SlideShare a Scribd company logo
1 of 53
 INTRODUCTION
 OBJECTIVE
 TYPES OF COFFERDAM
 FACTOR AFFECTING DESIGN OF COFFERDAM
ADVANTAGES
 The word "cofferdam" comes from "coffer" meaning
box, in other words a dam in the shape of a box.
A cofferdam is a temporary structure designed to
keep water and/or soil out of the excavation in
which a bridge pier or other structure is built.
A cofferdam involves the interaction of the structure,
soil, and water and the loads imposed include the
hydrostatic forces of the water, as well as the
dynamic forces due to currents and waves.
 The loads imposed on the cofferdam structure by
construction equipment and operations must be
considered, both during installation of the cofferdam
and during construction of the structure itself.
The main objectives of temporary structure
“COFFERDAM” are :-
Pile driving operation.
Place grillage & raft foundation.
Construct new structures.
Enclose space for removal.
Constructing without disturbances.
1. Braced: It is formed from a single
wall of sheet piling which
is driven into the ground to form a
“box” around the excavation site.
2. Earth-Type: It is the simplest type of cofferdam. It consists of an
earth bank with a lay core or vertical sheet piling enclosing the
excavation.
3. Timber Crib: Constructed on land and floated into
place. Lower portion of each cell is matched with
contour of river.
4. Double-Walled Sheet Pile: They are double wall
cofferdams comprising two parallel rows of sheet
piles driven into the ground and connected together
by a system of tie rod sat one or more levels.
5. Cellular: Cellular cofferdams are used only in those
circumstances where the excavation size precludes the
use of cross-excavation bracing. In this case, the
cofferdam must be stable by virtue of its own
resistance to lateral forces.
Working inside a cofferdam
Hydrostatic head of water
Dimensions of area.
Sub-soil condition.
Fluctuations of outside water level.
Possibility of erosion.
Presence of ice.
Work possible in poor environment.
Safe environment for workers.
Design responsibility
Easy work.
Re-usability of materials.
Cofferdams are temporary structures and
used in cases where the plan area of
foundation is very large, depth of water is less
and for the soft soils, where soils allow easy
driving of sheet piles.
Well Foundations
( Caissons )
 Well foundations are being used in India from
very early days.
 Taj Mahal was built on such foundations.
 Wells are classified as deep foundations.
 The main difference between a well and a pile
foundation:
 Pile is flexible like a beam under horizontal
loads
 well undergoes rigid body movement under
such loads
Wells have different shapes and
accordingly they are named as
( According to shape in plan)
• Circular Wells
• Dumb bell
• Double-D Wells
• Double Octagonal Wells
• Single and Double Rectangular Wells
• Multiple Dredged Holed Wells
( According to Material Used for Construction)
• Wood
• Steel
• Reinforced Concrete
Classification according to shape in cross section
Classification according to cutting edge type
• Large diameter, can be extended up to large depths.
• Similar to piles, but shorter
• If large bearing capacity soil (rock) is between 3-7 m, it can be
very effective
• If loads are not too large, but the upper 3-7 m of the soil is not
appropriate, can be applied effectively
• Cost of Construction is relatively less on bed level or lower
side.
• Since the placing of concrete is done for concrete seal
under water, it may not be satisfactory.
• If any obstruction of boulders or logs are encountered,
then progress of work becomes slow.
• Through cleaning and inspection at the bottom of
caisson is very difficult and hence not possible.
• The help of divers may be required for excavation near
haunches at the cutting edges.
The various component of
a well foundations are
1. Cutting Edge
2. Well Curb
3. Bottom Plug
4. Steining
5. Top Plug
6. Well Cap
Open Caisson
Cutting Edge:
• Sharp edge which is provided at the lower end of the
well or open and pneumatic caisson for accelerating
sinking operation is called cutting edge. It is made up
steel or it is made in R.C.C. Its angle to vertical is 30 0
and normally slope of 1 horizontal to 2 vertical given
better result.
• In concrete caissons, the lower part of the cutting
edge is rigidly fastened with 12 mm steel plates.
• The cutting edge should be sharp so as to penetrate
into the soil and it should resist the various stresses
caused by blows, boulders, blasting, etc.
• A sharp vertical edge is generally provided to the
outside face of the caisson. Edge facilities the rate of
sinking.
Well Curbs
• It is made of concrete or brick.
• Cutting edge of well or caisson is attached to well
curb.
• During sinking operation well curb impart to the
well steining and facilities the formation of bottom
Bottom Plug
• After final grounding of
the well to the required
foundation level, a
concrete plug is provided.
• The bottom plug transfer the
entire load to the ground.
• The bottom plug functions
as an inverted dome
supported along the periphery
of the steining.
• As it is not feasible to
provide reinforcement at the
bottom, it is generally made
thick and a rich concrete
mix (M20) is used.
Sand Filling
The bottom plug concrete is
cured and after curing, the well is
filled with sand in saturated
condition. Sand filling provides
1. Stability to the bottom of the well.
2. Eliminate the tensile forces at the
base
3. Cancels hoop stresses steining
induced in
Steining
• Steining is constructed in concrete or
masonry work.
• Use of steining is to provide dead load
during sinking operation.
Topping
• Covering provided over the well or caisson
is called as topping.
• Sand is filled in between topping and
bottom plug. Topping also acts as a part of
shuttering for laying the well cap.
Top Plug• The top plug is provided
after the filling is
completed.
• Top plug helps in transferring
the load of the pier and
superstructure to the
steining.
• The thickness of the top
plug is generally kept
greater than 50 % of the smaller
dimension of the dredge hole.
• If sand filling is used, the top
plug is simply constructed using
PCC of 1:2:4 otherwise it is
reinforced with steel bars and
lean concrete of 1:3:6 is used.
Well Cap
• As the shape of the well pier and cap are different, the
well cap forms an interim (acting) layer to accommodate
the pier.
• The well cap is so designed that the base of the pier is
provided with aminimum all round offset.
• The centre of the well cap is made to
coincide with that of the pier and not with
that of the well.
• Such positioning nullifies the effect of the
minor shifts which might have occurred
during well sinking.
Construction
Sequences
Well foundation> construction sequences
A well foundation supporting a bridge pier is
subjected to vertical and horizontal forces. The
various forces acting on the well are
1. Self weight of the well and its superstructure
2. Live loads
3. Water currents and buoyancy
4. Temperature, wind and earth quake
5. Breaking and tracking forces
6. Resistance of the well walls
7. Base and skin friction
The IRC and IS 3955 publications recommend
the following procedure for design of well
foundations in sand deposits (for clay the
expressions should be suitably modified)
1 Check the stability of well under working
loads, assuming elastic theory
2. Find the factor of safety of the well against ultimate
failure using ultimate load theory
Design of wells basically involves finding
1. Depth of the well
2. Size of the well and
3. Design of the other components.
1. Non uniform bearing capacity
2. Obstruction on one side of the well
3. Sand blowing in wells during sinking. It will cause sudden
sinking of well
4. Method of sinking: Material should be removed from all sides
equally otherwise the well may experience tilt
5. Sudden sinking due to blasting may also cause tilting of well
6. Irregular casting of steining will cause less friction on one side
leads to chances of tilting of well.
Precautions to be taken to avoid tilts and shift
• The cutting edge of caisson must be thick and sharp
pointed
• The external surface of steining and caisson curb should be
smooth.
• Dredging should be done uniformly on all sides and in all
pockets of caisson.
• Caisson should be symmetrically placed.
• The diameter (D) of the curb must be placed from 40 mm to
80 mm or larger or more than external diameter of steining.
1. Eccentric grabbing
2. Eccentric loading
3. Water jetting
4. Arresting the cutting edge
5. Pulling the well
6. Strutting the well
7. Pushing the well by jacks
Pushing the caissons or well with jack:
Eccentric loading
Water jetting
Providing temporary obstacles below the cutting edge:
Pulling the well or caisson
Strutting the caissons or well
Caisson Diseases
In case of sinking process of pneumatic caisson, workers or
workmen have to work in working chamber under compressed
air. If the compressed air pressure is less than 0.35 N/mm 2 to
0.4 N/ mm 2, then workmen may suffer from the following
pains:
 Workmen may suffer from giddiness
 There is pains in ears of workmen
 There is breaking of ear drums of workmen
 There is bursting of blood vessels in the nose or ears of workmen
 The above mentioned pains are not that serious or fatal, but
workmen is actually suffering during decompression and effect
causing depression is called caisson disease.
Following are the caisson disease caused by decompression:
 Severe pains in joints leading to bends
 It may cause paralytic death
 Excessive oxygen get absorbed in the blood may cause bursting
of vessels.
 If bubbles are developed in joints it causes bends
 If the bubbles are developed in spinal cord, it causes paralysis
and if the bubble are developed in heart, it causes heart attack.
 Caisson diseases can be controlled by recompression followed
by slow decompression.

More Related Content

What's hot (20)

Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Mixing of concrete.pptx
Mixing of concrete.pptxMixing of concrete.pptx
Mixing of concrete.pptx
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc building
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Production of concrete
Production of concreteProduction of concrete
Production of concrete
 
Shoring
ShoringShoring
Shoring
 
Caisson
CaissonCaisson
Caisson
 
Caissons
Caissons Caissons
Caissons
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Form Work
Form Work Form Work
Form Work
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
BCT MODULE 2 - Caisson
BCT MODULE 2 - CaissonBCT MODULE 2 - Caisson
BCT MODULE 2 - Caisson
 

Similar to Chapter 4.2 coffer dam, well foundation-final1

caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructionChinnuNinan
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptxJackRider12
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTUVATSAL PATEL
 
CASSION AND COFFER DAM.pptx
CASSION AND COFFER DAM.pptxCASSION AND COFFER DAM.pptx
CASSION AND COFFER DAM.pptxnileshsurti
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniquesShrideviAnil
 
shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdfSaimHaq
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsMitaliShelke
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptxAkshayGhorpade19
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
Aravind B RGUKT Basar
Aravind B RGUKT BasarAravind B RGUKT Basar
Aravind B RGUKT BasarARAVINDBORRA1
 

Similar to Chapter 4.2 coffer dam, well foundation-final1 (20)

Cofferdam
CofferdamCofferdam
Cofferdam
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Well foundation
Well foundationWell foundation
Well foundation
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
Lesson4
Lesson4Lesson4
Lesson4
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
 
CASSION AND COFFER DAM.pptx
CASSION AND COFFER DAM.pptxCASSION AND COFFER DAM.pptx
CASSION AND COFFER DAM.pptx
 
caissons.pptx
caissons.pptxcaissons.pptx
caissons.pptx
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniques
 
shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdf
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
Shaft
Shaft Shaft
Shaft
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
WELL COMPLETIONS.pptx
WELL COMPLETIONS.pptxWELL COMPLETIONS.pptx
WELL COMPLETIONS.pptx
 
Aravind B RGUKT Basar
Aravind B RGUKT BasarAravind B RGUKT Basar
Aravind B RGUKT Basar
 

More from DYPCET

Design of concrete structures-I- Design Steps
Design of concrete structures-I- Design StepsDesign of concrete structures-I- Design Steps
Design of concrete structures-I- Design StepsDYPCET
 
Chapter 6 earth pressure
Chapter 6 earth pressureChapter 6 earth pressure
Chapter 6 earth pressureDYPCET
 
Chapter 3 compaction and consolidation
Chapter 3 compaction and consolidationChapter 3 compaction and consolidation
Chapter 3 compaction and consolidationDYPCET
 
Modern trends in optimization techniques
Modern trends in optimization techniquesModern trends in optimization techniques
Modern trends in optimization techniquesDYPCET
 
Productivity tools for students
Productivity tools for studentsProductivity tools for students
Productivity tools for studentsDYPCET
 
Emotional intelligence at glance
Emotional intelligence at glanceEmotional intelligence at glance
Emotional intelligence at glanceDYPCET
 
Unit 2 building planning-final
Unit 2 building planning-finalUnit 2 building planning-final
Unit 2 building planning-finalDYPCET
 
Unit 1-introduction to civil engg final
Unit 1-introduction to civil engg finalUnit 1-introduction to civil engg final
Unit 1-introduction to civil engg finalDYPCET
 
BCE assignments
BCE assignmentsBCE assignments
BCE assignmentsDYPCET
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design stepsDYPCET
 
Assignments 1 to 8
Assignments 1 to 8Assignments 1 to 8
Assignments 1 to 8DYPCET
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notesDYPCET
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement DYPCET
 
Chapter 1.0 soil exploration
Chapter 1.0   soil explorationChapter 1.0   soil exploration
Chapter 1.0 soil explorationDYPCET
 
Section 2-gte-i
Section  2-gte-iSection  2-gte-i
Section 2-gte-iDYPCET
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notesDYPCET
 

More from DYPCET (16)

Design of concrete structures-I- Design Steps
Design of concrete structures-I- Design StepsDesign of concrete structures-I- Design Steps
Design of concrete structures-I- Design Steps
 
Chapter 6 earth pressure
Chapter 6 earth pressureChapter 6 earth pressure
Chapter 6 earth pressure
 
Chapter 3 compaction and consolidation
Chapter 3 compaction and consolidationChapter 3 compaction and consolidation
Chapter 3 compaction and consolidation
 
Modern trends in optimization techniques
Modern trends in optimization techniquesModern trends in optimization techniques
Modern trends in optimization techniques
 
Productivity tools for students
Productivity tools for studentsProductivity tools for students
Productivity tools for students
 
Emotional intelligence at glance
Emotional intelligence at glanceEmotional intelligence at glance
Emotional intelligence at glance
 
Unit 2 building planning-final
Unit 2 building planning-finalUnit 2 building planning-final
Unit 2 building planning-final
 
Unit 1-introduction to civil engg final
Unit 1-introduction to civil engg finalUnit 1-introduction to civil engg final
Unit 1-introduction to civil engg final
 
BCE assignments
BCE assignmentsBCE assignments
BCE assignments
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
 
Assignments 1 to 8
Assignments 1 to 8Assignments 1 to 8
Assignments 1 to 8
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement
 
Chapter 1.0 soil exploration
Chapter 1.0   soil explorationChapter 1.0   soil exploration
Chapter 1.0 soil exploration
 
Section 2-gte-i
Section  2-gte-iSection  2-gte-i
Section 2-gte-i
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 

Chapter 4.2 coffer dam, well foundation-final1

  • 1.
  • 2.  INTRODUCTION  OBJECTIVE  TYPES OF COFFERDAM  FACTOR AFFECTING DESIGN OF COFFERDAM ADVANTAGES
  • 3.  The word "cofferdam" comes from "coffer" meaning box, in other words a dam in the shape of a box. A cofferdam is a temporary structure designed to keep water and/or soil out of the excavation in which a bridge pier or other structure is built. A cofferdam involves the interaction of the structure, soil, and water and the loads imposed include the hydrostatic forces of the water, as well as the dynamic forces due to currents and waves.
  • 4.  The loads imposed on the cofferdam structure by construction equipment and operations must be considered, both during installation of the cofferdam and during construction of the structure itself.
  • 5. The main objectives of temporary structure “COFFERDAM” are :- Pile driving operation. Place grillage & raft foundation. Construct new structures. Enclose space for removal. Constructing without disturbances.
  • 6. 1. Braced: It is formed from a single wall of sheet piling which is driven into the ground to form a “box” around the excavation site. 2. Earth-Type: It is the simplest type of cofferdam. It consists of an earth bank with a lay core or vertical sheet piling enclosing the excavation.
  • 7. 3. Timber Crib: Constructed on land and floated into place. Lower portion of each cell is matched with contour of river. 4. Double-Walled Sheet Pile: They are double wall cofferdams comprising two parallel rows of sheet piles driven into the ground and connected together by a system of tie rod sat one or more levels.
  • 8. 5. Cellular: Cellular cofferdams are used only in those circumstances where the excavation size precludes the use of cross-excavation bracing. In this case, the cofferdam must be stable by virtue of its own resistance to lateral forces.
  • 9. Working inside a cofferdam
  • 10. Hydrostatic head of water Dimensions of area. Sub-soil condition. Fluctuations of outside water level. Possibility of erosion. Presence of ice.
  • 11. Work possible in poor environment. Safe environment for workers. Design responsibility Easy work. Re-usability of materials.
  • 12. Cofferdams are temporary structures and used in cases where the plan area of foundation is very large, depth of water is less and for the soft soils, where soils allow easy driving of sheet piles.
  • 14.  Well foundations are being used in India from very early days.  Taj Mahal was built on such foundations.  Wells are classified as deep foundations.  The main difference between a well and a pile foundation:  Pile is flexible like a beam under horizontal loads  well undergoes rigid body movement under such loads
  • 15.
  • 16. Wells have different shapes and accordingly they are named as ( According to shape in plan) • Circular Wells • Dumb bell • Double-D Wells • Double Octagonal Wells • Single and Double Rectangular Wells • Multiple Dredged Holed Wells ( According to Material Used for Construction) • Wood • Steel • Reinforced Concrete
  • 17.
  • 18.
  • 19. Classification according to shape in cross section Classification according to cutting edge type
  • 20. • Large diameter, can be extended up to large depths. • Similar to piles, but shorter • If large bearing capacity soil (rock) is between 3-7 m, it can be very effective • If loads are not too large, but the upper 3-7 m of the soil is not appropriate, can be applied effectively • Cost of Construction is relatively less on bed level or lower side.
  • 21. • Since the placing of concrete is done for concrete seal under water, it may not be satisfactory. • If any obstruction of boulders or logs are encountered, then progress of work becomes slow. • Through cleaning and inspection at the bottom of caisson is very difficult and hence not possible. • The help of divers may be required for excavation near haunches at the cutting edges.
  • 22.
  • 23. The various component of a well foundations are 1. Cutting Edge 2. Well Curb 3. Bottom Plug 4. Steining 5. Top Plug 6. Well Cap
  • 24.
  • 26. Cutting Edge: • Sharp edge which is provided at the lower end of the well or open and pneumatic caisson for accelerating sinking operation is called cutting edge. It is made up steel or it is made in R.C.C. Its angle to vertical is 30 0 and normally slope of 1 horizontal to 2 vertical given better result. • In concrete caissons, the lower part of the cutting edge is rigidly fastened with 12 mm steel plates. • The cutting edge should be sharp so as to penetrate into the soil and it should resist the various stresses caused by blows, boulders, blasting, etc. • A sharp vertical edge is generally provided to the outside face of the caisson. Edge facilities the rate of sinking.
  • 27. Well Curbs • It is made of concrete or brick. • Cutting edge of well or caisson is attached to well curb. • During sinking operation well curb impart to the well steining and facilities the formation of bottom
  • 28. Bottom Plug • After final grounding of the well to the required foundation level, a concrete plug is provided. • The bottom plug transfer the entire load to the ground. • The bottom plug functions as an inverted dome supported along the periphery of the steining. • As it is not feasible to provide reinforcement at the bottom, it is generally made thick and a rich concrete mix (M20) is used.
  • 29. Sand Filling The bottom plug concrete is cured and after curing, the well is filled with sand in saturated condition. Sand filling provides 1. Stability to the bottom of the well. 2. Eliminate the tensile forces at the base 3. Cancels hoop stresses steining induced in
  • 30. Steining • Steining is constructed in concrete or masonry work. • Use of steining is to provide dead load during sinking operation. Topping • Covering provided over the well or caisson is called as topping. • Sand is filled in between topping and bottom plug. Topping also acts as a part of shuttering for laying the well cap.
  • 31. Top Plug• The top plug is provided after the filling is completed. • Top plug helps in transferring the load of the pier and superstructure to the steining. • The thickness of the top plug is generally kept greater than 50 % of the smaller dimension of the dredge hole. • If sand filling is used, the top plug is simply constructed using PCC of 1:2:4 otherwise it is reinforced with steel bars and lean concrete of 1:3:6 is used.
  • 32. Well Cap • As the shape of the well pier and cap are different, the well cap forms an interim (acting) layer to accommodate the pier. • The well cap is so designed that the base of the pier is provided with aminimum all round offset. • The centre of the well cap is made to coincide with that of the pier and not with that of the well. • Such positioning nullifies the effect of the minor shifts which might have occurred during well sinking.
  • 35.
  • 36. A well foundation supporting a bridge pier is subjected to vertical and horizontal forces. The various forces acting on the well are 1. Self weight of the well and its superstructure 2. Live loads 3. Water currents and buoyancy 4. Temperature, wind and earth quake 5. Breaking and tracking forces 6. Resistance of the well walls 7. Base and skin friction
  • 37. The IRC and IS 3955 publications recommend the following procedure for design of well foundations in sand deposits (for clay the expressions should be suitably modified) 1 Check the stability of well under working loads, assuming elastic theory 2. Find the factor of safety of the well against ultimate failure using ultimate load theory
  • 38. Design of wells basically involves finding 1. Depth of the well 2. Size of the well and 3. Design of the other components.
  • 39.
  • 40. 1. Non uniform bearing capacity 2. Obstruction on one side of the well 3. Sand blowing in wells during sinking. It will cause sudden sinking of well 4. Method of sinking: Material should be removed from all sides equally otherwise the well may experience tilt 5. Sudden sinking due to blasting may also cause tilting of well 6. Irregular casting of steining will cause less friction on one side leads to chances of tilting of well.
  • 41.
  • 42. Precautions to be taken to avoid tilts and shift • The cutting edge of caisson must be thick and sharp pointed • The external surface of steining and caisson curb should be smooth. • Dredging should be done uniformly on all sides and in all pockets of caisson. • Caisson should be symmetrically placed. • The diameter (D) of the curb must be placed from 40 mm to 80 mm or larger or more than external diameter of steining.
  • 43. 1. Eccentric grabbing 2. Eccentric loading 3. Water jetting 4. Arresting the cutting edge 5. Pulling the well 6. Strutting the well 7. Pushing the well by jacks
  • 44. Pushing the caissons or well with jack:
  • 47.
  • 48. Providing temporary obstacles below the cutting edge:
  • 49. Pulling the well or caisson
  • 52. In case of sinking process of pneumatic caisson, workers or workmen have to work in working chamber under compressed air. If the compressed air pressure is less than 0.35 N/mm 2 to 0.4 N/ mm 2, then workmen may suffer from the following pains:  Workmen may suffer from giddiness  There is pains in ears of workmen  There is breaking of ear drums of workmen  There is bursting of blood vessels in the nose or ears of workmen  The above mentioned pains are not that serious or fatal, but workmen is actually suffering during decompression and effect causing depression is called caisson disease.
  • 53. Following are the caisson disease caused by decompression:  Severe pains in joints leading to bends  It may cause paralytic death  Excessive oxygen get absorbed in the blood may cause bursting of vessels.  If bubbles are developed in joints it causes bends  If the bubbles are developed in spinal cord, it causes paralysis and if the bubble are developed in heart, it causes heart attack.  Caisson diseases can be controlled by recompression followed by slow decompression.