SlideShare a Scribd company logo
Presented by : VENUMADHAV.R.YEMUL 
Guided by : MILIND.D.DARADE 
Roll No : 5073 
1
Manpower, equipment, and materials are 
important project resources that require 
management attention. 
The basic objective of resource planning and 
resource allocation is to supply and support 
the field operations. 
The term resource allocation is used in the 
case where required resources are assigned 
such that available resources are not 
exceeded. 
2
Resources are the means of production 
needed to complete a project. 
Most project managers would consider the 
big three resources that will require your 
attention to be: 
• Material 
• Labor 
• Equipment 
3
A. LABOUR 
a. In the limited resource allocation case, there 
are two assumptions: 
(1) There are a fixed number of crews available 
to perform the work and 
(2) The project may be delayed as a result of 
the limitation of crews. 
The objective of the resource allocation 
problem is to determine when the project will 
be completed. 
4
b. In the unlimited resource leveling case, there 
are two assumptions: 
(1) There are an unlimited number of crews 
available to perform the work and 
(2) The project may not be delayed. 
The objective of the resource leveling 
problem is to determine how to limit the 
fluctuation in crews required on the job. 
5
B. MATERIALS 
Materials, for projects with sufficient on-site 
storage, are delivered to the site and assumed 
to be available to workers as needed. 
A material-related concern for sites that have 
sufficient space is that of optimizing the position 
of materials on the site so that they require the 
least travel time from the lay-down yard to the 
work-face. 
6
C. EQUIPMENTS 
There are various types of equipment used on 
construction sites. 
Some of this equipment should be considered in 
the project plan, some need not be included. 
Workers, and their companies, are typically 
required to provide the small tools needed to 
complete their specific features of work. 
There are some types of equipment, however, that 
can affect the overall sequence and duration of the 
project. 
7
Resource allocation is used to assign the 
available resources in an economic way. 
It is part of resource management. 
In project management, resource allocation 
is the scheduling of activities and the 
resources required by those activities while 
taking into consideration both the resource 
availability and the project time. 
8
Resource planning cannot be accomplished 
without four essential resources necessary 
to accomplish the given scope of work: 
• MATERIAL 
• MAN POWER 
• MACHINARY 
• TIME 
9
Human resources for construction planning 
breaks down into three major categories as 
follows: 
• Home office personnel(Administrative 
Persons) 
• Construction personnel (field supervision 
and labor) 
• Construction subcontractors(Electrification, 
Plumbing, etc) 
10
The ideal form of a personnel loading curves 
is a trapezoid. 
The average personnel loading curve is a 
straight line. 
Actual practice loading curves take the 
shape of a bell curve 
11
12
The latter two result when the personnel 
loading curves occur earlier or later than 
planned on a project. 
Front loaded curve- the work started as early 
as possible. 
Normal loaded curve- the work started at 
normal time. 
Back loaded curve- the work started as late 
as possible. 
13
The "S" curve for the ideally loaded project has 
a gradual start and finish, which indicates 
smooth starting and finishing conditions. 
The forward loaded curve shows a rapid project 
start up and an even more gradual than normal 
phase out at the end. 
The backward-loaded project indicates a more 
relaxed start and a very steep finish slope on 
the "S" curve. 
14
15
16
Ensuring that the material resources for the 
project arrive on time involves these 
important planning areas: 
• Long-delivery equipment 
• Special materials and alloys 
• Common materials in short supply 
• Services and system requirements 
• Transportation systems 
17
Resource Limited: The project must be finished as 
soon as possible, but without exceeding some 
specific level of resource usage or some general 
resource constraint 
18
1. When the schedule demands more workers 
per day than are available or if we have 
workers standing around without jobs, we 
have a problem. 
2. When a new hire is trained, there is loss of 
productivity. So, if we can keep the trained 
people and reduce the number of new hires, 
we should be better off. 
19
. As we know, every project suffers from start-up 
problems of some sort. Superintendents and 
project managers are very busy trying to get 
everybody working in a productivity manner. 
Therefore, if we can start with a small crew and 
increase its size gradually, we will eliminate some 
of the start-up problems. 
. Most projects suffer from congestion around 
project completion time because of reduced work 
areas. Thus, if we can gradually reduce the crew 
size as we approach project completion, we can 
improve productivity by reducing congestion. 
20
The leveling procedure are as follows: 
• Scheduling all the critical jobs first. 
• Starting the non-critical jobs whenever there 
is a drop in scheduled man power upto the 
point where the peak is reached. 
• Starting the non-critical jobs whenever there 
is a drop so that no ups and downs occur in 
the resource profile. 
21
› Time Limited: The project must be finished by a 
certain time, using as few resources as possible. 
But it is time, not resource usage, that is critical 
22
Resource Histograms: 
• A bar chart showing the amount of time 
assigned to a resource for the time interval. 
• Resource availability is depicted as a line for 
comparison purposes. 
• Resources assigned more work than 
available hours are considered “over-allocated”. 
23
INTRODUCTION 
ERP is a business management software, 
usually a suite of integrated applications, that a 
company can use to store and manage data 
from every stage of business, including: 
Product planning, cost and development 
Manufacturing 
Marketing and sales 
Inventory management 
Shipping and payment 
24
ERP systems could be used in the construction 
industry for the following general purposes: 
1. To improve responsibilities in relation to 
customers. 
2. To strength supply chain partnerships. 
3. To enhance organizational flexibility. 
4. To improve decision-making capabilities. 
5. To reduce project completion time and cost. 
25
26
27
Without the proper resource allocation, one will 
pay the price for late job completions and cost 
overruns. 
The goal of resource leveling is to assign 
resources to project activities in a manner that 
will improve productivity and efficiency. 
During the last two decades, the construction 
industry has progressed in this trend of 
improving resource allocation it merely out of 
interest but as a means of survival in a more 
competitive world. 
28
29
30

More Related Content

What's hot

Types of Cost in Projects
Types of Cost in ProjectsTypes of Cost in Projects
Types of Cost in Projects
Ricardo Viana Vargas
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
IJMER
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
Rajat Nainwal
 
crashing of project
crashing of project crashing of project
crashing of project
Mir Zafarullah
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)
FahadHasan36
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
PedadaSaikumar
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
Crysanthus Raharjo, PMP
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Schedule of materials 2
Schedule of materials 2Schedule of materials 2
Schedule of materials 2
josephsalvatory
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
ProofHub
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
A Makwana
 
Project Organization and Structure
Project Organization and StructureProject Organization and Structure
Project Organization and Structureharoldtaylor1113
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
Sunayana Miglani
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Baker Khader Abdallah, PMP
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
MC Tubera
 
Project Management, Planning And Analysis Tools
Project Management, Planning And Analysis ToolsProject Management, Planning And Analysis Tools
Project Management, Planning And Analysis Tools
ahmad bassiouny
 

What's hot (20)

Types of Cost in Projects
Types of Cost in ProjectsTypes of Cost in Projects
Types of Cost in Projects
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
crashing of project
crashing of project crashing of project
crashing of project
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)
 
Budgeting
BudgetingBudgeting
Budgeting
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Schedule of materials 2
Schedule of materials 2Schedule of materials 2
Schedule of materials 2
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Project Organization and Structure
Project Organization and StructureProject Organization and Structure
Project Organization and Structure
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Project Management, Planning And Analysis Tools
Project Management, Planning And Analysis ToolsProject Management, Planning And Analysis Tools
Project Management, Planning And Analysis Tools
 

Similar to Resource planning and resource allocation

Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
Dr. Mahmoud Al-Naimi
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
Sagar Kaptan
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
TecnicoItca
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
Shree Swami atmanand saraswati inst. of technology, surat
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
LucasMogaka
 
Project time management
Project time managementProject time management
Project time management
Jack Pumpuni Frimpong-Manso
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
Snigdha Vashishth
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
TecnicoItca
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
dmdk12
 
Project typed
Project typedProject typed
Project typed
Rahul
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
TecnicoItca
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
KHUSHBU SHAH
 
Project Resource Management-Good one.ppt
Project Resource Management-Good one.pptProject Resource Management-Good one.ppt
Project Resource Management-Good one.ppt
Habibullah Qayumi
 
Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptx
Aditya Mane
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
TecnicoItca
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
THULASIMANOHARAN2
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
Saqib Raza
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
Saqib Raza
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
Saqib Raza
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
DejeneTsegaye6
 

Similar to Resource planning and resource allocation (20)

Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
Project time management
Project time managementProject time management
Project time management
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Project typed
Project typedProject typed
Project typed
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project Resource Management-Good one.ppt
Project Resource Management-Good one.pptProject Resource Management-Good one.ppt
Project Resource Management-Good one.ppt
 
Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptx
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
SPM Resource Management
SPM Resource ManagementSPM Resource Management
SPM Resource Management
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 

Recently uploaded

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 

Recently uploaded (20)

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 

Resource planning and resource allocation

  • 1. Presented by : VENUMADHAV.R.YEMUL Guided by : MILIND.D.DARADE Roll No : 5073 1
  • 2. Manpower, equipment, and materials are important project resources that require management attention. The basic objective of resource planning and resource allocation is to supply and support the field operations. The term resource allocation is used in the case where required resources are assigned such that available resources are not exceeded. 2
  • 3. Resources are the means of production needed to complete a project. Most project managers would consider the big three resources that will require your attention to be: • Material • Labor • Equipment 3
  • 4. A. LABOUR a. In the limited resource allocation case, there are two assumptions: (1) There are a fixed number of crews available to perform the work and (2) The project may be delayed as a result of the limitation of crews. The objective of the resource allocation problem is to determine when the project will be completed. 4
  • 5. b. In the unlimited resource leveling case, there are two assumptions: (1) There are an unlimited number of crews available to perform the work and (2) The project may not be delayed. The objective of the resource leveling problem is to determine how to limit the fluctuation in crews required on the job. 5
  • 6. B. MATERIALS Materials, for projects with sufficient on-site storage, are delivered to the site and assumed to be available to workers as needed. A material-related concern for sites that have sufficient space is that of optimizing the position of materials on the site so that they require the least travel time from the lay-down yard to the work-face. 6
  • 7. C. EQUIPMENTS There are various types of equipment used on construction sites. Some of this equipment should be considered in the project plan, some need not be included. Workers, and their companies, are typically required to provide the small tools needed to complete their specific features of work. There are some types of equipment, however, that can affect the overall sequence and duration of the project. 7
  • 8. Resource allocation is used to assign the available resources in an economic way. It is part of resource management. In project management, resource allocation is the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time. 8
  • 9. Resource planning cannot be accomplished without four essential resources necessary to accomplish the given scope of work: • MATERIAL • MAN POWER • MACHINARY • TIME 9
  • 10. Human resources for construction planning breaks down into three major categories as follows: • Home office personnel(Administrative Persons) • Construction personnel (field supervision and labor) • Construction subcontractors(Electrification, Plumbing, etc) 10
  • 11. The ideal form of a personnel loading curves is a trapezoid. The average personnel loading curve is a straight line. Actual practice loading curves take the shape of a bell curve 11
  • 12. 12
  • 13. The latter two result when the personnel loading curves occur earlier or later than planned on a project. Front loaded curve- the work started as early as possible. Normal loaded curve- the work started at normal time. Back loaded curve- the work started as late as possible. 13
  • 14. The "S" curve for the ideally loaded project has a gradual start and finish, which indicates smooth starting and finishing conditions. The forward loaded curve shows a rapid project start up and an even more gradual than normal phase out at the end. The backward-loaded project indicates a more relaxed start and a very steep finish slope on the "S" curve. 14
  • 15. 15
  • 16. 16
  • 17. Ensuring that the material resources for the project arrive on time involves these important planning areas: • Long-delivery equipment • Special materials and alloys • Common materials in short supply • Services and system requirements • Transportation systems 17
  • 18. Resource Limited: The project must be finished as soon as possible, but without exceeding some specific level of resource usage or some general resource constraint 18
  • 19. 1. When the schedule demands more workers per day than are available or if we have workers standing around without jobs, we have a problem. 2. When a new hire is trained, there is loss of productivity. So, if we can keep the trained people and reduce the number of new hires, we should be better off. 19
  • 20. . As we know, every project suffers from start-up problems of some sort. Superintendents and project managers are very busy trying to get everybody working in a productivity manner. Therefore, if we can start with a small crew and increase its size gradually, we will eliminate some of the start-up problems. . Most projects suffer from congestion around project completion time because of reduced work areas. Thus, if we can gradually reduce the crew size as we approach project completion, we can improve productivity by reducing congestion. 20
  • 21. The leveling procedure are as follows: • Scheduling all the critical jobs first. • Starting the non-critical jobs whenever there is a drop in scheduled man power upto the point where the peak is reached. • Starting the non-critical jobs whenever there is a drop so that no ups and downs occur in the resource profile. 21
  • 22. › Time Limited: The project must be finished by a certain time, using as few resources as possible. But it is time, not resource usage, that is critical 22
  • 23. Resource Histograms: • A bar chart showing the amount of time assigned to a resource for the time interval. • Resource availability is depicted as a line for comparison purposes. • Resources assigned more work than available hours are considered “over-allocated”. 23
  • 24. INTRODUCTION ERP is a business management software, usually a suite of integrated applications, that a company can use to store and manage data from every stage of business, including: Product planning, cost and development Manufacturing Marketing and sales Inventory management Shipping and payment 24
  • 25. ERP systems could be used in the construction industry for the following general purposes: 1. To improve responsibilities in relation to customers. 2. To strength supply chain partnerships. 3. To enhance organizational flexibility. 4. To improve decision-making capabilities. 5. To reduce project completion time and cost. 25
  • 26. 26
  • 27. 27
  • 28. Without the proper resource allocation, one will pay the price for late job completions and cost overruns. The goal of resource leveling is to assign resources to project activities in a manner that will improve productivity and efficiency. During the last two decades, the construction industry has progressed in this trend of improving resource allocation it merely out of interest but as a means of survival in a more competitive world. 28
  • 29. 29
  • 30. 30