SlideShare a Scribd company logo
Lockout/Tagout – Control of
Hazardous Energy
August 16, 2023
Objective,
Application and
Purpose
Objective, Application and
Purpose
Objective:
• To provide procedures for locking, tagging and trying
of equipment prior to installation of new equipment
or shutdown for servicing, repairs, tests or
adjustments of existing equipment such that
equipment may be repaired, cleaned, adjusted or
inspected safely.
Application:
• All areas where a source of energy could result in
accidental movement of equipment or other energy
source which could result in injury to persons,
property or process.
Lockout/Tagout
Definitions
DEFINITIONS
• Affected employee - Assigned to or operating a device.
• Authorized employee - Responsible for the LO/TO of
equipment.
• Capable of being locked out - has a built in LO/TO
mechanism or can be affixed.
• Energized - Contains stored/residual energy.
DEFINITIONS (continued)
• Energy Isolation Devices - Mechanical device that physically prevents
transmission or release of energy such as:
• Manually operated electrical circuit
breakers
• Disconnect switches
• Line valves
• Blocks
DEFINITIONS (continued)
• Energy sources -
• Electrical Power - Current
• Mechanical Power - Gears
• Fluid Power - Pressurized Fluids
• Gravity Power - Suspended Objects
• Pneumatic Power
• Chemical Power
• Thermal Power
DEFINITIONS (continued)
• Lockout - Placing a locking device on an energy isolation
device.
• Lockout device - A positive means (such as a lock) to hold
an energy isolation device in safe position. Locks used for
lock outs must be designated only for the purpose of lock
outs. Locks must be of appropriate size and design such
that it cannot be broken or tampered with.
DEFINITIONS (continued)
• Servicing / Maintenance - Construction, installation,
adjustment, inspecting, modification, maintenance,
servicing, cleaning, etc.
• Set-Up - Preparing a machine/equipment for normal
operation.
DEFINITIONS (continued)
•Tagout - Placement of Tagout device on an energy isolating
device.
•Tagout Device - Prominent warning such as a tag. Must be
used with lock or 1 additional safety measure.
Purpose &
Responsibilities
Purpose:
• To protect employees from injury caused by the sudden
start up of machines or other equipment during
maintenance or servicing
• To ensure that hazardous energy is isolated before an
employee performs an activity where unexpected
energizing could cause injury
Responsibilities
• Where lockout and tag out is being performed in order for a
contractor or other group to complete work on the piece of
equipment, it is the responsibility of operations personnel
to complete the initial lockout and tag out of the equipment
and properly isolate / de-energize the equipment and
communicate the purpose and status of the disconnecting
and locking out.
• Others that will perform work on the equipment have the
responsibility to review the lockout, tag out isolation and
de-energization with the operations personnel who
performed the work in order to ensure for themselves that
the equipment is safe. At that time, the contractor should
install their own locks.
Lockout/Tagout shall be used
when:
• A task requires an employee to bypass or remove or defeat a
safety device
• A task requires an employee to place any part of his or her
body anywhere equipment may be energized
• Authority to work on equipment must first be obtained from
the H&S Lead or his designate who will then take the
following steps to ensure that the equipment or machinery is
properly prepared for repair or maintenance.
Hazard Assessment
• Spark Science Centre shall identify and assess the hazards, or the
potential hazards of lockout tag out in accordance with the Hazard
Assessment Program
• The hazard assessment must include isolation and de-energization
hazards including:
1. Electrical Energy– live circuits, charged capacitors, etc.
2. Pressure Energy – pressure within piping, vessels and cavities with pieces
of equipment, etc.
3. Mechanical Energy – energy stored in springs, levers, etc.
4. Static Energy – equipment that could fall, suspended equipment, etc.
5. Dynamic Energy – energy stored in equipment that spins or rotates, Etc.
6. Chemical Energy – energy that may be released from chemicals (i.e.
chemicals that may be water or air reactive, etc.)
• SOPs shall be developed for compliance with lock-out tag out.
Lockout/Tagout Procedures
1. Shut down equipment as required.
2. Place "DO NOT OPERATE" tags on all necessary controls.
3. Install locks as required.
4. Block in, de-pressure and purge as required.
5. Lock control devices in the inoperative position and attach a
supplemental tag describing the work to be done and the name of
the person who installed the lock out device. Only the person who
installed the device or the operations supervisor may remove it.
6. Ensure that all hazards, pressure conditions, tension or toxic
substances have been removed or rendered safe.
7. Before starting any work, the workers who will be performing the
actual work must physically check all potential sources where
energy can be released and verify that they have been successfully
isolated (locked out, blocked, etc.). This check should be
documented on the LOTO form. Lockout locations must also be
documented on the LOTO form.
Lockout And Tagout Procedures
• A lockout and tagout procedure must be written for
every piece of equipment.
• That lockout tagout procedure must have an annual
review to ensure accuracy.
• Locking Out is Part of the Occupational Health and
Safety Act in all jurisdictions.
Group Lockout
• Each trade or group of workers must install their own locks on the
mechanical lock out device prior to the commencement of work. Such
locks shall be removed only by the worker who installed the lockout
device or in the case of an emergency, by the Manager of Operations &
H&S or their designate. In the case where a worker's lock is removed in
their absence, the worker will be informed before they start work again.
• Where group lock out is undertaken, the H&S Specialist must develop a
group lock out procedure and post it to make it readily available to
workers. The procedures must include designation of responsibilities for
two competent workers for
• Independently locking out the energy isolating devices,
• securing the keys for the locks to a key securing systems (i.e., a lock
box or other multiple lock device),
• completing the lock-out/Tag-out logbook, and
• determining that it is safe to end the group lock out after all
personal locks have been removed from the key securing system.
STANDARD SPARK LOCK OUT TAG
• These tags must accompany a lock out lock.
• Person applying lock must sign and date and fill in remark section.
Return to Operating Position
• It is the responsibility of the Locking out Employee or his/her
designate to ensure that all equipment and machinery is
ready for service and all locks, tools, etc., have been
removed before placing the equipment back into service.
Where an employee who installed the lock is unavailable
(i.e. off-shift), every reasonable effort must be made to
contact the employee (or the employee the responsibility
was transferred to) and to ensure that the
machinery/equipment can be operated safely before
removing the lock.
When Employee is Not There
Make every effort to find that individual.
Another employee and the Manager of Operations & H&S
must look at the situation separately and agree that
equipment is safe to operate.

More Related Content

What's hot

Safety Moment-Unsafe Act and Unsafe Condition.pptx
Safety Moment-Unsafe Act and Unsafe Condition.pptxSafety Moment-Unsafe Act and Unsafe Condition.pptx
Safety Moment-Unsafe Act and Unsafe Condition.pptx
Innocent Bhaikwa
 
Health & Safety Induction Training
Health & Safety Induction Training Health & Safety Induction Training
Health & Safety Induction Training
Claire
 

What's hot (20)

Work permit
Work permitWork permit
Work permit
 
Safety Moment-Unsafe Act and Unsafe Condition.pptx
Safety Moment-Unsafe Act and Unsafe Condition.pptxSafety Moment-Unsafe Act and Unsafe Condition.pptx
Safety Moment-Unsafe Act and Unsafe Condition.pptx
 
Electrical inspection-checklists
Electrical inspection-checklistsElectrical inspection-checklists
Electrical inspection-checklists
 
High pressure danger with compressed air
High pressure danger with compressed airHigh pressure danger with compressed air
High pressure danger with compressed air
 
The explosion and fires at the texaco refinery milford haven
The explosion and fires at the texaco refinery milford havenThe explosion and fires at the texaco refinery milford haven
The explosion and fires at the texaco refinery milford haven
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slides
 
An OSHA - LOTO Presentation
An OSHA - LOTO PresentationAn OSHA - LOTO Presentation
An OSHA - LOTO Presentation
 
HIERARCHY OF CONTROL
HIERARCHY OF CONTROLHIERARCHY OF CONTROL
HIERARCHY OF CONTROL
 
Plant Safety & Labour Laws
Plant Safety & Labour LawsPlant Safety & Labour Laws
Plant Safety & Labour Laws
 
FIRE EXTINGUISHER INSPECTION Form # HSEQ - FEI Rev 4.docx
FIRE EXTINGUISHER INSPECTION Form # HSEQ - FEI Rev 4.docxFIRE EXTINGUISHER INSPECTION Form # HSEQ - FEI Rev 4.docx
FIRE EXTINGUISHER INSPECTION Form # HSEQ - FEI Rev 4.docx
 
Industrial safety
Industrial safetyIndustrial safety
Industrial safety
 
EHS Presentation
EHS PresentationEHS Presentation
EHS Presentation
 
Personal safety in construction
Personal safety in constructionPersonal safety in construction
Personal safety in construction
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
The Basics Of Respiratory Protection
The Basics Of Respiratory ProtectionThe Basics Of Respiratory Protection
The Basics Of Respiratory Protection
 
Health & Safety Induction Training
Health & Safety Induction Training Health & Safety Induction Training
Health & Safety Induction Training
 
Fire and explosion
Fire and explosionFire and explosion
Fire and explosion
 
Loto presentation
Loto presentationLoto presentation
Loto presentation
 
Lock Out / Tag Out
Lock Out / Tag OutLock Out / Tag Out
Lock Out / Tag Out
 
Fire Hose Rack Inspection Guidelines
Fire Hose Rack Inspection GuidelinesFire Hose Rack Inspection Guidelines
Fire Hose Rack Inspection Guidelines
 

Similar to Lockout-Tagout 2023.ppt

Lockout tagout refresher training
Lockout tagout refresher trainingLockout tagout refresher training
Lockout tagout refresher training
Jost2012
 
Lockout tagout standard
Lockout tagout standardLockout tagout standard
Lockout tagout standard
Anbr Cama
 

Similar to Lockout-Tagout 2023.ppt (20)

LOTO Training.pdf
LOTO Training.pdfLOTO Training.pdf
LOTO Training.pdf
 
lockout-tagout-training.ppt
lockout-tagout-training.pptlockout-tagout-training.ppt
lockout-tagout-training.ppt
 
LOTO & ENERGY ISOLATION.pptx
LOTO & ENERGY ISOLATION.pptxLOTO & ENERGY ISOLATION.pptx
LOTO & ENERGY ISOLATION.pptx
 
Lockout tagout refresher training
Lockout tagout refresher trainingLockout tagout refresher training
Lockout tagout refresher training
 
shock_arc_flash
shock_arc_flashshock_arc_flash
shock_arc_flash
 
LOTO.pptx
LOTO.pptxLOTO.pptx
LOTO.pptx
 
LOTO 2
LOTO 2LOTO 2
LOTO 2
 
loto
lotoloto
loto
 
Energy Control Program by MCIEAST
Energy Control Program by MCIEASTEnergy Control Program by MCIEAST
Energy Control Program by MCIEAST
 
Overcoming The Challenges of Implementing a Lockout Program
Overcoming The Challenges of Implementing a Lockout ProgramOvercoming The Challenges of Implementing a Lockout Program
Overcoming The Challenges of Implementing a Lockout Program
 
Lock Out-Tag Out Training by Ryko
Lock Out-Tag Out Training by RykoLock Out-Tag Out Training by Ryko
Lock Out-Tag Out Training by Ryko
 
Loto online slides
Loto online slidesLoto online slides
Loto online slides
 
Lockout Tagout by KU
Lockout Tagout by KULockout Tagout by KU
Lockout Tagout by KU
 
Lock Out Tag Out
Lock Out Tag OutLock Out Tag Out
Lock Out Tag Out
 
Lockout/Tagout
Lockout/TagoutLockout/Tagout
Lockout/Tagout
 
Lockout tagout
Lockout tagoutLockout tagout
Lockout tagout
 
Lockout &tagout
Lockout &tagoutLockout &tagout
Lockout &tagout
 
The complete procedure of Logout & tagout
The complete procedure of Logout & tagoutThe complete procedure of Logout & tagout
The complete procedure of Logout & tagout
 
Lockout tagout standard
Lockout tagout standardLockout tagout standard
Lockout tagout standard
 
7115 Lockout 2019
7115 Lockout 20197115 Lockout 2019
7115 Lockout 2019
 

More from MichaelCazes1 (10)

Rigging and Hoisting PP.ppt
Rigging and Hoisting PP.pptRigging and Hoisting PP.ppt
Rigging and Hoisting PP.ppt
 
A Guide to Heat Stress1.ppt
A Guide to Heat Stress1.pptA Guide to Heat Stress1.ppt
A Guide to Heat Stress1.ppt
 
OHS Due Diligence For Workers.ppt
OHS Due Diligence For Workers.pptOHS Due Diligence For Workers.ppt
OHS Due Diligence For Workers.ppt
 
OHS Responsibilities.ppt
OHS Responsibilities.pptOHS Responsibilities.ppt
OHS Responsibilities.ppt
 
A Guide to Heat Stress1.ppt
A Guide to Heat Stress1.pptA Guide to Heat Stress1.ppt
A Guide to Heat Stress1.ppt
 
Hand Protection.pptx
Hand Protection.pptxHand Protection.pptx
Hand Protection.pptx
 
Hand Protection.pptx
Hand Protection.pptxHand Protection.pptx
Hand Protection.pptx
 
BBO PPP.ppt
BBO PPP.pptBBO PPP.ppt
BBO PPP.ppt
 
H&S orientation.pdf
H&S orientation.pdfH&S orientation.pdf
H&S orientation.pdf
 
presentation_Bee and Wasp stings.pptx
presentation_Bee and Wasp stings.pptxpresentation_Bee and Wasp stings.pptx
presentation_Bee and Wasp stings.pptx
 

Recently uploaded

Industrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportIndustrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training Report
Avinash Rai
 

Recently uploaded (20)

Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxJose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
 
How to Manage Notification Preferences in the Odoo 17
How to Manage Notification Preferences in the Odoo 17How to Manage Notification Preferences in the Odoo 17
How to Manage Notification Preferences in the Odoo 17
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
The Benefits and Challenges of Open Educational Resources
The Benefits and Challenges of Open Educational ResourcesThe Benefits and Challenges of Open Educational Resources
The Benefits and Challenges of Open Educational Resources
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Benefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational ResourcesBenefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational Resources
 
The Last Leaf, a short story by O. Henry
The Last Leaf, a short story by O. HenryThe Last Leaf, a short story by O. Henry
The Last Leaf, a short story by O. Henry
 
Industrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportIndustrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training Report
 
NCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdfNCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdf
 
size separation d pharm 1st year pharmaceutics
size separation d pharm 1st year pharmaceuticssize separation d pharm 1st year pharmaceutics
size separation d pharm 1st year pharmaceutics
 
Gyanartha SciBizTech Quiz slideshare.pptx
Gyanartha SciBizTech Quiz slideshare.pptxGyanartha SciBizTech Quiz slideshare.pptx
Gyanartha SciBizTech Quiz slideshare.pptx
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Salient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxSalient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptx
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
 
How to the fix Attribute Error in odoo 17
How to the fix Attribute Error in odoo 17How to the fix Attribute Error in odoo 17
How to the fix Attribute Error in odoo 17
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
 

Lockout-Tagout 2023.ppt

  • 1. Lockout/Tagout – Control of Hazardous Energy August 16, 2023
  • 3. Objective, Application and Purpose Objective: • To provide procedures for locking, tagging and trying of equipment prior to installation of new equipment or shutdown for servicing, repairs, tests or adjustments of existing equipment such that equipment may be repaired, cleaned, adjusted or inspected safely. Application: • All areas where a source of energy could result in accidental movement of equipment or other energy source which could result in injury to persons, property or process.
  • 5. DEFINITIONS • Affected employee - Assigned to or operating a device. • Authorized employee - Responsible for the LO/TO of equipment. • Capable of being locked out - has a built in LO/TO mechanism or can be affixed. • Energized - Contains stored/residual energy.
  • 6. DEFINITIONS (continued) • Energy Isolation Devices - Mechanical device that physically prevents transmission or release of energy such as: • Manually operated electrical circuit breakers • Disconnect switches • Line valves • Blocks
  • 7. DEFINITIONS (continued) • Energy sources - • Electrical Power - Current • Mechanical Power - Gears • Fluid Power - Pressurized Fluids • Gravity Power - Suspended Objects • Pneumatic Power • Chemical Power • Thermal Power
  • 8. DEFINITIONS (continued) • Lockout - Placing a locking device on an energy isolation device. • Lockout device - A positive means (such as a lock) to hold an energy isolation device in safe position. Locks used for lock outs must be designated only for the purpose of lock outs. Locks must be of appropriate size and design such that it cannot be broken or tampered with.
  • 9. DEFINITIONS (continued) • Servicing / Maintenance - Construction, installation, adjustment, inspecting, modification, maintenance, servicing, cleaning, etc. • Set-Up - Preparing a machine/equipment for normal operation.
  • 10. DEFINITIONS (continued) •Tagout - Placement of Tagout device on an energy isolating device. •Tagout Device - Prominent warning such as a tag. Must be used with lock or 1 additional safety measure.
  • 12. Purpose: • To protect employees from injury caused by the sudden start up of machines or other equipment during maintenance or servicing • To ensure that hazardous energy is isolated before an employee performs an activity where unexpected energizing could cause injury
  • 13. Responsibilities • Where lockout and tag out is being performed in order for a contractor or other group to complete work on the piece of equipment, it is the responsibility of operations personnel to complete the initial lockout and tag out of the equipment and properly isolate / de-energize the equipment and communicate the purpose and status of the disconnecting and locking out. • Others that will perform work on the equipment have the responsibility to review the lockout, tag out isolation and de-energization with the operations personnel who performed the work in order to ensure for themselves that the equipment is safe. At that time, the contractor should install their own locks.
  • 14. Lockout/Tagout shall be used when: • A task requires an employee to bypass or remove or defeat a safety device • A task requires an employee to place any part of his or her body anywhere equipment may be energized • Authority to work on equipment must first be obtained from the H&S Lead or his designate who will then take the following steps to ensure that the equipment or machinery is properly prepared for repair or maintenance.
  • 15. Hazard Assessment • Spark Science Centre shall identify and assess the hazards, or the potential hazards of lockout tag out in accordance with the Hazard Assessment Program • The hazard assessment must include isolation and de-energization hazards including: 1. Electrical Energy– live circuits, charged capacitors, etc. 2. Pressure Energy – pressure within piping, vessels and cavities with pieces of equipment, etc. 3. Mechanical Energy – energy stored in springs, levers, etc. 4. Static Energy – equipment that could fall, suspended equipment, etc. 5. Dynamic Energy – energy stored in equipment that spins or rotates, Etc. 6. Chemical Energy – energy that may be released from chemicals (i.e. chemicals that may be water or air reactive, etc.) • SOPs shall be developed for compliance with lock-out tag out.
  • 16. Lockout/Tagout Procedures 1. Shut down equipment as required. 2. Place "DO NOT OPERATE" tags on all necessary controls. 3. Install locks as required. 4. Block in, de-pressure and purge as required. 5. Lock control devices in the inoperative position and attach a supplemental tag describing the work to be done and the name of the person who installed the lock out device. Only the person who installed the device or the operations supervisor may remove it. 6. Ensure that all hazards, pressure conditions, tension or toxic substances have been removed or rendered safe. 7. Before starting any work, the workers who will be performing the actual work must physically check all potential sources where energy can be released and verify that they have been successfully isolated (locked out, blocked, etc.). This check should be documented on the LOTO form. Lockout locations must also be documented on the LOTO form.
  • 17. Lockout And Tagout Procedures • A lockout and tagout procedure must be written for every piece of equipment. • That lockout tagout procedure must have an annual review to ensure accuracy. • Locking Out is Part of the Occupational Health and Safety Act in all jurisdictions.
  • 18. Group Lockout • Each trade or group of workers must install their own locks on the mechanical lock out device prior to the commencement of work. Such locks shall be removed only by the worker who installed the lockout device or in the case of an emergency, by the Manager of Operations & H&S or their designate. In the case where a worker's lock is removed in their absence, the worker will be informed before they start work again. • Where group lock out is undertaken, the H&S Specialist must develop a group lock out procedure and post it to make it readily available to workers. The procedures must include designation of responsibilities for two competent workers for • Independently locking out the energy isolating devices, • securing the keys for the locks to a key securing systems (i.e., a lock box or other multiple lock device), • completing the lock-out/Tag-out logbook, and • determining that it is safe to end the group lock out after all personal locks have been removed from the key securing system.
  • 19. STANDARD SPARK LOCK OUT TAG • These tags must accompany a lock out lock. • Person applying lock must sign and date and fill in remark section.
  • 20. Return to Operating Position • It is the responsibility of the Locking out Employee or his/her designate to ensure that all equipment and machinery is ready for service and all locks, tools, etc., have been removed before placing the equipment back into service. Where an employee who installed the lock is unavailable (i.e. off-shift), every reasonable effort must be made to contact the employee (or the employee the responsibility was transferred to) and to ensure that the machinery/equipment can be operated safely before removing the lock.
  • 21. When Employee is Not There Make every effort to find that individual. Another employee and the Manager of Operations & H&S must look at the situation separately and agree that equipment is safe to operate.

Editor's Notes

  1. There are several instances where machines and equipment are required to be locked out or tagged out, such as when an employee has removed or bypassed a guard or safety device. This usually occurs when performing maintenance to a machine, and the safety device limits access to the machine. By disabling the guard or safety device, the worker has no protection from the machine if another worker inadvertently starts the machine. Many times safety devices must be disabled in order to get to the site of repairs. Other examples are when setting up machines (usually code changes or change overs in production equipment), or when adding or installing new components. Another example requiring lockout / tagout of the equipment is when an employee puts his or her body into the point of operation, where the work is actually being performed. If the employee is in a danger zone, the equipment should be secured to ensure that there is no risk of unexpected start up. The penalties issued for this violation in 1996 were $867,6753. Many organizations didn’t realize the importance, or were blatantly indifferent. ONE issue not covered in detail in books, is the removal of jam-ups or ball-ups. Common to manufacturing environments where conveyors move parts along a designated pathway. When removing ball-ups, Lockout/Tagout procedures must be followed.
  2. The next area that we will focus on is key terms that need to be defined. It is vital to comprehend these terms if this standard is to be clearly understood. All terms will be explained as they apply to this law: Affected employee - is an employee that is either assigned to an area where a lockout / tagout is being performed; or an employee whose job requires him/her to operate or use a machine that has been locked or tagged out. Again, this is usually done during servicing or maintenance. Authorized employee - is the person that will lock or tag out the equipment in order to perform the maintenance. Usually, authorized employees must undergo extensive training to possess the knowledge and skill necessary to repair such machinery. Also, an affected employee whose duties include servicing or repairs, such as preventive maintenance, will become an authorized person when in the act of servicing the equipment. Capable of being locked out - refers to the ability of a power source having a mechanism (hasp) which a lock can be affixed; or a built in locking mechanism. Energized - is when there is residual or stored energy; or being connected to an energy source.
  3. Have hardware (lockout devices to pass around as they are discussed. It is wise to take students on a “field trip” to a shop or location where these can be demonstrated as where they would be applied. It is important to note that push buttons, selector switches, and other such types of devices are not considered energy isolation devices. In other words, pushing the red stop button, or putting a machine in the off position (selector switch), does not mean the machine has been locked out. Make sure to cover items like lockouts for light switches, circuit breakers, etc...
  4. Most of the energy sources can be found in every home and industrial setting. Give examples of various types of power components. I.e.…Gravity power could be weight-actuated accumulators, pulleys, . Mechanical energy could be springs, gears, …… Fluid power - hydraulic or pneumatic cylinders. Energy source - below is a list of the different types of power sources found in industry: Electrical power (electrical current) Mechanical power (gears) Fluid power (either pneumatic or hydraulic pressurized fluid) Gravity power (heavy objects released to deliver power) Chemical power (reactive materials that can deliver force such as chemical cartridges in nail guns) Thermal power (steam can be channeled through ducts and pipes to deliver force)
  5. Hot tap - a procedure used in maintenance and servicing which involves welding on a piece of equipment under pressure, in order to install connections or add-ons. This is common when adding sections of pipeline without interrupting service. Lockout - is the placement of a locking device on an energy isolation device. This is to ensure that the equipment being controlled cannot be operated until the hardware is removed. Lockout device - a device that utilizes a positive means such as a lock (either key or combination type) to hold an energy isolation device in the safe position and prevent the energizing of a machine or equipment. Normal production operations - machinery or equipment performing its intended production function.
  6. Servicing and/or maintenance - includes constructing, installing, setting up, adjusting, inspecting, modifying, and maintaining and/or servicing machinery and equipment. Other items that will fall into this definition will be lubricating, cleaning, or un-jamming ball ups of material caught in the equipment. If you must make tool changes or adjustments, that too would be considered maintenance / servicing. Setting up - many times work areas must be set up for production. Large industrial presses must have set up work done when changing to run a different product. It is defined as any work performed to prepare a machine or equipment to perform its normal production operation.
  7. Tagout - is the placement of a tagout device on an energy isolating device, in accordance with an established procedure, to indicate that the energy isolating device and the equipment being controlled may not be operated until the tagout device is removed. Tagout device - a prominent warning device such as a tag which can be securely fastened to an energy isolating device in accordance with an established procedure, to indicate that the energy isolating device and the equipment being controlled may not be operated until the tagout device is removed. A tag used without a lock shall be supplemented by at least one additional safety measure that provides a level of safety equivalent to that obtained by the use of a lock, such as opening an additional disconnecting device, removal of an isolating circuit element, blocking of a controlling switch or the removal of a valve handle to reduce the likelihood of inadvertent energization.
  8. After the repairs have been made, the authorized employee can prepare for the release of the lockout or tagout devices. Again there is a procedure that must be followed to ensure worker safety. FROM GOODYEAR LOTO MANUAL 1) First the work area must be inspected to make sure that any tools or supplies are removed. Screwdrivers and other items left on the floor could create tripping / falling hazards. The authorized employee should also ensure that the machine components are intact. Make Sure that all guards have been replaced. 2) Next, the work area must be checked to confirm that all employees are in a safe position. Associates must be clear of machinery and cautious of parts of the machine that may cycle upon energization. 3) All affected or other employees in the area shall be notified before the lockout or tagout devices are removed. 4) After the employees have been notified, then the authorized employee can begin to physically remove the hardware. 5) Restore all energy to the machine.
  9. We’ve stressed that the only person that should remove locks or tags is the person that applied them. However, sometimes emergencies or other unforeseen circumstances might require authorized employees to be gone when maintenance is completed. 1) Verify that the employee is gone. Page them on intercom system, yell out to the shop, or whatever it takes to ensure they are gone. 2) Make every effort to contact the employee. Call them on their mobile phone, pager, at home, etc. Remember that each worker must have their own locks and tags. 3) The Maintenance tech may physically remove the lock or tag after obtaining permission (see slide). This should require bolt cutter or other means to remove. Remember it should withstand 50 lbs. of force - minimum.