UNDERWATER CONSTRUCTION
INDTRODUCTION
• During the construction of bridges, dams or any
other structure where the foundation part of the
structure is most likely to lie underwater , we have
to opt for underwater construction
• Construction in water poses many difficulties
especially in the places where there the depth is
considerable.
• During underwater construction our main objective
is to create dry and water free environment for
working in such a manner that the structural
stability of the structure is not compromised.
HOW IT ACT AS FOUNDATION
• Underwater construction works as observed by the
engineers and designers are considered as the most
difficult work. Caissons are sunk through ground or water
to exclude water and semi-fluid material during the process
of excavation of foundations and which subsequently
becomes an integral part of the substructure.
• Underwater foundations, also known as
subaqueous foundations, may be used in situations where
the use of a cofferdam or caisson is prohibitively expensive
or unfeasible. ... If the foundation is relatively short and in
shallow water, bagged concrete or cement placed in layers
may be used as formwork and left in position.
UNDERWATER CONSTRUCTION
TECHNIQUES
• Dry Construction
• Wet Construction
DRY CONSTRUCTION
1.CAISSON
• Water tight retaining structure.
• Permanent in nature.
• Used in construction of bridges,
piers,dams,etc.
• Constructed in a way
water can pumped out.
TYPES :
1. Open Caisson
2. Box Caisson
3. Suction Caisson
ADVANTAGES OF CAISSON
• Economic.
• Slight less noise and reduced vibrations.
• Easily adaptable to varying site conditions.
• High axial and lateral loading capacity.
2.COFFERDAMS
•Temporary structure.
•Built across body of water.
•Involves interection of
structure,soil and water.
•Creates a dry work
environment.
COMPONENTS:
1. Sheet Piling
2. Brace Piling
3. Concrete Seal
ADVANTAGES OF COFFERDAM
• Provides safe environment to work.
• Contractors have design responsibily.
• Steel sheet piles are easily installed and
removed
• Materials typically reused on other projects.
WET CONTRUCTION
• Evaculate the overall cost of the work.
• Considering time
• Equipment needs
• The capability of a diver to accomplish the
specific task.
• A more gross than fine nature.
TECHNIQUES FOR CONCRETING
UNDER WATER
• Use pre-cast concrete units and lower into
place
– Light enough to place
– Heavy enough to stay in place – or anchor
• Place wet concrete inside sacrificial bag
• Use a hopper with a bottom gate & skirt
• Use tremie pipe or flexible hose
TREMIE PIPE –
FOR SMALL QUANTITIES ONLY
• Crumpled paper used to
block tube initially
• Fresh concrete placed
within existing mass
• Formwork required – can
be pre-cast units
• Scour may be a problem
• Cofferdams can provide
protection
• Can use flexible hose &
pumped concrete
Water
level
Sea bed
level
Fresh
concrete in
hopper
PUMP METHOD
• Pumping concrete directly
into its final position ,
involving both horizontal
and vertical delivery of
concrete.
• Operational efficiency
with potential savings of
time and labour.
• For massive underwater
concrete construction of
navigation structures , the
method is prohibited.
TOGGLE BAGS
• Used for the placement of
small amounts of
concrete.
• Bag is filled in dry
condition with wet
concrete.
• Used mainly for repairing
works.
• Concrete is squeezed out
from the bag by the diver.
SHAPE RELATED TO PRESSURE
• The biggest challenge for
an underwater structure is
withstanding the constant
water pressure.
• To understand how these
structures solve this
problem we have to have
a better understanding of
the forces at play.
• Pressure is a force divided by the
area the force is acting on.
• The force of this pressure is
exerted perpendicular to the
surface on the object.
• The illustrations on the right are
based on a gas pressure from
inside the object, but the
principles work the same with
water pressure from the outside.
• The amount of water above the
object and the resulting pressure
on the object have a linear
relationship.
• Domes and arches are derived
from a spherical shape and are
therefore used in architecture
when dealing with large spans or
high carry loads.
SHAPE RELATED TO MATERIAL
• Pressure from the outside compresses the material
while pressure from inside of the object stretches
the material.
• This difference is very important, because materials
have different compressive and tensile strengths.
• Material used
• Steel concrete
• acrylic glass
SUBMERGED FLOATING TUNNEL
• LOCATION : Tokyo Bay Aqua – Line ( 9.6 km )
• Submerged floating tunnel is basically making a tunnel
to float underwater which is balanced by its buoyancy,
self weight and constraint forces resulted from cable
system and thus submerged to a certain depth
underwater.
• The tube is placed underwater, deep enough to avoid
water traffic and weather, but not so deep that high
water pressure needs to be deal with, usually 20 m to
50 m is sufficient.
CONSTRUCTION
• A trench is dredged in the bed of water
channel.
DREDGING :
• Dredging technology has improved
considerably in recent years and it is now
possible to remove a wide variety of material
underwater without adverse effects on the
environment of waterway.
PROCEDURE
• Construction of tunnel
segments on dry dock.
• Transporting the tunnel
segmenets to their final
places and placing the
underwater.
• Joinning of different tunnel
segments by using rubber
gasket.
• Anchoring the tunnel to
the cables.
STEP 1 : PRECASTING
• Huge tunnel section are constructed on dry dock.
• The procedure consists same as that of precast
construction.
• Dry dock is flooded and the panels are transported to
their respective places.
• Sinking of tunnel is controlled by the use of ballast
tank as in case of submarines.
STEP 2 : JOINTS
• After the submersion of different panels in
water they are connected with one another by
using a rubber gasket.
• Another procedure includes trapping of water
between the joints and then removing it
afterwards.
STEP 3 : FOUNDATION
• The application consists same as that of in caission
foundation.
• A hollow chamber is penetrated down the sea bed as
shown which evacuates the water trapped inside it
by a valve present on its top surface.
• Such type of foundations are been used for the
offshore oil rig plants.
STEP 4 : ANCHORING OF CABLES
• After the foundation work is completed, the
cables are anchored to the floating tunnel
which will avoid its movement and will place it
firmly in alignment.
• This operation can be carried out by drivers.
• Finally the tunnel will be in position and ready
to use.
MATERIAL USED
• As the tunnel is situated at a depth of 30 m.
• It should be perfectly water tight and secondly it
should resist the salty sea water thirdly it should
withstand against hydrostatic forces coming on it.
• It made of 4 layers.
• Outermost layer is constructed of aluminium to
resists the salty sea water.
• Second and third layer is made of the foam to float
the tunnel easily in water.
• Fourth layer is of concrete which gives strength to
the tunnel.
•The holland tunnel was built (1920-1924) by
pneumatically pushing cylindrical shields through the
river bottom.
• The shields not only dug through mud but also served
as the shell beneath which the actual tunnel walls (built
of iron rings filled with concrete) were constructed.
THE HOLLAND TUNNEL
• The Holland Tunnel opened in 1927 as the first
underwater vehicular crossing of the Hudson River
between Manhattan and Jersey City, New Jersey.
• It is the first tunnel constructed with a ventilation
system specifically designed to handle automobile
and truck exhaust fumes.
• By the 20th century, trains and cars had replaced
canals as the primary form of transportation
• The Holland Tunnel, completed in 1927, was one of
the first roadway tunnels and is still one of the
world's greatest engineering projects.
• Named for the engineer who oversaw
construction, the tunnel ushers nearly 100,000
vehicles daily between New York City and New
Jersey.
• Eleven different plans for the
tunnel were proposed,
including a design by General
George W. Goethals that
included a single tube lined
with concrete blocks having
two levels, each containing
three traffic lanes.
• experiments were conducted
to provide the data necessary
to design the special
ventilation system for motor
vehicle exhaust.
• Holland's plan called for twin
tubes lined with cast iron, each
containing two lanes of traffic
on a single deck, and was
ultimately selected.
• This type of longitudinal system would not work in
a vehicular tunnel because it would require gale
force winds of more than 70 miles per hour (113
km/h)
• a new type of ventilation system was devised in
which clean air would be supplied throughout the
tunnel through a fresh air duct located below the
roadway with openings.
• An exhaust duct would be located above the
roadway with openings at regular intervals to
remove the diluted exhaust fumes out of the
tunnel.
• large cylinder driven by 30 hydraulic jacks with a
total force of 6,000 tons (5,400 t).
• excavated, 2.5 foot (76 cm) thick cast iron rings are
added to support the walls.
Tunnel Construction: Soft Ground
and Hard Rock
• Workers generally use two
basic techniques to
advance a tunnel.
• In the full-face method,
they excavate the entire
diameter of the tunnel at
the same time.
• The second technique, is
the top-heading-and-bench
method.
• In this technique, workers dig a smaller tunnel
known as a heading.
• Once the top heading has advanced some distance
into the rock, workers begin excavating
immediately below the floor of the top heading;
this is a bench.
• One advantage of the top-heading-and-bench
method is that engineers can use the heading
tunnel to gauge the stability of the rock before
moving forward with the project.
Soft Ground (Earth)
• Workers dig soft-ground tunnels through clay, silt,
sand, gravel or mud.
• In this type of tunnel, stand-up time -- how long the
ground will safely stand by itself at the point of
excavation -- is of paramount importance.
• Because stand-up time is generally short when
tunnelling through soft ground, cave-ins are a
constant threat.
• To prevent this from happening, engineers use a
special piece of equipment called a shield.
• It carves a perfectly round
hole and supports the
surrounding earth.
• While workers remove debris
and install a permanent lining
made of cast iron or precast
concrete.
Hard Rock
• Tunnelling through hard rock almost always involves
blasting.
• Workers use a scaffold, called a jumbo.
• The jumbo drills mounted to make several holes in
the rock.
• The depth of the holes can vary depending on the
type of rock, but a typical hole is about 10 feet deep
and only a few inches in diameter.
• Then they repeat the process.
• Fire-setting is an alternative to blasting.
• In this technique, the tunnel wall is heated with fire,
and then cooled with water.
• In this environment, extra support for the tunnel roof
and walls may not be required.
• However, most tunnels pass through rock that
contains breaks or pockets of fractured rock, so
engineers must add additional support in the form of
bolts, sprayed concrete or rings of steel beams. In
most cases, they add a permanent concrete lining.
Tunnel Construction: Soft Rock
and Underwater
• Tunneling through soft rock and
tunneling underground require
different approaches.
• Blasting in soft, firm rock such
as shale or limestone is difficult
to control.
• The circular plate is covered
with disk cutters -- chisel-
shaped cutting teeth, steel disks
or a combination of the two.
• As the circular plate slowly rotates, the disk cutters
slice into the rock, which falls through spaces in the
cutting head onto a conveyor system.
• TBMs don't just bore the tunnels -- they also provide
support.
• As the machine excavates, two drills just behind the
cutters bore into the rock. Then workers pump grout
into the holes and attach bolts to hold everything in
place until the permanent lining can be installed.
• The TBM accomplishes this with a massive erector arm
that raises segments of the tunnel lining into place.
• Tunnels built across the bottoms of rivers, bays and
other bodies of water use the cut-and-cover method,
which involves immersing a tube in a trench and
covering it with material to keep the tube in place.
• Construction begins by dredging a trench in the riverbed
or ocean floor.
• Long, prefabricated tube sections, made of steel or
concrete and sealed to keep out water, are floated to the
site and sunk in the prepared trench.
• Then divers connect the sections and remove the seals.
• Any excess water is pumped out, and the entire tunnel is
covered with backfill
Underwater
• One of the most important
concerns is ventilation -- a
problem magnified by waste
gases produced by trains
and automobiles.
• His solution was to add two additional layers above and
below the main traffic tunnel.
• The upper layer clears exhaust fumes, while the lower
layer pumps in fresh air.
• Four large ventilation towers, two on each side of the
Hudson River, house the fans that move the air in and
out.
• Eighty-four fans, each 80 feet in diameter, can change
the air completely every 90 seconds.
Tunnel ventilation tower
Tunnel planning
• requires very different techniques than tunneling through
hard rock or soft rock, such as shale, chalk or sandstone.
• For New York City officials, the
solution was clear: Build an
automobile tunnel under the river
and let commuters drive
themselves from New Jersey into
the city.
• 51,694 vehicles made the crossing
• an average trip time of just 8
minutes.
• the challenge was an obsolete ferry system that strained to
transport more than 20,000 vehicles a day across the Hudson
River.
CONCLUSION
• Cofferdams are temporary structures and used in
cases where the plan area of foundation is very
large depth of water and for loose soils.
• At present,the tremie placement method is
standard way of placing high quality concrete
underwater.
• Underwater construction is useful for power
generation,bridges,ship husbandry,water
utilities,mining,pipeline,power and gas
trasmission.
• And attracting places for tourits.

More Related Content

What's hot

Folded Plate structures
Folded Plate structures Folded Plate structures
Folded Plate structures
rohan joshi
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
Udayram Patil
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structures
Akash Matthew
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structure
Manish Sharma
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
Ajay Reddy
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studies
Soumitra Smart
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structures
Krishnagnr
 
Geodesic Dome and Ribbed Dome
Geodesic Dome and Ribbed DomeGeodesic Dome and Ribbed Dome
Geodesic Dome and Ribbed Dome
Geetika Singla
 
Tensile structures and Pneumatic Structures
Tensile structures and Pneumatic StructuresTensile structures and Pneumatic Structures
Tensile structures and Pneumatic Structures
Geeva Chandana
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
Akshay Revekar
 
ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE
Gai3 Segar
 
presentation ON TALL BUILDING
 presentation ON TALL BUILDING presentation ON TALL BUILDING
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Rajesh Burde
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and Construction
Azra Maliha
 
curtain wall -skin of building
 curtain wall -skin of building curtain wall -skin of building
curtain wall -skin of building
abidha karthu
 
Tensile structures
Tensile structuresTensile structures
Tensile structures
Harpreet Bhatia
 
UNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTIONUNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTION
Hamsui Harold
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
Kiruthika Selvi K J
 
Empire state building
Empire state buildingEmpire state building
Empire state building
dishani chauhan
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
Prasad Thanthratey
 

What's hot (20)

Folded Plate structures
Folded Plate structures Folded Plate structures
Folded Plate structures
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structures
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structure
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studies
 
Pneumatic structures
Pneumatic structuresPneumatic structures
Pneumatic structures
 
Geodesic Dome and Ribbed Dome
Geodesic Dome and Ribbed DomeGeodesic Dome and Ribbed Dome
Geodesic Dome and Ribbed Dome
 
Tensile structures and Pneumatic Structures
Tensile structures and Pneumatic StructuresTensile structures and Pneumatic Structures
Tensile structures and Pneumatic Structures
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE ARCHITECTURE PROFESSIONAL PRACTICE
ARCHITECTURE PROFESSIONAL PRACTICE
 
presentation ON TALL BUILDING
 presentation ON TALL BUILDING presentation ON TALL BUILDING
presentation ON TALL BUILDING
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Geodesic Dome - History and Construction
Geodesic Dome - History and ConstructionGeodesic Dome - History and Construction
Geodesic Dome - History and Construction
 
curtain wall -skin of building
 curtain wall -skin of building curtain wall -skin of building
curtain wall -skin of building
 
Tensile structures
Tensile structuresTensile structures
Tensile structures
 
UNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTIONUNDERWATER CONSTRUCTION
UNDERWATER CONSTRUCTION
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
 
Empire state building
Empire state buildingEmpire state building
Empire state building
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 

Similar to Underwater construction

tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdf
BalpreetSingh47890
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
1971995
 
Floating tunnel
Floating tunnelFloating tunnel
Floating tunnel
Yasir Hashmi
 
Caissons
Caissons Caissons
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
Vinay Vb
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
kushpatel927805
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnel
Shaikh Ismail
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
Amir Amdani
 
Well foundations notes
 Well foundations notes Well foundations notes
Well foundations notes
PRASANTHI PETLURU
 
underwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxunderwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptx
Jayachandran68
 
Cofferdam
CofferdamCofferdam
Cofferdam
Shashank Namdeo
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
srinivas cnu
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
Dams and spillways
Dams and spillwaysDams and spillways
Transatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnelTransatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnel
Aglaia Connect
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
ChinnuNinan
 
Shotcrete concrete
Shotcrete concreteShotcrete concrete
Shotcrete concrete
srinivas cnu
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
Vicky Matwan
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
LovelyLavakumarLK
 

Similar to Underwater construction (20)

tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdf
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Floating tunnel
Floating tunnelFloating tunnel
Floating tunnel
 
Caissons
Caissons Caissons
Caissons
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnel
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Tunnel PDF.pdf
Tunnel PDF.pdfTunnel PDF.pdf
Tunnel PDF.pdf
 
Well foundations notes
 Well foundations notes Well foundations notes
Well foundations notes
 
underwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxunderwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptx
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Transatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnelTransatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnel
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
 
Shotcrete concrete
Shotcrete concreteShotcrete concrete
Shotcrete concrete
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 

More from HetviPatel58

Tensile structure
Tensile structureTensile structure
Tensile structure
HetviPatel58
 
Shell structure
Shell structureShell structure
Shell structure
HetviPatel58
 
Roof final
Roof finalRoof final
Roof final
HetviPatel58
 
Renault distribution centre
Renault distribution centreRenault distribution centre
Renault distribution centre
HetviPatel58
 
Podium
PodiumPodium
Podium
HetviPatel58
 
Loads on roof copy
Loads on roof   copyLoads on roof   copy
Loads on roof copy
HetviPatel58
 
Foundation
FoundationFoundation
Foundation
HetviPatel58
 
Container 1
Container 1Container 1
Container 1
HetviPatel58
 
Beijing airport(1)
Beijing airport(1)Beijing airport(1)
Beijing airport(1)
HetviPatel58
 

More from HetviPatel58 (9)

Tensile structure
Tensile structureTensile structure
Tensile structure
 
Shell structure
Shell structureShell structure
Shell structure
 
Roof final
Roof finalRoof final
Roof final
 
Renault distribution centre
Renault distribution centreRenault distribution centre
Renault distribution centre
 
Podium
PodiumPodium
Podium
 
Loads on roof copy
Loads on roof   copyLoads on roof   copy
Loads on roof copy
 
Foundation
FoundationFoundation
Foundation
 
Container 1
Container 1Container 1
Container 1
 
Beijing airport(1)
Beijing airport(1)Beijing airport(1)
Beijing airport(1)
 

Recently uploaded

Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Mansi Shah
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
9a93xvy
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
7sd8fier
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen Designs
Finzo Kitchens
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
jyz59f4j
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
ameli25062005
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdf
SudhanshuMandlik
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
Mansi Shah
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
ResDraft
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
taqyed
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
fabianavillanib
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
madhavlakhanpal29
 
Research 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdfResearch 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdf
ameli25062005
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
aaryangarg12
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
h7j5io0
 
Exploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdfExploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdf
fastfixgaragedoor
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
cy0krjxt
 

Recently uploaded (20)

Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen Designs
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdf
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
 
Research 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdfResearch 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdf
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
 
Exploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdfExploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdf
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
 

Underwater construction

  • 2. INDTRODUCTION • During the construction of bridges, dams or any other structure where the foundation part of the structure is most likely to lie underwater , we have to opt for underwater construction • Construction in water poses many difficulties especially in the places where there the depth is considerable. • During underwater construction our main objective is to create dry and water free environment for working in such a manner that the structural stability of the structure is not compromised.
  • 3. HOW IT ACT AS FOUNDATION • Underwater construction works as observed by the engineers and designers are considered as the most difficult work. Caissons are sunk through ground or water to exclude water and semi-fluid material during the process of excavation of foundations and which subsequently becomes an integral part of the substructure. • Underwater foundations, also known as subaqueous foundations, may be used in situations where the use of a cofferdam or caisson is prohibitively expensive or unfeasible. ... If the foundation is relatively short and in shallow water, bagged concrete or cement placed in layers may be used as formwork and left in position.
  • 4. UNDERWATER CONSTRUCTION TECHNIQUES • Dry Construction • Wet Construction
  • 5. DRY CONSTRUCTION 1.CAISSON • Water tight retaining structure. • Permanent in nature. • Used in construction of bridges, piers,dams,etc. • Constructed in a way water can pumped out. TYPES : 1. Open Caisson 2. Box Caisson 3. Suction Caisson
  • 6. ADVANTAGES OF CAISSON • Economic. • Slight less noise and reduced vibrations. • Easily adaptable to varying site conditions. • High axial and lateral loading capacity.
  • 7. 2.COFFERDAMS •Temporary structure. •Built across body of water. •Involves interection of structure,soil and water. •Creates a dry work environment. COMPONENTS: 1. Sheet Piling 2. Brace Piling 3. Concrete Seal
  • 8. ADVANTAGES OF COFFERDAM • Provides safe environment to work. • Contractors have design responsibily. • Steel sheet piles are easily installed and removed • Materials typically reused on other projects.
  • 9. WET CONTRUCTION • Evaculate the overall cost of the work. • Considering time • Equipment needs • The capability of a diver to accomplish the specific task. • A more gross than fine nature.
  • 10. TECHNIQUES FOR CONCRETING UNDER WATER • Use pre-cast concrete units and lower into place – Light enough to place – Heavy enough to stay in place – or anchor • Place wet concrete inside sacrificial bag • Use a hopper with a bottom gate & skirt • Use tremie pipe or flexible hose
  • 11. TREMIE PIPE – FOR SMALL QUANTITIES ONLY • Crumpled paper used to block tube initially • Fresh concrete placed within existing mass • Formwork required – can be pre-cast units • Scour may be a problem • Cofferdams can provide protection • Can use flexible hose & pumped concrete Water level Sea bed level Fresh concrete in hopper
  • 12.
  • 13. PUMP METHOD • Pumping concrete directly into its final position , involving both horizontal and vertical delivery of concrete. • Operational efficiency with potential savings of time and labour. • For massive underwater concrete construction of navigation structures , the method is prohibited.
  • 14. TOGGLE BAGS • Used for the placement of small amounts of concrete. • Bag is filled in dry condition with wet concrete. • Used mainly for repairing works. • Concrete is squeezed out from the bag by the diver.
  • 15. SHAPE RELATED TO PRESSURE • The biggest challenge for an underwater structure is withstanding the constant water pressure. • To understand how these structures solve this problem we have to have a better understanding of the forces at play.
  • 16. • Pressure is a force divided by the area the force is acting on. • The force of this pressure is exerted perpendicular to the surface on the object. • The illustrations on the right are based on a gas pressure from inside the object, but the principles work the same with water pressure from the outside. • The amount of water above the object and the resulting pressure on the object have a linear relationship. • Domes and arches are derived from a spherical shape and are therefore used in architecture when dealing with large spans or high carry loads.
  • 17. SHAPE RELATED TO MATERIAL • Pressure from the outside compresses the material while pressure from inside of the object stretches the material. • This difference is very important, because materials have different compressive and tensile strengths. • Material used • Steel concrete • acrylic glass
  • 18. SUBMERGED FLOATING TUNNEL • LOCATION : Tokyo Bay Aqua – Line ( 9.6 km )
  • 19. • Submerged floating tunnel is basically making a tunnel to float underwater which is balanced by its buoyancy, self weight and constraint forces resulted from cable system and thus submerged to a certain depth underwater. • The tube is placed underwater, deep enough to avoid water traffic and weather, but not so deep that high water pressure needs to be deal with, usually 20 m to 50 m is sufficient.
  • 20. CONSTRUCTION • A trench is dredged in the bed of water channel. DREDGING : • Dredging technology has improved considerably in recent years and it is now possible to remove a wide variety of material underwater without adverse effects on the environment of waterway.
  • 21. PROCEDURE • Construction of tunnel segments on dry dock. • Transporting the tunnel segmenets to their final places and placing the underwater. • Joinning of different tunnel segments by using rubber gasket. • Anchoring the tunnel to the cables.
  • 22. STEP 1 : PRECASTING • Huge tunnel section are constructed on dry dock. • The procedure consists same as that of precast construction. • Dry dock is flooded and the panels are transported to their respective places. • Sinking of tunnel is controlled by the use of ballast tank as in case of submarines.
  • 23. STEP 2 : JOINTS • After the submersion of different panels in water they are connected with one another by using a rubber gasket. • Another procedure includes trapping of water between the joints and then removing it afterwards.
  • 24. STEP 3 : FOUNDATION • The application consists same as that of in caission foundation. • A hollow chamber is penetrated down the sea bed as shown which evacuates the water trapped inside it by a valve present on its top surface. • Such type of foundations are been used for the offshore oil rig plants.
  • 25. STEP 4 : ANCHORING OF CABLES • After the foundation work is completed, the cables are anchored to the floating tunnel which will avoid its movement and will place it firmly in alignment. • This operation can be carried out by drivers. • Finally the tunnel will be in position and ready to use.
  • 26. MATERIAL USED • As the tunnel is situated at a depth of 30 m. • It should be perfectly water tight and secondly it should resist the salty sea water thirdly it should withstand against hydrostatic forces coming on it. • It made of 4 layers. • Outermost layer is constructed of aluminium to resists the salty sea water. • Second and third layer is made of the foam to float the tunnel easily in water. • Fourth layer is of concrete which gives strength to the tunnel.
  • 27. •The holland tunnel was built (1920-1924) by pneumatically pushing cylindrical shields through the river bottom. • The shields not only dug through mud but also served as the shell beneath which the actual tunnel walls (built of iron rings filled with concrete) were constructed. THE HOLLAND TUNNEL
  • 28. • The Holland Tunnel opened in 1927 as the first underwater vehicular crossing of the Hudson River between Manhattan and Jersey City, New Jersey. • It is the first tunnel constructed with a ventilation system specifically designed to handle automobile and truck exhaust fumes. • By the 20th century, trains and cars had replaced canals as the primary form of transportation • The Holland Tunnel, completed in 1927, was one of the first roadway tunnels and is still one of the world's greatest engineering projects. • Named for the engineer who oversaw construction, the tunnel ushers nearly 100,000 vehicles daily between New York City and New Jersey.
  • 29. • Eleven different plans for the tunnel were proposed, including a design by General George W. Goethals that included a single tube lined with concrete blocks having two levels, each containing three traffic lanes. • experiments were conducted to provide the data necessary to design the special ventilation system for motor vehicle exhaust. • Holland's plan called for twin tubes lined with cast iron, each containing two lanes of traffic on a single deck, and was ultimately selected.
  • 30. • This type of longitudinal system would not work in a vehicular tunnel because it would require gale force winds of more than 70 miles per hour (113 km/h) • a new type of ventilation system was devised in which clean air would be supplied throughout the tunnel through a fresh air duct located below the roadway with openings. • An exhaust duct would be located above the roadway with openings at regular intervals to remove the diluted exhaust fumes out of the tunnel. • large cylinder driven by 30 hydraulic jacks with a total force of 6,000 tons (5,400 t). • excavated, 2.5 foot (76 cm) thick cast iron rings are added to support the walls.
  • 31. Tunnel Construction: Soft Ground and Hard Rock • Workers generally use two basic techniques to advance a tunnel. • In the full-face method, they excavate the entire diameter of the tunnel at the same time. • The second technique, is the top-heading-and-bench method.
  • 32. • In this technique, workers dig a smaller tunnel known as a heading. • Once the top heading has advanced some distance into the rock, workers begin excavating immediately below the floor of the top heading; this is a bench. • One advantage of the top-heading-and-bench method is that engineers can use the heading tunnel to gauge the stability of the rock before moving forward with the project.
  • 33. Soft Ground (Earth) • Workers dig soft-ground tunnels through clay, silt, sand, gravel or mud. • In this type of tunnel, stand-up time -- how long the ground will safely stand by itself at the point of excavation -- is of paramount importance. • Because stand-up time is generally short when tunnelling through soft ground, cave-ins are a constant threat. • To prevent this from happening, engineers use a special piece of equipment called a shield.
  • 34. • It carves a perfectly round hole and supports the surrounding earth. • While workers remove debris and install a permanent lining made of cast iron or precast concrete.
  • 35. Hard Rock • Tunnelling through hard rock almost always involves blasting. • Workers use a scaffold, called a jumbo. • The jumbo drills mounted to make several holes in the rock. • The depth of the holes can vary depending on the type of rock, but a typical hole is about 10 feet deep and only a few inches in diameter.
  • 36. • Then they repeat the process. • Fire-setting is an alternative to blasting. • In this technique, the tunnel wall is heated with fire, and then cooled with water. • In this environment, extra support for the tunnel roof and walls may not be required. • However, most tunnels pass through rock that contains breaks or pockets of fractured rock, so engineers must add additional support in the form of bolts, sprayed concrete or rings of steel beams. In most cases, they add a permanent concrete lining.
  • 37. Tunnel Construction: Soft Rock and Underwater • Tunneling through soft rock and tunneling underground require different approaches. • Blasting in soft, firm rock such as shale or limestone is difficult to control. • The circular plate is covered with disk cutters -- chisel- shaped cutting teeth, steel disks or a combination of the two.
  • 38. • As the circular plate slowly rotates, the disk cutters slice into the rock, which falls through spaces in the cutting head onto a conveyor system. • TBMs don't just bore the tunnels -- they also provide support. • As the machine excavates, two drills just behind the cutters bore into the rock. Then workers pump grout into the holes and attach bolts to hold everything in place until the permanent lining can be installed. • The TBM accomplishes this with a massive erector arm that raises segments of the tunnel lining into place.
  • 39. • Tunnels built across the bottoms of rivers, bays and other bodies of water use the cut-and-cover method, which involves immersing a tube in a trench and covering it with material to keep the tube in place. • Construction begins by dredging a trench in the riverbed or ocean floor. • Long, prefabricated tube sections, made of steel or concrete and sealed to keep out water, are floated to the site and sunk in the prepared trench. • Then divers connect the sections and remove the seals. • Any excess water is pumped out, and the entire tunnel is covered with backfill Underwater
  • 40. • One of the most important concerns is ventilation -- a problem magnified by waste gases produced by trains and automobiles. • His solution was to add two additional layers above and below the main traffic tunnel. • The upper layer clears exhaust fumes, while the lower layer pumps in fresh air. • Four large ventilation towers, two on each side of the Hudson River, house the fans that move the air in and out. • Eighty-four fans, each 80 feet in diameter, can change the air completely every 90 seconds. Tunnel ventilation tower
  • 41. Tunnel planning • requires very different techniques than tunneling through hard rock or soft rock, such as shale, chalk or sandstone. • For New York City officials, the solution was clear: Build an automobile tunnel under the river and let commuters drive themselves from New Jersey into the city. • 51,694 vehicles made the crossing • an average trip time of just 8 minutes. • the challenge was an obsolete ferry system that strained to transport more than 20,000 vehicles a day across the Hudson River.
  • 42. CONCLUSION • Cofferdams are temporary structures and used in cases where the plan area of foundation is very large depth of water and for loose soils. • At present,the tremie placement method is standard way of placing high quality concrete underwater. • Underwater construction is useful for power generation,bridges,ship husbandry,water utilities,mining,pipeline,power and gas trasmission. • And attracting places for tourits.