1) The document discusses how changes to construction drawings can impact projects by increasing costs and causing schedule delays. It analyzes various factors that lead to changes in drawings like owners' requirements, geological conditions, and changes in builder needs. 2) Data was collected through site visits and interviews to identify common factors causing drawing changes. This data was analyzed using Minitab software which found owners' requirements to be the primary factor. 3) Changes to drawings can be minimized by using building information modeling software which allows quantities and costs to be calculated early, avoiding issues downstream. Proper coordination between all project stakeholders from the beginning is also important to limit unnecessary changes.