20%
PV of
out flows
PV of
In flows
PV of
Net flows
1 50 0.8333 -41.665 0 -41.67
2 200 0.6944 -138.88 0 -138.88
3 200 100 0.5787 -115.74 57.87 -57.87
4 89.65 200 0.4823 -43.2382 96.46 53.22
5 500 0.4019 0 200.95 200.95
Total 539.65 800 -339.523 355.28 15.76
Internal rate of return(IRR) Analysis
• IRR of Project A is 19% and of
Project B is 23 %
• a project's IRR is higher than the
prevailing interest rate, then it
may be smart to invest in it.
• IRR model assumes that money
employed is utilized all the time
and is not remain unutilized at all.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 11
Project A
Year Outflows Inflows
Discounting
factor @ 19%
PV of
out flows
PV of
In flows
PV of
Net flows
1 -200 0.8403 -168.06 0 -168.06
2 -200 0.7062 -141.24 0 -141.24
3 -100 100 0.5934 -59.34 59.34 0
4 200 0.4987 0 99.74 99.74
5 500 0.419 0 209.5 209.5
Total -500 800 -368.64 368.58 -0.06
Project B
Year Outflows Inflows
Discounting
factor @ 10%
PV of
out flows
PV of
In flows
PV of
Net flows
1 -50 0.813 -40.65 0 -40.65
2 -200 0.661 -132.2 0 -132.2
3 -200 100 0.5374 -107.48 53.74 -53.74
4 -89.65 200 0.4369 -39.1681 87.38 48.21
5 500 0.3552 0 177.6 177.6
Total -539.65 800 -319.498 318.72 -0.78
Benefit to Cost ratio
The benefit-cost ratio is nothing more than a measure of benefit divided by a measure of cost.
Measure of benefit can be anything: financial profit/ cost savings, happiness, error reduction,
throughput time, and so on.
Practically, the measure of benefit is revenue - or in non- revenue generating situations, cost
savings.
Benefit-cost ratio (B/C) > 1.0 Revenue is greater than expenditures. i.e. investment is
profitable.
Benefit-cost ratio (B/C) = 1.0. Revenue and expenditures offset each other.
Consequently, you are facing a breakeven situation.
Benefit-cost ratio (BE) < 1.0. In this case, expenditures outstrip revenue. You are losing money.
Example: BIC = Rs 40,000/Rs 50,000 = 0.8 Interpretation: For each dollar you are spending on
this project, you are only gaining 80 cents of revenue. Thus you are losing money.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 12
Benefit to Cost ratio
Discounted B/C for project A
= 428.71/390.89 =1.09
Discounted B/C for project B
= 428.71/377.46 =1.14
B/C for project A = 800/500 =1.6
B/C for project B = 800/539.65 =1.48
Benefit-cost ratio analysis using discounted
cash flow data, the computing what in
finance is called the profitability index.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 13
Project A
Year Outflows Inflows
Discounting
factor @ 15%
PV of
out flows
PV of
In flows
PV of
Net flows
1 200 0.8696 173.92 0 -173.92
2 200 0.7561 151.22 0 -151.22
3 100 100 0.6575 65.75 65.75 0
4 200 0.5718 0 114.36 114.36
5 500 0.4972 0 248.6 248.6
Total 500 800 390.89 428.71 37.82
Project B
Year Outflows Inflows
Discounting
factor @ 15%
PV of
out flows
PV of
In flows
PV of
Net flows
1 50 0.8696 43.48 0 -43.48
2 200 0.7561 151.22 0 -151.22
3 200 100 0.6575 131.5 65.75 -65.75
4 89.65 200 0.5718 51.26 114.36 63.1
5 500 0.4972 0 248.6 248.6
Total 539.65 800 377.46 428.71 51.25
Benefit to Cost ratio for non-revenue generating
project
Many projects that are carried out are not revenue generating
Ex. . a typical information technology (IT) project in an organization
This can improve revenue performance indirectly, as the organization reduces
operating costs. But it is not directly tied to generating revenue
Benefit-cost ratio analysis for this involves cost saving instead of revenue generation.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 14
B/C ratio : pitfalls
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 15
There are a number of pitfalls associated with benefit-cost analyses that are
important to know.
B/C ratios do not provide information on the size of the numbers being reviewed.
EX: Project A BIC = 3.1 Project B BIC = 2.7 Project A's is
better
Project A BIC = 3100/1000 = 3.1 Project B BIC = 2,700,000/1,000,000 = 2.7
• Since B/C is a ratio, sense of the size of the numbers vanishes. For most
organizations, Project B is more attractive than A, as B has substantial revenue.
• For valid comparisons among the B/C ratios of different projects, One must know
the actual size of the numbers that are used to compute the ratios.
B/C ratio : pitfalls
1. B/C ratios do not provide information on when payback occurs. Consider the following
two ratios: Project A B/C = 3.1 Project B B/C = 2.7
Again, Project A appears to be more attractive than Project B.
If Project A realizes a B/C of 3.1 after five years, it is less attractive than Project B, if
B realizes its B/C ratio in two years.
2. The easiest quantitative data to acquire is basic business data derived from estimated
budgets and, possibly, on anticipated revenues. Hard-to-measure factors are often ignored
when computing the ratios. For example, the main benefit of a project may be what is
called a second-order benefit - e.g., this project, while not profitable in itself, will provide
the groundwork for major revenue streams generated on future projects.
Another benefit might be improved public perceptions of the company's activities.
None of these pitfalls is fatal. With B/C, analysts should be aware of their existence and
should strive to deal with them so that the analyses are valid.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 16
Return on Investment (ROI)
The ROI is nothing more than a measure of NPV expressed as percentage of present
value of cost.
ROI = (NPV/PV of cost)x 100= (discounted B/C -1)x 100
ROI> 0 Revenue is greater than expenditures. i.e. investment is profitable.
ROI= 0. Revenue and expenditures offset each other.
Consequently, you are facing a breakeven situation.
ROI< 0. In this case, expenditures outstrip revenue. You are losing money.
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 17
Thank You
19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 18
Contact
Email: naimkidwai@gmail.com
https://nrkidwai.wordpress.com/

More Related Content

What's hot

INTRODUCTION TO FINANCIAL MANAGEMENT
INTRODUCTION TO FINANCIAL MANAGEMENTINTRODUCTION TO FINANCIAL MANAGEMENT
INTRODUCTION TO FINANCIAL MANAGEMENT
Mohammed Jasir PV
 
Project appraisal and its techniques
Project appraisal and its techniquesProject appraisal and its techniques
Project appraisal and its techniques
AksharaMahesh
 
Financial Planning and Forecasting
Financial Planning and ForecastingFinancial Planning and Forecasting
Financial Planning and Forecasting
Maged Elsakka
 
project appraisal
project appraisal project appraisal
project appraisal
Dronak Sahu
 
Bonds
BondsBonds
Bonds
Aaryendr
 
Risk and Return
Risk and ReturnRisk and Return
Risk and Return
saadiakh
 
Bond valuation
Bond valuationBond valuation
Bond valuation
shekhar sharma
 
Functions of finance
Functions of financeFunctions of finance
Functions of finance
Rohit Kumar
 
Estimation of Cash Flow
Estimation of Cash FlowEstimation of Cash Flow
Estimation of Cash Flow
Venkatakrishnan Narayanan
 
Npv and IRR, a link to Project Management
Npv and IRR, a link to Project ManagementNpv and IRR, a link to Project Management
Npv and IRR, a link to Project Management
Ujjwal Joshi
 
Time value of money
Time value of moneyTime value of money
Time value of money
Jubayer Alam Shoikat
 
Capital Structure and Leverage
Capital Structure and LeverageCapital Structure and Leverage
Capital Structure and Leverage
Megha Anilkumar
 
Financial Forecasting & Planning
Financial Forecasting & PlanningFinancial Forecasting & Planning
Financial Forecasting & Planning
tintin_leo
 
Cost of capital
Cost of capital   Cost of capital
Cost of capital
BELLARMINDIANA
 
Financial management complete note
Financial management complete noteFinancial management complete note
Financial management complete note
kabul university
 
Investment Appraisal
Investment AppraisalInvestment Appraisal
Investment Appraisal
Governance Learning Network®
 
Social Cost Benefit Analysis
Social Cost Benefit Analysis Social Cost Benefit Analysis
Social Cost Benefit Analysis
Azam FA
 
Cash and marketable securities management
Cash and marketable securities managementCash and marketable securities management
Cash and marketable securities management
Nikhil Soares
 
Investment Settings
Investment SettingsInvestment Settings
Investment Settings
Sunanda Sarker
 
Financial Reporting
Financial ReportingFinancial Reporting
Financial Reporting
Qasim Raza
 

What's hot (20)

INTRODUCTION TO FINANCIAL MANAGEMENT
INTRODUCTION TO FINANCIAL MANAGEMENTINTRODUCTION TO FINANCIAL MANAGEMENT
INTRODUCTION TO FINANCIAL MANAGEMENT
 
Project appraisal and its techniques
Project appraisal and its techniquesProject appraisal and its techniques
Project appraisal and its techniques
 
Financial Planning and Forecasting
Financial Planning and ForecastingFinancial Planning and Forecasting
Financial Planning and Forecasting
 
project appraisal
project appraisal project appraisal
project appraisal
 
Bonds
BondsBonds
Bonds
 
Risk and Return
Risk and ReturnRisk and Return
Risk and Return
 
Bond valuation
Bond valuationBond valuation
Bond valuation
 
Functions of finance
Functions of financeFunctions of finance
Functions of finance
 
Estimation of Cash Flow
Estimation of Cash FlowEstimation of Cash Flow
Estimation of Cash Flow
 
Npv and IRR, a link to Project Management
Npv and IRR, a link to Project ManagementNpv and IRR, a link to Project Management
Npv and IRR, a link to Project Management
 
Time value of money
Time value of moneyTime value of money
Time value of money
 
Capital Structure and Leverage
Capital Structure and LeverageCapital Structure and Leverage
Capital Structure and Leverage
 
Financial Forecasting & Planning
Financial Forecasting & PlanningFinancial Forecasting & Planning
Financial Forecasting & Planning
 
Cost of capital
Cost of capital   Cost of capital
Cost of capital
 
Financial management complete note
Financial management complete noteFinancial management complete note
Financial management complete note
 
Investment Appraisal
Investment AppraisalInvestment Appraisal
Investment Appraisal
 
Social Cost Benefit Analysis
Social Cost Benefit Analysis Social Cost Benefit Analysis
Social Cost Benefit Analysis
 
Cash and marketable securities management
Cash and marketable securities managementCash and marketable securities management
Cash and marketable securities management
 
Investment Settings
Investment SettingsInvestment Settings
Investment Settings
 
Financial Reporting
Financial ReportingFinancial Reporting
Financial Reporting
 

Similar to Project financial feasibility

Capital budgeting decisions:
Capital budgeting decisions:Capital budgeting decisions:
Capital budgeting decisions:
Dr Naim R Kidwai
 
3 capital budgeting
3 capital budgeting3 capital budgeting
3 capital budgeting
Dr.R. SELVAM
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
bindu sreevatsava
 
MBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptxMBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptx
kwame Oduro Amoako (PhD)
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
Ameen San
 
Cfa corporate finance chapter2
Cfa corporate finance chapter2Cfa corporate finance chapter2
Cfa corporate finance chapter2
gisilowati
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
premarhea
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04
rajeevgupta
 
LECTURE 13.pdf
LECTURE 13.pdfLECTURE 13.pdf
LECTURE 13.pdf
Akmuhammet Mammetjanov
 
Priyankabba
PriyankabbaPriyankabba
Priyankabba
PriyankaSachdeva35
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
yashpal01
 
Financial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation SlidesFinancial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation Slides
SlideTeam
 
Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...
Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...
Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...
SlideTeam
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
DR.MAHESH KUMAR K.R.
 
Ch12 cost
Ch12 costCh12 cost
Ch12 cost
Mahii
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)
tutor2u
 
Cb-1.pptx
Cb-1.pptxCb-1.pptx
Cb-1.pptx
ssuser1ecf25
 
Introducing financial analysis
Introducing financial analysisIntroducing financial analysis
Introducing financial analysis
venkataramanan Thiru
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
AKSHAYA0000
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
Hisham Haridy MBA, PMP®, RMP®, SP®
 

Similar to Project financial feasibility (20)

Capital budgeting decisions:
Capital budgeting decisions:Capital budgeting decisions:
Capital budgeting decisions:
 
3 capital budgeting
3 capital budgeting3 capital budgeting
3 capital budgeting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
MBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptxMBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptx
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Cfa corporate finance chapter2
Cfa corporate finance chapter2Cfa corporate finance chapter2
Cfa corporate finance chapter2
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04
 
LECTURE 13.pdf
LECTURE 13.pdfLECTURE 13.pdf
LECTURE 13.pdf
 
Priyankabba
PriyankabbaPriyankabba
Priyankabba
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Financial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation SlidesFinancial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation Slides
 
Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...
Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...
Fixed Capital Evaluation To Improve Business Growth Powerpoint Presentation S...
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Ch12 cost
Ch12 costCh12 cost
Ch12 cost
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)
 
Cb-1.pptx
Cb-1.pptxCb-1.pptx
Cb-1.pptx
 
Introducing financial analysis
Introducing financial analysisIntroducing financial analysis
Introducing financial analysis
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
 

More from Dr Naim R Kidwai

Asynchronous sequential circuit analysis
Asynchronous sequential circuit analysisAsynchronous sequential circuit analysis
Asynchronous sequential circuit analysis
Dr Naim R Kidwai
 
synchronous Sequential circuit counters and registers
synchronous Sequential circuit counters and registerssynchronous Sequential circuit counters and registers
synchronous Sequential circuit counters and registers
Dr Naim R Kidwai
 
Clocked Sequential circuit analysis and design
Clocked Sequential circuit analysis and designClocked Sequential circuit analysis and design
Clocked Sequential circuit analysis and design
Dr Naim R Kidwai
 
Sequential circuit-flip flops
Sequential circuit-flip flopsSequential circuit-flip flops
Sequential circuit-flip flops
Dr Naim R Kidwai
 
Sampling Theorem
Sampling TheoremSampling Theorem
Sampling Theorem
Dr Naim R Kidwai
 
Moodle introduction
Moodle introductionMoodle introduction
Moodle introduction
Dr Naim R Kidwai
 
financing infrastructure projects
financing infrastructure projectsfinancing infrastructure projects
financing infrastructure projects
Dr Naim R Kidwai
 
financing projects
financing projectsfinancing projects
financing projects
Dr Naim R Kidwai
 
multiple projects and constraints
multiple projects and constraintsmultiple projects and constraints
multiple projects and constraints
Dr Naim R Kidwai
 
project risk analysis
project risk analysisproject risk analysis
project risk analysis
Dr Naim R Kidwai
 
Nec 602 unit ii Random Variables and Random process
Nec 602 unit ii Random Variables and Random processNec 602 unit ii Random Variables and Random process
Nec 602 unit ii Random Variables and Random process
Dr Naim R Kidwai
 
spread spectrum communication
spread spectrum communicationspread spectrum communication
spread spectrum communication
Dr Naim R Kidwai
 
Error Control coding
Error Control codingError Control coding
Error Control coding
Dr Naim R Kidwai
 
information theory
information theoryinformation theory
information theory
Dr Naim R Kidwai
 
Rec101 unit ii (part 2) bjt biasing and re model
Rec101 unit ii (part 2) bjt biasing and re modelRec101 unit ii (part 2) bjt biasing and re model
Rec101 unit ii (part 2) bjt biasing and re model
Dr Naim R Kidwai
 
Rec101 unit ii (part 3) field effect transistor
Rec101 unit ii (part 3) field effect transistorRec101 unit ii (part 3) field effect transistor
Rec101 unit ii (part 3) field effect transistor
Dr Naim R Kidwai
 
Rec101 unit ii (part 1) bjt characteristics
Rec101 unit ii (part 1) bjt characteristicsRec101 unit ii (part 1) bjt characteristics
Rec101 unit ii (part 1) bjt characteristics
Dr Naim R Kidwai
 
Rec101 unit v communication engg
Rec101 unit v communication enggRec101 unit v communication engg
Rec101 unit v communication engg
Dr Naim R Kidwai
 
Rec101 unit iv emi
Rec101 unit iv emiRec101 unit iv emi
Rec101 unit iv emi
Dr Naim R Kidwai
 
Rec101 unit iii operational amplifier
Rec101 unit iii operational amplifierRec101 unit iii operational amplifier
Rec101 unit iii operational amplifier
Dr Naim R Kidwai
 

More from Dr Naim R Kidwai (20)

Asynchronous sequential circuit analysis
Asynchronous sequential circuit analysisAsynchronous sequential circuit analysis
Asynchronous sequential circuit analysis
 
synchronous Sequential circuit counters and registers
synchronous Sequential circuit counters and registerssynchronous Sequential circuit counters and registers
synchronous Sequential circuit counters and registers
 
Clocked Sequential circuit analysis and design
Clocked Sequential circuit analysis and designClocked Sequential circuit analysis and design
Clocked Sequential circuit analysis and design
 
Sequential circuit-flip flops
Sequential circuit-flip flopsSequential circuit-flip flops
Sequential circuit-flip flops
 
Sampling Theorem
Sampling TheoremSampling Theorem
Sampling Theorem
 
Moodle introduction
Moodle introductionMoodle introduction
Moodle introduction
 
financing infrastructure projects
financing infrastructure projectsfinancing infrastructure projects
financing infrastructure projects
 
financing projects
financing projectsfinancing projects
financing projects
 
multiple projects and constraints
multiple projects and constraintsmultiple projects and constraints
multiple projects and constraints
 
project risk analysis
project risk analysisproject risk analysis
project risk analysis
 
Nec 602 unit ii Random Variables and Random process
Nec 602 unit ii Random Variables and Random processNec 602 unit ii Random Variables and Random process
Nec 602 unit ii Random Variables and Random process
 
spread spectrum communication
spread spectrum communicationspread spectrum communication
spread spectrum communication
 
Error Control coding
Error Control codingError Control coding
Error Control coding
 
information theory
information theoryinformation theory
information theory
 
Rec101 unit ii (part 2) bjt biasing and re model
Rec101 unit ii (part 2) bjt biasing and re modelRec101 unit ii (part 2) bjt biasing and re model
Rec101 unit ii (part 2) bjt biasing and re model
 
Rec101 unit ii (part 3) field effect transistor
Rec101 unit ii (part 3) field effect transistorRec101 unit ii (part 3) field effect transistor
Rec101 unit ii (part 3) field effect transistor
 
Rec101 unit ii (part 1) bjt characteristics
Rec101 unit ii (part 1) bjt characteristicsRec101 unit ii (part 1) bjt characteristics
Rec101 unit ii (part 1) bjt characteristics
 
Rec101 unit v communication engg
Rec101 unit v communication enggRec101 unit v communication engg
Rec101 unit v communication engg
 
Rec101 unit iv emi
Rec101 unit iv emiRec101 unit iv emi
Rec101 unit iv emi
 
Rec101 unit iii operational amplifier
Rec101 unit iii operational amplifierRec101 unit iii operational amplifier
Rec101 unit iii operational amplifier
 

Recently uploaded

falcon-invoice-discounting-a-strategic-approach-to-optimize-investments
falcon-invoice-discounting-a-strategic-approach-to-optimize-investmentsfalcon-invoice-discounting-a-strategic-approach-to-optimize-investments
falcon-invoice-discounting-a-strategic-approach-to-optimize-investments
Falcon Invoice Discounting
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designs
egoetzinger
 
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFiTdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
nimaruinazawa258
 
Role of Information Technology in Revenue - Prof Oyedokun.pptx
Role of Information Technology in Revenue  - Prof Oyedokun.pptxRole of Information Technology in Revenue  - Prof Oyedokun.pptx
Role of Information Technology in Revenue - Prof Oyedokun.pptx
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
FCCS Basic Accounts Outline and Hierarchy.pptx
FCCS Basic Accounts Outline and Hierarchy.pptxFCCS Basic Accounts Outline and Hierarchy.pptx
FCCS Basic Accounts Outline and Hierarchy.pptx
nalamynandan
 
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
5spllj1l
 
1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf
Neal Brewster
 
2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf
Neal Brewster
 
Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...
Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...
Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...
AntoniaOwensDetwiler
 
This assessment plan proposal is to outline a structured approach to evaluati...
This assessment plan proposal is to outline a structured approach to evaluati...This assessment plan proposal is to outline a structured approach to evaluati...
This assessment plan proposal is to outline a structured approach to evaluati...
lamluanvan.net Viết thuê luận văn
 
Financial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptxFinancial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptx
Writo-Finance
 
1.2 Business Ideas Business Ideas Busine
1.2 Business Ideas Business Ideas Busine1.2 Business Ideas Business Ideas Busine
1.2 Business Ideas Business Ideas Busine
Lawrence101
 
The Rise of Generative AI in Finance: Reshaping the Industry with Synthetic Data
The Rise of Generative AI in Finance: Reshaping the Industry with Synthetic DataThe Rise of Generative AI in Finance: Reshaping the Industry with Synthetic Data
The Rise of Generative AI in Finance: Reshaping the Industry with Synthetic Data
Champak Jhagmag
 
Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...
Labour Market Information Council | Conseil de l’information sur le marché du travail
 
Who Is Abhay Bhutada, MD of Poonawalla Fincorp
Who Is Abhay Bhutada, MD of Poonawalla FincorpWho Is Abhay Bhutada, MD of Poonawalla Fincorp
Who Is Abhay Bhutada, MD of Poonawalla Fincorp
beulahfernandes8
 
Tumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdf
Tumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdfTumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdf
Tumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdf
Henry Tapper
 
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptxSWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样
1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样
1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样
qntjwn68
 
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptxOAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
hiddenlevers
 

Recently uploaded (20)

falcon-invoice-discounting-a-strategic-approach-to-optimize-investments
falcon-invoice-discounting-a-strategic-approach-to-optimize-investmentsfalcon-invoice-discounting-a-strategic-approach-to-optimize-investments
falcon-invoice-discounting-a-strategic-approach-to-optimize-investments
 
Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designs
 
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
Tax System, Behaviour, Justice, and Voluntary Compliance Culture in Nigeria -...
 
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFiTdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
Tdasx: Unveiling the Trillion-Dollar Potential of Bitcoin DeFi
 
Role of Information Technology in Revenue - Prof Oyedokun.pptx
Role of Information Technology in Revenue  - Prof Oyedokun.pptxRole of Information Technology in Revenue  - Prof Oyedokun.pptx
Role of Information Technology in Revenue - Prof Oyedokun.pptx
 
FCCS Basic Accounts Outline and Hierarchy.pptx
FCCS Basic Accounts Outline and Hierarchy.pptxFCCS Basic Accounts Outline and Hierarchy.pptx
FCCS Basic Accounts Outline and Hierarchy.pptx
 
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
在线办理(GU毕业证书)美国贡萨加大学毕业证学历证书一模一样
 
1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf1. Elemental Economics - Introduction to mining.pdf
1. Elemental Economics - Introduction to mining.pdf
 
2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf2. Elemental Economics - Mineral demand.pdf
2. Elemental Economics - Mineral demand.pdf
 
Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...
Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...
Independent Study - College of Wooster Research (2023-2024) FDI, Culture, Glo...
 
This assessment plan proposal is to outline a structured approach to evaluati...
This assessment plan proposal is to outline a structured approach to evaluati...This assessment plan proposal is to outline a structured approach to evaluati...
This assessment plan proposal is to outline a structured approach to evaluati...
 
Financial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptxFinancial Assets: Debit vs Equity Securities.pptx
Financial Assets: Debit vs Equity Securities.pptx
 
1.2 Business Ideas Business Ideas Busine
1.2 Business Ideas Business Ideas Busine1.2 Business Ideas Business Ideas Busine
1.2 Business Ideas Business Ideas Busine
 
The Rise of Generative AI in Finance: Reshaping the Industry with Synthetic Data
The Rise of Generative AI in Finance: Reshaping the Industry with Synthetic DataThe Rise of Generative AI in Finance: Reshaping the Industry with Synthetic Data
The Rise of Generative AI in Finance: Reshaping the Industry with Synthetic Data
 
Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...Does teamwork really matter? Looking beyond the job posting to understand lab...
Does teamwork really matter? Looking beyond the job posting to understand lab...
 
Who Is Abhay Bhutada, MD of Poonawalla Fincorp
Who Is Abhay Bhutada, MD of Poonawalla FincorpWho Is Abhay Bhutada, MD of Poonawalla Fincorp
Who Is Abhay Bhutada, MD of Poonawalla Fincorp
 
Tumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdf
Tumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdfTumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdf
Tumelo-deep-dive-into-pass-through-voting-Feb23 (1).pdf
 
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptxSWAIAP Fraud Risk Mitigation   Prof Oyedokun.pptx
SWAIAP Fraud Risk Mitigation Prof Oyedokun.pptx
 
1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样
1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样
1:1制作加拿大麦吉尔大学毕业证硕士学历证书原版一模一样
 
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptxOAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
OAT_RI_Ep20 WeighingTheRisks_May24_Trade Wars.pptx
 

Project financial feasibility

  • 1. Project: Financial feasibility 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 1
  • 2. Tools for financial feasibility analysis • Payback period analysis At what point of time we are making more money than we are spending ? • Benefit cost ratio analysis For each rupee how much will be generated? • Net Present value analysis How much is future revenue (or expenditure) flow worth in today ? • Internal rate of return (IRR) analysis rate of return on our investment for a fixed period, during which time we are spending money and making money 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 2
  • 3. Payback Analysis • A viable project is one that is able to pay back the original investment as early as possible. • The payback period is achieved at that point in time when cumulative cash inflows more than offset cumulative outflows, or When we are finally making more money in total than we have spent in total. • Payback period indicates when, our investment is out of the woods. • Projects with long payback are less attractive than those with short payback. - they tie up capital longer, not enabling its use for other productive purposes. - they are generally riskier than those with short payback periods as over a long stretch of time, many things can go wrong. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 3
  • 4. Payback Analysis • As per payback period, project A is more attractive 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 4 Project A Year Outflows Cumulative out flows Inflows Cumulative In flows 1 200 200 100 100 2 200 400 300 400 3 100 500 300 700 4 500 300 1000 5 500 300 1300 Total 500 1300 Project B Year Outflows Cumulative out flows Inflows Cumulative In flows 1 200 200 100 100 2 200 400 100 200 3 100 500 200 400 4 500 400 800 5 500 500 1300 Total 500 1300
  • 5. Net Present Value (NPV) Analysis or Discounted cash flows analysis • the late 1970s, Americans experienced inflation rates in the 17% per annum range • Inflation provides one example of what is called the time value of money i.e. A rupee today has a different value than a rupee one year from now. • There is more to time value of money than the force of inflation. • Consider if no inflation, i.e a rupee today has the same purchasing power as a rupee one year later. If you have an opportunity to lend Rs 1,000/- to a business at a 10% interest yearly then at year end you will receive a payment of Rs 1,100/- at the year end when the loan is paid off. Your initial investment of Rs 1,000/- has grown by 10% over time. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 5
  • 6. Net Present Value (NPV) Analysis or Discounted cash flows analysis • FV =PV (1+r)n where r is interest rate fraction and n is number of completed time slots Inflation provides one example of what is called the time value of money i.e. A rupee today has a different value than a rupee one year from now. • There is more to time value of money than the force of inflation. • Consider if no inflation, i.e a rupee today has the same purchasing power as a rupee one year later. If you have an opportunity to lend Rs 1,000/- to a business at a 10% interest yearly then at year end you will receive a payment of Rs 1,100/- at the year end when the loan is paid off. Your initial investment of Rs 1,000/- has grown by 10% over time. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 6
  • 7. Net Present Value (NPV) Analysis • Project A is more attractive than Project B, because its true, discounted profit (Rs 533.18) is greater than the discounted profit of Project B (Rs 485.24). 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 7 Project A Year Outflows Inflows Discounting factor @ 10% PV of out flows PV of In flows PV of Net flows 1 200 100 0.9091 181.82 90.91 -90.91 2 200 300 0.8264 165.28 247.92 82.64 3 100 300 0.7513 75.13 225.39 150.26 4 300 0.683 0 204.9 204.9 5 300 0.6209 0 186.27 186.27 Total 500 1300 422.23 955.39 533.16 Project B Year OutflowsInflows Discounting factor @ 10% PV of out flows PV of In flows PV of Net flows 1 200 100 0.9091 181.82 90.91 -90.91 2 200 100 0.8264 165.28 82.64 -82.64 3 100 200 0.7513 75.13 150.26 75.13 4 400 0.683 0 273.2 273.2 5 500 0.6209 0 310.45 310.45 Total 500 1300 422.23 907.46 485.23
  • 8. Net Present Value (NPV) Analysis • Both projects have same NPV 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 8 Project A Year Outflows Inflows Discounting factor @ 10% PV of out flows PV of In flows PV of Net flows 1 200 0.9091 181.82 0 -181.82 2 200 0.8264 165.28 0 -165.28 3 100 100 0.7513 75.13 75.13 0 4 200 0.683 0 136.6 136.6 5 500 0.6209 0 310.45 310.45 Total 500 800 422.23 522.18 99.95 Project B Year OutflowsInflows Discounting factor @ 10% PV of out flows PV of In flows PV of Net flows 1 50 0.9091 45.455 0 -45.46 2 200 0.8264 165.28 0 -165.28 3 200 100 0.7513 150.26 75.13 -75.13 4 89.65 200 0.683 61.23095 136.6 75.37 5 500 0.6209 0 310.45 310.45 Total 539.65 800 422.226 522.18 99.95
  • 9. Internal rate of return(IRR) Analysis • Both projects have same NPV • By Excel function IRR of project A is 14 % and Project B is 12 % 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 9 Project A Year Outflows Inflows Discounting factor @ 10% PV of out flows PV of In flows PV of Net flows 1 -200 0.9091 181.82 0 -181.82 2 -200 0.8264 165.28 0 -165.28 3 -100 100 0.7513 75.13 75.13 0 4 200 0.683 0 136.6 136.6 5 500 0.6209 0 310.45 310.45 Total -500 800 422.23 522.18 99.95 Project B Year Outflows Inflows Discounting factor @ 10% PV of out flows PV of In flows PV of Net flows 1 -50 0.9091 45.455 0 -45.46 2 -200 0.8264 165.28 0 -165.28 3 -200 100 0.7513 150.26 75.13 -75.13 4 -89.65 200 0.683 61.23095 136.6 75.37 5 500 0.6209 0 310.45 310.45 Total -539.65 800 422.226 522.18 99.95
  • 10. Internal rate of return(IRR) Analysis 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 10 Project A discounting @ 15 % Year Outflows Inflows Discounting factor @ 15% PV of out flows PV of In flows PV of Net flows 1 200 0.8696 -173.92 0 -173.92 2 200 0.7561 -151.22 0 -151.22 3 100 100 0.6575 -65.75 65.75 0 4 200 0.5718 0 114.36 114.36 5 500 0.4972 0 248.6 248.6 Total 500 800 -390.89 428.71 37.82 Project B discounting @ 15 % Year Outflows Inflows Discounting factor @ 15% PV of out flows PV of In flows PV of Net flows 1 50 0.8696 -43.48 0 -43.48 2 200 0.7561 -151.22 0 -151.22 3 200 100 0.6575 -131.5 65.75 -65.75 4 89.65 200 0.5718 -51.2619 114.36 63.1 5 500 0.4972 0 248.6 248.6 Total 539.65 800 -377.462 428.71 51.25 Project A discounting @ 20 % Year Outflows Inflows Discounting factor @ 20% PV of out flows PV of In flows PV of Net flows 1 200 0.8333 -166.66 0 -166.66 2 200 0.6944 -138.88 0 -138.88 3 100 100 0.5787 -57.87 57.87 0 4 200 0.4823 0 96.46 96.46 5 500 0.4019 0 200.95 200.95 Total 500 800 -363.41 355.28 -8.13 Project B discounting @ 20 % Year Outflows Inflows Discounting factor @ 20% PV of out flows PV of In flows PV of Net flows 1 50 0.8333 -41.665 0 -41.67 2 200 0.6944 -138.88 0 -138.88 3 200 100 0.5787 -115.74 57.87 -57.87 4 89.65 200 0.4823 -43.2382 96.46 53.22 5 500 0.4019 0 200.95 200.95 Total 539.65 800 -339.523 355.28 15.76
  • 11. Internal rate of return(IRR) Analysis • IRR of Project A is 19% and of Project B is 23 % • a project's IRR is higher than the prevailing interest rate, then it may be smart to invest in it. • IRR model assumes that money employed is utilized all the time and is not remain unutilized at all. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 11 Project A Year Outflows Inflows Discounting factor @ 19% PV of out flows PV of In flows PV of Net flows 1 -200 0.8403 -168.06 0 -168.06 2 -200 0.7062 -141.24 0 -141.24 3 -100 100 0.5934 -59.34 59.34 0 4 200 0.4987 0 99.74 99.74 5 500 0.419 0 209.5 209.5 Total -500 800 -368.64 368.58 -0.06 Project B Year Outflows Inflows Discounting factor @ 10% PV of out flows PV of In flows PV of Net flows 1 -50 0.813 -40.65 0 -40.65 2 -200 0.661 -132.2 0 -132.2 3 -200 100 0.5374 -107.48 53.74 -53.74 4 -89.65 200 0.4369 -39.1681 87.38 48.21 5 500 0.3552 0 177.6 177.6 Total -539.65 800 -319.498 318.72 -0.78
  • 12. Benefit to Cost ratio The benefit-cost ratio is nothing more than a measure of benefit divided by a measure of cost. Measure of benefit can be anything: financial profit/ cost savings, happiness, error reduction, throughput time, and so on. Practically, the measure of benefit is revenue - or in non- revenue generating situations, cost savings. Benefit-cost ratio (B/C) > 1.0 Revenue is greater than expenditures. i.e. investment is profitable. Benefit-cost ratio (B/C) = 1.0. Revenue and expenditures offset each other. Consequently, you are facing a breakeven situation. Benefit-cost ratio (BE) < 1.0. In this case, expenditures outstrip revenue. You are losing money. Example: BIC = Rs 40,000/Rs 50,000 = 0.8 Interpretation: For each dollar you are spending on this project, you are only gaining 80 cents of revenue. Thus you are losing money. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 12
  • 13. Benefit to Cost ratio Discounted B/C for project A = 428.71/390.89 =1.09 Discounted B/C for project B = 428.71/377.46 =1.14 B/C for project A = 800/500 =1.6 B/C for project B = 800/539.65 =1.48 Benefit-cost ratio analysis using discounted cash flow data, the computing what in finance is called the profitability index. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 13 Project A Year Outflows Inflows Discounting factor @ 15% PV of out flows PV of In flows PV of Net flows 1 200 0.8696 173.92 0 -173.92 2 200 0.7561 151.22 0 -151.22 3 100 100 0.6575 65.75 65.75 0 4 200 0.5718 0 114.36 114.36 5 500 0.4972 0 248.6 248.6 Total 500 800 390.89 428.71 37.82 Project B Year Outflows Inflows Discounting factor @ 15% PV of out flows PV of In flows PV of Net flows 1 50 0.8696 43.48 0 -43.48 2 200 0.7561 151.22 0 -151.22 3 200 100 0.6575 131.5 65.75 -65.75 4 89.65 200 0.5718 51.26 114.36 63.1 5 500 0.4972 0 248.6 248.6 Total 539.65 800 377.46 428.71 51.25
  • 14. Benefit to Cost ratio for non-revenue generating project Many projects that are carried out are not revenue generating Ex. . a typical information technology (IT) project in an organization This can improve revenue performance indirectly, as the organization reduces operating costs. But it is not directly tied to generating revenue Benefit-cost ratio analysis for this involves cost saving instead of revenue generation. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 14
  • 15. B/C ratio : pitfalls 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 15 There are a number of pitfalls associated with benefit-cost analyses that are important to know. B/C ratios do not provide information on the size of the numbers being reviewed. EX: Project A BIC = 3.1 Project B BIC = 2.7 Project A's is better Project A BIC = 3100/1000 = 3.1 Project B BIC = 2,700,000/1,000,000 = 2.7 • Since B/C is a ratio, sense of the size of the numbers vanishes. For most organizations, Project B is more attractive than A, as B has substantial revenue. • For valid comparisons among the B/C ratios of different projects, One must know the actual size of the numbers that are used to compute the ratios.
  • 16. B/C ratio : pitfalls 1. B/C ratios do not provide information on when payback occurs. Consider the following two ratios: Project A B/C = 3.1 Project B B/C = 2.7 Again, Project A appears to be more attractive than Project B. If Project A realizes a B/C of 3.1 after five years, it is less attractive than Project B, if B realizes its B/C ratio in two years. 2. The easiest quantitative data to acquire is basic business data derived from estimated budgets and, possibly, on anticipated revenues. Hard-to-measure factors are often ignored when computing the ratios. For example, the main benefit of a project may be what is called a second-order benefit - e.g., this project, while not profitable in itself, will provide the groundwork for major revenue streams generated on future projects. Another benefit might be improved public perceptions of the company's activities. None of these pitfalls is fatal. With B/C, analysts should be aware of their existence and should strive to deal with them so that the analyses are valid. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 16
  • 17. Return on Investment (ROI) The ROI is nothing more than a measure of NPV expressed as percentage of present value of cost. ROI = (NPV/PV of cost)x 100= (discounted B/C -1)x 100 ROI> 0 Revenue is greater than expenditures. i.e. investment is profitable. ROI= 0. Revenue and expenditures offset each other. Consequently, you are facing a breakeven situation. ROI< 0. In this case, expenditures outstrip revenue. You are losing money. 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 17
  • 18. Thank You 19-04-2018 BCH 505 Project Finance by Dr Naim R Kidwai 18 Contact Email: naimkidwai@gmail.com https://nrkidwai.wordpress.com/