Project Information:
Project Name: Company Name:
Location: Date :
Sl. No Description Yes No N/A Comments
DBs/ SDBs
1. Is earth conducted continued up to DB/ SDB?
2. Whether DBs & extension boards are protected from rain/ water?
3. Is there any overloading of DBs/ SDBs?
4. Are correct rated Circuit breakers provided in all main boards and sub-boards?
5. Is energized wiring in junction boxes, Circuit board panels & similar places covered all times?
CABLES
6. Whether the condition of cable is checked?
7. Are cables received checked for insulation resistance before using them?
8. Are all main cables taken either underground/ overhead?
9. Are main cables protected from sharp/ heavy materials?
10. Is any improper jointing of cable identified?
11. Are all plugs and sockets in good condition?
RCD (ELCB)
12. Is the connections routed through 30mA RCD?
13. EARTHING
14. Are main DB, Generator and other panel’s ear thing done?
15. Earth resistance checked and found within limits?
ELECTRICALLY OPERATED MACHINES/ ACCESSORIES
16. Whether the machine supply cable has industrial type socket and plug?
17. Are all metal parts of electrical equipment and light fittings/ accessories grounded?
18. Is there any shed/ cover for machines?
19. Are flood lights/ task lights fixed properly away from combustibles?
20. Others if any:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Noted by Project Leader : Signature:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Location / Area :
Panel No : Voltage:
Permit Validity:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
No: Checks Yes-No-NA Checks Yes-No-NA
ENERGIZATION (“Power On”) ISOLATION (“Power Off”)
1. Safety tool box briefing done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
2. Authorized personnel / operators available. ☐ ☐ ☐
Authorized personnel / operators available. ☐ ☐ ☐
3. Method statement/Risk assessment in place. ☐ ☐ ☐
Adjacent live areas protected. ☐ ☐ ☐
4. Safety Barriers in place and safety signage Displayed. ☐ ☐ ☐
PPE available, high voltage rubber gloves, Safety goggles and floor mat. ☐ ☐ ☐
5. Working area is well lighted. ☐ ☐ ☐
Isolation/Lock-out in place. ☐ ☐ ☐
6. Electrical instruments are available for any Purpose. ☐ ☐ ☐
Electrical circuits “proved” by calibrated Instrument and found out to be no power. ☐ ☐ ☐
7. Correct PPE available, high voltage rubber Gloves, safety goggles and floor mat. ☐ ☐ ☐
Unauthorized workers are cleared from the Area. ☐ ☐ ☐
8. Approved WIR for installation, testing and Termination are attached to the permit. ☐ ☐ ☐
Standby operatives in the event of contact With live circuits. ☐ ☐ ☐
9. Emergency light (Flashlight) available. ☐ ☐ ☐
Emergency light (Flashlight) available. ☐ ☐ ☐
10. Is live work absolutely necessary? ☐ ☐ ☐
Emergency response plan available ☐ ☐ ☐
11. Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☒ ☐ ☐
12. Power cable route from panel board to plant & equipment has been checked ☐ ☐ ☐
13 Emergency response plan available ☐ ☐ ☐
14 Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
Project Information:
Project Name: Company Name:
Location: Date :
Sl. No Description Yes No N/A Comments
DBs/ SDBs
1. Is earth conducted continued up to DB/ SDB?
2. Whether DBs & extension boards are protected from rain/ water?
3. Is there any overloading of DBs/ SDBs?
4. Are correct rated Circuit breakers provided in all main boards and sub-boards?
5. Is energized wiring in junction boxes, Circuit board panels & similar places covered all times?
CABLES
6. Whether the condition of cable is checked?
7. Are cables received checked for insulation resistance before using them?
8. Are all main cables taken either underground/ overhead?
9. Are main cables protected from sharp/ heavy materials?
10. Is any improper jointing of cable identified?
11. Are all plugs and sockets in good condition?
RCD (ELCB)
12. Is the connections routed through 30mA RCD?
13. EARTHING
14. Are main DB, Generator and other panel’s ear thing done?
15. Earth resistance checked and found within limits?
ELECTRICALLY OPERATED MACHINES/ ACCESSORIES
16. Whether the machine supply cable has industrial type socket and plug?
17. Are all metal parts of electrical equipment and light fittings/ accessories grounded?
18. Is there any shed/ cover for machines?
19. Are flood lights/ task lights fixed properly away from combustibles?
20. Others if any:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Noted by Project Leader : Signature:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Location / Area :
Panel No : Voltage:
Permit Validity:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
No: Checks Yes-No-NA Checks Yes-No-NA
ENERGIZATION (“Power On”) ISOLATION (“Power Off”)
1. Safety tool box briefing done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
2. Authorized personnel / operators available. ☐ ☐ ☐
Authorized personnel / operators available. ☐ ☐ ☐
3. Method statement/Risk assessment in place. ☐ ☐ ☐
Adjacent live areas protected. ☐ ☐ ☐
4. Safety Barriers in place and safety signage Displayed. ☐ ☐ ☐
PPE available, high voltage rubber gloves, Safety goggles and floor mat. ☐ ☐ ☐
5. Working area is well lighted. ☐ ☐ ☐
Isolation/Lock-out in place. ☐ ☐ ☐
6. Electrical instruments are available for any Purpose. ☐ ☐ ☐
Electrical circuits “proved” by calibrated Instrument and found out to be no power. ☐ ☐ ☐
7. Correct PPE available, high voltage rubber Gloves, safety goggles and floor mat. ☐ ☐ ☐
Unauthorized workers are cleared from the Area. ☐ ☐ ☐
8. Approved WIR for installation, testing and Termination are attached to the permit. ☐ ☐ ☐
Standby operatives in the event of contact With live circuits. ☐ ☐ ☐
9. Emergency light (Flashlight) available. ☐ ☐ ☐
Emergency light (Flashlight) available. ☐ ☐ ☐
10. Is live work absolutely necessary? ☐ ☐ ☐
Emergency response plan available ☐ ☐ ☐
11. Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☒ ☐ ☐
12. Power cable route from panel board to plant & equipment has been checked ☐ ☐ ☐
13 Emergency response plan available ☐ ☐ ☐
14 Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineJOBY Joby.Stephan
Sir/Madam, Looking for a new job.Available now at India.(shut down/short term/long term= oil&gas, refinery jobs)
B.tech mechanical engg/9.5 years/cswip 3.2.2/Lead auditor/ASNTlevel 2
post: Sr.inspector Qc welding/piping/pipeline
I will appreciate your valuable help. joby.stephan@yahoo.com/psjoby@gmail.com
I have over 11 years of work experience as QA/QC Inspector in Oil and Gas fields both offshore and onshore Construction and installations. focus on PQT/PQR, WQT, NDT, Destructive testing, Inspections of welding and Filed joint coating of Subsea Pipelines, Risers, Tie‐in spools, lateral joints, Jackets, Topside, and Pile pipes. Installation inspection of Pile driving, SPM, PLEMs, I&J tubes, Jackets & top sides.
Installation of distribution boards to work areas • Electricity • Electrocution;
• Fire;
Temporary electrics - offices • Electrical connections and terminations • Use of untrained electricians for electrical works;
• Use of substandard electrical fixtures and fittings;
• Use of substandard connections;
• Non-adherence to colour coding of wiring;
• Incorrect earthing;
• Tripping hazard; Damage to unprotected cables;
• Use of incorrectly rated fuses;
Site generators – offices and site
• Temporary supply • Generator fires;
• Incident due to incorrect earthing;
• Fuel leakage – environmental risk;
• Fuel storage;
• Noise;
This is a presentation on safe work practices at work site. The life is very precious not only for engineers but equally important for workers also, the presentation is based on my experience in Delhi Metro Rail corporation. Please follow safe work practices and enjoy the work.
Project Information
Project Name: Serial No:
Location: Manufacture Name:
Company Name: Date :
3rd Party Inspection valid till:
Sr. Description Yes No N/A Comments
1. Are compressors equipped with pressure relief valves and pressure gauges?
2. Are signs posted to warn about hot surfaces of the exhaust?
3. Air compressor 3rd party certificate available?
4. Is whip check arrestor used in all coupling points?
5. Is the belt drive system totally enclosed to provide protection for the front, back, top, and sides?
6. Air hoses in good condition without cracks/ damages.
7. Control valves in good condition
8. Is there any oil leakage
9. Drip tray provided
10. Fire extinguisher provided
11. Any damage/Cut in tires/ tire pressure
12. Meter gauge working properly
13. Lifting Hooks damaged
14. Battery of air compressor charged
15. Visible damage
16. Exhaust directed/ close to combustibles/ flammables
17. Exhaust not directed inside any room. (Internal Combustion Air Compressors shall be kept outside in the well-ventilated area)
18. Others specify:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / in charge : Signature:
Establishing exclusion zones • Personnel in area • Unauthorized access to test area;
• Workers struck by flying materials;
• Worker struck by High pressure water release;
Signage to test area • Personnel in area • Unauthorized access to test area;
• Inadequate signage to test area;
Pressure testing • High pressure to pipework; • Uncontrolled Stored Energy release;
• Rupture/failure in Pipe lines during testing;
• Valve/connection failure;
• Instrument failure resulting in system over-pressurization;
• End caps/plugs ejecting under high pressure;
• Weld/seal/fitting failure, flying objects;
• High pressure water/air injection.
Emergency procedures • High pressure to pipework; • Emergency procedures not briefed to task workers;
• Poor response in the event of an emergency;
Re-testing in the event of failure • Re-testing with high pressure • Injury due to uncontrolled testing;
• Worker injury due to working on pressurized system;
• Injury due to failure to ensure adequate pre-checks undertaken;
HSE INDUCTION
(Workers)
Name: _________________________________ Trade: ____________________________
M.B. No./Company Name : ________________
Date of Joining: __________________________
SL. N SUBJECT ON INDUCTION PREVIOUS SAFETY EXPOSURE FURTHER SAFETY TRAINING NEED ANALYSIS
1. Introduction Safety Requirements
2. Working Safety is of Primary Importance
3. General Safety Rules
4. Basic Safety Requirements
5. House Keeping
6. Health, Hygiene & Welfare Facilities
7. Fire Extinguisher / Fire Fighting
8. Emergency Procedure
9. Safety Violations & Penalty
10. Safety Award
11. Manual Handling
Induction Given By: Name: ___________________________
Designation: ___________________________
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineJOBY Joby.Stephan
Sir/Madam, Looking for a new job.Available now at India.(shut down/short term/long term= oil&gas, refinery jobs)
B.tech mechanical engg/9.5 years/cswip 3.2.2/Lead auditor/ASNTlevel 2
post: Sr.inspector Qc welding/piping/pipeline
I will appreciate your valuable help. joby.stephan@yahoo.com/psjoby@gmail.com
I have over 11 years of work experience as QA/QC Inspector in Oil and Gas fields both offshore and onshore Construction and installations. focus on PQT/PQR, WQT, NDT, Destructive testing, Inspections of welding and Filed joint coating of Subsea Pipelines, Risers, Tie‐in spools, lateral joints, Jackets, Topside, and Pile pipes. Installation inspection of Pile driving, SPM, PLEMs, I&J tubes, Jackets & top sides.
Installation of distribution boards to work areas • Electricity • Electrocution;
• Fire;
Temporary electrics - offices • Electrical connections and terminations • Use of untrained electricians for electrical works;
• Use of substandard electrical fixtures and fittings;
• Use of substandard connections;
• Non-adherence to colour coding of wiring;
• Incorrect earthing;
• Tripping hazard; Damage to unprotected cables;
• Use of incorrectly rated fuses;
Site generators – offices and site
• Temporary supply • Generator fires;
• Incident due to incorrect earthing;
• Fuel leakage – environmental risk;
• Fuel storage;
• Noise;
This is a presentation on safe work practices at work site. The life is very precious not only for engineers but equally important for workers also, the presentation is based on my experience in Delhi Metro Rail corporation. Please follow safe work practices and enjoy the work.
Project Information
Project Name: Serial No:
Location: Manufacture Name:
Company Name: Date :
3rd Party Inspection valid till:
Sr. Description Yes No N/A Comments
1. Are compressors equipped with pressure relief valves and pressure gauges?
2. Are signs posted to warn about hot surfaces of the exhaust?
3. Air compressor 3rd party certificate available?
4. Is whip check arrestor used in all coupling points?
5. Is the belt drive system totally enclosed to provide protection for the front, back, top, and sides?
6. Air hoses in good condition without cracks/ damages.
7. Control valves in good condition
8. Is there any oil leakage
9. Drip tray provided
10. Fire extinguisher provided
11. Any damage/Cut in tires/ tire pressure
12. Meter gauge working properly
13. Lifting Hooks damaged
14. Battery of air compressor charged
15. Visible damage
16. Exhaust directed/ close to combustibles/ flammables
17. Exhaust not directed inside any room. (Internal Combustion Air Compressors shall be kept outside in the well-ventilated area)
18. Others specify:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / in charge : Signature:
Establishing exclusion zones • Personnel in area • Unauthorized access to test area;
• Workers struck by flying materials;
• Worker struck by High pressure water release;
Signage to test area • Personnel in area • Unauthorized access to test area;
• Inadequate signage to test area;
Pressure testing • High pressure to pipework; • Uncontrolled Stored Energy release;
• Rupture/failure in Pipe lines during testing;
• Valve/connection failure;
• Instrument failure resulting in system over-pressurization;
• End caps/plugs ejecting under high pressure;
• Weld/seal/fitting failure, flying objects;
• High pressure water/air injection.
Emergency procedures • High pressure to pipework; • Emergency procedures not briefed to task workers;
• Poor response in the event of an emergency;
Re-testing in the event of failure • Re-testing with high pressure • Injury due to uncontrolled testing;
• Worker injury due to working on pressurized system;
• Injury due to failure to ensure adequate pre-checks undertaken;
HSE INDUCTION
(Workers)
Name: _________________________________ Trade: ____________________________
M.B. No./Company Name : ________________
Date of Joining: __________________________
SL. N SUBJECT ON INDUCTION PREVIOUS SAFETY EXPOSURE FURTHER SAFETY TRAINING NEED ANALYSIS
1. Introduction Safety Requirements
2. Working Safety is of Primary Importance
3. General Safety Rules
4. Basic Safety Requirements
5. House Keeping
6. Health, Hygiene & Welfare Facilities
7. Fire Extinguisher / Fire Fighting
8. Emergency Procedure
9. Safety Violations & Penalty
10. Safety Award
11. Manual Handling
Induction Given By: Name: ___________________________
Designation: ___________________________
Solitis Electrical Solutions Pvt. Ltd. is multi-disciplined management and engineering consultancy in Pune, Maharashtra that provides complete electrical engineering design and project management services. We are also actively involved in trading of electrical equipment and components along with consultancy.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.