Application of Earned Value Method and Delay Analysis on
Construction Project to Analyse Cost and Schedule
Rudresh L.1, Shashank U. Vanakudari 2
1P.G students, M. Tech, Department of Civil Engineering, Jain College of Engineering, Belagavi, Karnataka, India
2Assistant Professor, Department of Civil Engineering, Jain College of Engineering, Belagavi, Karnataka, India
----------------------------------------------------------------------***---------------------------------------------------------------------
ABSTRACT – In construction industry there are many
confrontations and increasing day to day. Above all this
confrontation a very important is to improve the performance
of the project with reference to cost and schedule to overcome
this confrontations. To achieve this one of the best tool is
earned value methodology to analyse and measure
performance of construction project. It is helpfulinmeasuring
progress and determining unfavourable issues. And delay
analysis is a process of analysing the project delay, helps
finding the root causes for the delay in project. Both earned
value and delay analysis is carried out using Microsoft project
software program. The main object of this project work is to
measure the performanceandanalysetheconstructionproject
with respect to cost and schedule. For this project work a
delayed construction project was selected as a case study to
carryout analysis to knowperformanceofconstructionproject
and to find the critical issues respect to cost and schedule and
delay analysis to find the variance in duration and root causes
for the delay in project.
Key Words: Earned Value Management, Earned Value
Analysis (EVA), Delay Analysis, MS Project
1. INTRODUCTION
In an increasingly challenging world, the markets have an
intense contest, customer satisfaction had increased the
central pivot of many company of construction industry and
they want to be successful. The fulfilment not only comes
from the quality and performance but also through timeand
cost indices in construction. Now a days the environment
and social issues are rising so, to minimize the wastage a
good allocation of resources is important. Construction field
is one of the most important sector in development of
countries like India. This faces challenges day to day.
Contribution from this field to growth of a country’s
economy to a large extent. The construction project main
issue with a project time and cost overturn. This caused by
the various reasons, so results in project budget overturns
and cannot complete the project in scheduled time. In spite
of many decades of practice and academic attention project
performance, remains problematic, verifiable evidence
suggests that projects do not generally achieve the required
scope, are frequently delay, and perform badly on quality of
deliverables as well as on cost budgets.
In construction industry, delay is project beyond the
completion date as stated in the contract agreement. It is
beyond the planned schedule and it is one of the common
problems in construction projects. It is important to find the
actual reasons or causes in project delay because to control
the delay in project future and minimize delay in upcoming
projects which results in cost over turn. As per PMBOK to
determine the cost and schedule variation, the earned value
management is one of the tools used.
In this project, my important target is to study earned value
method as a monitoring and controlling tool to check the
progress track. By doing this we get the proper costs and
time related viewpoint of the project at the particular stage.
In addition, can forecast that time required in the future
completion of project and calculates the cost required for
continuing the project in best planed pace. Also studyingthe
common issues in construction project delay.Iftheprojectis
not in planned pace. Finding the root causes for delay in
project.
2. TERMINOLOGIES
2.1 Earned Value Management
Earned value management (EVM) is a method that is a
combination of scope, schedule and resourcemeasurements
to help project performance and its progress. It is a widely
used method ofperformance measurementforprojects.EVM
is valuable technique to find the real gains and losses on
projects and helps in providing sort to balance profit/losses
and minimize losses. It is a powerful tool to control
concurrently cost and physical performance. The project
managers and management can track possible areas that
area susceptible to risk. They can create plans suitability. In
short earned valve methodology takes care of problems
through timely remedial actionbeforetheybecometoogreat
to overcome.
2.2 Earned Value Parameters
Current fields that measures different features of earned
value are the earned value fields. There are mainly 3 terms,
which identify earned value concept.
Planned Value: PV or budgeted cost of work scheduled it
measures budgeted cost of individual tasks/activesbased on
the resources and fixed costs that are assignedtotaskswhen
schedule them.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3205
Earned Value: EV or known as budgeted cost of work
performed indicates how much of a project or task/ activity
budget should have spent, given the actual duration of the
project or tasks/ activities date. It is also an approx. value of
physical work actually completed.
Actual Cost: AC or known as actual cost work performed.
Measures the actual cost that incurred to completion of
project or task. During the completion process, Actual cost
indicates the actual costs for work performed through the
projects status date.
Fig.-1 General representation of EV, PV & AC in Graph.
I) Variances
Cost Variance: Cost variance, (CV) is a comparison of
budgeted cost of work performed, EV with actual cost, AC. It
is calculated using
CV = EV – AC
A negative (-) cost variance means the project is overbudget
that is performing the work cost more than planned. The
causes for this may be analysed and suitable right measures
can be initialled to bring back the project on budget. When it
happens, the project managers or team will know that costs
is going over the planned budget.
A positive (+) cost variance means that the project progress
is at cost less than planned budget. This good sign shows the
project is progressing as planned.
Cost Variance (CV %): Cost variance (CV %) is a project
mathematically calculates CV% by CV Divided by EV and
multiplied by the 100.
CV % = CV / EV X 100
Schedule Variance: Schedule variance (SV) is the
comparison of quantity of work performed during a given
period of time to what has scheduled to be performed. It is
also represented in percentage (%). It is given by
SV = EV – PV
A negative (-) schedule variance indicates the project is
behind planned schedule, means took more time than
planned to complete the work.
Also if a positive (+) schedule variance that the project is
ahead of planned schedule, means took less time than
planned to complete.
Schedule Variance (SV%): Schedule variance, (SV %)is
a project mathematicallycalculatesCV%bySVDivided byPV
and multiplied by the 100.
SV % = SV / PV X 100
II) Performance Indices
a) Cost performance index (CPI): Cost performance
index (CPI is used to calculate the project cost to complete
the project basis on performance to date.
CPI = EV / AC
CPI > 1 (If CPI greater than 1 means that project is over
budget)
CPI < 1 (If CPI lesser than 1 means that project is under
budget)
CPI = 1 (If CPI equals to 1 means that project’s planned and
actual costs are some)
b) Schedule performance index (SPI): Schedule
performance index (SPI) is used to calculate the estimated
time to complete the project based on the performance to
date. It is given by:
SPI = EV / PV
SPI > 1 (If SPI greater than 1 means that project is ahead
schedule)
SPI < 1 (If SPI lesser than 1 means that project is behind
schedule)
SPI = 1 (If SPI equals to 1 means that project is on schedule)
III) Forecasting Indicators
a) Estimation at Completion (EAC): It is sum of actual
cost till date and the estimated cost for the other remaining
task in project. It is given by.
EAC = Actual Cost (AC) + Estimate to complete (ETC)
OR
EAC = Budget at Completion / Cost Performance Index
Based on the above formula the Microsoft project calculates
the Estimate at Competition. It is baseline cost that the
planned cost for a task in project, a resource for all allocated
tasks or for activity to be performed by the resource on a
task.
b) Estimation to complete (ETC): It is the difference
between and Estimate at Completion (EAC) and budget at
completion (BAC) or Actual cost. Thisisestimatedadditional
cost to complete the project at any point time of project.
ETC = EAC - AC
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3206
c) Variance at completion (VAC): It is the difference
between Budget at completion (BAC) and Estimate at
Completion (EAC). The value by which the project will be
under or over budget.
VAC = BAC - EAC
3. METHODOLOGY
Fig.-2: Flowchart showing the methodology of this project
work.
Firstly, the existing research, analysis study on earned value
analysis, which have earlier done, are collected.
Secondly the collection of cost and schedule data of an real
project which is to analysed under progress, so that earned
value analysis can be made and conclusion can be given to
the on/future of the project.
Thirdly, creating the project in MSP, entering the data
collected about the project in the analysis software and
defining the work breakdown structure (WBS).
Than it is to start tracking the project and keep a look on the
progress of different task/activities in project.
The next approach is to run the analysis on a particular date,
later by using the Microsoft Project software, the earned
value analysis is carried out.
In this approach, follow progress report on different status
dates. The report may contains crucial activities,activitiesin
progress, budgeted and actual of cost and schedule.
In final approach giving suitable conclusion on the schedule
and cost index obtained after earned value analysis and
delay analysis from Microsoft Project software.
3.1 Creating a Project for Data Analysis
Data analysis can be done manual or digitally by using
software program. In manual method the project
management team or project control & monitoring staff
analysis the data, but it is complex process there can be
human errors. So by using project analysing software tool
like Microsoft project, primavera etc. the complex process
can be simplified, accuracy in analysis is achieved.
3.2 MS Project
MSP is one of the project management software
program. It is created, developedand marketed byMicrosoft.
It is designed to assist the project management team or
managers in improving plan, resources assigning to tasks,
tracking progress,budgetsmanagement,workloadsanalysis.
In this project, the case study analysis is carried out using
Microsoft project professional 2013 version.
The steps involved in the Microsoft project softwarefor
project earned valve analysis. The step are below,
1. Creating and initiation project
2. Creating project calendar
3. Entering task and its relationships
4. Defining work breakdown structure
5. Assign resources, its analysis and levelling
6. Progress Tracking
7. Earned value analysis
8. Publishing reports
4. CASE STUDY-DATA ANALYSIS AND
INTERPRETATION
The main intention of this case study is to analyse and study
the earned value parameters and come to a conclusion.
4.1 Analysis of Tracking Project’s Progress Report
The details of tracking progress of complete project various
tasks are executed till that status date.
On status date i.e. February 2017 the tracking project’s
progress, showing 98 % complete of work in project.
Whereas at this date project should have completely
finished, but there was a delay. Therefore, from this tracking
project’s progress it comes to know that project was behind
the schedule and delay in project delivering.
From this progress tracking is can be concluded the project
is running 2% behind the schedule. So it can be concluded
that the project was delayed.
4.2 Analysis for Complete Construction Work
The Budget at competition (BAC) cost for various tasks of D-
mart project was around Rs.76.9 lakhs.
The planned value (PV) was around Rs.68. 78lakhs, the
Actual cost (AC) was about Rs.80.23 lakhs. And the Earned
value (EV) was around Rs.68.36 lakhs is recorded from the
project tracking report.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3207
Graph-1: Graphical representation of PV, EV & AC
By Earned value parameters interpretation, the CV around
Rs.-11.86 lakhs & SV around Rs.-0.41 lakhs these values and
CV% is -17% & SV% is -1%. These CV and SV values
conclude at this project execution is behind the planned
schedule and cost overturn.
Graph-2: Graphical representation of CV & SC
The Cost performance index, (CPI) was 0.85 and Schedule
performance index (SPI) was around 0.99. The value
indicates this project is foregoing over planned cost and
behind the planned.
Graph-3: Graphical representation of CPI and SPI
The EAC cost may be Rs.90.02 lakhs. The foreseen value
indicates the expected complete project cost
The VAC cost was around Rs.-13.34 lakhs. This foreseen
value indicates cost overruns at this project completion.
The calculated ETC cost was around Rs.10.02 lakhs. This
foreseen value indicates the additional required cost for
completing the remaining work of the project.
Graph-4: Graphical representation of forecasting indices
The contract agreement was item rate contract. The
contractor intention was to complete the project in less
amount than the contract agreement amount to make profit.
So he spent less amount, but due to reasons mention in
analysis part
Above values it can be concluded that he did not complete
the project in his planned budget and makemuchprofitfrom
this project.
Table -1: Details of Analysis on EVM parameters of
construction work in project
Planned value Rs.6,878,348.93
Earned value Rs.6,836,818.52
Actual costs Rs.8,023,352.93
Cost performance index 0.85
Schedule performance index 0.99
Cost variances Rs.-1,186,534.41
Cost variances % -17%
Schedule variances Rs.- 41,530.42
Schedule variances % -1%
Budget at completion Rs.7,691,062.08
Estimate at completion Rs.9,025,856.79
Estimated to completion Rs.1,002,503.86
Variance at completion Rs.-1,334,794.71
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3208
4.3 Delay Analysis for Complete Construction
Tasks
The obtained data from the MSP analysis indicating the
below values.
The tracking of project’s progress at particular status date
February 2017 is 98% completed.
The planned duration for executionofwork was224.13days
(7.5months), but actual duration took for execution was
258.59 days (8.5 months). At current status date the project
was 253.65days only 4.94 days left to complete the
remaining works.
The planned schedule date was 15/6/16 to 28/1/17 but
actual schedule was 15/6/16 to 04/03/17. The start
variances of project is 0 days and finish variances of project
34.46 days.
Graph-5: Graphical representation for variances in
duration of project.
By above values it concludes that the project was started on
schedule date, but project is delayed by 34.46 days (nearly a
month).
Table - 2: Details of Analysis on delay in construction
work in project
Planned duration for
project
224.13 days
Actual duration to complete
project
258.59days
Remaining duration left to
complete remaining work
4.49 days
Planed dates 15/6/16 to 28/1/17
Actual dates 15/6/16 to 04/03/17
Start variance 0 days
Finish variance 34.46 days
4.5 Main Causes for the Project Delay
Client and contractor related causes
1. Late in receiving and approving drawing/designs
and inadequate details and unclear doubts in
drawing and also Delay in getting permits and
orders from higher authorities.
2. Change design and plan in drawing during
construction.
3. Ineffective planning and scheduling of activities in
project and Poor communication and coordination
of engineers and labours
4. Delay by other contractors work in project i.e. (pre-
fabricated structure erection and MEP contractors)
and sub-contractor (waterproofing).
5. The structural work contractor spent less money
than budgeted cost for execution of works.
Material, Equipment and Labour related causes
1. Delay in material and equipment delivery and
procurement i.e. (m-sand, p-sand, AAC blocks, clay
bricks, and formwork and its other materials,
earthwork machines)
2. Equipment and machinesbreakdownsandshortage
3. Low productivity and efficiency of equipment and
shortage and low skill of labours
4. Improper communication and coordination
between labours
5. Improper payments for labours by their head i.e.
(maestri, sub-contractor)
6. Depend on the fresher’s and less experienced
personal to bear project.
External factors related causes
1. Extreme rainfall effecting on construction, Delay
causes by the services from utilities i.e. (electricity
and water)
2. Delay in getting permission from city Municipal
Corporation.
3. Site location and resource availability, High quality
of work execution.
4. Demonetization effected on contractors financial
payments for labour and staff.
4.6 Effects of Delay on Project
1. Delay in project effected the time and cost overrun
of construction work in project
2. Disputes between the contractor and client project
managers.
3. The contract agreement was item rate contract.The
contractor wanted to complete the project in less
cost than the contract agreement. Therefore, he
spent less amount than budgetedamountbutdueto
reasons mention above. He could not complete the
project in his planned budget. He could not make
much profit from this project.
4.7 Minimizing and Controlling Duration and Cost in
Project
1. Adopt 24 hours per day working calendar. They
have done this as they have to finish the project
within the deadline. Alternative working hours.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3209
2. Clear coordination and communication between
client, contractor and with labour the delay in this
project could be controlled.
3. Correct emphasis on past experience, considering
the practical experience in past for delay causing
issues. The experiencedpersonnel’sandstaffshould
be appointed. They can easily handle and control
delay by their past experience. Also Include more
skilled labours
4. The contractor should have accurately estimated
the budgeted cost at beginning considering all
circumstances. He would have reached his financial
intention on this project.
5. During bad weather conditions alternativeworking
period should be planned,
6. Proper project planning and scheduling by
considering and studying all factors effecting work
could reduce the delay and increase best results.
7. Improved site management and supervision with
staff the executing can be monitored and delay
could be minimized. In addition, motivating labour
and workers to complete task on schedule.
8. Plan and analysing the requirement in details.
5. CONCLUSION
This analysis enables project management or mangers to
know the information about project and its every activity.
Therefore, the project team can be aware of which
parameters are causing more schedule and cost overturn.
The client, owner and contractor will get information
regarding the cost overrun and schedule overturn.
The analysis calculates the variances in project and foresees
the variance of every activity at the completion of project.
The notable factor of this analysis is it will track right values
of the work progress. After obtaining data from the analysis,
the project team and managers can discuss and indicate the
notable issues and they can take corrective actions.
By using this software program, the delay analysis of project
can be evaluated. Therefore, the project managers and team
may get to know the status of the project and can minimize
and control the ongoing project delay or in future project.
The project performance can be measured by using earned
value analysis with respect to cost and duration.
It helps in finding the project status. The project execution
related to schedule, project execution as per the original
planned schedule.
By Case study analysis, the project actual financial return
investment for the work done is found out. This EVM gives
better understanding related to cash flow.
The final completion time of project alongwithloss/profitto
the contractor is predicted.
Case study enables that monitoring the progress of work in
terms of cost and schedule can be carried out effectively.
By delay analysis on project helps in finding, the actual tasks
that resulted in causing delay in project and identifying the
root cause for the delay in execution of tasks.
The project team and managers can discuss and indicate the
notable issues and they can take corrective actions.
Case study enables that delay analysis is useful for project
managers and team to know the status of the project.
Moreover, can minimize and control the ongoing project
delay or in future project.
REFERENCE
[1] Aditi Dinakar, Delay Analysis in Construction
Project, ISSN: 2250-2459, Vol. 4, Issue 5, May 2014
[2] Ankur Verma, K.K. Pathak, R K Dixit, Earned Value
Analysis of Contruction Project at Rashtriya
Sanskrit Sansthan, Bhopal, ISSN: 2319-875, Vol. 3,
Issue 4, April 2014
[3] Antony Prasanth M A and K ThirumalaiRaja,Project
Performance Evaluation by Earned Value Method,
ISSN 2319-8753, Vol 3, Issue 1, Feb 2014.
[4] Anuj Bubey, Earned Value Analysis for a
Construction Project, ISSN: 0976-6316, Vol. 6,Issue
6, June 2015, pp. 53-66
[5] Mohd Faris Khamidi, Waris Ali Khan and Arazi
Idrus, The Cost Monitoring of Construction Projects
through Earned Value Analysis, Vol 4, 2011
[6] MSP Foundation Reference guide, CADD Centre
Training Services Private Limited, August 2015
[7] Radhika Gupta, Earned value Management System,
ISSN-2349-4409, Vol 2, Issue 4, July 2014, pp 160-
165.
[8] Sandhya Suresh and Ganapathy Ramaswamy N,
Analysis of Project PerformanceUsingEarnedValue
Analysis, Vol. 4, Issue 4, April 2015
[9] Shatanand Patil, Akshay Patil and Prof. Pramila
Chavan, Earned value management for Tracking
Project Progress, ISSN: 2248-9622, Vol. 2, Issue 3,
May 2012, pp. 1026-1029
[10] Sunil Ganpat Mahadik andPankajP.Bhangale,Study
& Analysis of Construction Project Management
with Earned Value Management System, ISSN:
2278-3075, Volume-3, Issue-4, Sep.2011

More Related Content

What's hot

Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...IJERA Editor
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Project Management Definitions
Project Management DefinitionsProject Management Definitions
Project Management DefinitionsTURKI , PMP
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civilengsulaiman khan
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project ControlsDavid Mathews
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET Journal
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction EngineersAmit Kumar Senapati, PMP®
 
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Expo
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriaNewman Jonathan
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 

What's hot (20)

Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Project Management Definitions
Project Management DefinitionsProject Management Definitions
Project Management Definitions
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civileng
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project Controls
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Project cost management
Project cost managementProject cost management
Project cost management
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project Control System
Project Control SystemProject Control System
Project Control System
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
 
Chap013 4er1
Chap013 4er1Chap013 4er1
Chap013 4er1
 
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
Project Controls Technician Apprentice - Joining the puzzle together by "Shan...
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 

Similar to Application of Earned Value Method and Delay Analysis on Construction Project to Analyse Cost and Schedule

Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraIRJET Journal
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...IAEME Publication
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTIAEME Publication
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
Application of value engineering in construction
Application of value engineering in constructionApplication of value engineering in construction
Application of value engineering in constructionDr Ezzat Mansour
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementIRJET Journal
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 

Similar to Application of Earned Value Method and Delay Analysis on Construction Project to Analyse Cost and Schedule (20)

Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using Primavera
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHODCOST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
Application of value engineering in construction
Application of value engineering in constructionApplication of value engineering in construction
Application of value engineering in construction
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program Management
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and Programs
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 

Application of Earned Value Method and Delay Analysis on Construction Project to Analyse Cost and Schedule

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3204 Application of Earned Value Method and Delay Analysis on Construction Project to Analyse Cost and Schedule Rudresh L.1, Shashank U. Vanakudari 2 1P.G students, M. Tech, Department of Civil Engineering, Jain College of Engineering, Belagavi, Karnataka, India 2Assistant Professor, Department of Civil Engineering, Jain College of Engineering, Belagavi, Karnataka, India ----------------------------------------------------------------------***--------------------------------------------------------------------- ABSTRACT – In construction industry there are many confrontations and increasing day to day. Above all this confrontation a very important is to improve the performance of the project with reference to cost and schedule to overcome this confrontations. To achieve this one of the best tool is earned value methodology to analyse and measure performance of construction project. It is helpfulinmeasuring progress and determining unfavourable issues. And delay analysis is a process of analysing the project delay, helps finding the root causes for the delay in project. Both earned value and delay analysis is carried out using Microsoft project software program. The main object of this project work is to measure the performanceandanalysetheconstructionproject with respect to cost and schedule. For this project work a delayed construction project was selected as a case study to carryout analysis to knowperformanceofconstructionproject and to find the critical issues respect to cost and schedule and delay analysis to find the variance in duration and root causes for the delay in project. Key Words: Earned Value Management, Earned Value Analysis (EVA), Delay Analysis, MS Project 1. INTRODUCTION In an increasingly challenging world, the markets have an intense contest, customer satisfaction had increased the central pivot of many company of construction industry and they want to be successful. The fulfilment not only comes from the quality and performance but also through timeand cost indices in construction. Now a days the environment and social issues are rising so, to minimize the wastage a good allocation of resources is important. Construction field is one of the most important sector in development of countries like India. This faces challenges day to day. Contribution from this field to growth of a country’s economy to a large extent. The construction project main issue with a project time and cost overturn. This caused by the various reasons, so results in project budget overturns and cannot complete the project in scheduled time. In spite of many decades of practice and academic attention project performance, remains problematic, verifiable evidence suggests that projects do not generally achieve the required scope, are frequently delay, and perform badly on quality of deliverables as well as on cost budgets. In construction industry, delay is project beyond the completion date as stated in the contract agreement. It is beyond the planned schedule and it is one of the common problems in construction projects. It is important to find the actual reasons or causes in project delay because to control the delay in project future and minimize delay in upcoming projects which results in cost over turn. As per PMBOK to determine the cost and schedule variation, the earned value management is one of the tools used. In this project, my important target is to study earned value method as a monitoring and controlling tool to check the progress track. By doing this we get the proper costs and time related viewpoint of the project at the particular stage. In addition, can forecast that time required in the future completion of project and calculates the cost required for continuing the project in best planed pace. Also studyingthe common issues in construction project delay.Iftheprojectis not in planned pace. Finding the root causes for delay in project. 2. TERMINOLOGIES 2.1 Earned Value Management Earned value management (EVM) is a method that is a combination of scope, schedule and resourcemeasurements to help project performance and its progress. It is a widely used method ofperformance measurementforprojects.EVM is valuable technique to find the real gains and losses on projects and helps in providing sort to balance profit/losses and minimize losses. It is a powerful tool to control concurrently cost and physical performance. The project managers and management can track possible areas that area susceptible to risk. They can create plans suitability. In short earned valve methodology takes care of problems through timely remedial actionbeforetheybecometoogreat to overcome. 2.2 Earned Value Parameters Current fields that measures different features of earned value are the earned value fields. There are mainly 3 terms, which identify earned value concept. Planned Value: PV or budgeted cost of work scheduled it measures budgeted cost of individual tasks/activesbased on the resources and fixed costs that are assignedtotaskswhen schedule them.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3205 Earned Value: EV or known as budgeted cost of work performed indicates how much of a project or task/ activity budget should have spent, given the actual duration of the project or tasks/ activities date. It is also an approx. value of physical work actually completed. Actual Cost: AC or known as actual cost work performed. Measures the actual cost that incurred to completion of project or task. During the completion process, Actual cost indicates the actual costs for work performed through the projects status date. Fig.-1 General representation of EV, PV & AC in Graph. I) Variances Cost Variance: Cost variance, (CV) is a comparison of budgeted cost of work performed, EV with actual cost, AC. It is calculated using CV = EV – AC A negative (-) cost variance means the project is overbudget that is performing the work cost more than planned. The causes for this may be analysed and suitable right measures can be initialled to bring back the project on budget. When it happens, the project managers or team will know that costs is going over the planned budget. A positive (+) cost variance means that the project progress is at cost less than planned budget. This good sign shows the project is progressing as planned. Cost Variance (CV %): Cost variance (CV %) is a project mathematically calculates CV% by CV Divided by EV and multiplied by the 100. CV % = CV / EV X 100 Schedule Variance: Schedule variance (SV) is the comparison of quantity of work performed during a given period of time to what has scheduled to be performed. It is also represented in percentage (%). It is given by SV = EV – PV A negative (-) schedule variance indicates the project is behind planned schedule, means took more time than planned to complete the work. Also if a positive (+) schedule variance that the project is ahead of planned schedule, means took less time than planned to complete. Schedule Variance (SV%): Schedule variance, (SV %)is a project mathematicallycalculatesCV%bySVDivided byPV and multiplied by the 100. SV % = SV / PV X 100 II) Performance Indices a) Cost performance index (CPI): Cost performance index (CPI is used to calculate the project cost to complete the project basis on performance to date. CPI = EV / AC CPI > 1 (If CPI greater than 1 means that project is over budget) CPI < 1 (If CPI lesser than 1 means that project is under budget) CPI = 1 (If CPI equals to 1 means that project’s planned and actual costs are some) b) Schedule performance index (SPI): Schedule performance index (SPI) is used to calculate the estimated time to complete the project based on the performance to date. It is given by: SPI = EV / PV SPI > 1 (If SPI greater than 1 means that project is ahead schedule) SPI < 1 (If SPI lesser than 1 means that project is behind schedule) SPI = 1 (If SPI equals to 1 means that project is on schedule) III) Forecasting Indicators a) Estimation at Completion (EAC): It is sum of actual cost till date and the estimated cost for the other remaining task in project. It is given by. EAC = Actual Cost (AC) + Estimate to complete (ETC) OR EAC = Budget at Completion / Cost Performance Index Based on the above formula the Microsoft project calculates the Estimate at Competition. It is baseline cost that the planned cost for a task in project, a resource for all allocated tasks or for activity to be performed by the resource on a task. b) Estimation to complete (ETC): It is the difference between and Estimate at Completion (EAC) and budget at completion (BAC) or Actual cost. Thisisestimatedadditional cost to complete the project at any point time of project. ETC = EAC - AC
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3206 c) Variance at completion (VAC): It is the difference between Budget at completion (BAC) and Estimate at Completion (EAC). The value by which the project will be under or over budget. VAC = BAC - EAC 3. METHODOLOGY Fig.-2: Flowchart showing the methodology of this project work. Firstly, the existing research, analysis study on earned value analysis, which have earlier done, are collected. Secondly the collection of cost and schedule data of an real project which is to analysed under progress, so that earned value analysis can be made and conclusion can be given to the on/future of the project. Thirdly, creating the project in MSP, entering the data collected about the project in the analysis software and defining the work breakdown structure (WBS). Than it is to start tracking the project and keep a look on the progress of different task/activities in project. The next approach is to run the analysis on a particular date, later by using the Microsoft Project software, the earned value analysis is carried out. In this approach, follow progress report on different status dates. The report may contains crucial activities,activitiesin progress, budgeted and actual of cost and schedule. In final approach giving suitable conclusion on the schedule and cost index obtained after earned value analysis and delay analysis from Microsoft Project software. 3.1 Creating a Project for Data Analysis Data analysis can be done manual or digitally by using software program. In manual method the project management team or project control & monitoring staff analysis the data, but it is complex process there can be human errors. So by using project analysing software tool like Microsoft project, primavera etc. the complex process can be simplified, accuracy in analysis is achieved. 3.2 MS Project MSP is one of the project management software program. It is created, developedand marketed byMicrosoft. It is designed to assist the project management team or managers in improving plan, resources assigning to tasks, tracking progress,budgetsmanagement,workloadsanalysis. In this project, the case study analysis is carried out using Microsoft project professional 2013 version. The steps involved in the Microsoft project softwarefor project earned valve analysis. The step are below, 1. Creating and initiation project 2. Creating project calendar 3. Entering task and its relationships 4. Defining work breakdown structure 5. Assign resources, its analysis and levelling 6. Progress Tracking 7. Earned value analysis 8. Publishing reports 4. CASE STUDY-DATA ANALYSIS AND INTERPRETATION The main intention of this case study is to analyse and study the earned value parameters and come to a conclusion. 4.1 Analysis of Tracking Project’s Progress Report The details of tracking progress of complete project various tasks are executed till that status date. On status date i.e. February 2017 the tracking project’s progress, showing 98 % complete of work in project. Whereas at this date project should have completely finished, but there was a delay. Therefore, from this tracking project’s progress it comes to know that project was behind the schedule and delay in project delivering. From this progress tracking is can be concluded the project is running 2% behind the schedule. So it can be concluded that the project was delayed. 4.2 Analysis for Complete Construction Work The Budget at competition (BAC) cost for various tasks of D- mart project was around Rs.76.9 lakhs. The planned value (PV) was around Rs.68. 78lakhs, the Actual cost (AC) was about Rs.80.23 lakhs. And the Earned value (EV) was around Rs.68.36 lakhs is recorded from the project tracking report.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3207 Graph-1: Graphical representation of PV, EV & AC By Earned value parameters interpretation, the CV around Rs.-11.86 lakhs & SV around Rs.-0.41 lakhs these values and CV% is -17% & SV% is -1%. These CV and SV values conclude at this project execution is behind the planned schedule and cost overturn. Graph-2: Graphical representation of CV & SC The Cost performance index, (CPI) was 0.85 and Schedule performance index (SPI) was around 0.99. The value indicates this project is foregoing over planned cost and behind the planned. Graph-3: Graphical representation of CPI and SPI The EAC cost may be Rs.90.02 lakhs. The foreseen value indicates the expected complete project cost The VAC cost was around Rs.-13.34 lakhs. This foreseen value indicates cost overruns at this project completion. The calculated ETC cost was around Rs.10.02 lakhs. This foreseen value indicates the additional required cost for completing the remaining work of the project. Graph-4: Graphical representation of forecasting indices The contract agreement was item rate contract. The contractor intention was to complete the project in less amount than the contract agreement amount to make profit. So he spent less amount, but due to reasons mention in analysis part Above values it can be concluded that he did not complete the project in his planned budget and makemuchprofitfrom this project. Table -1: Details of Analysis on EVM parameters of construction work in project Planned value Rs.6,878,348.93 Earned value Rs.6,836,818.52 Actual costs Rs.8,023,352.93 Cost performance index 0.85 Schedule performance index 0.99 Cost variances Rs.-1,186,534.41 Cost variances % -17% Schedule variances Rs.- 41,530.42 Schedule variances % -1% Budget at completion Rs.7,691,062.08 Estimate at completion Rs.9,025,856.79 Estimated to completion Rs.1,002,503.86 Variance at completion Rs.-1,334,794.71
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3208 4.3 Delay Analysis for Complete Construction Tasks The obtained data from the MSP analysis indicating the below values. The tracking of project’s progress at particular status date February 2017 is 98% completed. The planned duration for executionofwork was224.13days (7.5months), but actual duration took for execution was 258.59 days (8.5 months). At current status date the project was 253.65days only 4.94 days left to complete the remaining works. The planned schedule date was 15/6/16 to 28/1/17 but actual schedule was 15/6/16 to 04/03/17. The start variances of project is 0 days and finish variances of project 34.46 days. Graph-5: Graphical representation for variances in duration of project. By above values it concludes that the project was started on schedule date, but project is delayed by 34.46 days (nearly a month). Table - 2: Details of Analysis on delay in construction work in project Planned duration for project 224.13 days Actual duration to complete project 258.59days Remaining duration left to complete remaining work 4.49 days Planed dates 15/6/16 to 28/1/17 Actual dates 15/6/16 to 04/03/17 Start variance 0 days Finish variance 34.46 days 4.5 Main Causes for the Project Delay Client and contractor related causes 1. Late in receiving and approving drawing/designs and inadequate details and unclear doubts in drawing and also Delay in getting permits and orders from higher authorities. 2. Change design and plan in drawing during construction. 3. Ineffective planning and scheduling of activities in project and Poor communication and coordination of engineers and labours 4. Delay by other contractors work in project i.e. (pre- fabricated structure erection and MEP contractors) and sub-contractor (waterproofing). 5. The structural work contractor spent less money than budgeted cost for execution of works. Material, Equipment and Labour related causes 1. Delay in material and equipment delivery and procurement i.e. (m-sand, p-sand, AAC blocks, clay bricks, and formwork and its other materials, earthwork machines) 2. Equipment and machinesbreakdownsandshortage 3. Low productivity and efficiency of equipment and shortage and low skill of labours 4. Improper communication and coordination between labours 5. Improper payments for labours by their head i.e. (maestri, sub-contractor) 6. Depend on the fresher’s and less experienced personal to bear project. External factors related causes 1. Extreme rainfall effecting on construction, Delay causes by the services from utilities i.e. (electricity and water) 2. Delay in getting permission from city Municipal Corporation. 3. Site location and resource availability, High quality of work execution. 4. Demonetization effected on contractors financial payments for labour and staff. 4.6 Effects of Delay on Project 1. Delay in project effected the time and cost overrun of construction work in project 2. Disputes between the contractor and client project managers. 3. The contract agreement was item rate contract.The contractor wanted to complete the project in less cost than the contract agreement. Therefore, he spent less amount than budgetedamountbutdueto reasons mention above. He could not complete the project in his planned budget. He could not make much profit from this project. 4.7 Minimizing and Controlling Duration and Cost in Project 1. Adopt 24 hours per day working calendar. They have done this as they have to finish the project within the deadline. Alternative working hours.
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 3209 2. Clear coordination and communication between client, contractor and with labour the delay in this project could be controlled. 3. Correct emphasis on past experience, considering the practical experience in past for delay causing issues. The experiencedpersonnel’sandstaffshould be appointed. They can easily handle and control delay by their past experience. Also Include more skilled labours 4. The contractor should have accurately estimated the budgeted cost at beginning considering all circumstances. He would have reached his financial intention on this project. 5. During bad weather conditions alternativeworking period should be planned, 6. Proper project planning and scheduling by considering and studying all factors effecting work could reduce the delay and increase best results. 7. Improved site management and supervision with staff the executing can be monitored and delay could be minimized. In addition, motivating labour and workers to complete task on schedule. 8. Plan and analysing the requirement in details. 5. CONCLUSION This analysis enables project management or mangers to know the information about project and its every activity. Therefore, the project team can be aware of which parameters are causing more schedule and cost overturn. The client, owner and contractor will get information regarding the cost overrun and schedule overturn. The analysis calculates the variances in project and foresees the variance of every activity at the completion of project. The notable factor of this analysis is it will track right values of the work progress. After obtaining data from the analysis, the project team and managers can discuss and indicate the notable issues and they can take corrective actions. By using this software program, the delay analysis of project can be evaluated. Therefore, the project managers and team may get to know the status of the project and can minimize and control the ongoing project delay or in future project. The project performance can be measured by using earned value analysis with respect to cost and duration. It helps in finding the project status. The project execution related to schedule, project execution as per the original planned schedule. By Case study analysis, the project actual financial return investment for the work done is found out. This EVM gives better understanding related to cash flow. The final completion time of project alongwithloss/profitto the contractor is predicted. Case study enables that monitoring the progress of work in terms of cost and schedule can be carried out effectively. By delay analysis on project helps in finding, the actual tasks that resulted in causing delay in project and identifying the root cause for the delay in execution of tasks. The project team and managers can discuss and indicate the notable issues and they can take corrective actions. Case study enables that delay analysis is useful for project managers and team to know the status of the project. Moreover, can minimize and control the ongoing project delay or in future project. REFERENCE [1] Aditi Dinakar, Delay Analysis in Construction Project, ISSN: 2250-2459, Vol. 4, Issue 5, May 2014 [2] Ankur Verma, K.K. Pathak, R K Dixit, Earned Value Analysis of Contruction Project at Rashtriya Sanskrit Sansthan, Bhopal, ISSN: 2319-875, Vol. 3, Issue 4, April 2014 [3] Antony Prasanth M A and K ThirumalaiRaja,Project Performance Evaluation by Earned Value Method, ISSN 2319-8753, Vol 3, Issue 1, Feb 2014. [4] Anuj Bubey, Earned Value Analysis for a Construction Project, ISSN: 0976-6316, Vol. 6,Issue 6, June 2015, pp. 53-66 [5] Mohd Faris Khamidi, Waris Ali Khan and Arazi Idrus, The Cost Monitoring of Construction Projects through Earned Value Analysis, Vol 4, 2011 [6] MSP Foundation Reference guide, CADD Centre Training Services Private Limited, August 2015 [7] Radhika Gupta, Earned value Management System, ISSN-2349-4409, Vol 2, Issue 4, July 2014, pp 160- 165. [8] Sandhya Suresh and Ganapathy Ramaswamy N, Analysis of Project PerformanceUsingEarnedValue Analysis, Vol. 4, Issue 4, April 2015 [9] Shatanand Patil, Akshay Patil and Prof. Pramila Chavan, Earned value management for Tracking Project Progress, ISSN: 2248-9622, Vol. 2, Issue 3, May 2012, pp. 1026-1029 [10] Sunil Ganpat Mahadik andPankajP.Bhangale,Study & Analysis of Construction Project Management with Earned Value Management System, ISSN: 2278-3075, Volume-3, Issue-4, Sep.2011