SlideShare a Scribd company logo
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 13, Issue 3, Ver. II (May- Jun. 2016), PP 05-08
www.iosrjournals.org
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 5 | Page
Planning And Scheduling With Optimization Of Cost And Time
Of Six Lane Bridge With Cast In Situ And Precast Elements At
Kolathur, Chennai
Mr.S.Ashik Ahamed 1
, Dr.V.Thamilarasu 2
Mr.R.Padmanaban 3
1
(M.Tech CEM,, Civil Engineering Department, SRM University, Chennai ,India)
2
(Professor – Civil, Civil Engineering Department, SRM University, Chennai,India)
3
(Research Scholar, Civil Engineering Department, Anna University, Chennai,India)
Abstract: Construction industries play a vital role in the economy of all developing countries including India.
In any construction “Time and cost” are the two main concerns which decide the effectiveness of the project.
Further, optimization of time and cost is also very vital. This has increased the importance of adopting time and
Cost optimization in all construction projects. Optimization is a systematic effort made to ensure a reasonable
profit margins and to obtain the best results under given circumstances or situations.
The optimization of “Time and cost” in any construction project can be obtained by proper planning and
scheduling of each part or activity involved and by using multiple construction techniques.
Here It is proposed to try to optimize the “Time and cost” involved in a highway bridge construction at
Kolathur junction, Chennai. For the optimization of “Time and cost’ involved in the project, two different
construction techniques called “ Cast in situ method” & “Pre cast technology”, are analyzed and optimum
planning and scheduling is prepared.
Keywords: Construction Industry, Time&Cost, Cast in situ Elements, Precast Elements, Cost Optimization)
I. Introduction
There are many challenges faced by the construction industries which include, design and
Constructability issues, land acquisition issues, adverse political changes, shortage of talent, time and cost
related issues, material and labour cost escalations, structural changes. Time and cost are two main factors in
planning of construction projects and hence there is an increase in importance of time and Cost optimization. It
is important to estimate the time and cost of each activity through which the total duration and total cost of the
project are determined for the planning task. Optimization is a systematic effort made to improve profit margins
and obtain the best results under given circumstances or situations. The main objective of cost optimization of a
project is to gain the maximum profit within the design period and with satisfactory quality of work.
1.1 Objective of the project
To prepare a detailed planning and work schedule with optimization of cost and time including cost
estimate for the construction of Six Lane Bridge with “cast in situ” and “precast elements” at Kolathur,
Chennai .
1.2 Scope of the project
The exercise of optimizing the cost and time through value planning and scheduling for both cast in
situ and Precast Construction method can be extended to other similar projects in our country.
1.3 Project Goals
A project is successful when the needs of the stakeholders have been met. A stakeholder is anybody
directly or indirectly impacted by the project.
As a first step it is important to identify the stakeholders in your project. It is not always easy to
identify the stakeholders of a project, particularly those impacted indirectly. Examples of stakeholders are:
 The project sponsor
 The customer who receives the deliverables
 The users of the project outputs
 The project manager and project team
1.4 Project Methodology
An efficient project control methodology systems generates information that can improve the
productivity of men and materials economize the employment of resources;
Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ..
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 6 | Page
The methodology adopted involves the following steps.
 Collection of all relevant and required data of Six Lane Bridge work at Kolathur at Chennai from Highways
Department and Contractor.
 Carrying out Preliminary Analysis and Detailed Analysis of the project proposal.
 Preparing a detailed planning and work schedule with optimization of cost and time using PRIMAVERA
and preparing the cost estimate for both cast in situ and precast elements.
 Comparing the Cost and Project time for Cast in Situ and Precast Elements and proposing the best for
adoption.
II. Literature Review
2.1 Introduction
In this chapter a review of literature of the techniques used in planning and scheduling of Construction
projects are presented.
2.2 Definitions & Findings
A. Christ.Hendrickson (1990) - Use of Advanced Scheduling Techniques
In this study he explained Construction project scheduling is a topic that has received extensive
research over a number of decades. With the availability of more powerful computers and software, the use of
advanced scheduling techniques is becoming easier and of greater relevance to practice
K.K.Chitkara (1998) - Explains the methodology used in Planning and Scheduling of Construction
Projects.
In this study he explained the methodology used in Planning and Scheduling of Construction Projects.
Shanmugapriya S., Dr. Subramanian K.,( 2013) - “Investigation of Significant Factors Influencing Time
And Cost”
In this study they explained, Time and cost overruns is a severe problems faced by large construction
industries in India. They was found that five most significant factors causing time and cost overruns in Indian
construction are material, market rate, contract modification, high level of quality requirement, project location,
depends on the freshers to bear the whole responsibility for time overruns and high transportation cost, change
in materials specification, escalation of material price, frequent breakdown of construction machineries and
rework for cost overrun.
Mr.CI Anyanwu (2013) – Project Cost control in the Nigerian Construction Industry
In this study they explained, the resources well managed or mismanaged today that makes for
tomorrow prosperity or depression. The economic depression we are now facing is more out of mismanagement
of resources than lack of resources.
Mr.Seyed Ali Mousavi Dehmourdi (2014) – Optimization of Construction Cost Applying Advanced
Techniques
In this study he explained, Construction industry can do a better job by using advanced construction
techniques. Systematic data collection, analysis, reviews to monitor progress will reduce the possible errors in
any project thereby avoiding all possible expenditure. He considered least cost method / North West corner
Method can be the best result oriented of transportation problem to optimize the transportation cost.
Prof.Dipak.P.Patil , Prof. Pankaj P.Bhangale & Swapnil S.Kulkarni (2014) – “ Study of Cost Control on
Construction Project
In this study they explained, they are observed that the major factors that contributes to poor inventory
control are -
a) Improper management of time, cost and manpower.
b) Ignorance of contractor towards material management in construction project.
Ms.Anuja Rajguru, & Mr.Parag Mahatme (2015) - Effective Techniques in Cost optimization of
construction project
In this study they analyzed different techniques for optimization and found the construction cost and
duration at each stage is important to minimize
III. Research
3.1 Cost Optimization Techniques
It is necessary to decide which optimization is required and amount of detail that will be in used into
the construction stage. Many cost optimization methods have been implemented in the past by different
companies and have not survived. The cost itself is a major difficulty in operating a detailed cost optimization
system. It is an expensive operation for a large contract to carry out a detailed cost optimization system. There
are three types of cost optimization system; they are by comparison with a cost standard, by subdivision by
detail and by integration with other functions. In comparison with a cost standard method, the standard set up by
Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ..
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 7 | Page
estimator is compared at the time of tender. For example, it may be combined with a labor utilization scheme, in
which the optimization is kept on the optimal utilization of the labor employed.
3.2Time optimization Techniques:
A general mathematical formulation is presented for the scheduling of construction projects and is applied to
the problem of highway construction scheduling. The new construction scheduling model provides the
capabilities of both the critical path method ( CPM) and linear scheduling method ( LSM) approaches.
Repetitive and non-repetitive tasks, multiple group strategies, work continuity constraints and the effects of
varying job conditions on the performance of a team can be modeled. An optimization formulation is presented
for the construction project scheduling problem, with the goal of minimizing the direct construction cost. For
any given construction duration, the model yields the optimum construction schedule for minimum construction
cost automatically.
The project is scheduled for both the techniques cast in situ and precast, which is tabulated in Table 2 & 3.
The details cost estimate is worked out by using MS Excel and shown in Table.4.
Table.2 Programme with Cast in Situ Elements
S.No Task Name Start Date Finish Date Duration in Days
OVERALL DURATION 27.03.2016 03.07.2017 464
1 Foundation Works 27.03.2016 21.07.2016 117
2 Sub Structure Works 02.04.2016 26.07.2016 116
3 Super Structure Works 09.05.2016 28.06.2017 416
4 RE Wall 15.06.2016 31.03.2017 290
5 Road Works 02.12.2016 19.06.2017 200
6 Painting Works 02.03.2017 04.06.2017 95
7 Handing Over 24.06.2017 03.07.2017 10
Table No.4 Cost Estimate Abstract for Both Cast in Situ and Precast Elements
S.No Task Name Cast in situ Elements Precast Elements
Amount In Lakhs
1 Earth Work Excavation 12.53 12.53
2 Piling Works 701.40 701.40
3 Structure Works ( PCC / RCC) 979.49 929.27
4 Reinforcement Steel 1587.60 1587.60
5 HTS Strands 96.10 209.25
6 Bearing 57.39 57.39
7 Strip Seal Expansion Joint 34.65 34.65
8 G.I.Drainage Spout 6.50 6.50
9 Mastic With BC 142.00 142.00
10 Road Works 602.40 602.40
11 RE Wall 604.44 604.44
12 Painting Works 203.11 203.11
13 Erection of Girders 118.96
TOTAL 5027.61 5209.50
The Cost benefit over the time is considered as advantage in precast construction method, because all other
recurring costs like right of way maintenance, resurfacing at an fixed intervals etc are same in both the cases.
The cost benefit over time optimization is
 Interest over the capital cost at 14.5% Per Annum
Rs.50.27 Crores x 14.5% /365days x 184 Days = Rs.3.67 Crores
 As per traffic survey 11721 PCU / HR So the interest on time
Savings value by the road users
11721 x 24 Hrs x 184 days x Rs.50/ Vehicle x14.5% /365 days = Rs.0.11 Crores
Total Cost benefit due to time savings = Rs.3.78 Crores
Table.3 Programme with Pre Cast Elements
S.No Task Name Start Date Finish Date Duration in Days
OVERALL DURATION 07.04.2016 11.01.2017 280
1 Foundation Works 14.04.2016 03.08.2016 112
2 Sub Structure Works 11.05.2016 24.08.2016 106
3 Super Structure Works 07.04.2016 01.10.2016 178
4 RE Wall 12.05.2016 23.10.2016 165
5 Road Works 26.06.2016 22.11.2016 200
6 Painting Works 24.09.2016 27.12.2016 95
7 Handing Over 23.12.2016 11.01.2017 21
Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ..
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 8 | Page
Estimated cost of construction Using Precast Element = Rs.52.09 Crores
Cost benefit due to time Savings = (-) Rs. 3.78 Crores
Net Cost by Using Precast construction technique = Rs.48.31 Crores
ITEMS CAST IN SITU ELEMENTS PRECAST ELEMENTS ADVANTAGE
Time 464 Days 280 Days Early completion of 184 days
Cost Rs.50.27 Crores Rs.48.31 Crores Rs.1.96 Crores Savings over using Cast in
situ elements
IV. Conclusion
 From the results obtained, it is observed that when the Pre Cast Elements is used in the construction of
Bridges, the total project cost and the duration of the project is lesser than the Construction of Bridges by
Cast in Situ.
 The Pre Cast Girders can be Casted simultaneously along with substructure construction and hence the
structure duration could be reduced by184 days (35 to 40 percent) over the Construction of Bridges by
cast in Situ.
 The Precast construction can achieve not only faster rate of construction and can also bring down the
estimated cost by 1.96 Crores (3 to 5 percent) over the Construction of Bridges by Cast in Situ method
with lesser labour inputs and minimum disturbance to the existing traffic.
References
Journal papers
[1] Dr.Harold Kerzner Ph.D –A System Approach to Planning , Scheduling and Controlling – Eighth Edition (2003)
[2] Shanmugapriya S., Dr. Subramanian K.,( 2013) - “Investigation of Significant Factors Influencing Time And Cost”
[3] Mr.CI Anyanwu (2013) – Project Cost control in the Nigerian Construction Industry.
[4] Mr.Seyed Ali Mousavi Dehmourdi (2014) – Optimization of Construction Cost Applying Advanced Techniques
[5] Ms.Anuja Rajguru, & Mr.Parag Mahatme (2015) - Effective Techniques in Cost optimization of construction project
Chapter in Books
[6] Christ.Hendrickson (1990) - Use of Advanced Scheduling Techniques

More Related Content

What's hot

Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
IJERA Editor
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
IRJET Journal
 
1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri
Oyeniyi Samuel
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
eSAT Publishing House
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise Building
IJERA Editor
 
IRJET - Optimum Utilization of Construction Resources: A Review
IRJET -  	  Optimum Utilization of Construction Resources: A ReviewIRJET -  	  Optimum Utilization of Construction Resources: A Review
IRJET - Optimum Utilization of Construction Resources: A Review
IRJET Journal
 
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheorySenstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
IRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET Journal
 
Role of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case StudyRole of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case Study
IJERA Editor
 
time-cost-quality.pdf
time-cost-quality.pdftime-cost-quality.pdf
time-cost-quality.pdf
sam26a
 
Use of network scheduling technique
Use of network scheduling technique Use of network scheduling technique
Use of network scheduling technique
Siva Pradeep Bolisetti
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
 
Network scheduling
Network schedulingNetwork scheduling
Network scheduling
Ravi Shekhar
 
Cost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen RaymentCost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen Rayment
Stephen Rayment UK
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
Vamsi Kovalam
 
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...
ijiert bestjournal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET Journal
 
Ijetr012001
Ijetr012001Ijetr012001
Ijetr012001
ER Publication.org
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
IOSR Journals
 
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
IJERA Editor
 

What's hot (20)

Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri1. article azojete vol 10 1 11 waziri
1. article azojete vol 10 1 11 waziri
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise Building
 
IRJET - Optimum Utilization of Construction Resources: A Review
IRJET -  	  Optimum Utilization of Construction Resources: A ReviewIRJET -  	  Optimum Utilization of Construction Resources: A Review
IRJET - Optimum Utilization of Construction Resources: A Review
 
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheorySenstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Role of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case StudyRole of PMC in Construction of Collector Well Project, a Case Study
Role of PMC in Construction of Collector Well Project, a Case Study
 
time-cost-quality.pdf
time-cost-quality.pdftime-cost-quality.pdf
time-cost-quality.pdf
 
Use of network scheduling technique
Use of network scheduling technique Use of network scheduling technique
Use of network scheduling technique
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Network scheduling
Network schedulingNetwork scheduling
Network scheduling
 
Cost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen RaymentCost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen Rayment
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
 
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
Ijetr012001
Ijetr012001Ijetr012001
Ijetr012001
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
 
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
 

Viewers also liked

E017263040
E017263040E017263040
E017263040
IOSR Journals
 
H017215057
H017215057H017215057
H017215057
IOSR Journals
 
Q0173299104
Q0173299104Q0173299104
Q0173299104
IOSR Journals
 
J012455865
J012455865J012455865
J012455865
IOSR Journals
 
R01821116120
R01821116120R01821116120
R01821116120
IOSR Journals
 
B017221317
B017221317B017221317
B017221317
IOSR Journals
 
I012135157
I012135157I012135157
I012135157
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
F010214352
F010214352F010214352
F010214352
IOSR Journals
 
Encryption Technique for a Trusted Cloud Computing Environment
Encryption Technique for a Trusted Cloud Computing EnvironmentEncryption Technique for a Trusted Cloud Computing Environment
Encryption Technique for a Trusted Cloud Computing Environment
IOSR Journals
 
Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...
Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...
Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...
IOSR Journals
 
V01761152156
V01761152156V01761152156
V01761152156
IOSR Journals
 
F0552935
F0552935F0552935
F0552935
IOSR Journals
 
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver DiseaseCore Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
IOSR Journals
 
L1303046572
L1303046572L1303046572
L1303046572
IOSR Journals
 
K017367680
K017367680K017367680
K017367680
IOSR Journals
 
B0310711
B0310711B0310711
B0310711
IOSR Journals
 
J011138795
J011138795J011138795
J011138795
IOSR Journals
 
F1803023843
F1803023843F1803023843
F1803023843
IOSR Journals
 
A018140107
A018140107A018140107
A018140107
IOSR Journals
 

Viewers also liked (20)

E017263040
E017263040E017263040
E017263040
 
H017215057
H017215057H017215057
H017215057
 
Q0173299104
Q0173299104Q0173299104
Q0173299104
 
J012455865
J012455865J012455865
J012455865
 
R01821116120
R01821116120R01821116120
R01821116120
 
B017221317
B017221317B017221317
B017221317
 
I012135157
I012135157I012135157
I012135157
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
F010214352
F010214352F010214352
F010214352
 
Encryption Technique for a Trusted Cloud Computing Environment
Encryption Technique for a Trusted Cloud Computing EnvironmentEncryption Technique for a Trusted Cloud Computing Environment
Encryption Technique for a Trusted Cloud Computing Environment
 
Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...
Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...
Overview of Improving Robustness of MAODV Protocol by Combining Tree and Mesh...
 
V01761152156
V01761152156V01761152156
V01761152156
 
F0552935
F0552935F0552935
F0552935
 
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver DiseaseCore Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
Core Components of the Metabolic Syndrome in Nonalcohlic Fatty Liver Disease
 
L1303046572
L1303046572L1303046572
L1303046572
 
K017367680
K017367680K017367680
K017367680
 
B0310711
B0310711B0310711
B0310711
 
J011138795
J011138795J011138795
J011138795
 
F1803023843
F1803023843F1803023843
F1803023843
 
A018140107
A018140107A018140107
A018140107
 

Similar to B1303020508

Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
IJAEMSJORNAL
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
Dawn Cook
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
Nat Rice
 
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaValue Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
AI Publications
 
asdfds
asdfdsasdfds
asdfds
fkdnld1
 
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTIONEFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
IAEME Publication
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET Journal
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
eSAT Publishing House
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A Review
IRJET Journal
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
IRJET Journal
 
Application of last planner system
Application of last planner systemApplication of last planner system
Application of last planner system
Anshi Verma
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
IRJET Journal
 
Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...
NellutlaKishore
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
IRJET Journal
 
Construction project management
Construction project managementConstruction project management
Construction project management
saif hasan
 
Application of Value Engineering in Commercial Building Projects
Application of Value Engineering in  Commercial Building ProjectsApplication of Value Engineering in  Commercial Building Projects
Application of Value Engineering in Commercial Building Projects
nitinrane33
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
Sagar Kaptan
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
IRJET Journal
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
IRJET Journal
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
Beth Hall
 

Similar to B1303020508 (20)

Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
 
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaValue Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
 
asdfds
asdfdsasdfds
asdfds
 
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTIONEFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A Review
 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
 
Application of last planner system
Application of last planner systemApplication of last planner system
Application of last planner system
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...Modern methods of constructions and their impact upon estimation of cost plan...
Modern methods of constructions and their impact upon estimation of cost plan...
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Application of Value Engineering in Commercial Building Projects
Application of Value Engineering in  Commercial Building ProjectsApplication of Value Engineering in  Commercial Building Projects
Application of Value Engineering in Commercial Building Projects
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
 

More from IOSR Journals

A011140104
A011140104A011140104
A011140104
IOSR Journals
 
M0111397100
M0111397100M0111397100
M0111397100
IOSR Journals
 
L011138596
L011138596L011138596
L011138596
IOSR Journals
 
K011138084
K011138084K011138084
K011138084
IOSR Journals
 
J011137479
J011137479J011137479
J011137479
IOSR Journals
 
I011136673
I011136673I011136673
I011136673
IOSR Journals
 
G011134454
G011134454G011134454
G011134454
IOSR Journals
 
H011135565
H011135565H011135565
H011135565
IOSR Journals
 
F011134043
F011134043F011134043
F011134043
IOSR Journals
 
E011133639
E011133639E011133639
E011133639
IOSR Journals
 
D011132635
D011132635D011132635
D011132635
IOSR Journals
 
C011131925
C011131925C011131925
C011131925
IOSR Journals
 
B011130918
B011130918B011130918
B011130918
IOSR Journals
 
A011130108
A011130108A011130108
A011130108
IOSR Journals
 
I011125160
I011125160I011125160
I011125160
IOSR Journals
 
H011124050
H011124050H011124050
H011124050
IOSR Journals
 
G011123539
G011123539G011123539
G011123539
IOSR Journals
 
F011123134
F011123134F011123134
F011123134
IOSR Journals
 
E011122530
E011122530E011122530
E011122530
IOSR Journals
 
D011121524
D011121524D011121524
D011121524
IOSR Journals
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
CatarinaPereira64715
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 

Recently uploaded (20)

DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 

B1303020508

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 13, Issue 3, Ver. II (May- Jun. 2016), PP 05-08 www.iosrjournals.org DOI: 10.9790/1684-1303020508 www.iosrjournals.org 5 | Page Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ And Precast Elements At Kolathur, Chennai Mr.S.Ashik Ahamed 1 , Dr.V.Thamilarasu 2 Mr.R.Padmanaban 3 1 (M.Tech CEM,, Civil Engineering Department, SRM University, Chennai ,India) 2 (Professor – Civil, Civil Engineering Department, SRM University, Chennai,India) 3 (Research Scholar, Civil Engineering Department, Anna University, Chennai,India) Abstract: Construction industries play a vital role in the economy of all developing countries including India. In any construction “Time and cost” are the two main concerns which decide the effectiveness of the project. Further, optimization of time and cost is also very vital. This has increased the importance of adopting time and Cost optimization in all construction projects. Optimization is a systematic effort made to ensure a reasonable profit margins and to obtain the best results under given circumstances or situations. The optimization of “Time and cost” in any construction project can be obtained by proper planning and scheduling of each part or activity involved and by using multiple construction techniques. Here It is proposed to try to optimize the “Time and cost” involved in a highway bridge construction at Kolathur junction, Chennai. For the optimization of “Time and cost’ involved in the project, two different construction techniques called “ Cast in situ method” & “Pre cast technology”, are analyzed and optimum planning and scheduling is prepared. Keywords: Construction Industry, Time&Cost, Cast in situ Elements, Precast Elements, Cost Optimization) I. Introduction There are many challenges faced by the construction industries which include, design and Constructability issues, land acquisition issues, adverse political changes, shortage of talent, time and cost related issues, material and labour cost escalations, structural changes. Time and cost are two main factors in planning of construction projects and hence there is an increase in importance of time and Cost optimization. It is important to estimate the time and cost of each activity through which the total duration and total cost of the project are determined for the planning task. Optimization is a systematic effort made to improve profit margins and obtain the best results under given circumstances or situations. The main objective of cost optimization of a project is to gain the maximum profit within the design period and with satisfactory quality of work. 1.1 Objective of the project To prepare a detailed planning and work schedule with optimization of cost and time including cost estimate for the construction of Six Lane Bridge with “cast in situ” and “precast elements” at Kolathur, Chennai . 1.2 Scope of the project The exercise of optimizing the cost and time through value planning and scheduling for both cast in situ and Precast Construction method can be extended to other similar projects in our country. 1.3 Project Goals A project is successful when the needs of the stakeholders have been met. A stakeholder is anybody directly or indirectly impacted by the project. As a first step it is important to identify the stakeholders in your project. It is not always easy to identify the stakeholders of a project, particularly those impacted indirectly. Examples of stakeholders are:  The project sponsor  The customer who receives the deliverables  The users of the project outputs  The project manager and project team 1.4 Project Methodology An efficient project control methodology systems generates information that can improve the productivity of men and materials economize the employment of resources;
  • 2. Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ.. DOI: 10.9790/1684-1303020508 www.iosrjournals.org 6 | Page The methodology adopted involves the following steps.  Collection of all relevant and required data of Six Lane Bridge work at Kolathur at Chennai from Highways Department and Contractor.  Carrying out Preliminary Analysis and Detailed Analysis of the project proposal.  Preparing a detailed planning and work schedule with optimization of cost and time using PRIMAVERA and preparing the cost estimate for both cast in situ and precast elements.  Comparing the Cost and Project time for Cast in Situ and Precast Elements and proposing the best for adoption. II. Literature Review 2.1 Introduction In this chapter a review of literature of the techniques used in planning and scheduling of Construction projects are presented. 2.2 Definitions & Findings A. Christ.Hendrickson (1990) - Use of Advanced Scheduling Techniques In this study he explained Construction project scheduling is a topic that has received extensive research over a number of decades. With the availability of more powerful computers and software, the use of advanced scheduling techniques is becoming easier and of greater relevance to practice K.K.Chitkara (1998) - Explains the methodology used in Planning and Scheduling of Construction Projects. In this study he explained the methodology used in Planning and Scheduling of Construction Projects. Shanmugapriya S., Dr. Subramanian K.,( 2013) - “Investigation of Significant Factors Influencing Time And Cost” In this study they explained, Time and cost overruns is a severe problems faced by large construction industries in India. They was found that five most significant factors causing time and cost overruns in Indian construction are material, market rate, contract modification, high level of quality requirement, project location, depends on the freshers to bear the whole responsibility for time overruns and high transportation cost, change in materials specification, escalation of material price, frequent breakdown of construction machineries and rework for cost overrun. Mr.CI Anyanwu (2013) – Project Cost control in the Nigerian Construction Industry In this study they explained, the resources well managed or mismanaged today that makes for tomorrow prosperity or depression. The economic depression we are now facing is more out of mismanagement of resources than lack of resources. Mr.Seyed Ali Mousavi Dehmourdi (2014) – Optimization of Construction Cost Applying Advanced Techniques In this study he explained, Construction industry can do a better job by using advanced construction techniques. Systematic data collection, analysis, reviews to monitor progress will reduce the possible errors in any project thereby avoiding all possible expenditure. He considered least cost method / North West corner Method can be the best result oriented of transportation problem to optimize the transportation cost. Prof.Dipak.P.Patil , Prof. Pankaj P.Bhangale & Swapnil S.Kulkarni (2014) – “ Study of Cost Control on Construction Project In this study they explained, they are observed that the major factors that contributes to poor inventory control are - a) Improper management of time, cost and manpower. b) Ignorance of contractor towards material management in construction project. Ms.Anuja Rajguru, & Mr.Parag Mahatme (2015) - Effective Techniques in Cost optimization of construction project In this study they analyzed different techniques for optimization and found the construction cost and duration at each stage is important to minimize III. Research 3.1 Cost Optimization Techniques It is necessary to decide which optimization is required and amount of detail that will be in used into the construction stage. Many cost optimization methods have been implemented in the past by different companies and have not survived. The cost itself is a major difficulty in operating a detailed cost optimization system. It is an expensive operation for a large contract to carry out a detailed cost optimization system. There are three types of cost optimization system; they are by comparison with a cost standard, by subdivision by detail and by integration with other functions. In comparison with a cost standard method, the standard set up by
  • 3. Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ.. DOI: 10.9790/1684-1303020508 www.iosrjournals.org 7 | Page estimator is compared at the time of tender. For example, it may be combined with a labor utilization scheme, in which the optimization is kept on the optimal utilization of the labor employed. 3.2Time optimization Techniques: A general mathematical formulation is presented for the scheduling of construction projects and is applied to the problem of highway construction scheduling. The new construction scheduling model provides the capabilities of both the critical path method ( CPM) and linear scheduling method ( LSM) approaches. Repetitive and non-repetitive tasks, multiple group strategies, work continuity constraints and the effects of varying job conditions on the performance of a team can be modeled. An optimization formulation is presented for the construction project scheduling problem, with the goal of minimizing the direct construction cost. For any given construction duration, the model yields the optimum construction schedule for minimum construction cost automatically. The project is scheduled for both the techniques cast in situ and precast, which is tabulated in Table 2 & 3. The details cost estimate is worked out by using MS Excel and shown in Table.4. Table.2 Programme with Cast in Situ Elements S.No Task Name Start Date Finish Date Duration in Days OVERALL DURATION 27.03.2016 03.07.2017 464 1 Foundation Works 27.03.2016 21.07.2016 117 2 Sub Structure Works 02.04.2016 26.07.2016 116 3 Super Structure Works 09.05.2016 28.06.2017 416 4 RE Wall 15.06.2016 31.03.2017 290 5 Road Works 02.12.2016 19.06.2017 200 6 Painting Works 02.03.2017 04.06.2017 95 7 Handing Over 24.06.2017 03.07.2017 10 Table No.4 Cost Estimate Abstract for Both Cast in Situ and Precast Elements S.No Task Name Cast in situ Elements Precast Elements Amount In Lakhs 1 Earth Work Excavation 12.53 12.53 2 Piling Works 701.40 701.40 3 Structure Works ( PCC / RCC) 979.49 929.27 4 Reinforcement Steel 1587.60 1587.60 5 HTS Strands 96.10 209.25 6 Bearing 57.39 57.39 7 Strip Seal Expansion Joint 34.65 34.65 8 G.I.Drainage Spout 6.50 6.50 9 Mastic With BC 142.00 142.00 10 Road Works 602.40 602.40 11 RE Wall 604.44 604.44 12 Painting Works 203.11 203.11 13 Erection of Girders 118.96 TOTAL 5027.61 5209.50 The Cost benefit over the time is considered as advantage in precast construction method, because all other recurring costs like right of way maintenance, resurfacing at an fixed intervals etc are same in both the cases. The cost benefit over time optimization is  Interest over the capital cost at 14.5% Per Annum Rs.50.27 Crores x 14.5% /365days x 184 Days = Rs.3.67 Crores  As per traffic survey 11721 PCU / HR So the interest on time Savings value by the road users 11721 x 24 Hrs x 184 days x Rs.50/ Vehicle x14.5% /365 days = Rs.0.11 Crores Total Cost benefit due to time savings = Rs.3.78 Crores Table.3 Programme with Pre Cast Elements S.No Task Name Start Date Finish Date Duration in Days OVERALL DURATION 07.04.2016 11.01.2017 280 1 Foundation Works 14.04.2016 03.08.2016 112 2 Sub Structure Works 11.05.2016 24.08.2016 106 3 Super Structure Works 07.04.2016 01.10.2016 178 4 RE Wall 12.05.2016 23.10.2016 165 5 Road Works 26.06.2016 22.11.2016 200 6 Painting Works 24.09.2016 27.12.2016 95 7 Handing Over 23.12.2016 11.01.2017 21
  • 4. Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ.. DOI: 10.9790/1684-1303020508 www.iosrjournals.org 8 | Page Estimated cost of construction Using Precast Element = Rs.52.09 Crores Cost benefit due to time Savings = (-) Rs. 3.78 Crores Net Cost by Using Precast construction technique = Rs.48.31 Crores ITEMS CAST IN SITU ELEMENTS PRECAST ELEMENTS ADVANTAGE Time 464 Days 280 Days Early completion of 184 days Cost Rs.50.27 Crores Rs.48.31 Crores Rs.1.96 Crores Savings over using Cast in situ elements IV. Conclusion  From the results obtained, it is observed that when the Pre Cast Elements is used in the construction of Bridges, the total project cost and the duration of the project is lesser than the Construction of Bridges by Cast in Situ.  The Pre Cast Girders can be Casted simultaneously along with substructure construction and hence the structure duration could be reduced by184 days (35 to 40 percent) over the Construction of Bridges by cast in Situ.  The Precast construction can achieve not only faster rate of construction and can also bring down the estimated cost by 1.96 Crores (3 to 5 percent) over the Construction of Bridges by Cast in Situ method with lesser labour inputs and minimum disturbance to the existing traffic. References Journal papers [1] Dr.Harold Kerzner Ph.D –A System Approach to Planning , Scheduling and Controlling – Eighth Edition (2003) [2] Shanmugapriya S., Dr. Subramanian K.,( 2013) - “Investigation of Significant Factors Influencing Time And Cost” [3] Mr.CI Anyanwu (2013) – Project Cost control in the Nigerian Construction Industry. [4] Mr.Seyed Ali Mousavi Dehmourdi (2014) – Optimization of Construction Cost Applying Advanced Techniques [5] Ms.Anuja Rajguru, & Mr.Parag Mahatme (2015) - Effective Techniques in Cost optimization of construction project Chapter in Books [6] Christ.Hendrickson (1990) - Use of Advanced Scheduling Techniques