SlideShare a Scribd company logo
CAISSON FOUNDATION
INTRODUCTION
• The term caisson has been derived from the French
word ‘CAISSEE’, meaning BOX.
• It can be round or rectangle in plan.
• It is commonly used where foundation under water is
done.
• It can sunk from surface of either land or water to the
desired depth.
TYPES OF CAISSON
• Open caisson
• Box caisson
• Pneumatic caisson
OPEN CAISSON
• Also called as well caisson.
• They are open at both the ends.
• These are boxes of timber, steel or R.C or masonry.
• Small caisson consists of one opening or well, while
larger one contain a series of wells.
PROCEDURE
• The caisson is cast and flatted to the site and sunk.
• When it reaches the required depth concrete is
deposited through water to some depth.
• After the concrete gets hardened, the water will be
pumped out.
• The caisson is finally filled completely with concrete.
BOX CAISSON
• Also called as Floating caisson.
• They are open at top and closed at bottom.
• They can be made of steel, R.C or timber.
• The caisson is built on land, then launched and brought
to the site where they have to be sunk.
• They are filled with concrete or stone masonry and
sunk until it rests on the river bed, which has been
prepared to receive it, or on a pile cluster to form a
lower part of a bridge pier.
PROCEDURE
TOWING OF CAISSON
APPLICATIONS OF BOX CAISSON
• Bearing stratum is available at shallow depth
• Loads are not heavy
• For wharfs and break waters
PNEUMATIC CAISSON
• “Pneumatic" means "with air" “Caisson" means "a box“
• The pneumatic caisson method works on the same
principle as a cup pressed into some water upside
down
1.Preparation of the ground for installation
We level surface of working site where the
caisson is to be installed and improve the surface
conditions so that appropriate supporting force can be
supplied.
2.Construction of working chamber
We construct a working chamber at a bottom of
the caisson, in which earth is excavated and removed.
The chamber is pressurized to the same pressure as
the ground water pressure to make it watertight
EXECUTION OF THE PNEUMATIC CAISSON
3. Rigging
Cylindrical steel shafts are used for workers to
enter or exit the pressurized working chamber and to
remove excavated earth. These shafts have locks (for
both men and materials) to regulate the difference
between the atmospheric pressure on the ground and
the pressure in the chamber. Installation of such
locks and shafts is called "rigging work".
4. Repeated excavation to sink & construct
caisson
We excavate and construct the caisson every 4m
height, and repeatedly sink it by excavating the
ground and constructing it to the desired depth.
EXECUTION OF THE PNEUMATIC CAISSON
5. Testing the bearing capacity of soil
After the caisson has sunk to the specified depth,
we test and confirm that if sufficient bearing
capacity of soil has been obtained.
6. After concrete filling for working
chamber
After confirming the bearing capacity, we remove
equipments in the working chamber and fill
concrete, which means completion of works.
EXECUTION OF THE PNEUMATIC CAISSON
1.PREPARATION OF THE GROUND FOR
INSTALLATION
2.CONSTRUCTION OF WORKING
CHAMBER
3.RIGGING
4a.REPEATED EXCAVATING TO SINK
AND CONSTRUCT THE CAISSON
4b.REPEATED EXCAVATING TO SINK
AND CONSTRUCT THE CAISSON
5.TESTING THE BEARING CAPACITY OF
SOIL
6.AFTER CONCRETE FILLING FOR
WORKING CHAMBER
APPLICATIONS
The Pneumatic Caisson Method is used for many
different structures:
• Foundations of road and railway bridges
• Subway tunnels facilities
• Basements and foundations buildings
• Water supply and sewage facilities
• Other facilities (e.g. garbage pits)
FOUNDATIONS OF ROAD AND RAILWAY
BRIDGES
BRIDGES CONSTRUCTED AT THE
WATER DEPTH OF 50 TO 60 M.
SUBWAY TUNNELS FACILITIES
BASEMENT AND FOUNDATION BUILDINGS
(Eg. UNDERGROUND PARKING ZONES)
WATER SUPPLY AND SEWAGE FACILITIES
(Eg. TREATMENT PUMP BUILDING)
OTHER FACILITIES (E.G. GARBAGE PITS)
OTHER TYPES
There are few more methods in caisson foundation.
• Jacking caisson method
• Space System Caisson
JACKING CAISSON METHOD
Jacking caisson method is to sink large scale caisson
thruster into ground by using jacks with rods connected to
earth anchor.
Intake shaft of 14 meter ø. is thrusted in
the ground at 50.7 meter below by using
12 jacks of 240 ton thrust force. The
caisson itself is constructed on the
ground by each rot of 5 meter.
Dimension of 26x19 meter is sunk by 8
jacks in the ground depth 18.5 meter,
while inside of caisson is excavated by
clam shell
JACKING CAISSON METHOD
SPACE SYSTEM CAISSON
• The gravel is filled between wall
surface and ground, and the
skin friction resistance is
reduced.
• The SS caisson method gently
and accurately install the
caisson in non-loading.
• The problem of the conventional
open caisson method is solved.
FEATURES OF THE SS CAISSON METHOD
• It is gently installed only at the dead weight at the good
accuracy.
• Subsidence and collapse of the ground in the
circumference are not caused.
• It is applicable for various geology.

More Related Content

What's hot

River training works lecture
River training works lectureRiver training works lecture
River training works lecture
sarhad university peshawer
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
ajinkya gaikwad
 
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
VATSAL PATEL
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
Binu Karki
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
Divya Vishnoi
 
DAMS AND IT'S TYPES . . .
DAMS AND IT'S TYPES . . .DAMS AND IT'S TYPES . . .
DAMS AND IT'S TYPES . . .
Mohammad Sheraz Javed Awan
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-DewateringMoe Abadla
 
Canal
CanalCanal
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
GAURAV. H .TANDON
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
Vidhi Khokhani
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
KHUSHBU SHAH
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
Abid Khan
 
SHALLOW FOUNDATION
SHALLOW FOUNDATIONSHALLOW FOUNDATION
SHALLOW FOUNDATION
dhara dattani
 
Dewatering
DewateringDewatering
Dewatering
swetha110
 
Cofferdam
CofferdamCofferdam
Cofferdam
Shashank Namdeo
 
Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating Equipment
Kiran Goswami
 
Spillway and its types
Spillway and its typesSpillway and its types
Spillway and its types
Bilal Mirani
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
PrasannaRaniB
 
Well foundations notes
 Well foundations notes Well foundations notes
Well foundations notes
PRASANTHI PETLURU
 

What's hot (20)

River training works lecture
River training works lectureRiver training works lecture
River training works lecture
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
 
DAMS AND IT'S TYPES . . .
DAMS AND IT'S TYPES . . .DAMS AND IT'S TYPES . . .
DAMS AND IT'S TYPES . . .
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
Canal
CanalCanal
Canal
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
SHALLOW FOUNDATION
SHALLOW FOUNDATIONSHALLOW FOUNDATION
SHALLOW FOUNDATION
 
Dewatering
DewateringDewatering
Dewatering
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Excavating Equipment
Excavating EquipmentExcavating Equipment
Excavating Equipment
 
Spillway and its types
Spillway and its typesSpillway and its types
Spillway and its types
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
 
Well foundations notes
 Well foundations notes Well foundations notes
Well foundations notes
 

Viewers also liked

Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.pptTarique048
 
Type of caissons
Type of caissonsType of caissons
Type of caissons
AB MAKASANA
 
UNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTIONUNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTION
Hamsui Harold
 
Well foundation pdf
Well foundation pdfWell foundation pdf
Well foundation pdf
Alauddin aziz khan
 
Building construction redo
Building construction redoBuilding construction redo
Building construction redo
ZHALNJR
 
Raffles Institute_Foundations
Raffles Institute_FoundationsRaffles Institute_Foundations
Raffles Institute_Foundations
Sandra Draskovic
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwater
AJITA PANDEY
 
1008 caissons-specification
1008 caissons-specification1008 caissons-specification
1008 caissons-specification
Dr Fereidoun Dejahang
 
Osteochondritis dessicans ,caisson disease, caffey’s disease
Osteochondritis dessicans ,caisson disease, caffey’s diseaseOsteochondritis dessicans ,caisson disease, caffey’s disease
Osteochondritis dessicans ,caisson disease, caffey’s disease
airwave12
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
Er.Sunil Wasade
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Gautam Sharma
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
Sourabh Jain
 
Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundationAmiRul AFiq
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONS
jagrutib22
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
Alauddin aziz khan
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
Agnesh Shetty
 

Viewers also liked (20)

Driving process of caisson
Driving  process of  caissonDriving  process of  caisson
Driving process of caisson
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
 
Type of caissons
Type of caissonsType of caissons
Type of caissons
 
UNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTIONUNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTION
 
Well foundation pdf
Well foundation pdfWell foundation pdf
Well foundation pdf
 
Building construction redo
Building construction redoBuilding construction redo
Building construction redo
 
Caisson types
Caisson typesCaisson types
Caisson types
 
Raffles Institute_Foundations
Raffles Institute_FoundationsRaffles Institute_Foundations
Raffles Institute_Foundations
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwater
 
1008 caissons-specification
1008 caissons-specification1008 caissons-specification
1008 caissons-specification
 
Osteochondritis dessicans ,caisson disease, caffey’s disease
Osteochondritis dessicans ,caisson disease, caffey’s diseaseOsteochondritis dessicans ,caisson disease, caffey’s disease
Osteochondritis dessicans ,caisson disease, caffey’s disease
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Deep foundation
Deep foundationDeep foundation
Deep foundation
 
Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundation
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONS
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
 

Similar to 1.6 caisson

caissons.pptx
caissons.pptxcaissons.pptx
caissons.pptx
PavanNadgouda2
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
VATSAL PATEL
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
kushpatel927805
 
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil EngineeringCaissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
A Makwana
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
AkshayGhorpade19
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
ChinnuNinan
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniques
ShrideviAnil
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
VICTOR A. KIPLAGAT
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
Dave Chinmyee
 
Pile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction TechnologyPile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction Technology
A Makwana
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
HetviPatel58
 
BC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptxBC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptx
NisthaPathak2
 
pire and well.pptx
pire and  well.pptxpire and  well.pptx
pire and well.pptx
NisthaPathak2
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
DYPCET
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)
Jyoti Khatiwada
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
LovelyLavakumarLK
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
GAURAV. H .TANDON
 
underwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxunderwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptx
Jayachandran68
 
Well foundation
Well foundationWell foundation

Similar to 1.6 caisson (20)

caissons.pptx
caissons.pptxcaissons.pptx
caissons.pptx
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
 
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil EngineeringCaissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniques
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Pile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction TechnologyPile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction Technology
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
BC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptxBC-II lec 6 pierand deep fdn.pptx
BC-II lec 6 pierand deep fdn.pptx
 
pire and well.pptx
pire and  well.pptxpire and  well.pptx
pire and well.pptx
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
Presentation tos
Presentation tosPresentation tos
Presentation tos
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
underwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxunderwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptx
 
Well foundation
Well foundationWell foundation
Well foundation
 

Recently uploaded

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 

Recently uploaded (20)

Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 

1.6 caisson

  • 2. INTRODUCTION • The term caisson has been derived from the French word ‘CAISSEE’, meaning BOX. • It can be round or rectangle in plan. • It is commonly used where foundation under water is done. • It can sunk from surface of either land or water to the desired depth.
  • 3. TYPES OF CAISSON • Open caisson • Box caisson • Pneumatic caisson
  • 4. OPEN CAISSON • Also called as well caisson. • They are open at both the ends. • These are boxes of timber, steel or R.C or masonry. • Small caisson consists of one opening or well, while larger one contain a series of wells.
  • 5. PROCEDURE • The caisson is cast and flatted to the site and sunk. • When it reaches the required depth concrete is deposited through water to some depth. • After the concrete gets hardened, the water will be pumped out. • The caisson is finally filled completely with concrete.
  • 6. BOX CAISSON • Also called as Floating caisson. • They are open at top and closed at bottom. • They can be made of steel, R.C or timber.
  • 7. • The caisson is built on land, then launched and brought to the site where they have to be sunk. • They are filled with concrete or stone masonry and sunk until it rests on the river bed, which has been prepared to receive it, or on a pile cluster to form a lower part of a bridge pier. PROCEDURE
  • 9. APPLICATIONS OF BOX CAISSON • Bearing stratum is available at shallow depth • Loads are not heavy • For wharfs and break waters
  • 10. PNEUMATIC CAISSON • “Pneumatic" means "with air" “Caisson" means "a box“ • The pneumatic caisson method works on the same principle as a cup pressed into some water upside down
  • 11. 1.Preparation of the ground for installation We level surface of working site where the caisson is to be installed and improve the surface conditions so that appropriate supporting force can be supplied. 2.Construction of working chamber We construct a working chamber at a bottom of the caisson, in which earth is excavated and removed. The chamber is pressurized to the same pressure as the ground water pressure to make it watertight EXECUTION OF THE PNEUMATIC CAISSON
  • 12. 3. Rigging Cylindrical steel shafts are used for workers to enter or exit the pressurized working chamber and to remove excavated earth. These shafts have locks (for both men and materials) to regulate the difference between the atmospheric pressure on the ground and the pressure in the chamber. Installation of such locks and shafts is called "rigging work". 4. Repeated excavation to sink & construct caisson We excavate and construct the caisson every 4m height, and repeatedly sink it by excavating the ground and constructing it to the desired depth. EXECUTION OF THE PNEUMATIC CAISSON
  • 13. 5. Testing the bearing capacity of soil After the caisson has sunk to the specified depth, we test and confirm that if sufficient bearing capacity of soil has been obtained. 6. After concrete filling for working chamber After confirming the bearing capacity, we remove equipments in the working chamber and fill concrete, which means completion of works. EXECUTION OF THE PNEUMATIC CAISSON
  • 14. 1.PREPARATION OF THE GROUND FOR INSTALLATION
  • 17. 4a.REPEATED EXCAVATING TO SINK AND CONSTRUCT THE CAISSON
  • 18. 4b.REPEATED EXCAVATING TO SINK AND CONSTRUCT THE CAISSON
  • 19. 5.TESTING THE BEARING CAPACITY OF SOIL
  • 20. 6.AFTER CONCRETE FILLING FOR WORKING CHAMBER
  • 21. APPLICATIONS The Pneumatic Caisson Method is used for many different structures: • Foundations of road and railway bridges • Subway tunnels facilities • Basements and foundations buildings • Water supply and sewage facilities • Other facilities (e.g. garbage pits)
  • 22. FOUNDATIONS OF ROAD AND RAILWAY BRIDGES
  • 23. BRIDGES CONSTRUCTED AT THE WATER DEPTH OF 50 TO 60 M.
  • 25. BASEMENT AND FOUNDATION BUILDINGS (Eg. UNDERGROUND PARKING ZONES)
  • 26. WATER SUPPLY AND SEWAGE FACILITIES (Eg. TREATMENT PUMP BUILDING)
  • 27. OTHER FACILITIES (E.G. GARBAGE PITS)
  • 28. OTHER TYPES There are few more methods in caisson foundation. • Jacking caisson method • Space System Caisson
  • 29. JACKING CAISSON METHOD Jacking caisson method is to sink large scale caisson thruster into ground by using jacks with rods connected to earth anchor.
  • 30. Intake shaft of 14 meter ø. is thrusted in the ground at 50.7 meter below by using 12 jacks of 240 ton thrust force. The caisson itself is constructed on the ground by each rot of 5 meter. Dimension of 26x19 meter is sunk by 8 jacks in the ground depth 18.5 meter, while inside of caisson is excavated by clam shell JACKING CAISSON METHOD
  • 31. SPACE SYSTEM CAISSON • The gravel is filled between wall surface and ground, and the skin friction resistance is reduced. • The SS caisson method gently and accurately install the caisson in non-loading. • The problem of the conventional open caisson method is solved.
  • 32. FEATURES OF THE SS CAISSON METHOD • It is gently installed only at the dead weight at the good accuracy. • Subsidence and collapse of the ground in the circumference are not caused. • It is applicable for various geology.