SlideShare a Scribd company logo
COFFER DAM
Contents
 Definition
 Uses
 Selection of Coffer Dams
 Types of Coffer Dams
 Design features of coffer dams
 Leakage Prevention
 Economic Height
Definition
 Cofferdams are temporary enclosures to keep out water
and soil so as to permit dewatering and construction of
the permanent facility (structure) in the dry.
 A Coffer Dam is a temporary structure designed to keep
water and /or soil out of the excavation in which a
bridge pier or other structure is built.
 Meaning of Coffer Dam : Coffer = Box
 To take up the Foundation works in the Marine Region,
it is necessary to obstruct the water flow by means of
Coffer Dam.
PURPOSE TO USE COFFER DAM
STRUCTURE
 To retain Soil & Water
 Can be used as either Temporary or Permanent
 Main purpose is to provide dry working area for workers
 It is constructed to facilitate pile driving operations.
 It is used to place grillage as well as the raft foundations
 It is used ,when the foundations for piers and abutments of a bridge,
dams, locks, etc. are to be constructed.
 Some times it is also provided to store water temporarily.
 Cofferdams can be used in all the sectors as explained below.
 Civil Engineering: Underground Car Parking, Foundation,
Basement Construction
 Transport Engineering: Bridge Pier, Support Walls, Ramps,
Ground Water Retention, Tunnel Work etc.
 Water Engineering: Weirs, Culverts, Flood Protection
Walls, Scour Protection Walls, Securing Embankment etc.
 Port Construction: Dock Works, Jetty Works etc.
SELECTION OF TYPES OF COFFERDAMS
1. Low heads of water – earth fill cofferdams
2. Narrow Excavations – single wall sheet
pile cofferdams otherwise double wall
cofferdams or cellular sheet piling are
suitable for wide excavations
3. The materials available at site of work for
construction
4. The possibility of overtopping by floods,
tides, etc. and sliding – rock filled crib
cofferdams
5. The nature of bed on which the cofferdam is to rest –
deep deposits of soft clay, A heavy earth filled crib
or cellular cofferdam could not be suitable but
single wall sheet pile would be required in these
conditions.
6. The nature of velocity of flow,i.e. water flowing with
slow current or with swift current
7. The chances of bed erosion due to reduction of water
way caused by the construction of a cofferdam.
8. The facilities available for the transport of equipment
and material required for the construction of a
cofferdam.
Types of Coffer Dam
1.Earth fill cofferdams - mainly for low level water
2. Sand Bag Coffer Dam – to divert coarse of water
3.Rock fill cofferdams
4.Timber Crib or rock filled crib cofferdams -
Construction on land and than floated into place,
which is also known as Gravity Dam
5.Braced / Sheet Pile Coffer Dam- Consisting of Sheet
Piles, mainly used in shallow water depth
(i). Single wall coffer dams
(ii). Double wall coffer dams
(iii). Cellular cofferdams
6. Movable or suspended cofferdams
EARTH FILL COFFERDAMS
 Suitable for rivers or streams having shallow depth of
water, about 120 to 150 cm, with low velocity of flow
 It is the simplest type of cofferdam.
 Free board – 60 to 90 cm
 Top width of earth dyke – one meter
 Suitable side slope should be provided
 Provided suitable drain
 Its depends on soil availability and site conditions.
 Dry conditions – clay embankment provided
 Wet condition – sand materials suitable
ROCK FILL COFFERDAMS
 The construction of rock fill cofferdams is similar to
earth fill dams
 It can be constructed with steeper slopes
 Water depths – 3 m.
 In case of high heads of water , this can be achieved
by a clay or concrete care wall
 Impervious layer provided(concrete or caly corewall
or sheet pile ) for reducing entry of seepage
TIMBER CRIB OR ROCK FILLED CRIB
COFFERDAMS
 It consists of timber cribs made from logs of wood
 Constructed on land and floated into place
 It consists of a unit or a cell open at the bottom and
having the framework of horizontal timber members.
 Hollow space thus formed are then filled with rock or
gravel
 Depth of water – 10 to 20 m
 Used for wide excavation and rocky river bottoms
SHEET PILE COFFER DAM
1. Single wall cofferdams
-it used in places, where the area to be enclosed is very
small
-depth of water is more = 4.5 to 6 m
- A single row of sheet piles is provided on the whole length
of the cofferdam
- Guide piles, Wales and struts (wood)
- guide piles are first driven deep in the river bed and
spacing between them 1.8 to 3.0 m
- The sand bags are stacked on the inside and outside faces
of the sheet to increase the stability of cofferdam
Use of Guide Block to prevent
twisting of Sheet Piles
2. Double wall cofferdams
- when the area to be enclosed is large it is
necessary to provide double wall cofferdam
- The double wall cofferdams are of two types:
(i) Ohio – river type cofferdams
(ii) timber or steel sheeting cofferdams
3. Cellular Cofferdams
- The cellular cofferdams are mostly used for
dewatering large areas , where the depth of water may
be 19 to 21 m.
-Mostly used the constuction of marine structures like
Dams ,Locks etc.
- The two common shapes of the cellular cofferdam
are:
(i) Circular type
(ii) Diaphragm type
MOVABLE OR SUSPENDED
COFFERDAMS
 Where there are numbers of repetition
work in under water foundations ,such
as in the piers of multi span river bridges
, it is economical to design the
cofferdams to be moved as a single unit
from one foundation to another.
DESIGN FEATURES OF COFFERDAMS
 The design of a cofferdam depends on various factors such as.
(i).Hydrostatic head of Water
(ii).Dimensions of the area to be covered by the cofferdams
(iii).Subsoil conditions
(iv).Fluctuations or of outside water level
(v).Possibility of erosion
(vi).Presence of ice
(vii).Floating logs(the stem of a cut-down tree, etc.
 A purely theoretically designed cofferdam may fail
for factors unaccounted in its design.
 Therefore ,become necessary to combine practical
knowledge or experience with the theoretical aspects
in the design of a cofferdam.
 For width and Depth of cofferdam :
for H < 3 m, W = W
H > 3, W = 3 + ½*(H-3)
Where, W = Width of cofferdam in
metres
H = Height of water above river bed
in metres
Construction Sequence of
Coffer Dam :
1.Driving of Guide Frame
2.Lowering of Sheet Pile
3.Driving of Sheet Pile
4.Horizontal Bracing (Waller & Strut arrangement) to
withstand the load coming on sheet piles from outside.
5.Excavation and Plug in Concrete to resist uplift pressure
6.Reinforcement and Concrete work of the Permanent
Structure
COFFER DAM
• Factors governing the Economic Height of Coffer Dam
• 1.Depth of Water
- Low depth => Earthen Dam
- High Depth => Sheet Pile Coffer Dam
• 2.Current and nature of flowering of Sheet Pile
- High Current => Sheet Pile Coffer Dam
(Higher Seepage Control Capacity)
- Low Current => Earthen or any other Dam
(Less Seepage Control Capacity)
• 3.Type and Period of Work
- Short Duration Work => Timber Dam
- Long Duration work => Sheet Pile Coffer
Dam
• 4.High and Low Tide Level of Reservoir
- Sheet Pile must have top level slightly higher
than that of the HTL. So that even in
extreme case water can not over top the
coffer dam, to achieve the dry working
through out the season.
• 5.Scour Level of Reservoir
- Scour level can be considered as the bottom
most layer of the loose soil of river Bed Level.
- Up to Scour level there are chances of erosion
due to the current of water. In any Pile or Well
foundation, the care to be taken that the
founding level must be below the scour water
level
• 6.Type of Material to be used
- Structural Sheet pile is costly but can be reused
at different projects.
SHEET PILE COFFER DAM
• Some Photographs
GAMMON INDIA LIMITED
CABLE STAY BRIDGESURAT
AP-02 (EXCAVATION WORK)
Bracing welding work in
progress
SHEET PILE COFFER DAM
• Some Photographs
Coffer dam and its type
Coffer dam and its type
Coffer dam and its type
Coffer dam and its type
Coffer dam and its type
Coffer dam and its type
Coffer dam and its type

More Related Content

What's hot (20)

Settlement of soil/foundation
Settlement of soil/foundationSettlement of soil/foundation
Settlement of soil/foundation
 
Caisson
CaissonCaisson
Caisson
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
Gallery in Concrete Gravity Dam
Gallery in Concrete Gravity DamGallery in Concrete Gravity Dam
Gallery in Concrete Gravity Dam
 
Well foundation
Well foundationWell foundation
Well foundation
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
Vertical Drain
Vertical Drain Vertical Drain
Vertical Drain
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
Earthen Dam
Earthen DamEarthen Dam
Earthen Dam
 
Concept of floating foundation
Concept of floating foundationConcept of floating foundation
Concept of floating foundation
 
Soil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilSoil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton Soil
 
Reinforced earth structures
Reinforced earth structuresReinforced earth structures
Reinforced earth structures
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
Reinforced earth walls
Reinforced earth wallsReinforced earth walls
Reinforced earth walls
 
Failures of a earthen dam
Failures of a earthen damFailures of a earthen dam
Failures of a earthen dam
 
Lecture 3 foundation settlement
Lecture 3 foundation settlementLecture 3 foundation settlement
Lecture 3 foundation settlement
 
DIFFERENT TYPE OF SHALLOW FOUNDATION
DIFFERENT TYPE OF SHALLOW FOUNDATIONDIFFERENT TYPE OF SHALLOW FOUNDATION
DIFFERENT TYPE OF SHALLOW FOUNDATION
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 

Similar to Coffer dam and its type

Similar to Coffer dam and its type (20)

4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU
 
cofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptxcofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptx
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
 
Aravind B RGUKT Basar
Aravind B RGUKT BasarAravind B RGUKT Basar
Aravind B RGUKT Basar
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
Lesson4
Lesson4Lesson4
Lesson4
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Introduction to Dams.pptx
Introduction to Dams.pptxIntroduction to Dams.pptx
Introduction to Dams.pptx
 
underwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptxunderwater consruction VIII sem MMBC.pptx
underwater consruction VIII sem MMBC.pptx
 
Coffer dams
Coffer damsCoffer dams
Coffer dams
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Dams
DamsDams
Dams
 
Dams
DamsDams
Dams
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
First assignment group (2) presentation.pdf
First assignment group (2) presentation.pdfFirst assignment group (2) presentation.pdf
First assignment group (2) presentation.pdf
 

More from Gaurang Kakadiya

More from Gaurang Kakadiya (11)

Basic runway length
Basic runway lengthBasic runway length
Basic runway length
 
Earthquack 2001 Bhuj,Gujarat
Earthquack 2001 Bhuj,GujaratEarthquack 2001 Bhuj,Gujarat
Earthquack 2001 Bhuj,Gujarat
 
Non Destructive test
Non Destructive testNon Destructive test
Non Destructive test
 
Geotechnical engineering II
Geotechnical engineering IIGeotechnical engineering II
Geotechnical engineering II
 
Methods of in site Permeability Test
Methods of in site Permeability TestMethods of in site Permeability Test
Methods of in site Permeability Test
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
Admixtures
AdmixturesAdmixtures
Admixtures
 
Blasting equipment
Blasting equipmentBlasting equipment
Blasting equipment
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
Wind Energy Non Conventional Energy Sources
Wind Energy Non Conventional  Energy SourcesWind Energy Non Conventional  Energy Sources
Wind Energy Non Conventional Energy Sources
 

Recently uploaded

Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationDr. Radhey Shyam
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageRCC Institute of Information Technology
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectRased Khan
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptxfaamieahmd
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdfKamal Acharya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 

Recently uploaded (20)

Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptx
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdf
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 

Coffer dam and its type

  • 2. Contents  Definition  Uses  Selection of Coffer Dams  Types of Coffer Dams  Design features of coffer dams  Leakage Prevention  Economic Height
  • 3. Definition  Cofferdams are temporary enclosures to keep out water and soil so as to permit dewatering and construction of the permanent facility (structure) in the dry.  A Coffer Dam is a temporary structure designed to keep water and /or soil out of the excavation in which a bridge pier or other structure is built.  Meaning of Coffer Dam : Coffer = Box  To take up the Foundation works in the Marine Region, it is necessary to obstruct the water flow by means of Coffer Dam.
  • 4. PURPOSE TO USE COFFER DAM STRUCTURE  To retain Soil & Water  Can be used as either Temporary or Permanent  Main purpose is to provide dry working area for workers  It is constructed to facilitate pile driving operations.  It is used to place grillage as well as the raft foundations  It is used ,when the foundations for piers and abutments of a bridge, dams, locks, etc. are to be constructed.  Some times it is also provided to store water temporarily.
  • 5.  Cofferdams can be used in all the sectors as explained below.  Civil Engineering: Underground Car Parking, Foundation, Basement Construction  Transport Engineering: Bridge Pier, Support Walls, Ramps, Ground Water Retention, Tunnel Work etc.  Water Engineering: Weirs, Culverts, Flood Protection Walls, Scour Protection Walls, Securing Embankment etc.  Port Construction: Dock Works, Jetty Works etc.
  • 6. SELECTION OF TYPES OF COFFERDAMS 1. Low heads of water – earth fill cofferdams 2. Narrow Excavations – single wall sheet pile cofferdams otherwise double wall cofferdams or cellular sheet piling are suitable for wide excavations 3. The materials available at site of work for construction 4. The possibility of overtopping by floods, tides, etc. and sliding – rock filled crib cofferdams
  • 7. 5. The nature of bed on which the cofferdam is to rest – deep deposits of soft clay, A heavy earth filled crib or cellular cofferdam could not be suitable but single wall sheet pile would be required in these conditions. 6. The nature of velocity of flow,i.e. water flowing with slow current or with swift current 7. The chances of bed erosion due to reduction of water way caused by the construction of a cofferdam. 8. The facilities available for the transport of equipment and material required for the construction of a cofferdam.
  • 8. Types of Coffer Dam 1.Earth fill cofferdams - mainly for low level water 2. Sand Bag Coffer Dam – to divert coarse of water 3.Rock fill cofferdams 4.Timber Crib or rock filled crib cofferdams - Construction on land and than floated into place, which is also known as Gravity Dam 5.Braced / Sheet Pile Coffer Dam- Consisting of Sheet Piles, mainly used in shallow water depth (i). Single wall coffer dams (ii). Double wall coffer dams (iii). Cellular cofferdams 6. Movable or suspended cofferdams
  • 10.  Suitable for rivers or streams having shallow depth of water, about 120 to 150 cm, with low velocity of flow  It is the simplest type of cofferdam.  Free board – 60 to 90 cm  Top width of earth dyke – one meter  Suitable side slope should be provided  Provided suitable drain  Its depends on soil availability and site conditions.  Dry conditions – clay embankment provided  Wet condition – sand materials suitable
  • 12.  The construction of rock fill cofferdams is similar to earth fill dams  It can be constructed with steeper slopes  Water depths – 3 m.  In case of high heads of water , this can be achieved by a clay or concrete care wall  Impervious layer provided(concrete or caly corewall or sheet pile ) for reducing entry of seepage
  • 13. TIMBER CRIB OR ROCK FILLED CRIB COFFERDAMS
  • 14.  It consists of timber cribs made from logs of wood  Constructed on land and floated into place  It consists of a unit or a cell open at the bottom and having the framework of horizontal timber members.  Hollow space thus formed are then filled with rock or gravel  Depth of water – 10 to 20 m  Used for wide excavation and rocky river bottoms
  • 15. SHEET PILE COFFER DAM 1. Single wall cofferdams -it used in places, where the area to be enclosed is very small -depth of water is more = 4.5 to 6 m - A single row of sheet piles is provided on the whole length of the cofferdam - Guide piles, Wales and struts (wood) - guide piles are first driven deep in the river bed and spacing between them 1.8 to 3.0 m - The sand bags are stacked on the inside and outside faces of the sheet to increase the stability of cofferdam
  • 16.
  • 17. Use of Guide Block to prevent twisting of Sheet Piles
  • 18.
  • 19. 2. Double wall cofferdams - when the area to be enclosed is large it is necessary to provide double wall cofferdam - The double wall cofferdams are of two types: (i) Ohio – river type cofferdams (ii) timber or steel sheeting cofferdams
  • 20.
  • 21.
  • 22.
  • 23. 3. Cellular Cofferdams - The cellular cofferdams are mostly used for dewatering large areas , where the depth of water may be 19 to 21 m. -Mostly used the constuction of marine structures like Dams ,Locks etc. - The two common shapes of the cellular cofferdam are: (i) Circular type (ii) Diaphragm type
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29. MOVABLE OR SUSPENDED COFFERDAMS  Where there are numbers of repetition work in under water foundations ,such as in the piers of multi span river bridges , it is economical to design the cofferdams to be moved as a single unit from one foundation to another.
  • 30. DESIGN FEATURES OF COFFERDAMS  The design of a cofferdam depends on various factors such as. (i).Hydrostatic head of Water (ii).Dimensions of the area to be covered by the cofferdams (iii).Subsoil conditions (iv).Fluctuations or of outside water level (v).Possibility of erosion (vi).Presence of ice (vii).Floating logs(the stem of a cut-down tree, etc.
  • 31.  A purely theoretically designed cofferdam may fail for factors unaccounted in its design.  Therefore ,become necessary to combine practical knowledge or experience with the theoretical aspects in the design of a cofferdam.  For width and Depth of cofferdam : for H < 3 m, W = W H > 3, W = 3 + ½*(H-3) Where, W = Width of cofferdam in metres H = Height of water above river bed in metres
  • 32. Construction Sequence of Coffer Dam : 1.Driving of Guide Frame 2.Lowering of Sheet Pile 3.Driving of Sheet Pile 4.Horizontal Bracing (Waller & Strut arrangement) to withstand the load coming on sheet piles from outside. 5.Excavation and Plug in Concrete to resist uplift pressure 6.Reinforcement and Concrete work of the Permanent Structure
  • 33. COFFER DAM • Factors governing the Economic Height of Coffer Dam • 1.Depth of Water - Low depth => Earthen Dam - High Depth => Sheet Pile Coffer Dam • 2.Current and nature of flowering of Sheet Pile - High Current => Sheet Pile Coffer Dam (Higher Seepage Control Capacity) - Low Current => Earthen or any other Dam (Less Seepage Control Capacity)
  • 34. • 3.Type and Period of Work - Short Duration Work => Timber Dam - Long Duration work => Sheet Pile Coffer Dam • 4.High and Low Tide Level of Reservoir - Sheet Pile must have top level slightly higher than that of the HTL. So that even in extreme case water can not over top the coffer dam, to achieve the dry working through out the season.
  • 35. • 5.Scour Level of Reservoir - Scour level can be considered as the bottom most layer of the loose soil of river Bed Level. - Up to Scour level there are chances of erosion due to the current of water. In any Pile or Well foundation, the care to be taken that the founding level must be below the scour water level • 6.Type of Material to be used - Structural Sheet pile is costly but can be reused at different projects.
  • 36.
  • 37. SHEET PILE COFFER DAM • Some Photographs
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.
  • 44.
  • 45.
  • 46. GAMMON INDIA LIMITED CABLE STAY BRIDGESURAT AP-02 (EXCAVATION WORK)
  • 47. Bracing welding work in progress
  • 48.
  • 49.
  • 50.
  • 51. SHEET PILE COFFER DAM • Some Photographs

Editor's Notes

  1. 10/18/10
  2. 10/18/10