SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1787
Impact of Change of Construction Drawing on Project Works
Kajol Ashok Mohite1, Prof. Hemant H Salunkhe2
1Second Year M.E. Construction and Management D Y Patil Institute of Engineering and Technology, Ambi, Pune,
Maharashtra, India
2Professor Department of Civil Engineering Management D Y Patil Institute of Engineering and Technology, Ambi,
Pune, Maharashtra, India
---------------------------------------------------------------------------***---------------------------------------------------------------------------
ABSTRACT - Construction documents forms the core of any construction projects it includes contract documents,
plans, drawings etc. Construction drawings are the graphic representation of what is to be built. The construction
drawing should be precise and should be well coordinated in order to avoid uncertainty and confusion. If the
construction drawings are drawn with proper coordination then it will minimize the delays in the construction as the
changes in the drawing throughout the design and construction process can lead to budget and schedule overruns
and also the delivering of project on time.
The objectives of this paper is to determine the various factors leading to change in construction drawing and how this
changes can affect the completion of project in scheduled time and budget through various case studies. In order to determine
the main factor causing the change in drawing the data collected through various site visits were analyzed through Minitab
software. To determine how the impact of change in drawing can be minimize if the drawings are made in building
information modeling.
KEYWORDS: Construction drawing, Time, Budget.
I. INTRODUCTION
Construction drawings is the crucial part of the construction project, to complete the construction within stipulated time
period and budget it is necessary that the drawing should be precise and well coordinated.
Construction drawing is used as a communication tool between the client and the contractor. Construction drawing forms the
medium through which the client expresses his requirements to the contractor, and accordingly the execution of work is done.
The drawings provide both the graphic as well as written information, about the project. The detailed information such as
walls, doors, furniture and color of wall and so on, are all specified. In a construction project drawing consists of generally two
parts one is architectural and the other is engineering. The complete drawing set is used to find the cost of the project. There
are various ways in which construction drawing is prepared it can be prepared by hand, computer aided design or building
information modeling software. But it is more common for them to be prepared using computer aided design. This paper aims
at determining various factors contributing change in drawing during construction and how these changes can lead to increase
in cost and time of the project. And how the implementation of proper design software can lead to minimize these effects.
1.1 Objective of Project:
1) To determine how the use of improper Design documents in the project life cycle influence the client’s satisfaction with
duration, cost and quality and overrunning the duration and budget.
2) How the implementation of Proper design software can help to achieve targets of any construction projects.
II. LITERATURE REVIEW
Iliyas J. Suleiman, Valentine G.M Luvara: This paper determines the various factors causing change in drawing by collecting
data through questionnaire survey and then the analysis of collected data were done using SPSS 2.0. Based on the analysis
done it was found that the client’s factors and design consultant factors are the major factors causing change in design during
construction. To avoid this changes the measure taken by them were to ensure feasibility study before design, effective
involvement of everyone involved in construction activity during design stage, provision of proper time at the time of
designing and provision of clear brief by the client.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1788
M. Gokulkarthi, K.S Gowrishankar: The paper focuses on the impact of change order on construction project. Questionnaire
survey was done to collect the data and then analysis of collected data were done based on which it was concluded that the
owner’s requirement is the major source of change in plans.
Qihao, Weiming Shen, Joseph Neelamkavil, Russ Thomas: This paper determines the various factors causing delay in
project schedule and how it affects the completion of project in stipulated time period and budget. The primary cause of
change that were found was the owner’s requirements and designer’s errors and omissions. They have concluded that
innovative, effective and practical solution has to be developed that are adaptable by industry in order to resolve this changes.
Sepani Senarate and Jeevana Mayuran: Here author has done questionnaire survey was done to determine the reason for
poor documentation in Sri-lankan construction industry. Based on the survey they concluded that there is a gap between the
requirements and the document usage. To overcome this problem and to fill the gap suggestions related to the procedures,
awareness of the staff and allocation of resources were revealed through survey.
Luis F. Alarcon and Daniel A. Mardones: This paper determines the design defects and their corresponding impact on
the construction industry. The data were collected through interview with the various industry experts. The problem
which was identified were incomplete drawing, change in order, poor design quality and their impacts were rework,
delay in construction and increase in cost. To overcome this the author suggested that proper information must be given
to the designers before the start of drawing and identify the various documents involved in the construction project in
order to avoid rework and all types of waste in designers office and construction site.
III. METHODOLOGY AND DATA COLLECTION
A detailed literature review was done to identify the problems and then the data were collected through site visit which was
done to determine what are the various factors causing change in construction drawing. During the site visits an unstructured
interview was done with the engineers to find out the factors causing the change in drawing. The factors which were identified
were owner’s requirements, neglecting the geological condition at the time of planning, change in the requirement of builders,
change of drawing due to structural reason etc. And then analyses of collected data were done in Minitab software in order to
determine the main factor causing change in drawing. After the putting the values in the software the mean for each factor
were obtained and then ranking were done based on the mean value, giving first rank to the one having higher mean value and
last to one having least mean value.
IV. RESULT AND ANALYSIS
Analysis of collected data is shown in the table 1 which shows the various factors causing change in drawing and their
corresponding mean value and based on its mean value ranking is done.
Based on the analysis it can be seen that owner’s requirement is the main factor causing change in drawing followed by
geological condition of soil and so on.
Fig1. Output from Minitab
3210-1
1.2
1.0
0.8
0.6
0.4
0.2
0.0
Mean 1
StDev 1
N 3
Geological Condition
Frequency
Histogram of Geological Condition
Normal
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1789
Table1. Summary of various factors causing change of drawing during construction
V. CONCLUSION
From the above result obtained it can be said that there is always some or other factors causing change in drawing due to
which there is increase in cost and duration of project. The effect of this change can be minimized if the drawings are made in
building information modeling 360 instead of computer aided design. As building information modeling software provide an
option to calculate the quantity of various materials at the time of drawing only.
VI. REFERENCES:
1. Iliyas J. Suleiman, Valentine G.M Luvara ‘Factors Influencing change of Design of building Projects during Construction
Stage in Dar-es-salaam Tanzania’ International journal of Construction Engineering and Management 2016.
2. M. Gokulkarthi, K.S. Gowrishankar ‘A Study on Impacts of Change order in construction Projects’ International journal of
Science and Engineering Research 2015.
3. Qihao , Weiming Shen , Joseph Neelamkavil , Russ Thomas. ‘Change management in Construction Projects’ International
Conference on Information technology in construction Santigo,Chile.
4. Sepani Senaratne and Jeevana Mayuran. Developing Countries, 20(2), 81-95,2015. “Documentation management Based on
ISO for Construction Industries in Developing Countries”
5.Kolawale, A.R (RQS) and Olaoti A.S. “Record keeping and management in construction:Its Importance and Intructions”, The
Nigerian Academic forum Vol.7 No. I October 2004.
6. Mamoon Mousa Atout. ‘Delays Caused by Project Consultants and Designers inConstruction Project’ International Journal
of Structural and Civil Engineering Research2016.
7. Maria Koglovska , Daniela Mackova , Marcela Spisakova. ‘Survey of Construction Management Documentation usage in
Planning and construction of Building Project’ World multidisciplinary Civil Engineering- Architecture-Urban Planning
Symposium 2016.
8. Luis F. Alarcon and Daniel A. Mardones. “Improving the Design Construction Interface.
Sr. No
Factors causing change of
Drawing
Mean Rank
1 Structural Reason 0.5 3
2 Owner's Requirements 1.5 1
3 Geological condition 1 2
4 Incorrect drawing 0.5 2
5 Incorrect Survey 0.5 3
6 Financial Reason 0.5 3
7 Lack of Supervision 1 2
8 Change of Builder Scheme 0.5 3
9 Political Reason 0.5 3

More Related Content

What's hot

CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
Muhammad Daniyal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...
Alexander Decker
 
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIMIRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET Journal
 
Effective techniques in cost optimization of construction project an review
Effective techniques in cost optimization of construction project   an reviewEffective techniques in cost optimization of construction project   an review
Effective techniques in cost optimization of construction project an review
eSAT Journals
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET Journal
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
IRJET Journal
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET Journal
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
vivatechijri
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
UTHM
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
Hagi Sahib
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
civej
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
IJERA Editor
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
World-Academic Journal
 
20320140503023
2032014050302320320140503023
20320140503023
IAEME Publication
 
Construction project management
Construction project managementConstruction project management
Construction project management
saif hasan
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
IRJET Journal
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
Keshav Seewraz
 

What's hot (20)

CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...
 
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIMIRJET- Digital Engineering & Project Management for AEC Industry using BIM
IRJET- Digital Engineering & Project Management for AEC Industry using BIM
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Effective techniques in cost optimization of construction project an review
Effective techniques in cost optimization of construction project   an reviewEffective techniques in cost optimization of construction project   an review
Effective techniques in cost optimization of construction project an review
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
20320140503023
2032014050302320320140503023
20320140503023
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 

Similar to IRJET- Impact of Change of Construction Drawing on Project Works

IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET Journal
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET Journal
 
IRJET- Redevelopment of Structure with the Help of Building Information M...
IRJET-  	  Redevelopment of Structure with the Help of Building Information M...IRJET-  	  Redevelopment of Structure with the Help of Building Information M...
IRJET- Redevelopment of Structure with the Help of Building Information M...
IRJET Journal
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET Journal
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
IRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
IRJET Journal
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET Journal
 
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET Journal
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business Decisions
IRJET Journal
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
IRJET Journal
 
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET Journal
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
KarthikeyanP288430
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
IRJET -  	  Digital Engineering & Project Management for AEC Industry using BIMIRJET -  	  Digital Engineering & Project Management for AEC Industry using BIM
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
IRJET Journal
 

Similar to IRJET- Impact of Change of Construction Drawing on Project Works (20)

IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...IRJET- Building Information Modeling in AEC Industry with its Implementation ...
IRJET- Building Information Modeling in AEC Industry with its Implementation ...
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
IRJET- Redevelopment of Structure with the Help of Building Information M...
IRJET-  	  Redevelopment of Structure with the Help of Building Information M...IRJET-  	  Redevelopment of Structure with the Help of Building Information M...
IRJET- Redevelopment of Structure with the Help of Building Information M...
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...IRJET-  	  Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
IRJET- Testing Practical Applicability of 5-Dimensional BIM using a Pilot...
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business Decisions
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case Study
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
IRJET -  	  Digital Engineering & Project Management for AEC Industry using BIMIRJET -  	  Digital Engineering & Project Management for AEC Industry using BIM
IRJET - Digital Engineering & Project Management for AEC Industry using BIM
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 

Recently uploaded (20)

Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 

IRJET- Impact of Change of Construction Drawing on Project Works

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1787 Impact of Change of Construction Drawing on Project Works Kajol Ashok Mohite1, Prof. Hemant H Salunkhe2 1Second Year M.E. Construction and Management D Y Patil Institute of Engineering and Technology, Ambi, Pune, Maharashtra, India 2Professor Department of Civil Engineering Management D Y Patil Institute of Engineering and Technology, Ambi, Pune, Maharashtra, India ---------------------------------------------------------------------------***--------------------------------------------------------------------------- ABSTRACT - Construction documents forms the core of any construction projects it includes contract documents, plans, drawings etc. Construction drawings are the graphic representation of what is to be built. The construction drawing should be precise and should be well coordinated in order to avoid uncertainty and confusion. If the construction drawings are drawn with proper coordination then it will minimize the delays in the construction as the changes in the drawing throughout the design and construction process can lead to budget and schedule overruns and also the delivering of project on time. The objectives of this paper is to determine the various factors leading to change in construction drawing and how this changes can affect the completion of project in scheduled time and budget through various case studies. In order to determine the main factor causing the change in drawing the data collected through various site visits were analyzed through Minitab software. To determine how the impact of change in drawing can be minimize if the drawings are made in building information modeling. KEYWORDS: Construction drawing, Time, Budget. I. INTRODUCTION Construction drawings is the crucial part of the construction project, to complete the construction within stipulated time period and budget it is necessary that the drawing should be precise and well coordinated. Construction drawing is used as a communication tool between the client and the contractor. Construction drawing forms the medium through which the client expresses his requirements to the contractor, and accordingly the execution of work is done. The drawings provide both the graphic as well as written information, about the project. The detailed information such as walls, doors, furniture and color of wall and so on, are all specified. In a construction project drawing consists of generally two parts one is architectural and the other is engineering. The complete drawing set is used to find the cost of the project. There are various ways in which construction drawing is prepared it can be prepared by hand, computer aided design or building information modeling software. But it is more common for them to be prepared using computer aided design. This paper aims at determining various factors contributing change in drawing during construction and how these changes can lead to increase in cost and time of the project. And how the implementation of proper design software can lead to minimize these effects. 1.1 Objective of Project: 1) To determine how the use of improper Design documents in the project life cycle influence the client’s satisfaction with duration, cost and quality and overrunning the duration and budget. 2) How the implementation of Proper design software can help to achieve targets of any construction projects. II. LITERATURE REVIEW Iliyas J. Suleiman, Valentine G.M Luvara: This paper determines the various factors causing change in drawing by collecting data through questionnaire survey and then the analysis of collected data were done using SPSS 2.0. Based on the analysis done it was found that the client’s factors and design consultant factors are the major factors causing change in design during construction. To avoid this changes the measure taken by them were to ensure feasibility study before design, effective involvement of everyone involved in construction activity during design stage, provision of proper time at the time of designing and provision of clear brief by the client.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1788 M. Gokulkarthi, K.S Gowrishankar: The paper focuses on the impact of change order on construction project. Questionnaire survey was done to collect the data and then analysis of collected data were done based on which it was concluded that the owner’s requirement is the major source of change in plans. Qihao, Weiming Shen, Joseph Neelamkavil, Russ Thomas: This paper determines the various factors causing delay in project schedule and how it affects the completion of project in stipulated time period and budget. The primary cause of change that were found was the owner’s requirements and designer’s errors and omissions. They have concluded that innovative, effective and practical solution has to be developed that are adaptable by industry in order to resolve this changes. Sepani Senarate and Jeevana Mayuran: Here author has done questionnaire survey was done to determine the reason for poor documentation in Sri-lankan construction industry. Based on the survey they concluded that there is a gap between the requirements and the document usage. To overcome this problem and to fill the gap suggestions related to the procedures, awareness of the staff and allocation of resources were revealed through survey. Luis F. Alarcon and Daniel A. Mardones: This paper determines the design defects and their corresponding impact on the construction industry. The data were collected through interview with the various industry experts. The problem which was identified were incomplete drawing, change in order, poor design quality and their impacts were rework, delay in construction and increase in cost. To overcome this the author suggested that proper information must be given to the designers before the start of drawing and identify the various documents involved in the construction project in order to avoid rework and all types of waste in designers office and construction site. III. METHODOLOGY AND DATA COLLECTION A detailed literature review was done to identify the problems and then the data were collected through site visit which was done to determine what are the various factors causing change in construction drawing. During the site visits an unstructured interview was done with the engineers to find out the factors causing the change in drawing. The factors which were identified were owner’s requirements, neglecting the geological condition at the time of planning, change in the requirement of builders, change of drawing due to structural reason etc. And then analyses of collected data were done in Minitab software in order to determine the main factor causing change in drawing. After the putting the values in the software the mean for each factor were obtained and then ranking were done based on the mean value, giving first rank to the one having higher mean value and last to one having least mean value. IV. RESULT AND ANALYSIS Analysis of collected data is shown in the table 1 which shows the various factors causing change in drawing and their corresponding mean value and based on its mean value ranking is done. Based on the analysis it can be seen that owner’s requirement is the main factor causing change in drawing followed by geological condition of soil and so on. Fig1. Output from Minitab 3210-1 1.2 1.0 0.8 0.6 0.4 0.2 0.0 Mean 1 StDev 1 N 3 Geological Condition Frequency Histogram of Geological Condition Normal
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1789 Table1. Summary of various factors causing change of drawing during construction V. CONCLUSION From the above result obtained it can be said that there is always some or other factors causing change in drawing due to which there is increase in cost and duration of project. The effect of this change can be minimized if the drawings are made in building information modeling 360 instead of computer aided design. As building information modeling software provide an option to calculate the quantity of various materials at the time of drawing only. VI. REFERENCES: 1. Iliyas J. Suleiman, Valentine G.M Luvara ‘Factors Influencing change of Design of building Projects during Construction Stage in Dar-es-salaam Tanzania’ International journal of Construction Engineering and Management 2016. 2. M. Gokulkarthi, K.S. Gowrishankar ‘A Study on Impacts of Change order in construction Projects’ International journal of Science and Engineering Research 2015. 3. Qihao , Weiming Shen , Joseph Neelamkavil , Russ Thomas. ‘Change management in Construction Projects’ International Conference on Information technology in construction Santigo,Chile. 4. Sepani Senaratne and Jeevana Mayuran. Developing Countries, 20(2), 81-95,2015. “Documentation management Based on ISO for Construction Industries in Developing Countries” 5.Kolawale, A.R (RQS) and Olaoti A.S. “Record keeping and management in construction:Its Importance and Intructions”, The Nigerian Academic forum Vol.7 No. I October 2004. 6. Mamoon Mousa Atout. ‘Delays Caused by Project Consultants and Designers inConstruction Project’ International Journal of Structural and Civil Engineering Research2016. 7. Maria Koglovska , Daniela Mackova , Marcela Spisakova. ‘Survey of Construction Management Documentation usage in Planning and construction of Building Project’ World multidisciplinary Civil Engineering- Architecture-Urban Planning Symposium 2016. 8. Luis F. Alarcon and Daniel A. Mardones. “Improving the Design Construction Interface. Sr. No Factors causing change of Drawing Mean Rank 1 Structural Reason 0.5 3 2 Owner's Requirements 1.5 1 3 Geological condition 1 2 4 Incorrect drawing 0.5 2 5 Incorrect Survey 0.5 3 6 Financial Reason 0.5 3 7 Lack of Supervision 1 2 8 Change of Builder Scheme 0.5 3 9 Political Reason 0.5 3