A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
Project planning is the important task in many areas like construction, resource allocation and many. A sequence of activities has to be performed to complete one task. Each activity has its unique processing time and all together to identify the critical activities which affect the completion of the project. In this paper the probabilistic and deterministic models to determine the project completion time and also the critical activities are considered. A case study on building construction project has been performed to demonstrate the application of the above said models. The two project scheduling namely PERT and CPM are used to determine numerically the different types of floating times of each activity and hence determined the critical path which plays an important role in the project completion time. Also a linear programing model has been developed to reduce the project completion time which optimize the resource allocation. To apply these techniques numerically the primary data from a housing project company in a metropolitan city has been taken, the network diagram of the activities involved in the building construction project has been drawn and the results are tabulated
Planning is a guideline in implementing the project so that development can be
implemented in accordance with the time and cost planned. Control discrepancy
between initial plan and realization that exists in implementation project required a
project management, therefore required optimization analysis of project duration, so
it can be known how long a project is completed and look for the possibility of project
acceleration implementation by Project Evaluation and Review Technique (PERT)
and Critical Path Method (CPM) or critical path method. This research aims to apply
Project Evaluation and Review Technique (PERT) and Critical Project Management
(CPM) methods to find optimize solutions and control the performance of time and
cost in project scheduling. The research method used case study method at hospital
project in Bogor District, Indonesia, by collecting data direct observation and
interview results at contractor. Based on these data, create a schedule by using PERT
and CPM methods, which will be measured performance of time performance and
project cost which is expected to overcome the problem of controlling and completion
of project. The results of this study, using PERT and CPM methods proved to optimize
the project. Based on calculation by PERT method reduce duration of work: 12 days
(13, 18%). Based on calculation by CPM method reduce duration of work: 31 days
(34, 06%) but direct cost increase 112.208,300, - rupiahs (0, 25%).
Time-cost optimization using harmony search algorithm in construction projectsMohammad Lemar ZALMAİ
Abstract
In construction projects, the relationship between project cost and duration, which is one of the main factors of the project, are considered the parameters decision-makers. When a construction schedule is planned by the planners, additional resources are allocated to shorten the project duration considering the completion time and cost of the activities so that the most suitable construction schedule is prepared by providing a trade-off between project duration and total cost. In the case of time-cost trade-off problems, the total cost of the project is determined by summing each activities’ cost by adding indirect costs. Moreover, total project duration is determined by obtaining total project duration after CPM (Critical Path Method) calculations. Obtaining optimum duration and costs is such a problematic issue with using conventional methods and common software packages. These techniques consider deterministic project values and include CPM calculations for fitness value calculation. Moreover, current studies defined alternatives as non-variable discrete values. However, construction projects are dynamic processes, and quantities are prone to be changed related to project size. In this study, time-cost trade-off optimization is performed by using harmony search method with introducing different implementation that can be more easily used for different projects. The model is implemented in a real construction project, and the conclusions are interpreted.
Effective techniques in cost optimization of construction project an revieweSAT Journals
Abstract
In the construction project, time and cost are the most important factors to be considered in the planning of every project. The aim of project is to finish the projects on time, within budget and to achieve other project objectives. It is a difficult task undertaken by project managers in practice, which include constantly measuring progress, evaluation of plans, and corrective actions should be taken whenever required. Optimization is a systematic effort made to improve profit margins and obtain the best results under given circumstances. There is a Systematic planning and programming with effective management is necessary for timely completion of the project. there is availability of various tools and techniques for optimization. Optimizing performance of the different techniques adopted at one stage of the construction process may not be beneficial if the methods used are not to up the efficient level. In this approach we have studied various factors which affect the cost of projects. again in this approach we have studied various techniques and various materials used for cost optimization. Also the need of optimization is discussed.
Keywords: time, cost, optimization.
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Studyijceronline
In construction project, cost and time reduction is crucial in today’s competitive market respect. Cost and time along with quality of the project play vital role in construction project’s decision. Reduction in cost and time of projects has increased the demand of construction project in the recent years. Trade-off between different conflicting aspects of projects is one of the challenging problems often faced by construction companies. Time, cost and quality of project delivery are the important aspects of each project which lead researchers in developing time-cost trade-off model. These models are serving as important management tool for overcoming the limitation of critical path methods frequently used by company. The objective of time-cost trade-off analysis is to reduce the original project duration with possible least total cost. In this paper critical path method with a heuristic method is used to find out the crash durations and crash costs. A regression analysis is performed to identify the relationship between the times and costs in order to formulize an optimization problem model. The problem is then solved by Matlab program which yields a least cost of $60937 with duration 129.50 ≈130 days. Applying this approach, the result obtained is satisfactory, which is an indication of usefulness of this approach in construction project problems.
Evaluate the effective resource management through pert analysiseSAT Publishing House
IJRET : International Journal of Research in Engineering and Technology is an international peer reviewed, online journal published by eSAT Publishing House for the enhancement of research in various disciplines of Engineering and Technology. The aim and scope of the journal is to provide an academic medium and an important reference for the advancement and dissemination of research results that support high-level learning, teaching and research in the fields of Engineering and Technology. We bring together Scientists, Academician, Field Engineers, Scholars and Students of related fields of Engineering and Technology
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
Project planning is the important task in many areas like construction, resource allocation and many. A sequence of activities has to be performed to complete one task. Each activity has its unique processing time and all together to identify the critical activities which affect the completion of the project. In this paper the probabilistic and deterministic models to determine the project completion time and also the critical activities are considered. A case study on building construction project has been performed to demonstrate the application of the above said models. The two project scheduling namely PERT and CPM are used to determine numerically the different types of floating times of each activity and hence determined the critical path which plays an important role in the project completion time. Also a linear programing model has been developed to reduce the project completion time which optimize the resource allocation. To apply these techniques numerically the primary data from a housing project company in a metropolitan city has been taken, the network diagram of the activities involved in the building construction project has been drawn and the results are tabulated
Planning is a guideline in implementing the project so that development can be
implemented in accordance with the time and cost planned. Control discrepancy
between initial plan and realization that exists in implementation project required a
project management, therefore required optimization analysis of project duration, so
it can be known how long a project is completed and look for the possibility of project
acceleration implementation by Project Evaluation and Review Technique (PERT)
and Critical Path Method (CPM) or critical path method. This research aims to apply
Project Evaluation and Review Technique (PERT) and Critical Project Management
(CPM) methods to find optimize solutions and control the performance of time and
cost in project scheduling. The research method used case study method at hospital
project in Bogor District, Indonesia, by collecting data direct observation and
interview results at contractor. Based on these data, create a schedule by using PERT
and CPM methods, which will be measured performance of time performance and
project cost which is expected to overcome the problem of controlling and completion
of project. The results of this study, using PERT and CPM methods proved to optimize
the project. Based on calculation by PERT method reduce duration of work: 12 days
(13, 18%). Based on calculation by CPM method reduce duration of work: 31 days
(34, 06%) but direct cost increase 112.208,300, - rupiahs (0, 25%).
Time-cost optimization using harmony search algorithm in construction projectsMohammad Lemar ZALMAİ
Abstract
In construction projects, the relationship between project cost and duration, which is one of the main factors of the project, are considered the parameters decision-makers. When a construction schedule is planned by the planners, additional resources are allocated to shorten the project duration considering the completion time and cost of the activities so that the most suitable construction schedule is prepared by providing a trade-off between project duration and total cost. In the case of time-cost trade-off problems, the total cost of the project is determined by summing each activities’ cost by adding indirect costs. Moreover, total project duration is determined by obtaining total project duration after CPM (Critical Path Method) calculations. Obtaining optimum duration and costs is such a problematic issue with using conventional methods and common software packages. These techniques consider deterministic project values and include CPM calculations for fitness value calculation. Moreover, current studies defined alternatives as non-variable discrete values. However, construction projects are dynamic processes, and quantities are prone to be changed related to project size. In this study, time-cost trade-off optimization is performed by using harmony search method with introducing different implementation that can be more easily used for different projects. The model is implemented in a real construction project, and the conclusions are interpreted.
Effective techniques in cost optimization of construction project an revieweSAT Journals
Abstract
In the construction project, time and cost are the most important factors to be considered in the planning of every project. The aim of project is to finish the projects on time, within budget and to achieve other project objectives. It is a difficult task undertaken by project managers in practice, which include constantly measuring progress, evaluation of plans, and corrective actions should be taken whenever required. Optimization is a systematic effort made to improve profit margins and obtain the best results under given circumstances. There is a Systematic planning and programming with effective management is necessary for timely completion of the project. there is availability of various tools and techniques for optimization. Optimizing performance of the different techniques adopted at one stage of the construction process may not be beneficial if the methods used are not to up the efficient level. In this approach we have studied various factors which affect the cost of projects. again in this approach we have studied various techniques and various materials used for cost optimization. Also the need of optimization is discussed.
Keywords: time, cost, optimization.
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Studyijceronline
In construction project, cost and time reduction is crucial in today’s competitive market respect. Cost and time along with quality of the project play vital role in construction project’s decision. Reduction in cost and time of projects has increased the demand of construction project in the recent years. Trade-off between different conflicting aspects of projects is one of the challenging problems often faced by construction companies. Time, cost and quality of project delivery are the important aspects of each project which lead researchers in developing time-cost trade-off model. These models are serving as important management tool for overcoming the limitation of critical path methods frequently used by company. The objective of time-cost trade-off analysis is to reduce the original project duration with possible least total cost. In this paper critical path method with a heuristic method is used to find out the crash durations and crash costs. A regression analysis is performed to identify the relationship between the times and costs in order to formulize an optimization problem model. The problem is then solved by Matlab program which yields a least cost of $60937 with duration 129.50 ≈130 days. Applying this approach, the result obtained is satisfactory, which is an indication of usefulness of this approach in construction project problems.
Evaluate the effective resource management through pert analysiseSAT Publishing House
IJRET : International Journal of Research in Engineering and Technology is an international peer reviewed, online journal published by eSAT Publishing House for the enhancement of research in various disciplines of Engineering and Technology. The aim and scope of the journal is to provide an academic medium and an important reference for the advancement and dissemination of research results that support high-level learning, teaching and research in the fields of Engineering and Technology. We bring together Scientists, Academician, Field Engineers, Scholars and Students of related fields of Engineering and Technology
Efficient Planning Scheduling and Delay Analysis of Residential ProjectIJERA Editor
Planning and scheduling have become an essential part of any project for the timely and economical completion of the project. A proper construction schedule can be used for different purposes. By using construction schedule to predict project completion, contractors can adjust crew size, shifts or equipment to speed or slow the progress. All the construction projects will vary from each other in size. All the projects have time constraint. Delay in completion of project will increase the overall cost of the project. Small projects can be managed efficiently manually; whereas large projects are not so large projects can be better handled by the use of computers. Many types of software are available with the help of which project management can be done easily. Large quantities of different kinds of resources are also required for execution and the risk is more in the case of projects. So planning and scheduling of activities for construction of big projects is essential. In this study, an effort is made in planning, scheduling and delay analysis updating of various activities, which is done by using MS Project and MS Excel software, manpower of each activity is determined and allocation is done using the software. Labor requirement for each activity is calculated from standards obtained from site. An updated schedule, which helps to finish the project well in time with optimum resources and update helps in delay analysis, is under the scope of this study.
Implementation of Line of Balance Method for Scheduling High-rise BuildingIJERA Editor
In linear construction projects like high rise buildings, roadways, pipelines where activities are repeated after a specific interval, it is very much important for project manager to monitor the project at each stage. Line of Balance method is therefore useful for the project like high rise building to monitor the progress of the work. This method is useful for calculating the total duration of the project, crew synchronization and also shows the process, status, timing and phasing of the project activities. The overall objective of this study is to identify the total duration required by the project for its completion and its comparison with the actual plan by using Line of Balance method, to crash some of the activities and find out the total duration of crashed activities and to calculate labours required for the crashed activities by drawing the graph of Histogram.Keywords- crashing, crew synchronization, buffer, Histogram, Rate of Production
Role of PMC in Construction of Collector Well Project, a Case StudyIJERA Editor
The rapid expansion and intricacy in the construction industry cause difficulties in maintaining performance, time, and quality services of a construction project, which leads to the failure to meet the scope and objective of a project. In addition, improper planning, widespread dependence, and low availability of materials increase the cost of the construction project. To manage such issues, Project Management Consultancy is one of the management solutions that have been widely used. Project Management Consultancy plays a multifaceted role in providing services from the beginning of construction to its completion. Project Management Consultancy makes sure whether we are moving in the right pathway according to the planned schedule. Use of Project Management Consultancy offers constructive management solution for the proper execution of work, improved performance, quality, and outcome of the project. The objective of this paper is to study the role and responsibilities of Project Management Consultancy while executing a project and the risks associated with it. This research is carried out via a case study of the construction of an industrial project governed by a Project Management Consultancy from preconstruction phase to completion.
The project was carried out keeping in mind the daily processes related to glassware industry (LA OPALA pvt ltd.) production. The analysis was carried out by Network Scheduling using CPM (Critical Path method). This project enabled me to apply the theoretical studies in practical application. It helped me to get an complete overview of modern day scenario and how the problems are tackled and the solutions are brought into application
Cost Effective Construction Techniques By Stephen RaymentStephen Rayment UK
So here are a few secrets of Stephen Rayment that one wish to get through them that could help them to cut the cost of the over expenditure and provide their customers some extra leniency in total cost expenditure.
For more details visit :-https://medium.com/@stephenraymentsystech/
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...Vamsi Kovalam
The development of a new building material based on vetiver grass ash for use in the rural areas of the developing countries is experimentally investigated.
The properties of VGA were experimentally studied to consider the possibility of using VGA as a pozzolanic material.
Many developing countries are attempting to develop substitutes for cement from locally available raw materials like agricultural and industrial waste.
Fly ash ,rice husk ash and rice straw ash have been proven to be economical partial substitutes for cement
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...ijiert bestjournal
Role of optimization in engineering design is prominent one with the a dvent of computers. Optimization has become a part of computer aided design methodology. It is primarily being used in those design activities in which the goal is not only to achieve a feasible design,but als o a design objective. The paper reviews the optimization in detail followed by the literature review and b rief discussion of Hooks and Jeeves Method Analysis with an example.
ER Publication,
IJETR, IJMCTR,
Journals,
International Journals,
High Impact Journals,
Monthly Journal,
Good quality Journals,
Research,
Research Papers,
Research Article,
Free Journals, Open access Journals,
erpublication.org,
Engineering Journal,
Science Journals,
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...IOSR Journals
This paper presents two models for predicting the delay percentage in construction projects in Egypt.
The first model based on regression analysis. 74 causes that lead to delay in construction projects gathered
from literature. A questionnaire survey was made on construction contractors of construction projects in Egypt
to evaluate the relative importance of these causes. 14 causes were obtained as the most significant causes that
affect the delay percentage (DP) and these are the independent variables of the proposed model. Data for the
occurrence of the previous causes on a yes/no basis and the corresponding DP (dependent variable) for 20
construction projects was collected. The data was divided into two sets, the first set contains projects for the
purpose of model building. The results revealed that there was a strong linear relationship between DP and 9
causes from 14 causes that significantly affect DP of projects. These causes are: difficulties in obtaining work
permits from authorities concerned, original contract duration too short, inflation, difficulties in financing the
project by the contractor, effect of subsurface conditions, changes in the scope of the project, economic
conditions, excessive bureaucracy in the owner administration, and inefficient coordination by the owner in the
early planning &design stages. The second set contains 8 projects for the validation purposes and comparison
with the second model. The second model is a statistical fuzzy approach which is a hybrid approach from fuzzy
logic and regression analysis. A regression equation between each cause and DP using projects of first set was
extracted. The relative weight of each cause is determined by its coefficient of determination (R2
) value. The
degree of severity each cause had received from questionnaire analysis was used to fuzzify this cause. A
trapezoidal membership function was used to represent the delay percentages in construction projects in
general depending on 18 out of 30 the previous 20 projects. Two projects were excluded from this function due
to their divergence values from other projects. Thus, the expected delay percentage of a project is then
determined using fuzzy rules. Validation of the two models using projects of the second set revealed that
regression model has prediction capabilities higher than that of statistical fuzzy model. The average percentage
error for regression model was 30.3, against 38.5 for statistical fuzzy model.
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...IJERA Editor
It is well known that decisions at early stages of a construction project have great impact on subsequent project performance. Conceptual cost estimate is a challenging task that is done with limited information at the early stages of a project life where many factors affecting the project costs are still unknown. The objective of this paper is to support decision makers in predicting the conceptual cost of highway construction projects in Libya. Initially, the factors that significantly influence highway construction are identified. Then, an artificial neural network model is developed for predicting the cost. The network is trained and tested with a total of 67 projects historical data. Training of the model is administered via back-propagation algorithm. The model is coded ad implemented using MATLAB® to facilitate its use. An optimization module is also added to the Neural Network model with the objective of minimizing the error of the predicted cost. The model is then validated and the results show better predictions of conceptual cost of highway projects in Libya.
Efficient Planning Scheduling and Delay Analysis of Residential ProjectIJERA Editor
Planning and scheduling have become an essential part of any project for the timely and economical completion of the project. A proper construction schedule can be used for different purposes. By using construction schedule to predict project completion, contractors can adjust crew size, shifts or equipment to speed or slow the progress. All the construction projects will vary from each other in size. All the projects have time constraint. Delay in completion of project will increase the overall cost of the project. Small projects can be managed efficiently manually; whereas large projects are not so large projects can be better handled by the use of computers. Many types of software are available with the help of which project management can be done easily. Large quantities of different kinds of resources are also required for execution and the risk is more in the case of projects. So planning and scheduling of activities for construction of big projects is essential. In this study, an effort is made in planning, scheduling and delay analysis updating of various activities, which is done by using MS Project and MS Excel software, manpower of each activity is determined and allocation is done using the software. Labor requirement for each activity is calculated from standards obtained from site. An updated schedule, which helps to finish the project well in time with optimum resources and update helps in delay analysis, is under the scope of this study.
Implementation of Line of Balance Method for Scheduling High-rise BuildingIJERA Editor
In linear construction projects like high rise buildings, roadways, pipelines where activities are repeated after a specific interval, it is very much important for project manager to monitor the project at each stage. Line of Balance method is therefore useful for the project like high rise building to monitor the progress of the work. This method is useful for calculating the total duration of the project, crew synchronization and also shows the process, status, timing and phasing of the project activities. The overall objective of this study is to identify the total duration required by the project for its completion and its comparison with the actual plan by using Line of Balance method, to crash some of the activities and find out the total duration of crashed activities and to calculate labours required for the crashed activities by drawing the graph of Histogram.Keywords- crashing, crew synchronization, buffer, Histogram, Rate of Production
Role of PMC in Construction of Collector Well Project, a Case StudyIJERA Editor
The rapid expansion and intricacy in the construction industry cause difficulties in maintaining performance, time, and quality services of a construction project, which leads to the failure to meet the scope and objective of a project. In addition, improper planning, widespread dependence, and low availability of materials increase the cost of the construction project. To manage such issues, Project Management Consultancy is one of the management solutions that have been widely used. Project Management Consultancy plays a multifaceted role in providing services from the beginning of construction to its completion. Project Management Consultancy makes sure whether we are moving in the right pathway according to the planned schedule. Use of Project Management Consultancy offers constructive management solution for the proper execution of work, improved performance, quality, and outcome of the project. The objective of this paper is to study the role and responsibilities of Project Management Consultancy while executing a project and the risks associated with it. This research is carried out via a case study of the construction of an industrial project governed by a Project Management Consultancy from preconstruction phase to completion.
The project was carried out keeping in mind the daily processes related to glassware industry (LA OPALA pvt ltd.) production. The analysis was carried out by Network Scheduling using CPM (Critical Path method). This project enabled me to apply the theoretical studies in practical application. It helped me to get an complete overview of modern day scenario and how the problems are tackled and the solutions are brought into application
Cost Effective Construction Techniques By Stephen RaymentStephen Rayment UK
So here are a few secrets of Stephen Rayment that one wish to get through them that could help them to cut the cost of the over expenditure and provide their customers some extra leniency in total cost expenditure.
For more details visit :-https://medium.com/@stephenraymentsystech/
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...Vamsi Kovalam
The development of a new building material based on vetiver grass ash for use in the rural areas of the developing countries is experimentally investigated.
The properties of VGA were experimentally studied to consider the possibility of using VGA as a pozzolanic material.
Many developing countries are attempting to develop substitutes for cement from locally available raw materials like agricultural and industrial waste.
Fly ash ,rice husk ash and rice straw ash have been proven to be economical partial substitutes for cement
Review of Hooke and Jeeves Direct Search Solution Method Analysis Applicable ...ijiert bestjournal
Role of optimization in engineering design is prominent one with the a dvent of computers. Optimization has become a part of computer aided design methodology. It is primarily being used in those design activities in which the goal is not only to achieve a feasible design,but als o a design objective. The paper reviews the optimization in detail followed by the literature review and b rief discussion of Hooks and Jeeves Method Analysis with an example.
ER Publication,
IJETR, IJMCTR,
Journals,
International Journals,
High Impact Journals,
Monthly Journal,
Good quality Journals,
Research,
Research Papers,
Research Article,
Free Journals, Open access Journals,
erpublication.org,
Engineering Journal,
Science Journals,
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...IOSR Journals
This paper presents two models for predicting the delay percentage in construction projects in Egypt.
The first model based on regression analysis. 74 causes that lead to delay in construction projects gathered
from literature. A questionnaire survey was made on construction contractors of construction projects in Egypt
to evaluate the relative importance of these causes. 14 causes were obtained as the most significant causes that
affect the delay percentage (DP) and these are the independent variables of the proposed model. Data for the
occurrence of the previous causes on a yes/no basis and the corresponding DP (dependent variable) for 20
construction projects was collected. The data was divided into two sets, the first set contains projects for the
purpose of model building. The results revealed that there was a strong linear relationship between DP and 9
causes from 14 causes that significantly affect DP of projects. These causes are: difficulties in obtaining work
permits from authorities concerned, original contract duration too short, inflation, difficulties in financing the
project by the contractor, effect of subsurface conditions, changes in the scope of the project, economic
conditions, excessive bureaucracy in the owner administration, and inefficient coordination by the owner in the
early planning &design stages. The second set contains 8 projects for the validation purposes and comparison
with the second model. The second model is a statistical fuzzy approach which is a hybrid approach from fuzzy
logic and regression analysis. A regression equation between each cause and DP using projects of first set was
extracted. The relative weight of each cause is determined by its coefficient of determination (R2
) value. The
degree of severity each cause had received from questionnaire analysis was used to fuzzify this cause. A
trapezoidal membership function was used to represent the delay percentages in construction projects in
general depending on 18 out of 30 the previous 20 projects. Two projects were excluded from this function due
to their divergence values from other projects. Thus, the expected delay percentage of a project is then
determined using fuzzy rules. Validation of the two models using projects of the second set revealed that
regression model has prediction capabilities higher than that of statistical fuzzy model. The average percentage
error for regression model was 30.3, against 38.5 for statistical fuzzy model.
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...IJERA Editor
It is well known that decisions at early stages of a construction project have great impact on subsequent project performance. Conceptual cost estimate is a challenging task that is done with limited information at the early stages of a project life where many factors affecting the project costs are still unknown. The objective of this paper is to support decision makers in predicting the conceptual cost of highway construction projects in Libya. Initially, the factors that significantly influence highway construction are identified. Then, an artificial neural network model is developed for predicting the cost. The network is trained and tested with a total of 67 projects historical data. Training of the model is administered via back-propagation algorithm. The model is coded ad implemented using MATLAB® to facilitate its use. An optimization module is also added to the Neural Network model with the objective of minimizing the error of the predicted cost. The model is then validated and the results show better predictions of conceptual cost of highway projects in Libya.
IOSR Journal of Pharmacy and Biological Sciences(IOSR-JPBS) is an open access international journal that provides rapid publication (within a month) of articles in all areas of Pharmacy and Biological Science. The journal welcomes publications of high quality papers on theoretical developments and practical applications in Pharmacy and Biological Science. Original research papers, state-of-the-art reviews, and high quality technical notes are invited for publications.
IOSR Journal of Applied Physics (IOSR-JAP) is an open access international journal that provides rapid publication (within a month) of articles in all areas of physics and its applications. The journal welcomes publications of high quality papers on theoretical developments and practical applications in applied physics. Original research papers, state-of-the-art reviews, and high quality technical notes are invited for publications.
Delay Analysis in EPC Projects using Ishikawa DiagramIJAEMSJORNAL
Delay is one of the major issues in EPC projects in Oman. Project managers are not considering the root causes of delay while taking preventive measures. This project aims to identify the most common types of delay in EPC projects, to find out the root causes of delay by using Ishikawa diagram and further to prepare acceleration plan for a running project by using schedule compression techniques. The objectives of this project are: (a ) to identify root causes of various delays commonly affecting the EPC projects in Oman by using Ishikawa diagram. (b) to identify critical delay cause factors for a running project by conducting questionnaire survey. (c) to prepare acceleration plan for the project by using schedule compression techniques. To achieve this study: all the information was collected, schedules were compared to calculate the delay in each activity, questionnaire survey was conducted to study the impact of various factors causing delay and the root causes by using Ishikawa diagram and finally prepared an acceleration plan by using schedule compression techniques . The results found are: time and cost constraints are the biggest obstacle causing delay in EPC projects. The study identified the importance of analyzing the root causes before taking any particular preventive measures.
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaAI Publications
In the implementation of a project, many problems can be found that can waste the costs. The construction of the Bias Munjul Port in Nusa Ceningan went through re-design due to a request from the Minister of Transportation and the Governor of Bali because the design did not meet the Bali Provincial Regulation Number 5 of 2005 about Architectural Requirements for Buildings. It cost IDR 110,837,794,000.00 or more than 11.32% of the contract price IDR 98,292,823,000.00. It means that the price of construction has increased which exceeds the maximum limit for adding to the contract price based on Presidential Regulation Number 16 of 2018 which is 10% of the initial contract price. Therefore, it is necessary to do cost-effectiveness; a method that can be used to make costs efficient without reducing the value of the function is the Value Engineering method, a quantitive method. The steps taken in this research are: Information Phase, Functional Analysis Phase, Creative Phase, Evaluation Phase, Presentation Stage. In the first phase, the cost of the works is included in the budget plan using Pareto diagram. The results showed that the savings cost on the ro-ro dock was 6% of the initial plan using a pile foundation with a depth of 47 m. The dredging works obtained a 17% savings from the original plan using a dredging width of 100 m and a depth of -3.7 m. On architectural work, 81% savings from the original plan were obtained using batu candi. The total saving for all of these works was IDR 5,944,671,890.80 or 5.89% from the initial plan.
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTIONIAEME Publication
Objective:To find out cost variations ofmaterials used for the conventional building and precast building, wastagepercentage in construction of a commercial building using conventional andprecast technology. And to find out the time and cost variations inconstruction of commercial building using conventional and precast technology.
Methods/Analysis:Outwardly the technique of using precast members inconstruction has played one of the key roles in the industry. This techniquehas been measured and speckled in terms of cost inference. A Model was carriedout on a Residential building project and the data was collected for study andconcluded that the use of precast members is a better tradable factor to thatof conventional system.
Findings:Precast construction saves time and cost whencompared to conventional type of construction.
Novelty/Improvement: The transformation and revolution in the technology was grown outof the demand of the clients/customers of both residential and commercialpurposes. Outwardly the technique of using precast members in construction hasplayed one of the key roles in the industry.
Procurement principle towards effective management of construction projectseSAT Publishing House
IJRET : International Journal of Research in Engineering and Technology is an international peer reviewed, online journal published by eSAT Publishing House for the enhancement of research in various disciplines of Engineering and Technology. The aim and scope of the journal is to provide an academic medium and an important reference for the advancement and dissemination of research results that support high-level learning, teaching and research in the fields of Engineering and Technology. We bring together Scientists, Academician, Field Engineers, Scholars and Students of related fields of Engineering and Technology.
Application of Value Engineering in Commercial Building Projectsnitinrane33
The current construction industry conditions have entailed the use of rational method and techniques and
research and application of new techniques by utilizing advancements in technology in the field of production as well as in
every field. Value Engineering is a proven management technique that can make valuable contributions to value
enhancement and cost reduction in construction industry. Value Engineering is one of the most effective techniques
known to identify and eliminate unnecessary costs in product design, testing, manufacturing, construction, operations,
maintenance, data, procedures and practices. The methodology is composed of three main stages. The first stage is the
Pre-Study of the Value Engineering. The purpose of this stage is to plan and organize the value study. Value Engineering
is the systematic application of recognized techniques that identify the functions of the product or service, creatively
establish the worth of those functions, and provide only the necessary functions to meet the required performance at the
lowest overall cost. Value Engineering focuses on accomplishing the required functions at the lowest overall cost. It helps
in eliminating or minimizing wastage of material, time, and unnecessary cost, which improves value to the customer. The
second stage is the Value Study which is the core of Value Engineering study and it is composed of five phases, the
Information phase, Function Analysis Phase, Creative Phase, Evaluation Phase and the Presentation phase. All phases
and steps perform sequentially. Such sequence of the methodology is expected to assist in logical and systematic flow of
the process to achieve the targets of the VE study. The third stage is the Post Study. The objective during post-study
activities is to assure the implementation of the approved value study change recommendations. In this study, how the
principles of Value Engineering are applied in construction projects is explained, and by taking case study on commercial
building as the sample project, practices of Value Engineering in this project are described.
DevOps and Testing slides at DASA ConnectKari Kakkonen
My and Rik Marselis slides at 30.5.2024 DASA Connect conference. We discuss about what is testing, then what is agile testing and finally what is Testing in DevOps. Finally we had lovely workshop with the participants trying to find out different ways to think about quality and testing in different parts of the DevOps infinity loop.
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Ramesh Iyer
In today's fast-changing business world, Companies that adapt and embrace new ideas often need help to keep up with the competition. However, fostering a culture of innovation takes much work. It takes vision, leadership and willingness to take risks in the right proportion. Sachin Dev Duggal, co-founder of Builder.ai, has perfected the art of this balance, creating a company culture where creativity and growth are nurtured at each stage.
Search and Society: Reimagining Information Access for Radical FuturesBhaskar Mitra
The field of Information retrieval (IR) is currently undergoing a transformative shift, at least partly due to the emerging applications of generative AI to information access. In this talk, we will deliberate on the sociotechnical implications of generative AI for information access. We will argue that there is both a critical necessity and an exciting opportunity for the IR community to re-center our research agendas on societal needs while dismantling the artificial separation between the work on fairness, accountability, transparency, and ethics in IR and the rest of IR research. Instead of adopting a reactionary strategy of trying to mitigate potential social harms from emerging technologies, the community should aim to proactively set the research agenda for the kinds of systems we should build inspired by diverse explicitly stated sociotechnical imaginaries. The sociotechnical imaginaries that underpin the design and development of information access technologies needs to be explicitly articulated, and we need to develop theories of change in context of these diverse perspectives. Our guiding future imaginaries must be informed by other academic fields, such as democratic theory and critical theory, and should be co-developed with social science scholars, legal scholars, civil rights and social justice activists, and artists, among others.
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...UiPathCommunity
💥 Speed, accuracy, and scaling – discover the superpowers of GenAI in action with UiPath Document Understanding and Communications Mining™:
See how to accelerate model training and optimize model performance with active learning
Learn about the latest enhancements to out-of-the-box document processing – with little to no training required
Get an exclusive demo of the new family of UiPath LLMs – GenAI models specialized for processing different types of documents and messages
This is a hands-on session specifically designed for automation developers and AI enthusiasts seeking to enhance their knowledge in leveraging the latest intelligent document processing capabilities offered by UiPath.
Speakers:
👨🏫 Andras Palfi, Senior Product Manager, UiPath
👩🏫 Lenka Dulovicova, Product Program Manager, UiPath
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualityInflectra
In this insightful webinar, Inflectra explores how artificial intelligence (AI) is transforming software development and testing. Discover how AI-powered tools are revolutionizing every stage of the software development lifecycle (SDLC), from design and prototyping to testing, deployment, and monitoring.
Learn about:
• The Future of Testing: How AI is shifting testing towards verification, analysis, and higher-level skills, while reducing repetitive tasks.
• Test Automation: How AI-powered test case generation, optimization, and self-healing tests are making testing more efficient and effective.
• Visual Testing: Explore the emerging capabilities of AI in visual testing and how it's set to revolutionize UI verification.
• Inflectra's AI Solutions: See demonstrations of Inflectra's cutting-edge AI tools like the ChatGPT plugin and Azure Open AI platform, designed to streamline your testing process.
Whether you're a developer, tester, or QA professional, this webinar will give you valuable insights into how AI is shaping the future of software delivery.
Transcript: Selling digital books in 2024: Insights from industry leaders - T...BookNet Canada
The publishing industry has been selling digital audiobooks and ebooks for over a decade and has found its groove. What’s changed? What has stayed the same? Where do we go from here? Join a group of leading sales peers from across the industry for a conversation about the lessons learned since the popularization of digital books, best practices, digital book supply chain management, and more.
Link to video recording: https://bnctechforum.ca/sessions/selling-digital-books-in-2024-insights-from-industry-leaders/
Presented by BookNet Canada on May 28, 2024, with support from the Department of Canadian Heritage.
Connector Corner: Automate dynamic content and events by pushing a buttonDianaGray10
Here is something new! In our next Connector Corner webinar, we will demonstrate how you can use a single workflow to:
Create a campaign using Mailchimp with merge tags/fields
Send an interactive Slack channel message (using buttons)
Have the message received by managers and peers along with a test email for review
But there’s more:
In a second workflow supporting the same use case, you’ll see:
Your campaign sent to target colleagues for approval
If the “Approve” button is clicked, a Jira/Zendesk ticket is created for the marketing design team
But—if the “Reject” button is pushed, colleagues will be alerted via Slack message
Join us to learn more about this new, human-in-the-loop capability, brought to you by Integration Service connectors.
And...
Speakers:
Akshay Agnihotri, Product Manager
Charlie Greenberg, Host
JMeter webinar - integration with InfluxDB and GrafanaRTTS
Watch this recorded webinar about real-time monitoring of application performance. See how to integrate Apache JMeter, the open-source leader in performance testing, with InfluxDB, the open-source time-series database, and Grafana, the open-source analytics and visualization application.
In this webinar, we will review the benefits of leveraging InfluxDB and Grafana when executing load tests and demonstrate how these tools are used to visualize performance metrics.
Length: 30 minutes
Session Overview
-------------------------------------------
During this webinar, we will cover the following topics while demonstrating the integrations of JMeter, InfluxDB and Grafana:
- What out-of-the-box solutions are available for real-time monitoring JMeter tests?
- What are the benefits of integrating InfluxDB and Grafana into the load testing stack?
- Which features are provided by Grafana?
- Demonstration of InfluxDB and Grafana using a practice web application
To view the webinar recording, go to:
https://www.rttsweb.com/jmeter-integration-webinar
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...James Anderson
Effective Application Security in Software Delivery lifecycle using Deployment Firewall and DBOM
The modern software delivery process (or the CI/CD process) includes many tools, distributed teams, open-source code, and cloud platforms. Constant focus on speed to release software to market, along with the traditional slow and manual security checks has caused gaps in continuous security as an important piece in the software supply chain. Today organizations feel more susceptible to external and internal cyber threats due to the vast attack surface in their applications supply chain and the lack of end-to-end governance and risk management.
The software team must secure its software delivery process to avoid vulnerability and security breaches. This needs to be achieved with existing tool chains and without extensive rework of the delivery processes. This talk will present strategies and techniques for providing visibility into the true risk of the existing vulnerabilities, preventing the introduction of security issues in the software, resolving vulnerabilities in production environments quickly, and capturing the deployment bill of materials (DBOM).
Speakers:
Bob Boule
Robert Boule is a technology enthusiast with PASSION for technology and making things work along with a knack for helping others understand how things work. He comes with around 20 years of solution engineering experience in application security, software continuous delivery, and SaaS platforms. He is known for his dynamic presentations in CI/CD and application security integrated in software delivery lifecycle.
Gopinath Rebala
Gopinath Rebala is the CTO of OpsMx, where he has overall responsibility for the machine learning and data processing architectures for Secure Software Delivery. Gopi also has a strong connection with our customers, leading design and architecture for strategic implementations. Gopi is a frequent speaker and well-known leader in continuous delivery and integrating security into software delivery.
Let's dive deeper into the world of ODC! Ricardo Alves (OutSystems) will join us to tell all about the new Data Fabric. After that, Sezen de Bruijn (OutSystems) will get into the details on how to best design a sturdy architecture within ODC.
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf91mobiles
91mobiles recently conducted a Smart TV Buyer Insights Survey in which we asked over 3,000 respondents about the TV they own, aspects they look at on a new TV, and their TV buying preferences.
1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 13, Issue 3, Ver. II (May- Jun. 2016), PP 05-08
www.iosrjournals.org
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 5 | Page
Planning And Scheduling With Optimization Of Cost And Time
Of Six Lane Bridge With Cast In Situ And Precast Elements At
Kolathur, Chennai
Mr.S.Ashik Ahamed 1
, Dr.V.Thamilarasu 2
Mr.R.Padmanaban 3
1
(M.Tech CEM,, Civil Engineering Department, SRM University, Chennai ,India)
2
(Professor – Civil, Civil Engineering Department, SRM University, Chennai,India)
3
(Research Scholar, Civil Engineering Department, Anna University, Chennai,India)
Abstract: Construction industries play a vital role in the economy of all developing countries including India.
In any construction “Time and cost” are the two main concerns which decide the effectiveness of the project.
Further, optimization of time and cost is also very vital. This has increased the importance of adopting time and
Cost optimization in all construction projects. Optimization is a systematic effort made to ensure a reasonable
profit margins and to obtain the best results under given circumstances or situations.
The optimization of “Time and cost” in any construction project can be obtained by proper planning and
scheduling of each part or activity involved and by using multiple construction techniques.
Here It is proposed to try to optimize the “Time and cost” involved in a highway bridge construction at
Kolathur junction, Chennai. For the optimization of “Time and cost’ involved in the project, two different
construction techniques called “ Cast in situ method” & “Pre cast technology”, are analyzed and optimum
planning and scheduling is prepared.
Keywords: Construction Industry, Time&Cost, Cast in situ Elements, Precast Elements, Cost Optimization)
I. Introduction
There are many challenges faced by the construction industries which include, design and
Constructability issues, land acquisition issues, adverse political changes, shortage of talent, time and cost
related issues, material and labour cost escalations, structural changes. Time and cost are two main factors in
planning of construction projects and hence there is an increase in importance of time and Cost optimization. It
is important to estimate the time and cost of each activity through which the total duration and total cost of the
project are determined for the planning task. Optimization is a systematic effort made to improve profit margins
and obtain the best results under given circumstances or situations. The main objective of cost optimization of a
project is to gain the maximum profit within the design period and with satisfactory quality of work.
1.1 Objective of the project
To prepare a detailed planning and work schedule with optimization of cost and time including cost
estimate for the construction of Six Lane Bridge with “cast in situ” and “precast elements” at Kolathur,
Chennai .
1.2 Scope of the project
The exercise of optimizing the cost and time through value planning and scheduling for both cast in
situ and Precast Construction method can be extended to other similar projects in our country.
1.3 Project Goals
A project is successful when the needs of the stakeholders have been met. A stakeholder is anybody
directly or indirectly impacted by the project.
As a first step it is important to identify the stakeholders in your project. It is not always easy to
identify the stakeholders of a project, particularly those impacted indirectly. Examples of stakeholders are:
The project sponsor
The customer who receives the deliverables
The users of the project outputs
The project manager and project team
1.4 Project Methodology
An efficient project control methodology systems generates information that can improve the
productivity of men and materials economize the employment of resources;
2. Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ..
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 6 | Page
The methodology adopted involves the following steps.
Collection of all relevant and required data of Six Lane Bridge work at Kolathur at Chennai from Highways
Department and Contractor.
Carrying out Preliminary Analysis and Detailed Analysis of the project proposal.
Preparing a detailed planning and work schedule with optimization of cost and time using PRIMAVERA
and preparing the cost estimate for both cast in situ and precast elements.
Comparing the Cost and Project time for Cast in Situ and Precast Elements and proposing the best for
adoption.
II. Literature Review
2.1 Introduction
In this chapter a review of literature of the techniques used in planning and scheduling of Construction
projects are presented.
2.2 Definitions & Findings
A. Christ.Hendrickson (1990) - Use of Advanced Scheduling Techniques
In this study he explained Construction project scheduling is a topic that has received extensive
research over a number of decades. With the availability of more powerful computers and software, the use of
advanced scheduling techniques is becoming easier and of greater relevance to practice
K.K.Chitkara (1998) - Explains the methodology used in Planning and Scheduling of Construction
Projects.
In this study he explained the methodology used in Planning and Scheduling of Construction Projects.
Shanmugapriya S., Dr. Subramanian K.,( 2013) - “Investigation of Significant Factors Influencing Time
And Cost”
In this study they explained, Time and cost overruns is a severe problems faced by large construction
industries in India. They was found that five most significant factors causing time and cost overruns in Indian
construction are material, market rate, contract modification, high level of quality requirement, project location,
depends on the freshers to bear the whole responsibility for time overruns and high transportation cost, change
in materials specification, escalation of material price, frequent breakdown of construction machineries and
rework for cost overrun.
Mr.CI Anyanwu (2013) – Project Cost control in the Nigerian Construction Industry
In this study they explained, the resources well managed or mismanaged today that makes for
tomorrow prosperity or depression. The economic depression we are now facing is more out of mismanagement
of resources than lack of resources.
Mr.Seyed Ali Mousavi Dehmourdi (2014) – Optimization of Construction Cost Applying Advanced
Techniques
In this study he explained, Construction industry can do a better job by using advanced construction
techniques. Systematic data collection, analysis, reviews to monitor progress will reduce the possible errors in
any project thereby avoiding all possible expenditure. He considered least cost method / North West corner
Method can be the best result oriented of transportation problem to optimize the transportation cost.
Prof.Dipak.P.Patil , Prof. Pankaj P.Bhangale & Swapnil S.Kulkarni (2014) – “ Study of Cost Control on
Construction Project
In this study they explained, they are observed that the major factors that contributes to poor inventory
control are -
a) Improper management of time, cost and manpower.
b) Ignorance of contractor towards material management in construction project.
Ms.Anuja Rajguru, & Mr.Parag Mahatme (2015) - Effective Techniques in Cost optimization of
construction project
In this study they analyzed different techniques for optimization and found the construction cost and
duration at each stage is important to minimize
III. Research
3.1 Cost Optimization Techniques
It is necessary to decide which optimization is required and amount of detail that will be in used into
the construction stage. Many cost optimization methods have been implemented in the past by different
companies and have not survived. The cost itself is a major difficulty in operating a detailed cost optimization
system. It is an expensive operation for a large contract to carry out a detailed cost optimization system. There
are three types of cost optimization system; they are by comparison with a cost standard, by subdivision by
detail and by integration with other functions. In comparison with a cost standard method, the standard set up by
3. Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ..
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 7 | Page
estimator is compared at the time of tender. For example, it may be combined with a labor utilization scheme, in
which the optimization is kept on the optimal utilization of the labor employed.
3.2Time optimization Techniques:
A general mathematical formulation is presented for the scheduling of construction projects and is applied to
the problem of highway construction scheduling. The new construction scheduling model provides the
capabilities of both the critical path method ( CPM) and linear scheduling method ( LSM) approaches.
Repetitive and non-repetitive tasks, multiple group strategies, work continuity constraints and the effects of
varying job conditions on the performance of a team can be modeled. An optimization formulation is presented
for the construction project scheduling problem, with the goal of minimizing the direct construction cost. For
any given construction duration, the model yields the optimum construction schedule for minimum construction
cost automatically.
The project is scheduled for both the techniques cast in situ and precast, which is tabulated in Table 2 & 3.
The details cost estimate is worked out by using MS Excel and shown in Table.4.
Table.2 Programme with Cast in Situ Elements
S.No Task Name Start Date Finish Date Duration in Days
OVERALL DURATION 27.03.2016 03.07.2017 464
1 Foundation Works 27.03.2016 21.07.2016 117
2 Sub Structure Works 02.04.2016 26.07.2016 116
3 Super Structure Works 09.05.2016 28.06.2017 416
4 RE Wall 15.06.2016 31.03.2017 290
5 Road Works 02.12.2016 19.06.2017 200
6 Painting Works 02.03.2017 04.06.2017 95
7 Handing Over 24.06.2017 03.07.2017 10
Table No.4 Cost Estimate Abstract for Both Cast in Situ and Precast Elements
S.No Task Name Cast in situ Elements Precast Elements
Amount In Lakhs
1 Earth Work Excavation 12.53 12.53
2 Piling Works 701.40 701.40
3 Structure Works ( PCC / RCC) 979.49 929.27
4 Reinforcement Steel 1587.60 1587.60
5 HTS Strands 96.10 209.25
6 Bearing 57.39 57.39
7 Strip Seal Expansion Joint 34.65 34.65
8 G.I.Drainage Spout 6.50 6.50
9 Mastic With BC 142.00 142.00
10 Road Works 602.40 602.40
11 RE Wall 604.44 604.44
12 Painting Works 203.11 203.11
13 Erection of Girders 118.96
TOTAL 5027.61 5209.50
The Cost benefit over the time is considered as advantage in precast construction method, because all other
recurring costs like right of way maintenance, resurfacing at an fixed intervals etc are same in both the cases.
The cost benefit over time optimization is
Interest over the capital cost at 14.5% Per Annum
Rs.50.27 Crores x 14.5% /365days x 184 Days = Rs.3.67 Crores
As per traffic survey 11721 PCU / HR So the interest on time
Savings value by the road users
11721 x 24 Hrs x 184 days x Rs.50/ Vehicle x14.5% /365 days = Rs.0.11 Crores
Total Cost benefit due to time savings = Rs.3.78 Crores
Table.3 Programme with Pre Cast Elements
S.No Task Name Start Date Finish Date Duration in Days
OVERALL DURATION 07.04.2016 11.01.2017 280
1 Foundation Works 14.04.2016 03.08.2016 112
2 Sub Structure Works 11.05.2016 24.08.2016 106
3 Super Structure Works 07.04.2016 01.10.2016 178
4 RE Wall 12.05.2016 23.10.2016 165
5 Road Works 26.06.2016 22.11.2016 200
6 Painting Works 24.09.2016 27.12.2016 95
7 Handing Over 23.12.2016 11.01.2017 21
4. Planning And Scheduling With Optimization Of Cost And Time Of Six Lane Bridge With Cast In Situ..
DOI: 10.9790/1684-1303020508 www.iosrjournals.org 8 | Page
Estimated cost of construction Using Precast Element = Rs.52.09 Crores
Cost benefit due to time Savings = (-) Rs. 3.78 Crores
Net Cost by Using Precast construction technique = Rs.48.31 Crores
ITEMS CAST IN SITU ELEMENTS PRECAST ELEMENTS ADVANTAGE
Time 464 Days 280 Days Early completion of 184 days
Cost Rs.50.27 Crores Rs.48.31 Crores Rs.1.96 Crores Savings over using Cast in
situ elements
IV. Conclusion
From the results obtained, it is observed that when the Pre Cast Elements is used in the construction of
Bridges, the total project cost and the duration of the project is lesser than the Construction of Bridges by
Cast in Situ.
The Pre Cast Girders can be Casted simultaneously along with substructure construction and hence the
structure duration could be reduced by184 days (35 to 40 percent) over the Construction of Bridges by
cast in Situ.
The Precast construction can achieve not only faster rate of construction and can also bring down the
estimated cost by 1.96 Crores (3 to 5 percent) over the Construction of Bridges by Cast in Situ method
with lesser labour inputs and minimum disturbance to the existing traffic.
References
Journal papers
[1] Dr.Harold Kerzner Ph.D –A System Approach to Planning , Scheduling and Controlling – Eighth Edition (2003)
[2] Shanmugapriya S., Dr. Subramanian K.,( 2013) - “Investigation of Significant Factors Influencing Time And Cost”
[3] Mr.CI Anyanwu (2013) – Project Cost control in the Nigerian Construction Industry.
[4] Mr.Seyed Ali Mousavi Dehmourdi (2014) – Optimization of Construction Cost Applying Advanced Techniques
[5] Ms.Anuja Rajguru, & Mr.Parag Mahatme (2015) - Effective Techniques in Cost optimization of construction project
Chapter in Books
[6] Christ.Hendrickson (1990) - Use of Advanced Scheduling Techniques