International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 465
IMPLEMENTING TIME AND COST OPTIMIZATION IN COMMERCIAL
BUILDING USING PROJECT MANAGEMENT TECHNIQUES IN MICROSOFT
PROJECT
Mr. Umesh Kamble1, Prof. Shashank U. Vanakudari2
1PG student, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India.
2 Assistant Professor, Civil Engineering Dept., Jain College of Engineering, Belagavi, Karnataka, India.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Project management is main stream which
overall makes a civil industry worth into existence in
accordance with the control on constraints such as time
and cost. This paper will mainly help out to investigate the
behavioural improvements in time according to the relative
cost. Microsoft project software is used to enhance the
scheduling adding Crashing, Slack time and alternative
building material to the work planning activity. Crashing
makes a proper inventory behavioural time benefits from
the overtime of huge workforce and improvement in the
duration of an activity using slack time in software. An
alteration with the cost is maintained which helpful in
retrogression of overall costs of the project. This project is
very much applicable where the time and cost is the major
constraint which make a building more economical.
Key Words: Crashing, Slack time, Critical Path
Method, Alternative Building Material, Polycarbonate
Sheet.
1. INTRODUCTION
In today’s era there are many heaps of sectors which are
increasing globalisation & civilisation such as IT’s,
Infrastructures, Energy conservative projects. In these,
one of the major sector is Infrastructure which is
profoundly increasing the economy of the country.
Leading to this mainly time & cost is exceedingly more
into consideration in this world. Everyone wants to be
more conservative when it comes into time constraint &
within shorter duration work should be done giving more
profitable results. In the other way of profitable results
cost constraint is predominating the efficiency of work to
be done in construction industry. More often cost is
directly proportional to the work to be carried out by the
resources.
In other aspects small scale construction industry could
not take these constraints into consideration which leads
to more cost overrun & time overrun. So it is better to
optimize the time and cost which makes constraint flow
off. Many projects have some risk and uncertainties which
we not consider it orally but it comes into account when
we execute it practically which makes increase in time,
cost and overallocation of resources. So mainly
recognising those uncertainties and doing a proper
analysis one should make a project more feasible.
So mainly the easiest way to minimize the cost of the
project is the natural sustainable material and using the
alternative materials which cut out the excess increase in
the overall cost of the project. An analysis of raw
materials and resources, from meeting up of parent
material to their definitive composition, gives out a
preferential judgmatic long term costs benefits. These
benefits are paid to the clients, owner, the occupier, & the
environment. Accordingly, time and cost of each item of
work is estimated which gives ultimate time & cost of the
project.
Optimisation is the method of improving profit gain and
effectively going through a sensible result under given
state of affairs. The method in which the actual cost
should not traverse the estimated cost limit is called as
Cost Optimisation.
There are mainly two areas where cost is optimised:
1.) Optimising during the pre-construction phase of the
project i.e., Design stage.
2.) Optimising when the construction gets started by the
project manager or the contractor.
Optimisation means collecting all the data cost of the
project and the advancement of work. The motive of the
cost optimisation is to gain profit satisfactory without
getting more chaos and finishing the work in actual
estimated cost or lesser than it.
1.1 Objectives
Key objectives in the construction sector is to complete
each project in a timely manner, budget and quality.
Building viability requires useful effectiveness,
organizational persistence, cheap, swiftness and
superiority. The behaviour of the project in various
disputed areas is challenging. Often the construction
company has to deal with the problems, it is always
expensive to reduce time and save time by saving all the
parties in the project having a commonality between
profit time and expenditure. Time optimization is
necessary and very important for construction projects.
The purpose of time value optimization is that it is
possible to fix the optimum project duration related to
the minimum cost and it can be obtained with the help
reducing the duration of critical tasks in the network by
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 466
violating critical activities reducing total project duration.
In this study, the critical path method (CPM) with analysis
path is used to find out the crash duration and crash costs
and it is analysed to identify the relationship between
them. The time and cost to create a model for
optimization problems. In the part of the analysis, this
will be for solving this problem done by manual methods.
After that the explanations for the extension of the project
were extended and then thereafter project crashing
technology time and expense utility projects will be easy
to implement contact with the results obtained
satisfactorily, that the construction is an indication of the
utility of this approach.
The key project objectives is described below:
1. The main aim of this project is to reduce the
improved development period from new time and to
meet a specific deadline.
2. The main motivation behind this project is to reduce
time using crashing and slack (Time Optimization).
3. For cost optimization alternative building material is
used to reduce the cost and making project more
well-organized and inexpensive.
2. METHODOLOGY
Fig-1 Flowchart of Work Methodology
2.1 Crashing of an Activity
A crashing of an activity is a method of reducing the
overall decreasing the duration of an activity with the help
of some techniques. Crashing is the performance that had
better use when fast tracking has not hold back sufficient
time in the database. In this technique the equipment and
manual resources are added in terms of lowest possible
techniques and cost. The advantage and disadvantages of
the cost and the schedule are evaluated to conclude how
to attain the highest quantity of firmness at the lowermost
incremental cost.
Crashing refers to a particular variety of compression
of the project schedule that is carried out for the purpose
of decreasing the total period of time (also known as the
total duration of the project schedule). The decrease of the
duration of the project is usually carried out after a careful
and exhaustive analysis of all possible alternatives for
minimizing the duration of the project in which each and
every one of the methods to reach the maximum duration
of the program by the lower additional cost.
Crashing the schedule means adding extra resources
in critical path without getting the highest level of
efficiency to the important resources.
It is another technique where you add the
program to resources for extra time. On contrary to the
crashing we are mainly into account of establishing or
employing resources which could reduce the overall cost.
Once we are aware of those activities crashing can be
applied to the manageable activity of the project.
2.2 Crashing of Network Manually
In specific projects, deduction of complete project
schedule is necessary, even if its cost is increased. This is
habitually desired where thinking of cost is persistent or
less important than completing the project in the fullest
time. It is generally possible to reduce the resources
allocated to the project allocation by reducing the
resources. Due to the escalation or reduction in cost of the
project, the cost of the project has drop off or improved.
For this resolution, time and cost are methodically
evaluated.
By scheduling the techniques of construction
projects by network technologies, the rate of progress of
each activity will produce the lowest practical cost. This is
based on the distribution of progress materials, the
number of workers available and the type of devices
available for each activity at a minimum cost. When these
projects are built in these situations, it is mentioned as a
general program. However, sometimes it may be
desirable to reduce the time needed to build the project.
When normal time has been reduced, the project or its
part is built under the program crash.
For crashing of an activity following points is to be
considered:
1. Rate of materials is increased.
2. Number of workers is increased.
3. Overtime work should be allotted with a higher pay
scale per men hour of work.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 467
4. Additional unit of equipment is allotted to the critical
activities.
Furthermore, in crashing of an activity the two main
constraints that is time and cost is always been inversely
proportional to each other. Proper handling and making
the project smooth one should be very careful against
disputes which will make overall project more disturbed
and may increase the total investment and capital
budgeting of the project.
2.3 Crashing using Microsoft Project
The main approaches for crashing of an activity in
Microsoft project is:
1. Apportioning additional resources to the project
which makes easy way for crashing of an activity.
2. Overtime allocated to the resources mainly human
resource.
3. Hiring additional resources.
4. For Early completion extra payments.
It would be possible to complete the outsourcing parts of
the project within a short period of time if the same work
was to be completed by internal resources.
With the help of critical activity (The sum up of longest
duration in a particular project) a in a particular project
we can easily crash the duration of an activity. Non-critical
activity may be unresolved and may not give better result
and hence it is ineffective to crash an activity which is in
Non-critical area. If a project regulates with a proper cost,
time and quality material bound then it is easy to get a
virtuous result with an ease of getting nicely quoted
budget with reduced quality time. Meanwhile both the
functions time and cost mainly stretch the proper way of
budgeting.
2.4 Method of Crashing using Overtime Allocation
According to the bureau of labour statistics the overtime is
totally depend on the total wages of the construction
project. Overtime can be calculated from total main hour
worked on an activity should be 15 percent working on
land project whereas it should be 25 percent for the work
under dredging projects. For a project which is
individually constituted the percentage should 1 to 34 on
ground jobs and it should be 17 to 34 for dredging project.
Due to extensive overtime in the nature of work under
the study. By using modern equipment’s for allied
operations as an alternative of human resources may
increase the overall cost but has a tendency to decrease
the overall duration of the project. This modern
equipment eventually worked in an outdoor different
seasonal condition which may extensively increase the
overall operational cost of the project. The equipment
should be used accordingly best suited seasonal
conditions.
So, it is good to increase the daily working time for heavy
construction where modern equipment is required. In
ideal conditions, 10 hours of working a day and 6 days a
week in land operations when modern equipment’s is
involved whereas dredging projects take a longer
working hour because the dredge operated continuously.
For dredging works in ideal condition, shifts have been
prepared with at least one day off and organised 84 hours
of work per day.
It is mandatory to be very condemnatory whether to use
the human resource or the modern mechanisation
resource. For an enthusiastic result it should be a proper
balance between the guidelines in accordance with the
employing resources and the investments.
3. Slack Time
Slack time in project management is a time in which an
activity can increase or decrease the duration of the
project without affecting succeeding overall tasks and
overall duration of the project. It is also known as “Float
time”.
Slack time can be calculated by subtracting the time
allotted from the overall duration of task. Such as if 12
days is being allotted for a particular project but it can be
completed in 6 hours than the slack would be 6 days.
Critical path designates zero slack of the construction
project because any increase in time will indirectly affect
the overall duration of the project.
With the help of critical path and the overall slack in
every non-critical activity, maximum slack can be
calculated.
3.1 Types of Slack
1. Total slack.
2. Safety slack.
3. Free slack.
1. Total Slack: Without affecting the overall duration of
the project the total slack is equivalent to the permissible
increase in duration. It can be calculated as
LFi - EFi = LSi - ESi
With the LSi and LFi is denoted as latest start and latest
finish time of an activity whereas EFi and Esi denotes the
earliest start and earliest finish.
2. Safety Slack: When all predecessors finish late
possibly then the safety slack is equal to provided delay of
an activity.
LSi – maxall predecessors j (LFj)
Latest finish time (LFj) of an activity i that succeeds
activity j.
3. Free slack: Free slack has not at all conclude on the
earliest start of successor activity.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 468
Minall successor’s j (ESj) - EFi
With Earliest start time (ESj) of an activity i that precedes
activity j.
3.2 Total Slack
Total slack is used to reduce the time in Microsoft Project.
Microsoft Office Project bases its counts of Total slack on
examinations of the dates in the Early Start, Early Finish,
Late Start, and Late Finish fields for the assignment,
which thus consider the dates for any successor errands.
Add up to slack is figured as the littler estimation of the
Late Finish short the Early Finish field, and the Late Start
less the Early Start field.
Utilize the Total Slack field to decide if the errand has
whenever accessible for a postponement. This can be
helpful if an asset needs additional time on an errand, or
in the event that you need to allocate an asset to another
assignment. You can likewise utilize the Aggregate Slack
field to decide how to recoup a timetable that is slipping.
4. Alternative Building Material
For this project work mainly, polycarbonate glasses are
alternative for the structural glazing. It cuts down overall
costs by 2-3 lakhs.
Polycarbonate is a material which contains a group of
carbonates in their chemically build structure.
Polycarbonate is mainly as similar to a conventional
transparent glass but inflexible as plastic. Polycarbonate
glass is easily installed, cut and easily available in ribbed
single sheet or flat twin-wall thicknesses.
Advantages of Polycarbonate Glass Glazing:
1. Use of polycarbonate sheet is much lesser than the
cost of insulated glass. Polycarbonate sheet may cut
down the cost one-third to half from the insulated
glass.
2. Polycarbonate sheet is 200 times stronger than
insulated glass i.e. it provides structure with a very
high impact resistance. This quality helps in getting
stronger benefits to structure giving a proper
maintained temperature resistance.
3. Polycarbonate sheet has a good fire resistance. Class
1 rating is given to polycarbonate sheet when tested
according to BS476 part 7.
4. For heat reduction and controlling solar power it has
a 25mm opal which provides a light transmission as
low as 24%.
5. Polycarbonate sheets has a tendency to provide UV
protection on the outer surface which helps in
preventing sheets from UV radiation.
6. Polycarbonate sheet is very light weight and allows a
greater deflection in comparison to glass. It can be
easily available in sheet up to 39 feet which helps in
reducing overall duration.
7. According to 2006 IBC slop glazing code
polycarbonate is a safe glazing technique.
5. RESULTS AND DISCUSIONS
5.1 Results for Time Optimization
The below figure shows optimizing the duration using
planning and scheduling. The duration which is
conventionally observed is 377 days which is being
decreased by crashing and with the help of slack time.
The approximately reduced duration is 349 days. Hence
these constraints are mainly helpful in considering and
reducing the overall costs of an activity or the whole
project. These results are mainly helpful to induce more
results from labour productivity using the overtime
allocation. As we know that an individual labour can do
minimum of 8 hours of work a day. But this project
eventually distributed certain working activity into
number of labours which does not make much hectic to
the labour. Moreover, in construction project labours
doesn’t engage to a specific activity but they are in huge
number working of multi sets of work. As from case study
practical labours actually applied in the project is
dissimilar to the theoretical calculated labour so the
number of labour applied in the software is from the
actual working labours and their wages. Proper wages
also attract the labours to work more which make project
progress more into right way off time optimisation.
Majorly for optimising time the methodology practically
implemented is shift wise work schedule so that at a
separate shift of schedule that is day and night shift
labours and workers work easily without any hectic
situations. Similarly using more modern equipment in
construction project will also reduce time oriented
objectives. But it is directly concerned with the
availability issues. So overtiming allocation majorly
attracts worker which is directly results into their weekly
incentives and with a major workforce working at a site
will also decrease the exertion on labour. The time
optimisation is also depending on how well a contractor
organises his work schedule with a proper utilisation of
material, machineries and human resource.
5.2 Results for Cost Optimization
The result mainly shows that how well organised
material helps out in getting the cost more into economic
zone. As we know that crashing of an activity
consequently decreases the time by using several
methods in construction project. But it will make an
owner more satisfactory in consideration of before
completion of project but it also makes more satisfying if
the owner gets the result under the budgeted
investments. So, in this project cost optimisation is done
by using the alternative building oriented materials which
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 469
readily cut down the cost of the whole project but also
satisfies owner with an economical result.
So for alternative building material an insulated
structural glass glazing is replaced by polycarbonate
sheets which cuts the overall cost of the project. The cost
of polycarbonate sheet is Rs. 700/ sq.m. which is
considerably very much less compared to insulated
structural glass glazing which is Rs. 5860/sq.m. as per
scheduled rates book. Conventionally it is being seen that
the cost of the project is Rs. 50,657,057.83/-, by applying
crashing the cost again got increased due to reduction of
work time which is Rs. 52,416,091.44/-. Again, by
applying the alternative material cost the overall cost of
the building is reduced by Rs. 48,879,432.36/-. So this
method of cost optimisation majorly decrease the
conventional cost of the project up to Rs. 17,77,625.47/-
Chart -1: Reduction in Time
Chart -2: Reduction in Cost
6.CONCLUSION
As we had reduced the overall cost by 6.98 % and the
overall duration by 7.71 %. This project concludes that
any relative construction project mainly depends on the
Time and Cost constraints which gives a proper
economical weightage to any project. Moreover, it also
depends on the project manager and types of resources
which is involved in the project. Consequently, how the
overtime will influence the project duration by
simultaneously decreasing the slack time. A proper
planning and scheduling will also make a huge difference
in construction project considering the labour
management. This project also concludes that the project
effectively depends on the seasonal variations and the
location such that it will be either advantageous or
disadvantageous to the owner. It also concludes that
proper maintained work ethics will also helpful to make a
project more time and cost bound i.e. economical.
REFERENCES
[1] W. Willard Wirtz (1964), Bureau of labour statistics.
[2] Luís Bragança, Ricardo Mateus and Heli Koukkari
(2010), “Building Sustainibilty Assessment”,
International Journal of Civil and Structural
Engineering, ISSN 2071–1050.
[3] Ashok Mohanty, Jibitesh Mishra, Biswajit Satpathy
(2011), “Activity modes selection for project
crashing through deterministic simulation”, Journal
of Industrial Engineering and Management, JIEM
2011-4(4), ISSN 2013-0953, PP 610-623.
[4] Omar M. Elmabrouk (2012), “Scheduling Project
Crashing Time using Linear Programming
Technique”, International Conference on Industrial
Engineering and Operations Management Istanbul,
Turkey, July 3 – 6, 2012.
[5] Jong-Jin Kim (2012), “Qualities, Use and Examples of
Sustainable Building Materials”, National Pollution
Prevention Center for Higher Education, 430 E.
University Ave., Ann Arbor, MI 48109-1115
734.764.1412.
[6] Nafish Sarwar Islam (2013), “Complex Project
Crashing Algorithm”, IOSR Journal of Business and
Management (IOSR-JBM) e-ISSN: 2278-487X, p-ISSN:
2319-7668. Volume 11, Issue 4 (Jul. - Aug. 2013), PP
10-17.
[7] Mrs. Ruchita Shrimali Vyas (2013), “Scheduling
Project Management Using Crashing CPM Network to
get Project completed on Time”, International Journal
of Engineering Research & Technology (IJERT), ISSN:
2278-0181, Vol. 2 Issue 2, February-2013.
335
340
345
350
355
360
365
370
375
380
Overall time Crash time
Normal time Crash time
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 470
[8] Nuhu Braimah (2013), “Construction Delay Analysis
Techniques- A Review of Application Issues and
Improvement Needs”, International Journal of Civil
and Structural Engineering, ISSN 2075-5309, PP 506-
531.
[9] S. C. Sharma (2013), “Construction Engineering &
Management of Projects”, ISBN 978-81-7409-234-2.
[10] Hong-Hai Tran and Nhat-Duc Hoang (2014), “A Novel
Resource-Leveling Approach for Construction
Project Based on Differential Evolution”, Hindawi
Publishing Corporation, Journal of Construction
Engineering, Volume 2014, Article ID 648938, 7
pages.
[11] Komesh Sahu and Meenu Sahu (2014), “Cost & Time
and Also Minimum Project Duration Using
Alternative Method”, International Review of
Applied Engineering Research. ISSN 2248-9967
Volume 4, Number 5 (2014), pp. 403-412.
[12] Urmila A Mahadik (2015), “Cost Reduction in
Construction Projects”, International Journal of
Engineering Technology, Management and Applied
Sciences, ISSN 2349-4476 Volume 3, Special Issue,
September 2015.
[13] Dr.P.Hima Bindu (2015), “Approach of Crashing
Critical Activity (CCA) and stretching Non-critical
Activity (SNA) of Time Cost Trade off problems using
Critical Path Method”, International Journal of
Scientific and Research Publications, Volume 5, Issue
2, February 2015, ISSN 2250-3153.
[14] Anuja rajguru and Parag mahatme (2016), “Effective
Techniques in cost optimization in construction
project”, International Journal of Research in
Engineering and Technology, eISSN: 2319-1163
pISSN: 2321-7308.
[15] S. K. Biswas, C. L. Karmaker, T. K. Biswas (2016),
“Time-Cost Trade-Off Analysis in a Construction
Project Problem: Case Study”, International Journal
of Computational Engineering Research (IJCER),
Volume 6, Issue 10, October – 2016, ISSN (e): 2250 –
3005.
[16] Dr. Euysup Shim and Dr. Seong Jin-kim (2016), “Cost
Item-based Markup Distribution in Construction
Projects”, The Journey of Technology, Management
and Applied Engineering, April 2016, Volume 32,
Number 1.
[17] D. B. Phadatare and S. B. Charhate (2016), “Impact of
Construction Equipment’s on Building Site
Productivity”, International Journal of Civil
Engineering and Technology (IJCIET), Volume 7,
Issue 4, July-August 2016, pp. 513–520.
[18] Prachi R. Ghate, Ashok B. More, Pravin R. Minde
(2016), “Importance of measurement of labour
productivity in construction”, IJRET: International
Journal of Research in Engineering and Technology
eISSN: 2319-1163 pISSN: 2321-7308.
[19] T. G. K. Vasista (2017), “Strategic cost management
for construction project success: A systematic
study”, Civil Engineering and Urban Planning: An
International Journal (CiVEJ) Vol.4, No.1, March
2017.
[20] Scheduled book of rates for various construction
material.

More Related Content

What's hot

10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
SHAZEBALIKHAN1
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?
Catherine Bendell
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
Essam Lotffy, PMP®, CCP®
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
Sayed Ahmed
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Project controls
Project controlsProject controls
Project controls
Ashok Kumar
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Shrikant Kate
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
IRJET Journal
 
Project Management Definitions
Project Management DefinitionsProject Management Definitions
Project Management Definitions
TURKI , PMP
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
Sagar Kaptan
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
SHAZEBALIKHAN1
 
Cost management
Cost managementCost management
Cost management
Suranji Kannangara
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
Venu Yemul
 
Engineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01webEngineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01web
GABISA DEMISIE
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
Amit Kumar Senapati, PMP®
 
Project cost management
Project cost managementProject cost management
Project cost management
ProjectManager247
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
AMARAYYA
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
Newman Jonathan
 

What's hot (20)

Cost Control Process for Construction
Cost Control Process for ConstructionCost Control Process for Construction
Cost Control Process for Construction
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Project controls
Project controlsProject controls
Project controls
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
 
Project Management Definitions
Project Management DefinitionsProject Management Definitions
Project Management Definitions
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
Cost management
Cost managementCost management
Cost management
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
Engineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01webEngineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01web
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 

Similar to IRJET- Implementing Time and Cost Optimization in Commercial Building using Project Management Techniques in Microsoft Project

IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
IRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
IRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
IRJET Journal
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
IRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET Journal
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
IRJET Journal
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET Journal
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
IRJET Journal
 
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET Journal
 
Construction project management
Construction project managementConstruction project management
Construction project management
saif hasan
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
B1303020508
B1303020508B1303020508
B1303020508
IOSR Journals
 
Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!
sanjeeev bahadur, m.tech,mba
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
briankirui9
 
Calculation of the construction time systematic management of project uncert...
Calculation of the construction time  systematic management of project uncert...Calculation of the construction time  systematic management of project uncert...
Calculation of the construction time systematic management of project uncert...
eSAT Journals
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET Journal
 
Innovative project management practices for large power sector projects.
Innovative project management  practices for large power sector projects.Innovative project management  practices for large power sector projects.
Innovative project management practices for large power sector projects.
sanjeeev bahadur, m.tech,mba
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
eSAT Journals
 

Similar to IRJET- Implementing Time and Cost Optimization in Commercial Building using Project Management Techniques in Microsoft Project (20)

IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial Buildings
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
B1303020508
B1303020508B1303020508
B1303020508
 
Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!Save USD 25 billion thru new project management practices!
Save USD 25 billion thru new project management practices!
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Calculation of the construction time systematic management of project uncert...
Calculation of the construction time  systematic management of project uncert...Calculation of the construction time  systematic management of project uncert...
Calculation of the construction time systematic management of project uncert...
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
Innovative project management practices for large power sector projects.
Innovative project management  practices for large power sector projects.Innovative project management  practices for large power sector projects.
Innovative project management practices for large power sector projects.
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

IRJET- Implementing Time and Cost Optimization in Commercial Building using Project Management Techniques in Microsoft Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 465 IMPLEMENTING TIME AND COST OPTIMIZATION IN COMMERCIAL BUILDING USING PROJECT MANAGEMENT TECHNIQUES IN MICROSOFT PROJECT Mr. Umesh Kamble1, Prof. Shashank U. Vanakudari2 1PG student, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India. 2 Assistant Professor, Civil Engineering Dept., Jain College of Engineering, Belagavi, Karnataka, India. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Project management is main stream which overall makes a civil industry worth into existence in accordance with the control on constraints such as time and cost. This paper will mainly help out to investigate the behavioural improvements in time according to the relative cost. Microsoft project software is used to enhance the scheduling adding Crashing, Slack time and alternative building material to the work planning activity. Crashing makes a proper inventory behavioural time benefits from the overtime of huge workforce and improvement in the duration of an activity using slack time in software. An alteration with the cost is maintained which helpful in retrogression of overall costs of the project. This project is very much applicable where the time and cost is the major constraint which make a building more economical. Key Words: Crashing, Slack time, Critical Path Method, Alternative Building Material, Polycarbonate Sheet. 1. INTRODUCTION In today’s era there are many heaps of sectors which are increasing globalisation & civilisation such as IT’s, Infrastructures, Energy conservative projects. In these, one of the major sector is Infrastructure which is profoundly increasing the economy of the country. Leading to this mainly time & cost is exceedingly more into consideration in this world. Everyone wants to be more conservative when it comes into time constraint & within shorter duration work should be done giving more profitable results. In the other way of profitable results cost constraint is predominating the efficiency of work to be done in construction industry. More often cost is directly proportional to the work to be carried out by the resources. In other aspects small scale construction industry could not take these constraints into consideration which leads to more cost overrun & time overrun. So it is better to optimize the time and cost which makes constraint flow off. Many projects have some risk and uncertainties which we not consider it orally but it comes into account when we execute it practically which makes increase in time, cost and overallocation of resources. So mainly recognising those uncertainties and doing a proper analysis one should make a project more feasible. So mainly the easiest way to minimize the cost of the project is the natural sustainable material and using the alternative materials which cut out the excess increase in the overall cost of the project. An analysis of raw materials and resources, from meeting up of parent material to their definitive composition, gives out a preferential judgmatic long term costs benefits. These benefits are paid to the clients, owner, the occupier, & the environment. Accordingly, time and cost of each item of work is estimated which gives ultimate time & cost of the project. Optimisation is the method of improving profit gain and effectively going through a sensible result under given state of affairs. The method in which the actual cost should not traverse the estimated cost limit is called as Cost Optimisation. There are mainly two areas where cost is optimised: 1.) Optimising during the pre-construction phase of the project i.e., Design stage. 2.) Optimising when the construction gets started by the project manager or the contractor. Optimisation means collecting all the data cost of the project and the advancement of work. The motive of the cost optimisation is to gain profit satisfactory without getting more chaos and finishing the work in actual estimated cost or lesser than it. 1.1 Objectives Key objectives in the construction sector is to complete each project in a timely manner, budget and quality. Building viability requires useful effectiveness, organizational persistence, cheap, swiftness and superiority. The behaviour of the project in various disputed areas is challenging. Often the construction company has to deal with the problems, it is always expensive to reduce time and save time by saving all the parties in the project having a commonality between profit time and expenditure. Time optimization is necessary and very important for construction projects. The purpose of time value optimization is that it is possible to fix the optimum project duration related to the minimum cost and it can be obtained with the help reducing the duration of critical tasks in the network by
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 466 violating critical activities reducing total project duration. In this study, the critical path method (CPM) with analysis path is used to find out the crash duration and crash costs and it is analysed to identify the relationship between them. The time and cost to create a model for optimization problems. In the part of the analysis, this will be for solving this problem done by manual methods. After that the explanations for the extension of the project were extended and then thereafter project crashing technology time and expense utility projects will be easy to implement contact with the results obtained satisfactorily, that the construction is an indication of the utility of this approach. The key project objectives is described below: 1. The main aim of this project is to reduce the improved development period from new time and to meet a specific deadline. 2. The main motivation behind this project is to reduce time using crashing and slack (Time Optimization). 3. For cost optimization alternative building material is used to reduce the cost and making project more well-organized and inexpensive. 2. METHODOLOGY Fig-1 Flowchart of Work Methodology 2.1 Crashing of an Activity A crashing of an activity is a method of reducing the overall decreasing the duration of an activity with the help of some techniques. Crashing is the performance that had better use when fast tracking has not hold back sufficient time in the database. In this technique the equipment and manual resources are added in terms of lowest possible techniques and cost. The advantage and disadvantages of the cost and the schedule are evaluated to conclude how to attain the highest quantity of firmness at the lowermost incremental cost. Crashing refers to a particular variety of compression of the project schedule that is carried out for the purpose of decreasing the total period of time (also known as the total duration of the project schedule). The decrease of the duration of the project is usually carried out after a careful and exhaustive analysis of all possible alternatives for minimizing the duration of the project in which each and every one of the methods to reach the maximum duration of the program by the lower additional cost. Crashing the schedule means adding extra resources in critical path without getting the highest level of efficiency to the important resources. It is another technique where you add the program to resources for extra time. On contrary to the crashing we are mainly into account of establishing or employing resources which could reduce the overall cost. Once we are aware of those activities crashing can be applied to the manageable activity of the project. 2.2 Crashing of Network Manually In specific projects, deduction of complete project schedule is necessary, even if its cost is increased. This is habitually desired where thinking of cost is persistent or less important than completing the project in the fullest time. It is generally possible to reduce the resources allocated to the project allocation by reducing the resources. Due to the escalation or reduction in cost of the project, the cost of the project has drop off or improved. For this resolution, time and cost are methodically evaluated. By scheduling the techniques of construction projects by network technologies, the rate of progress of each activity will produce the lowest practical cost. This is based on the distribution of progress materials, the number of workers available and the type of devices available for each activity at a minimum cost. When these projects are built in these situations, it is mentioned as a general program. However, sometimes it may be desirable to reduce the time needed to build the project. When normal time has been reduced, the project or its part is built under the program crash. For crashing of an activity following points is to be considered: 1. Rate of materials is increased. 2. Number of workers is increased. 3. Overtime work should be allotted with a higher pay scale per men hour of work.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 467 4. Additional unit of equipment is allotted to the critical activities. Furthermore, in crashing of an activity the two main constraints that is time and cost is always been inversely proportional to each other. Proper handling and making the project smooth one should be very careful against disputes which will make overall project more disturbed and may increase the total investment and capital budgeting of the project. 2.3 Crashing using Microsoft Project The main approaches for crashing of an activity in Microsoft project is: 1. Apportioning additional resources to the project which makes easy way for crashing of an activity. 2. Overtime allocated to the resources mainly human resource. 3. Hiring additional resources. 4. For Early completion extra payments. It would be possible to complete the outsourcing parts of the project within a short period of time if the same work was to be completed by internal resources. With the help of critical activity (The sum up of longest duration in a particular project) a in a particular project we can easily crash the duration of an activity. Non-critical activity may be unresolved and may not give better result and hence it is ineffective to crash an activity which is in Non-critical area. If a project regulates with a proper cost, time and quality material bound then it is easy to get a virtuous result with an ease of getting nicely quoted budget with reduced quality time. Meanwhile both the functions time and cost mainly stretch the proper way of budgeting. 2.4 Method of Crashing using Overtime Allocation According to the bureau of labour statistics the overtime is totally depend on the total wages of the construction project. Overtime can be calculated from total main hour worked on an activity should be 15 percent working on land project whereas it should be 25 percent for the work under dredging projects. For a project which is individually constituted the percentage should 1 to 34 on ground jobs and it should be 17 to 34 for dredging project. Due to extensive overtime in the nature of work under the study. By using modern equipment’s for allied operations as an alternative of human resources may increase the overall cost but has a tendency to decrease the overall duration of the project. This modern equipment eventually worked in an outdoor different seasonal condition which may extensively increase the overall operational cost of the project. The equipment should be used accordingly best suited seasonal conditions. So, it is good to increase the daily working time for heavy construction where modern equipment is required. In ideal conditions, 10 hours of working a day and 6 days a week in land operations when modern equipment’s is involved whereas dredging projects take a longer working hour because the dredge operated continuously. For dredging works in ideal condition, shifts have been prepared with at least one day off and organised 84 hours of work per day. It is mandatory to be very condemnatory whether to use the human resource or the modern mechanisation resource. For an enthusiastic result it should be a proper balance between the guidelines in accordance with the employing resources and the investments. 3. Slack Time Slack time in project management is a time in which an activity can increase or decrease the duration of the project without affecting succeeding overall tasks and overall duration of the project. It is also known as “Float time”. Slack time can be calculated by subtracting the time allotted from the overall duration of task. Such as if 12 days is being allotted for a particular project but it can be completed in 6 hours than the slack would be 6 days. Critical path designates zero slack of the construction project because any increase in time will indirectly affect the overall duration of the project. With the help of critical path and the overall slack in every non-critical activity, maximum slack can be calculated. 3.1 Types of Slack 1. Total slack. 2. Safety slack. 3. Free slack. 1. Total Slack: Without affecting the overall duration of the project the total slack is equivalent to the permissible increase in duration. It can be calculated as LFi - EFi = LSi - ESi With the LSi and LFi is denoted as latest start and latest finish time of an activity whereas EFi and Esi denotes the earliest start and earliest finish. 2. Safety Slack: When all predecessors finish late possibly then the safety slack is equal to provided delay of an activity. LSi – maxall predecessors j (LFj) Latest finish time (LFj) of an activity i that succeeds activity j. 3. Free slack: Free slack has not at all conclude on the earliest start of successor activity.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 468 Minall successor’s j (ESj) - EFi With Earliest start time (ESj) of an activity i that precedes activity j. 3.2 Total Slack Total slack is used to reduce the time in Microsoft Project. Microsoft Office Project bases its counts of Total slack on examinations of the dates in the Early Start, Early Finish, Late Start, and Late Finish fields for the assignment, which thus consider the dates for any successor errands. Add up to slack is figured as the littler estimation of the Late Finish short the Early Finish field, and the Late Start less the Early Start field. Utilize the Total Slack field to decide if the errand has whenever accessible for a postponement. This can be helpful if an asset needs additional time on an errand, or in the event that you need to allocate an asset to another assignment. You can likewise utilize the Aggregate Slack field to decide how to recoup a timetable that is slipping. 4. Alternative Building Material For this project work mainly, polycarbonate glasses are alternative for the structural glazing. It cuts down overall costs by 2-3 lakhs. Polycarbonate is a material which contains a group of carbonates in their chemically build structure. Polycarbonate is mainly as similar to a conventional transparent glass but inflexible as plastic. Polycarbonate glass is easily installed, cut and easily available in ribbed single sheet or flat twin-wall thicknesses. Advantages of Polycarbonate Glass Glazing: 1. Use of polycarbonate sheet is much lesser than the cost of insulated glass. Polycarbonate sheet may cut down the cost one-third to half from the insulated glass. 2. Polycarbonate sheet is 200 times stronger than insulated glass i.e. it provides structure with a very high impact resistance. This quality helps in getting stronger benefits to structure giving a proper maintained temperature resistance. 3. Polycarbonate sheet has a good fire resistance. Class 1 rating is given to polycarbonate sheet when tested according to BS476 part 7. 4. For heat reduction and controlling solar power it has a 25mm opal which provides a light transmission as low as 24%. 5. Polycarbonate sheets has a tendency to provide UV protection on the outer surface which helps in preventing sheets from UV radiation. 6. Polycarbonate sheet is very light weight and allows a greater deflection in comparison to glass. It can be easily available in sheet up to 39 feet which helps in reducing overall duration. 7. According to 2006 IBC slop glazing code polycarbonate is a safe glazing technique. 5. RESULTS AND DISCUSIONS 5.1 Results for Time Optimization The below figure shows optimizing the duration using planning and scheduling. The duration which is conventionally observed is 377 days which is being decreased by crashing and with the help of slack time. The approximately reduced duration is 349 days. Hence these constraints are mainly helpful in considering and reducing the overall costs of an activity or the whole project. These results are mainly helpful to induce more results from labour productivity using the overtime allocation. As we know that an individual labour can do minimum of 8 hours of work a day. But this project eventually distributed certain working activity into number of labours which does not make much hectic to the labour. Moreover, in construction project labours doesn’t engage to a specific activity but they are in huge number working of multi sets of work. As from case study practical labours actually applied in the project is dissimilar to the theoretical calculated labour so the number of labour applied in the software is from the actual working labours and their wages. Proper wages also attract the labours to work more which make project progress more into right way off time optimisation. Majorly for optimising time the methodology practically implemented is shift wise work schedule so that at a separate shift of schedule that is day and night shift labours and workers work easily without any hectic situations. Similarly using more modern equipment in construction project will also reduce time oriented objectives. But it is directly concerned with the availability issues. So overtiming allocation majorly attracts worker which is directly results into their weekly incentives and with a major workforce working at a site will also decrease the exertion on labour. The time optimisation is also depending on how well a contractor organises his work schedule with a proper utilisation of material, machineries and human resource. 5.2 Results for Cost Optimization The result mainly shows that how well organised material helps out in getting the cost more into economic zone. As we know that crashing of an activity consequently decreases the time by using several methods in construction project. But it will make an owner more satisfactory in consideration of before completion of project but it also makes more satisfying if the owner gets the result under the budgeted investments. So, in this project cost optimisation is done by using the alternative building oriented materials which
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 469 readily cut down the cost of the whole project but also satisfies owner with an economical result. So for alternative building material an insulated structural glass glazing is replaced by polycarbonate sheets which cuts the overall cost of the project. The cost of polycarbonate sheet is Rs. 700/ sq.m. which is considerably very much less compared to insulated structural glass glazing which is Rs. 5860/sq.m. as per scheduled rates book. Conventionally it is being seen that the cost of the project is Rs. 50,657,057.83/-, by applying crashing the cost again got increased due to reduction of work time which is Rs. 52,416,091.44/-. Again, by applying the alternative material cost the overall cost of the building is reduced by Rs. 48,879,432.36/-. So this method of cost optimisation majorly decrease the conventional cost of the project up to Rs. 17,77,625.47/- Chart -1: Reduction in Time Chart -2: Reduction in Cost 6.CONCLUSION As we had reduced the overall cost by 6.98 % and the overall duration by 7.71 %. This project concludes that any relative construction project mainly depends on the Time and Cost constraints which gives a proper economical weightage to any project. Moreover, it also depends on the project manager and types of resources which is involved in the project. Consequently, how the overtime will influence the project duration by simultaneously decreasing the slack time. A proper planning and scheduling will also make a huge difference in construction project considering the labour management. This project also concludes that the project effectively depends on the seasonal variations and the location such that it will be either advantageous or disadvantageous to the owner. It also concludes that proper maintained work ethics will also helpful to make a project more time and cost bound i.e. economical. REFERENCES [1] W. Willard Wirtz (1964), Bureau of labour statistics. [2] Luís Bragança, Ricardo Mateus and Heli Koukkari (2010), “Building Sustainibilty Assessment”, International Journal of Civil and Structural Engineering, ISSN 2071–1050. [3] Ashok Mohanty, Jibitesh Mishra, Biswajit Satpathy (2011), “Activity modes selection for project crashing through deterministic simulation”, Journal of Industrial Engineering and Management, JIEM 2011-4(4), ISSN 2013-0953, PP 610-623. [4] Omar M. Elmabrouk (2012), “Scheduling Project Crashing Time using Linear Programming Technique”, International Conference on Industrial Engineering and Operations Management Istanbul, Turkey, July 3 – 6, 2012. [5] Jong-Jin Kim (2012), “Qualities, Use and Examples of Sustainable Building Materials”, National Pollution Prevention Center for Higher Education, 430 E. University Ave., Ann Arbor, MI 48109-1115 734.764.1412. [6] Nafish Sarwar Islam (2013), “Complex Project Crashing Algorithm”, IOSR Journal of Business and Management (IOSR-JBM) e-ISSN: 2278-487X, p-ISSN: 2319-7668. Volume 11, Issue 4 (Jul. - Aug. 2013), PP 10-17. [7] Mrs. Ruchita Shrimali Vyas (2013), “Scheduling Project Management Using Crashing CPM Network to get Project completed on Time”, International Journal of Engineering Research & Technology (IJERT), ISSN: 2278-0181, Vol. 2 Issue 2, February-2013. 335 340 345 350 355 360 365 370 375 380 Overall time Crash time Normal time Crash time
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 470 [8] Nuhu Braimah (2013), “Construction Delay Analysis Techniques- A Review of Application Issues and Improvement Needs”, International Journal of Civil and Structural Engineering, ISSN 2075-5309, PP 506- 531. [9] S. C. Sharma (2013), “Construction Engineering & Management of Projects”, ISBN 978-81-7409-234-2. [10] Hong-Hai Tran and Nhat-Duc Hoang (2014), “A Novel Resource-Leveling Approach for Construction Project Based on Differential Evolution”, Hindawi Publishing Corporation, Journal of Construction Engineering, Volume 2014, Article ID 648938, 7 pages. [11] Komesh Sahu and Meenu Sahu (2014), “Cost & Time and Also Minimum Project Duration Using Alternative Method”, International Review of Applied Engineering Research. ISSN 2248-9967 Volume 4, Number 5 (2014), pp. 403-412. [12] Urmila A Mahadik (2015), “Cost Reduction in Construction Projects”, International Journal of Engineering Technology, Management and Applied Sciences, ISSN 2349-4476 Volume 3, Special Issue, September 2015. [13] Dr.P.Hima Bindu (2015), “Approach of Crashing Critical Activity (CCA) and stretching Non-critical Activity (SNA) of Time Cost Trade off problems using Critical Path Method”, International Journal of Scientific and Research Publications, Volume 5, Issue 2, February 2015, ISSN 2250-3153. [14] Anuja rajguru and Parag mahatme (2016), “Effective Techniques in cost optimization in construction project”, International Journal of Research in Engineering and Technology, eISSN: 2319-1163 pISSN: 2321-7308. [15] S. K. Biswas, C. L. Karmaker, T. K. Biswas (2016), “Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study”, International Journal of Computational Engineering Research (IJCER), Volume 6, Issue 10, October – 2016, ISSN (e): 2250 – 3005. [16] Dr. Euysup Shim and Dr. Seong Jin-kim (2016), “Cost Item-based Markup Distribution in Construction Projects”, The Journey of Technology, Management and Applied Engineering, April 2016, Volume 32, Number 1. [17] D. B. Phadatare and S. B. Charhate (2016), “Impact of Construction Equipment’s on Building Site Productivity”, International Journal of Civil Engineering and Technology (IJCIET), Volume 7, Issue 4, July-August 2016, pp. 513–520. [18] Prachi R. Ghate, Ashok B. More, Pravin R. Minde (2016), “Importance of measurement of labour productivity in construction”, IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 pISSN: 2321-7308. [19] T. G. K. Vasista (2017), “Strategic cost management for construction project success: A systematic study”, Civil Engineering and Urban Planning: An International Journal (CiVEJ) Vol.4, No.1, March 2017. [20] Scheduled book of rates for various construction material.