BUILDING MATERIALS
& CONSTRUCTIONS
POORNIMA COLLEGE OF ENGINEERING, JAIPUR
DEPARTMENT OF CIVIL ENGINEERING
Damp Proof Course
DIVYA VISHNOI
ASSISTANT PROFESSOR
CUASES OF DAMPNESS
Definition
“Dampness is the presence of hygroscopic
or gravitational moisture”
 Building should remain dry or free from moisture
travelling through waals, roofs and floors.
 Dampness gives un hygienic conditions apart from
reduction in strength of structural components.
 Provision of damp proof courses prevent entry of
moisture in the building.
(1) Moisture rising up the walls from ground.
a) All structures are founded on soils
b) If the soil is pervious, moisture constantly travels
through it.
c) Even in the impervious soil, lot of soil moisture may be
present.
d) This moisture rise up into wall & floor through capillary
action.
e) Ground water rise also result in moisture entry into the
building through walls.
(2) rain travel trough wall tops:
If the wall tops are not properly protected
from rain penetration, rain will enter the
wall & will travel down.
Leaking roofs will also permit water to
enter.
(3) Rain beating against external walls :
 Heavy showers of rain may beat against the external
faces of walls & if the walls are not properly treated,
moisture will enter the wall causing dampness in the
interior.
 If balconies and chajja projections do not have proper
slope, water will accumulate on these & will enter the
walls through their junctions.
 Moisture will completely damage interior paints of walls.
(4) Condensation
 Due to condensation of atmospheric moisture, water is
deposited on the walls, floors & ceilings.
 This moisture causes dampness.
EFFECTS OF DAMPNESS
Following are ill effects of entry of
dampness:
1. Dampness gives rise to breeding of mosquitoes &
create unhealthy conditions.
2. Travel of moisture on wall causes unsighty patches.
3. It may cause softening & crumling of plasters.
4. Wall decoration or paint is damaged.
5. Continuous presence of moisture in wall may cause
florescence which result in disintegration of bricks,
stones,tiles
EFFECTS OF DAMPNESS
6. Flooring gets loosened due to reduction in adhesion
when moisture enters through the floor.
7. Timber fittings such as doors, windows almira etc
coming in contact with damp walls, damp floors get
deteriorated because of warping etc.
8. Electrical fittings get deteriorated, giving rise to
leakage of electricity & danger of short shirtings.
9. Floor coverings are damaged.
10. Dampness promotes & accelerated growth of termites.
11. Dampness breeds germs of disease like tuberculosis,
neuralgia, rheumatism.
12. Moisture causes rusting & corrosion of metal fittings.
METHODS OF DAMP PROOFING
(1) use of damp proofing course (DPC) :
Membrane damp proofing.
(2) Integral Damp Proofing
(3) Surface Treatment
(4) Cavity wall construction
(5) Guniting
(6) Pressure Guniting
(1) Membrane Damp Proofing (Use of
DPC)
(1) Membrane Damp Proofing (Use of
DPC)
 In this method water repellent membrane or damp proof
course (DPC) between the source of dampness and
part of building adjacent to it.
 DPC may be bitumen, mastic asphalt, bituminous felts,
plastic sheet, metal sheets, cement concrete
 DPC may be provided horizontally or vertically in floors,
walls etc.
(1 ) Membrane Damp Proofing (Use of DPC)
Following general principles should be applied while
providing DPC:
a) DPC should cover full thickness of wall.
b) Mortar bed supporting DPC should be levelled & even and should
be free from projections, so that DPC is not damaged.
c) At junctions & corners of walls, the horizontal DPC (on floor)
should be laid continuous.
d) When a horizontal DPC is continued to vertical face, a cement
concrete fillet of 7.5 cm radius should be provided at junction.
e) DPC should not be kept exposed on wall surface otherwise it may
get damaged during finishing.
(2) INTEGRAL DAMP PROOFING
This consists of adding certain water proofing compounds of
materials to the concrete mix, so that it becomes impermeable
These water proofing compounds may be in three forms:
1. Compounds made from chalk, talk,fullers earth, which may fill the
voids of concrete under the mechanical action principle
2. Compounds like alkaline silicates, aluminium sulphate, calcium
chlorides etc which reacts chemically with concrete to produce
water proof concrete.
3. Compounds work on water repulsion principle. like soap,
petroleum, oils fatty acid compounds such as Stearates of calcium,
sodium, ammonia etc. When they are mixed with concrete
becomes water pepellant.
4. Commercially available compounds like Publo, Permo, Silka etc.
(3) SURFACE TREATMENT
 The surface treatment consists of application of layer of
water repellant substances on the surface through which
moisture enters.
 The use of water repellant metallic soaps such as
Calcium & Aluminium Oletes and Stearates are effective
against rain water penetration.
 Pointing & plastering of the exposed surfaces must be
done carefully using water proofing agents like Sodium
or Potassium silicates, Aluminium or Zinc sulphates,
Barrium hydroxide and magnassium sulphate.
 Surface treatment is successful when moisture is
superficial.
(4) Cavity Wall Construction
• In this method of damp prevention in
which main wall of building is sheilded by
an outer skin wall, leaving a cavity
between the two.
(5) Guniting
This consists of depositing layer of rich
cement mortar by pressure to the exposed
surface of wall, pipes.
Cement mortar is 1:3 cement sand mix.
Mortar is shot on clean surface with
cement gun under 2 to 3 kg/cm2 pressure.
Nozzle of machine is kept at a distance
about 75 to 90 cm from wall.
Curing of mortar is done for 10 days.
(6) Pressure Grouting
In this method, cement grout is filled in
cracks, voids in the structure of building by
pressure.
Foundation of building are subjected to
grouting to make water-penetration-
resistant.
This method is effective to control entry of
ground water through foundations
MATERIALS FOR DPC
• Ideal DPC should have following quality:
• Should be perfectly impervious
• Should not permit moisture penetration
• Material should be durable with life equal to
building life.
• Material should be strong to resist superimposed
load/ pressure.
• Material should be flexible to accommodate the
structural movements without any craks.
• Material should not be costly.
• Material should remain steady in its position.
MATERIALS FOR DPC
(1) Hot bitumen:
This is highly flexible.
Can be applied with a minimum thickness
of 3 mm.
It is placed on bedding of concrete in hot
condition
MATERIALS FOR DPC
(2) Mastic Asphalt
It is made by mixing bitumen & sand &
mineral fillers
It is semi rigid material.
It is squeezed out in hot climate or under
pressure.
MATERIALS FOR DPC
(3) Bituminous Asphalt:
 It is ready made roll of dry asphalt sheets
 It is laid on levelled flat layer of cement mortar.
 An overlap 10 cm provided at joints.
 The laps is sealed with bitumen.
 It can not resist heavy load.
 It can accommodate slight movement.
MATERIALS FOR DPC
(4)
Metal Sheets
 Sheets of lead,copper,aluminium is used as DPC.
 Lead sheet is more flexible.
 Thickness of sheet should be such that its weight is not
kless than 20 kg/m2.
 They are laid similar to bitumnous felts.
 Lead sheet is completely impervious, resistant to
atmospheric corrosion, can take complex shaperesistant
to sliding action.
MATERIALS FOR DPC
(4)
Metal Sheets
 Lead will have corrosion if comes in contact with
cement/lime. It is covered by bitumen.
 Copper Sheets of 3 mm thickness are embeded in
cement /lime mortar.
 It has high resistance to dampness, sliding and pressure.
 Aluminium sheets is also used for DPC but not better
than copper & lead.
MATERIALS FOR DPC
(5) Combination of sheets & bituminous felts
 Lead foils sandwiched between asphaltic or bitumious
felts cabn be used as DPC.
 The combination known as Lead Core can be laid easily,
is durable, efficient,economic & resistant to cracks.
MATERIALS FOR DPC
(6) Bricks
 Special bricks, having water absorption not less
than 4.5 % of their weight can be used as DPC
where dampness is excessive.
 Bricks are laid in 2 to 4 courses in cement
mortar.
 The joints of bricks are kept open.
MATERIALS FOR DPC
(7) Stones
 Dense & sound stones, such as granite,
trap,slates etc are laid in cement mortar 1:3 in
two layer to form effective DPC.
 Stone should be extended to full width of wall.
MATERIALS FOR DPC
(8) Mortar
 Cement mortar 1:3 is used as bedding layer for housing
other DPC.
 Small quantity of lime may be added to increase
workability of mortar.
 In water used for mixing, 75 gm soap is dissolved per
liter of water.
 This Mortar can be used for plaster of outer walls
MATERIALS FOR DPC
(9) Cement Concrete
 Concrete 1:2:4 mix or 1:11/2:3 mix is provided at
plinth level to work as DPC.
 The thickness may vary from 4 cm to 15 cm.
 This layer prevent water rise in wall by capillary
action.
 Where dampness is more two layer can be
made.
MATERIALS FOR DPC
(10) Plastic sheets
This is new type of DPC material made of
black polythene sheet of 0.5 mm to 1 mm
thickness.
Available in 30 m length in market.
The treatment is cheaper but not
permanent.
DPC Treatment in Buildings
(1) Treatment to foundations against gravitational water :
 Foundation may receive water percolating from adjacent ground
and this moisture may rise in walls.
 This can be checked by providing air drain parallel to the external
wall.
 The width of air drain may be about 20 to 30 cm.
 The outer wall of the drain is kept above ground to check the entry
of surface water.
 RCC cover is provided
 Openings with gratings are provided at regular interval for
passage of air.
 Usual DPC are also provided horizontally and vertically.
DPC Treatment in Buildings
(2) Treatment to basements
When basement in dump soils are constructed,
following methods are followed:
a) Provision of foundation drains and DPC.
b) Provision of RCC raft & slab.
c) Asphalt tanking
(2) Treatment to basements
a) Provision of foundation drains and DPC.
 When basement rests on soils which are not properly drained,
(such as peat soil ) great hydrostatic pressure is exerted and the
floor as well as wall receive water continuously oozing out.
 In such case it is necessary to make a trench all around upto
foundation level & fill it with gravel, coke,
 Open jointed drains may be provided to collect the underground
water.
 Drainage pipes,embeded in gravel bed, may also be provided
before foundation concrete.
 Horizontal & vertical DPC are provided in wall as well as
foundation concrete.
 Drain may have suitable longitudnal slope,ultimately draining
water into catch drain.
 Drain pipes under basement slab may be provided at some
interval.
(2) Treatment to basements
b) Provision of RCC raft
References
1) “Building Construction” authored by S.C. Rangwala,
Charotar publishing house Pvt. Ltd.
2) “Building Construction” authored by Bindra and Arora,
Dhanpat Rai publication.
3) “Building Construction” authored by M.L. Gambhir, Tata
Meghraw Hills publication.
Damp proof course
Damp proof course

More Related Content

What's hot

Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
Aglaia Connect
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTION
Ravindra Patnayaka
 

What's hot (20)

Plastering
PlasteringPlastering
Plastering
 
Brick bond
Brick bondBrick bond
Brick bond
 
Lintels
LintelsLintels
Lintels
 
Foundation
FoundationFoundation
Foundation
 
Chapter 8 floorings
Chapter 8 flooringsChapter 8 floorings
Chapter 8 floorings
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 
Doors and windows
Doors and windowsDoors and windows
Doors and windows
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Floors
FloorsFloors
Floors
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof covering
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
 
Walls
WallsWalls
Walls
 
Ground and upper floor
Ground and upper floorGround and upper floor
Ground and upper floor
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Lintels and arches in construction
Lintels and arches in constructionLintels and arches in construction
Lintels and arches in construction
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTION
 
Plaster
PlasterPlaster
Plaster
 
Brick masonary
Brick masonaryBrick masonary
Brick masonary
 
Mortars and Plasters
Mortars and PlastersMortars and Plasters
Mortars and Plasters
 

Similar to Damp proof course

Similar to Damp proof course (20)

Deterioration in building
Deterioration in buildingDeterioration in building
Deterioration in building
 
Dpc.pptx
Dpc.pptxDpc.pptx
Dpc.pptx
 
DPC, lintel and chajja yreuyfgfffff.pptx
DPC, lintel and chajja yreuyfgfffff.pptxDPC, lintel and chajja yreuyfgfffff.pptx
DPC, lintel and chajja yreuyfgfffff.pptx
 
Damp proofing
Damp proofingDamp proofing
Damp proofing
 
dampness in structure by umar khan
dampness in structure by umar khandampness in structure by umar khan
dampness in structure by umar khan
 
DPC (Damp Proof Course).pptx
DPC (Damp Proof Course).pptxDPC (Damp Proof Course).pptx
DPC (Damp Proof Course).pptx
 
7 building construction part 1 pre-construction work,dampness and doors - edit
7 building construction part 1   pre-construction work,dampness and doors - edit7 building construction part 1   pre-construction work,dampness and doors - edit
7 building construction part 1 pre-construction work,dampness and doors - edit
 
Damp proofing
Damp proofingDamp proofing
Damp proofing
 
Water leakage problem
Water leakage problem Water leakage problem
Water leakage problem
 
Dampness in building
Dampness in buildingDampness in building
Dampness in building
 
Bmc flooring
Bmc flooring   Bmc flooring
Bmc flooring
 
Damp proof course
Damp proof courseDamp proof course
Damp proof course
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
Shakshi Joshi.pptx
Shakshi Joshi.pptxShakshi Joshi.pptx
Shakshi Joshi.pptx
 
Workability of Concrete.ppt
Workability of Concrete.pptWorkability of Concrete.ppt
Workability of Concrete.ppt
 
Unit 5 bmc
Unit 5 bmcUnit 5 bmc
Unit 5 bmc
 
Crack repair in building construction
Crack repair in building constructionCrack repair in building construction
Crack repair in building construction
 
Workability of Concrete.ppt
Workability of Concrete.pptWorkability of Concrete.ppt
Workability of Concrete.ppt
 
Waterproofing in buildings
Waterproofing in buildingsWaterproofing in buildings
Waterproofing in buildings
 
Special Concrete - Concrete Technology
Special Concrete - Concrete TechnologySpecial Concrete - Concrete Technology
Special Concrete - Concrete Technology
 

More from Divya Vishnoi

More from Divya Vishnoi (20)

Understanding of Disasters
Understanding of DisastersUnderstanding of Disasters
Understanding of Disasters
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
 
Hydropower
HydropowerHydropower
Hydropower
 
Spillways
SpillwaysSpillways
Spillways
 
Failures of an earthen dam
Failures of an earthen damFailures of an earthen dam
Failures of an earthen dam
 
Force acting on gravity dam
Force acting on gravity damForce acting on gravity dam
Force acting on gravity dam
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
 
Theory for impervious floor
Theory for impervious floorTheory for impervious floor
Theory for impervious floor
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
 
Building foundation
Building foundationBuilding foundation
Building foundation
 
Temporary structures
Temporary structuresTemporary structures
Temporary structures
 
Mortar plaster pointing
Mortar plaster pointingMortar plaster pointing
Mortar plaster pointing
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
Brick masonry and stone masonry
Brick masonry and stone masonryBrick masonry and stone masonry
Brick masonry and stone masonry
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Tension coefficient method
Tension coefficient methodTension coefficient method
Tension coefficient method
 
IS 13827
IS 13827IS 13827
IS 13827
 
IS 13828
IS 13828IS 13828
IS 13828
 

Recently uploaded

Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
AbrahamGadissa
 

Recently uploaded (20)

Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 

Damp proof course

  • 1. ALLPPT.com _ Free PowerPoint Templates, Diagrams and Charts BUILDING MATERIALS & CONSTRUCTIONS POORNIMA COLLEGE OF ENGINEERING, JAIPUR DEPARTMENT OF CIVIL ENGINEERING Damp Proof Course DIVYA VISHNOI ASSISTANT PROFESSOR
  • 2. CUASES OF DAMPNESS Definition “Dampness is the presence of hygroscopic or gravitational moisture”  Building should remain dry or free from moisture travelling through waals, roofs and floors.  Dampness gives un hygienic conditions apart from reduction in strength of structural components.  Provision of damp proof courses prevent entry of moisture in the building.
  • 3. (1) Moisture rising up the walls from ground. a) All structures are founded on soils b) If the soil is pervious, moisture constantly travels through it. c) Even in the impervious soil, lot of soil moisture may be present. d) This moisture rise up into wall & floor through capillary action. e) Ground water rise also result in moisture entry into the building through walls.
  • 4. (2) rain travel trough wall tops: If the wall tops are not properly protected from rain penetration, rain will enter the wall & will travel down. Leaking roofs will also permit water to enter.
  • 5. (3) Rain beating against external walls :  Heavy showers of rain may beat against the external faces of walls & if the walls are not properly treated, moisture will enter the wall causing dampness in the interior.  If balconies and chajja projections do not have proper slope, water will accumulate on these & will enter the walls through their junctions.  Moisture will completely damage interior paints of walls.
  • 6. (4) Condensation  Due to condensation of atmospheric moisture, water is deposited on the walls, floors & ceilings.  This moisture causes dampness.
  • 7. EFFECTS OF DAMPNESS Following are ill effects of entry of dampness: 1. Dampness gives rise to breeding of mosquitoes & create unhealthy conditions. 2. Travel of moisture on wall causes unsighty patches. 3. It may cause softening & crumling of plasters. 4. Wall decoration or paint is damaged. 5. Continuous presence of moisture in wall may cause florescence which result in disintegration of bricks, stones,tiles
  • 8. EFFECTS OF DAMPNESS 6. Flooring gets loosened due to reduction in adhesion when moisture enters through the floor. 7. Timber fittings such as doors, windows almira etc coming in contact with damp walls, damp floors get deteriorated because of warping etc. 8. Electrical fittings get deteriorated, giving rise to leakage of electricity & danger of short shirtings. 9. Floor coverings are damaged. 10. Dampness promotes & accelerated growth of termites. 11. Dampness breeds germs of disease like tuberculosis, neuralgia, rheumatism. 12. Moisture causes rusting & corrosion of metal fittings.
  • 9. METHODS OF DAMP PROOFING (1) use of damp proofing course (DPC) : Membrane damp proofing. (2) Integral Damp Proofing (3) Surface Treatment (4) Cavity wall construction (5) Guniting (6) Pressure Guniting
  • 10. (1) Membrane Damp Proofing (Use of DPC) (1) Membrane Damp Proofing (Use of DPC)  In this method water repellent membrane or damp proof course (DPC) between the source of dampness and part of building adjacent to it.  DPC may be bitumen, mastic asphalt, bituminous felts, plastic sheet, metal sheets, cement concrete  DPC may be provided horizontally or vertically in floors, walls etc.
  • 11. (1 ) Membrane Damp Proofing (Use of DPC) Following general principles should be applied while providing DPC: a) DPC should cover full thickness of wall. b) Mortar bed supporting DPC should be levelled & even and should be free from projections, so that DPC is not damaged. c) At junctions & corners of walls, the horizontal DPC (on floor) should be laid continuous. d) When a horizontal DPC is continued to vertical face, a cement concrete fillet of 7.5 cm radius should be provided at junction. e) DPC should not be kept exposed on wall surface otherwise it may get damaged during finishing.
  • 12. (2) INTEGRAL DAMP PROOFING This consists of adding certain water proofing compounds of materials to the concrete mix, so that it becomes impermeable These water proofing compounds may be in three forms: 1. Compounds made from chalk, talk,fullers earth, which may fill the voids of concrete under the mechanical action principle 2. Compounds like alkaline silicates, aluminium sulphate, calcium chlorides etc which reacts chemically with concrete to produce water proof concrete. 3. Compounds work on water repulsion principle. like soap, petroleum, oils fatty acid compounds such as Stearates of calcium, sodium, ammonia etc. When they are mixed with concrete becomes water pepellant. 4. Commercially available compounds like Publo, Permo, Silka etc.
  • 13. (3) SURFACE TREATMENT  The surface treatment consists of application of layer of water repellant substances on the surface through which moisture enters.  The use of water repellant metallic soaps such as Calcium & Aluminium Oletes and Stearates are effective against rain water penetration.  Pointing & plastering of the exposed surfaces must be done carefully using water proofing agents like Sodium or Potassium silicates, Aluminium or Zinc sulphates, Barrium hydroxide and magnassium sulphate.  Surface treatment is successful when moisture is superficial.
  • 14. (4) Cavity Wall Construction • In this method of damp prevention in which main wall of building is sheilded by an outer skin wall, leaving a cavity between the two.
  • 15. (5) Guniting This consists of depositing layer of rich cement mortar by pressure to the exposed surface of wall, pipes. Cement mortar is 1:3 cement sand mix. Mortar is shot on clean surface with cement gun under 2 to 3 kg/cm2 pressure. Nozzle of machine is kept at a distance about 75 to 90 cm from wall. Curing of mortar is done for 10 days.
  • 16. (6) Pressure Grouting In this method, cement grout is filled in cracks, voids in the structure of building by pressure. Foundation of building are subjected to grouting to make water-penetration- resistant. This method is effective to control entry of ground water through foundations
  • 17. MATERIALS FOR DPC • Ideal DPC should have following quality: • Should be perfectly impervious • Should not permit moisture penetration • Material should be durable with life equal to building life. • Material should be strong to resist superimposed load/ pressure. • Material should be flexible to accommodate the structural movements without any craks. • Material should not be costly. • Material should remain steady in its position.
  • 18. MATERIALS FOR DPC (1) Hot bitumen: This is highly flexible. Can be applied with a minimum thickness of 3 mm. It is placed on bedding of concrete in hot condition
  • 19. MATERIALS FOR DPC (2) Mastic Asphalt It is made by mixing bitumen & sand & mineral fillers It is semi rigid material. It is squeezed out in hot climate or under pressure.
  • 20. MATERIALS FOR DPC (3) Bituminous Asphalt:  It is ready made roll of dry asphalt sheets  It is laid on levelled flat layer of cement mortar.  An overlap 10 cm provided at joints.  The laps is sealed with bitumen.  It can not resist heavy load.  It can accommodate slight movement.
  • 21. MATERIALS FOR DPC (4) Metal Sheets  Sheets of lead,copper,aluminium is used as DPC.  Lead sheet is more flexible.  Thickness of sheet should be such that its weight is not kless than 20 kg/m2.  They are laid similar to bitumnous felts.  Lead sheet is completely impervious, resistant to atmospheric corrosion, can take complex shaperesistant to sliding action.
  • 22. MATERIALS FOR DPC (4) Metal Sheets  Lead will have corrosion if comes in contact with cement/lime. It is covered by bitumen.  Copper Sheets of 3 mm thickness are embeded in cement /lime mortar.  It has high resistance to dampness, sliding and pressure.  Aluminium sheets is also used for DPC but not better than copper & lead.
  • 23. MATERIALS FOR DPC (5) Combination of sheets & bituminous felts  Lead foils sandwiched between asphaltic or bitumious felts cabn be used as DPC.  The combination known as Lead Core can be laid easily, is durable, efficient,economic & resistant to cracks.
  • 24. MATERIALS FOR DPC (6) Bricks  Special bricks, having water absorption not less than 4.5 % of their weight can be used as DPC where dampness is excessive.  Bricks are laid in 2 to 4 courses in cement mortar.  The joints of bricks are kept open.
  • 25. MATERIALS FOR DPC (7) Stones  Dense & sound stones, such as granite, trap,slates etc are laid in cement mortar 1:3 in two layer to form effective DPC.  Stone should be extended to full width of wall.
  • 26. MATERIALS FOR DPC (8) Mortar  Cement mortar 1:3 is used as bedding layer for housing other DPC.  Small quantity of lime may be added to increase workability of mortar.  In water used for mixing, 75 gm soap is dissolved per liter of water.  This Mortar can be used for plaster of outer walls
  • 27. MATERIALS FOR DPC (9) Cement Concrete  Concrete 1:2:4 mix or 1:11/2:3 mix is provided at plinth level to work as DPC.  The thickness may vary from 4 cm to 15 cm.  This layer prevent water rise in wall by capillary action.  Where dampness is more two layer can be made.
  • 28. MATERIALS FOR DPC (10) Plastic sheets This is new type of DPC material made of black polythene sheet of 0.5 mm to 1 mm thickness. Available in 30 m length in market. The treatment is cheaper but not permanent.
  • 29. DPC Treatment in Buildings (1) Treatment to foundations against gravitational water :  Foundation may receive water percolating from adjacent ground and this moisture may rise in walls.  This can be checked by providing air drain parallel to the external wall.  The width of air drain may be about 20 to 30 cm.  The outer wall of the drain is kept above ground to check the entry of surface water.  RCC cover is provided  Openings with gratings are provided at regular interval for passage of air.  Usual DPC are also provided horizontally and vertically.
  • 30. DPC Treatment in Buildings (2) Treatment to basements When basement in dump soils are constructed, following methods are followed: a) Provision of foundation drains and DPC. b) Provision of RCC raft & slab. c) Asphalt tanking
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36. (2) Treatment to basements a) Provision of foundation drains and DPC.  When basement rests on soils which are not properly drained, (such as peat soil ) great hydrostatic pressure is exerted and the floor as well as wall receive water continuously oozing out.  In such case it is necessary to make a trench all around upto foundation level & fill it with gravel, coke,  Open jointed drains may be provided to collect the underground water.  Drainage pipes,embeded in gravel bed, may also be provided before foundation concrete.  Horizontal & vertical DPC are provided in wall as well as foundation concrete.  Drain may have suitable longitudnal slope,ultimately draining water into catch drain.  Drain pipes under basement slab may be provided at some interval.
  • 37. (2) Treatment to basements b) Provision of RCC raft
  • 38. References 1) “Building Construction” authored by S.C. Rangwala, Charotar publishing house Pvt. Ltd. 2) “Building Construction” authored by Bindra and Arora, Dhanpat Rai publication. 3) “Building Construction” authored by M.L. Gambhir, Tata Meghraw Hills publication.