SlideShare a Scribd company logo
1 of 6
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1678
Identification of Bottleneck and Reducing Cycle Time of an Industrial
Oven by Using Project Management Techniques
Vikas S. Jadhav[1], V. Vivekanand [2]
1 P G Student, Industrial Engineering Department, Ramaiah Institute of Technology, Bangaluru.
2 Assistant Professor Industrial Engineering Department, Ramaiah Institute of Technology, Bangaluru.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - The present work was carried inaovenindustry.In
order to reduce the manufacturing time of Industrial Oven. a
process oriented crashing approach to projectmanagementis
proposed which givesinformationabouttotalprojectdataand
about individual activities as a function of contractual. The
decision to reduce the project duration must be based on the
analysis of trade off between time and cost. In current method
the assembly of industrial oven is done in 2041minutes i.e.
34.01hours and within 4.3 working days critical path method
is the proposed method to carry out the assembly operation in
parallel way so that the assembly of the complete oven can be
completed in 1694minutes i.e. 28.23hours therefore saving
5.78hours i.e. (347 minutes) reduced cycle time by 17% of
initial cycle time.
Keywords: industrial oven machine, Product Breakdown
Structure, Network Techniques, Critical Path Method and
crashing technique, Project management.
1. INTRODUCTION
The aim of the paper is to reduce the cycle time of Industrial
Oven machines by Identifying the bottleneck and reducing
cycle time of activities. This is done by using the industrial
engineering techniques such as,
Critical Path Method (CPM)
CPM and PERT are network based methods to assist in the
planning, scheduling and control of projects. A project is
defined as a collection of interrelated activities with each
activity consumingtimeandresources.Boththemethods are
basically time oriented methods in the sense that they both
lead to the determination of a time schedule for a project.
1.1 PROBLEM STATEMENT
After studying the problem Earlier the oven industryused to
take 2041 minutes i.e. 34.01hours and within 4.3 working
days this is because of using the same resources to carry out
the other subassemblies
1.2 OBJECTIVES
The objective of the project is to identify the location of
Bottleneck in the existing process, determine the project
critical path duration, reduce the cycle time of project and
decrease the production cost by applying the project
management techniques.
2 LITERATURE REVIEW
Komesh Sahu and Meenu Sahu[1]. “Minimizing Cost and
Time of Project using Crashing” this paper tells about the
crashing in project management. Crashing is reducing
project time by expendingadditional resources.Crashing the
network is nothing but contracting or compressing the
network that means to reduce the project duration at
minimum cost with minimum project duration. Naveen
Kumar and Dalgobind Mahto[2] “Assembly Line Balancing”,
here the authors said that Assembly line balancing is to
know how tasks are to be assigned to individual work
stations, so that the predetermined goal is achieved.
Minimization of number of work stations and maximization
of the production rate are the most common goals. Peter
Shelth Professor Guy Le Roy[3] “Project Analysis Through
CPM Critical path method” here he said that CPM is a
technique for analyzing projects by determining the longest
sequence of tasks (or the sequence of task with the least
slack) through a project network. The CPM and the CCPM
(Critical chain project management) are both valuable tools
that any organization can use successfully to manage their
projects. “Scope management, cost management, and time
management” are important variablesfor projects.Concepts
like network diagram (PERT and CPM),learnt how to draw
the CPM network, precedence diagram and management
engineering were more useful in this project.
3 METHODOLOGY
Figure-1
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1679
3.1 WORK BREAKDOWN STRUCTURE
The product breakdown structure in project management
and systems engineering is a deliverable oriented
decomposition of a project into smaller components.Awork
breakdown structure element may bea product,a service,or
any combination. A work breakdown structure. Theproduct
breakdown structure of an industrial oven manufacturing.
Work Breakdown Structure
Figure- 2 Work Breakdown Structure
It can be seen in above figure that the industrial oven is
divided in main two component i.e. 1)Blower and burning
assembly 2) Turn table ,ramp assembly than further again
divided in to their subassemblies such as heat exchanger,
blower housing, motor coupling assemblyandcontrol panel.
The another main assembly separated by their
subassemblies like Baking chamber door, bottom base
assembly, inner ramp, air flow sheet. The manufacturing
time and operations of subassemblies are given tables at
different work stations. The subassemblies like heat
exchanger, blower housing. Baking chamber door and
bottom base all are manufactured parallel at different
workstations.
3.2 ACTIVITY RELATIONSHIP TABLE
In the process of manufacturing industrial oven there are
number of activities which needs to perform and the
sequence of operation, operation time and the total number
of activities are tabulated in table 1.
Table – 1 Activity Relationship Table
3.3 DEVELOPMENT OF PROJECT NETWORK
Figure – 3 Precedence Network
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1680
3.4 IDENTIFICATION OF CRITICAL PATH
The path which has highest duration
The critical Path Is
1-2-3-4-7-12-16-20-25-27-28-29-30-31
And critical path duration is = 2041 minutes (34.01 hours)
The total Indirect cost 4800/shift = 600/hour
3.5 CRASHING
Crashing the project refers to reduce crashing a number of
activities to reduce the duration of project below normal
value.
The special measures might include using overtime, hiring
additional temporary help, using special time saving
materials, obtaining special equipment.
Critical path method of Time Cost Trade Offs is concerned
with how much (if any) to crash each of the activities to
anticipated duration of the project down to a desired value.
The data required for determining how much to crash a
particular activity is calculated by the time cost trade for the
activities.
Cost Scheduling Computations:
Let
NT= Normal time: - completion of an activity with allocation
of resources
NC= Normal cost: - cost associated with normal time
CT=Crash time: - shortest completiontimeofanactivity with
extra resources
CC= Crash cost: - cost associated with crash time
Cost Slope = change in cost/change in time
= (Normal cost - crash cost) / (crash time - normal time)
CRASH TIME AND CRASH COST
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1681
Table 2
Total direct cost (TDC) – it is the one in which we can
allocate the cost of the job directly
Example: Raw material cost, labor cost
Total indirect cost (TIC) – in which not possible to allocate
the cost of job directly
TIC = 600/hour
Slope of each activity can be calculated as
Slope = CC-NC /ND-CD
Crashing along this critical path and looking into their
minimum slope the crashing can be start on activity which
has lower slope and its ascending order along the critical
path and ∆t value which is found (0.15). The activity “16 to
20” has lower ∆t value can be crashed by 0.15hours
(9minutes)
Crashing table
Table 3 Crashing Critical Path 1
After crashing along the critical path the duration of
project is reduced from 34.01hours to 32.21hours
Similarly further crashing can done to another critical
Path and so on.
Figure – 4 Final Precedence Network
Critical path 2 is
1-2-3-4-9-13-16-20-25-27-28-29-30-31
=1775minutes (29.58 hours)
Table- 4 Crashing Critical Path 4
In above table 4 it can seen that after crashing the critical
path 4 the duration of the project reduced from 34.01hours
to 28.23hours which is 5.78hours has been saved and hence
the minimum duration of the project is 28.23hours which in
terms of 3.5days.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1682
4 OPTIMUM SCHEDULE COST
Determining Time estimation for all activities
– EST- Earliest start time: the earliest time at which
the activity can start given that its precedent
activities must be completed first.
– EFT-Earliest finish time: equals to the earliest start
time for the activity plus the time required to
complete the activity.
– LFT- Latest finish time: the latest time in which the
activity can be completed without delaying the
project.
– LST- Latest start time: equal to the latest finishtime
minus the time required to complete the activity.
– TF- total float = LFT – EFT
Table -5 Optimum Scheduling Time Estimation
It is seen in above table the total float along the critical path
is zero, the activity which are not comes in the critical path
having total float.
4 RESULTS
Because crashing a non critical activity does not affect the
overall project duration, only critical activities can be
crashed are crashed are considered. The activities to be
crashed are chosen in order of increasing expanses.Thusthe
activity with the smaller crash cost in table is chosen to be
crashed first. Initial cycle time for 1 complete oven was
34.01hours after crashing the cycle time reduces up to
28.23hours The total time saved is 5.78hours (347minutes).
The normal duration of the project is 34.01hours and the
corresponding cost was 27470, the minimum duration of
project is 28.23hours and its cost is 35139 The number of
hours saved = 5.78 hours (17%) The common activity
duration reduced by 189minutes (54.46%) The parallel
activity duration reduced by 158minutes (45.53%) Further
crashing will results in change in critical path so after that
crashing is stopped.
6 CONCLUSION
The aim of this project was to reduce assembly time of
industrial oven, by using various industrial engineering
concepts. in the current method theassemblyofthemachine
is done in 2040 min i.e. 34.01hours and 4.3 working days.
Critical path method is the proposed methodtocarryoutthe
assembly operations in parallel way so that the assembly of
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1683
the complete oven can be completed in 1694mins
i.e.28.23hours. by allocating extra resources to crashed
activity Therefore saving 5.78hours i.e. (347minutes).
In order to validate the Critical path method results and it
also showed the same result i.e. complete machineassembly
can be done in 3.4 working days the minimum duration of
project is 28.23hours and its cost is 35139 and the number
of hours saved = 5.78 hours (17%).
REFERENCES
[1] Hadi Gokcen, Kursad Aggak “Balancing Of Parallel
Assembly Line”
[2] S.Shanmugasundaram, V.Mathan Kumar “Applicationof
project scheduling and Cost analysis Using PERT and
CPM” Vol. 4, No. 2, April 2015 (ISSN 2278 – 5973)
[3] Michael A. Chilton “Resource Allocation in IT Projects”
[4] Tung Yang and Photios G. Ioannou “Scheduling Systems
With Focus On Practical ConcernsInRepetitiveProjects”
[5] Ali Goksu, Selma Catovic.”Implementation of CPM and
PERT In Assembly Line”
[6] Komesh Sahu and Meenu “Minimizing Cost and Time of
Project using Crashing”
[7] Hamdy A. Taha”Operations Research: An Introduction
Book”
[8] Frederick S Hillier and Gerald J. Lieberman
“Introduction to Operations Research”

More Related Content

What's hot

Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityIRJET Journal
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5VancityInstitute
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
PERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGPERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGAlam Nuzhathalam
 
IRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET Journal
 
IRJET- Determination of Time Period and Evaluation of Seismic Response of...
IRJET-  	  Determination of Time Period and Evaluation of Seismic Response of...IRJET-  	  Determination of Time Period and Evaluation of Seismic Response of...
IRJET- Determination of Time Period and Evaluation of Seismic Response of...IRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencingBuha Payal
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
 
022 B Construction Croductivity-WRITE SYSTEM
022 B Construction Croductivity-WRITE SYSTEM 022 B Construction Croductivity-WRITE SYSTEM
022 B Construction Croductivity-WRITE SYSTEM Dr Fereidoun Dejahang
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraIRJET Journal
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 

What's hot (18)

Final Review
Final ReviewFinal Review
Final Review
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
PERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGPERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKING
 
vignesh conference
vignesh conferencevignesh conference
vignesh conference
 
Ffeb69332c5a484
Ffeb69332c5a484Ffeb69332c5a484
Ffeb69332c5a484
 
IRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection Molding
 
IRJET- Determination of Time Period and Evaluation of Seismic Response of...
IRJET-  	  Determination of Time Period and Evaluation of Seismic Response of...IRJET-  	  Determination of Time Period and Evaluation of Seismic Response of...
IRJET- Determination of Time Period and Evaluation of Seismic Response of...
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencing
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
055 KPI'S Success Factor
055 KPI'S Success Factor 055 KPI'S Success Factor
055 KPI'S Success Factor
 
022 B Construction Croductivity-WRITE SYSTEM
022 B Construction Croductivity-WRITE SYSTEM 022 B Construction Croductivity-WRITE SYSTEM
022 B Construction Croductivity-WRITE SYSTEM
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using Primavera
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 

Similar to Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by using Project Management Techniques

COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPIRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...IRJET Journal
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET Journal
 
Improvement of Process and Product Layout for Metro Coach using Craft Method...
Improvement of Process and  Product Layout for Metro Coach using Craft Method...Improvement of Process and  Product Layout for Metro Coach using Craft Method...
Improvement of Process and Product Layout for Metro Coach using Craft Method...IRJET Journal
 
Improvement of Process and Product Layout for Metro Coach using Craft Method...
Improvement of Process and  Product Layout for Metro Coach using Craft Method...Improvement of Process and  Product Layout for Metro Coach using Craft Method...
Improvement of Process and Product Layout for Metro Coach using Craft Method...IRJET Journal
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolIRJET Journal
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTIRJET Journal
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET Journal
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
Advanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference ModelAdvanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference ModelAurélien Chassagne
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET Journal
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET Journal
 
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONIRJET Journal
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...IRJET Journal
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET Journal
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Offssuserfe1b72
 

Similar to Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by using Project Management Techniques (20)

COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...Time Study and Method Study Application in Machining Plant for Improvement in...
Time Study and Method Study Application in Machining Plant for Improvement in...
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
 
Improvement of Process and Product Layout for Metro Coach using Craft Method...
Improvement of Process and  Product Layout for Metro Coach using Craft Method...Improvement of Process and  Product Layout for Metro Coach using Craft Method...
Improvement of Process and Product Layout for Metro Coach using Craft Method...
 
Improvement of Process and Product Layout for Metro Coach using Craft Method...
Improvement of Process and  Product Layout for Metro Coach using Craft Method...Improvement of Process and  Product Layout for Metro Coach using Craft Method...
Improvement of Process and Product Layout for Metro Coach using Craft Method...
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
Ijmet 09 11_006
Ijmet 09 11_006Ijmet 09 11_006
Ijmet 09 11_006
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
Advanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference ModelAdvanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference Model
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 

Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by using Project Management Techniques

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1678 Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by Using Project Management Techniques Vikas S. Jadhav[1], V. Vivekanand [2] 1 P G Student, Industrial Engineering Department, Ramaiah Institute of Technology, Bangaluru. 2 Assistant Professor Industrial Engineering Department, Ramaiah Institute of Technology, Bangaluru. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - The present work was carried inaovenindustry.In order to reduce the manufacturing time of Industrial Oven. a process oriented crashing approach to projectmanagementis proposed which givesinformationabouttotalprojectdataand about individual activities as a function of contractual. The decision to reduce the project duration must be based on the analysis of trade off between time and cost. In current method the assembly of industrial oven is done in 2041minutes i.e. 34.01hours and within 4.3 working days critical path method is the proposed method to carry out the assembly operation in parallel way so that the assembly of the complete oven can be completed in 1694minutes i.e. 28.23hours therefore saving 5.78hours i.e. (347 minutes) reduced cycle time by 17% of initial cycle time. Keywords: industrial oven machine, Product Breakdown Structure, Network Techniques, Critical Path Method and crashing technique, Project management. 1. INTRODUCTION The aim of the paper is to reduce the cycle time of Industrial Oven machines by Identifying the bottleneck and reducing cycle time of activities. This is done by using the industrial engineering techniques such as, Critical Path Method (CPM) CPM and PERT are network based methods to assist in the planning, scheduling and control of projects. A project is defined as a collection of interrelated activities with each activity consumingtimeandresources.Boththemethods are basically time oriented methods in the sense that they both lead to the determination of a time schedule for a project. 1.1 PROBLEM STATEMENT After studying the problem Earlier the oven industryused to take 2041 minutes i.e. 34.01hours and within 4.3 working days this is because of using the same resources to carry out the other subassemblies 1.2 OBJECTIVES The objective of the project is to identify the location of Bottleneck in the existing process, determine the project critical path duration, reduce the cycle time of project and decrease the production cost by applying the project management techniques. 2 LITERATURE REVIEW Komesh Sahu and Meenu Sahu[1]. “Minimizing Cost and Time of Project using Crashing” this paper tells about the crashing in project management. Crashing is reducing project time by expendingadditional resources.Crashing the network is nothing but contracting or compressing the network that means to reduce the project duration at minimum cost with minimum project duration. Naveen Kumar and Dalgobind Mahto[2] “Assembly Line Balancing”, here the authors said that Assembly line balancing is to know how tasks are to be assigned to individual work stations, so that the predetermined goal is achieved. Minimization of number of work stations and maximization of the production rate are the most common goals. Peter Shelth Professor Guy Le Roy[3] “Project Analysis Through CPM Critical path method” here he said that CPM is a technique for analyzing projects by determining the longest sequence of tasks (or the sequence of task with the least slack) through a project network. The CPM and the CCPM (Critical chain project management) are both valuable tools that any organization can use successfully to manage their projects. “Scope management, cost management, and time management” are important variablesfor projects.Concepts like network diagram (PERT and CPM),learnt how to draw the CPM network, precedence diagram and management engineering were more useful in this project. 3 METHODOLOGY Figure-1
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1679 3.1 WORK BREAKDOWN STRUCTURE The product breakdown structure in project management and systems engineering is a deliverable oriented decomposition of a project into smaller components.Awork breakdown structure element may bea product,a service,or any combination. A work breakdown structure. Theproduct breakdown structure of an industrial oven manufacturing. Work Breakdown Structure Figure- 2 Work Breakdown Structure It can be seen in above figure that the industrial oven is divided in main two component i.e. 1)Blower and burning assembly 2) Turn table ,ramp assembly than further again divided in to their subassemblies such as heat exchanger, blower housing, motor coupling assemblyandcontrol panel. The another main assembly separated by their subassemblies like Baking chamber door, bottom base assembly, inner ramp, air flow sheet. The manufacturing time and operations of subassemblies are given tables at different work stations. The subassemblies like heat exchanger, blower housing. Baking chamber door and bottom base all are manufactured parallel at different workstations. 3.2 ACTIVITY RELATIONSHIP TABLE In the process of manufacturing industrial oven there are number of activities which needs to perform and the sequence of operation, operation time and the total number of activities are tabulated in table 1. Table – 1 Activity Relationship Table 3.3 DEVELOPMENT OF PROJECT NETWORK Figure – 3 Precedence Network
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1680 3.4 IDENTIFICATION OF CRITICAL PATH The path which has highest duration The critical Path Is 1-2-3-4-7-12-16-20-25-27-28-29-30-31 And critical path duration is = 2041 minutes (34.01 hours) The total Indirect cost 4800/shift = 600/hour 3.5 CRASHING Crashing the project refers to reduce crashing a number of activities to reduce the duration of project below normal value. The special measures might include using overtime, hiring additional temporary help, using special time saving materials, obtaining special equipment. Critical path method of Time Cost Trade Offs is concerned with how much (if any) to crash each of the activities to anticipated duration of the project down to a desired value. The data required for determining how much to crash a particular activity is calculated by the time cost trade for the activities. Cost Scheduling Computations: Let NT= Normal time: - completion of an activity with allocation of resources NC= Normal cost: - cost associated with normal time CT=Crash time: - shortest completiontimeofanactivity with extra resources CC= Crash cost: - cost associated with crash time Cost Slope = change in cost/change in time = (Normal cost - crash cost) / (crash time - normal time) CRASH TIME AND CRASH COST
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1681 Table 2 Total direct cost (TDC) – it is the one in which we can allocate the cost of the job directly Example: Raw material cost, labor cost Total indirect cost (TIC) – in which not possible to allocate the cost of job directly TIC = 600/hour Slope of each activity can be calculated as Slope = CC-NC /ND-CD Crashing along this critical path and looking into their minimum slope the crashing can be start on activity which has lower slope and its ascending order along the critical path and ∆t value which is found (0.15). The activity “16 to 20” has lower ∆t value can be crashed by 0.15hours (9minutes) Crashing table Table 3 Crashing Critical Path 1 After crashing along the critical path the duration of project is reduced from 34.01hours to 32.21hours Similarly further crashing can done to another critical Path and so on. Figure – 4 Final Precedence Network Critical path 2 is 1-2-3-4-9-13-16-20-25-27-28-29-30-31 =1775minutes (29.58 hours) Table- 4 Crashing Critical Path 4 In above table 4 it can seen that after crashing the critical path 4 the duration of the project reduced from 34.01hours to 28.23hours which is 5.78hours has been saved and hence the minimum duration of the project is 28.23hours which in terms of 3.5days.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1682 4 OPTIMUM SCHEDULE COST Determining Time estimation for all activities – EST- Earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. – EFT-Earliest finish time: equals to the earliest start time for the activity plus the time required to complete the activity. – LFT- Latest finish time: the latest time in which the activity can be completed without delaying the project. – LST- Latest start time: equal to the latest finishtime minus the time required to complete the activity. – TF- total float = LFT – EFT Table -5 Optimum Scheduling Time Estimation It is seen in above table the total float along the critical path is zero, the activity which are not comes in the critical path having total float. 4 RESULTS Because crashing a non critical activity does not affect the overall project duration, only critical activities can be crashed are crashed are considered. The activities to be crashed are chosen in order of increasing expanses.Thusthe activity with the smaller crash cost in table is chosen to be crashed first. Initial cycle time for 1 complete oven was 34.01hours after crashing the cycle time reduces up to 28.23hours The total time saved is 5.78hours (347minutes). The normal duration of the project is 34.01hours and the corresponding cost was 27470, the minimum duration of project is 28.23hours and its cost is 35139 The number of hours saved = 5.78 hours (17%) The common activity duration reduced by 189minutes (54.46%) The parallel activity duration reduced by 158minutes (45.53%) Further crashing will results in change in critical path so after that crashing is stopped. 6 CONCLUSION The aim of this project was to reduce assembly time of industrial oven, by using various industrial engineering concepts. in the current method theassemblyofthemachine is done in 2040 min i.e. 34.01hours and 4.3 working days. Critical path method is the proposed methodtocarryoutthe assembly operations in parallel way so that the assembly of
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1683 the complete oven can be completed in 1694mins i.e.28.23hours. by allocating extra resources to crashed activity Therefore saving 5.78hours i.e. (347minutes). In order to validate the Critical path method results and it also showed the same result i.e. complete machineassembly can be done in 3.4 working days the minimum duration of project is 28.23hours and its cost is 35139 and the number of hours saved = 5.78 hours (17%). REFERENCES [1] Hadi Gokcen, Kursad Aggak “Balancing Of Parallel Assembly Line” [2] S.Shanmugasundaram, V.Mathan Kumar “Applicationof project scheduling and Cost analysis Using PERT and CPM” Vol. 4, No. 2, April 2015 (ISSN 2278 – 5973) [3] Michael A. Chilton “Resource Allocation in IT Projects” [4] Tung Yang and Photios G. Ioannou “Scheduling Systems With Focus On Practical ConcernsInRepetitiveProjects” [5] Ali Goksu, Selma Catovic.”Implementation of CPM and PERT In Assembly Line” [6] Komesh Sahu and Meenu “Minimizing Cost and Time of Project using Crashing” [7] Hamdy A. Taha”Operations Research: An Introduction Book” [8] Frederick S Hillier and Gerald J. Lieberman “Introduction to Operations Research”