Time delay and cost escalation
in construction works
Ankit Jaiswal, Dennies Thomas, Rahul Kushwaha, Ravikant Mahato
(Civil Department, Viva Institute of Technology, India)
Abstract : The objective of the present study was to measure the effects of delay in construction projects like cost-
overrun, time-overrun, litigation and project abandonment. Data on the study variables has been collected
through a structured questionnaire. Statistical tool One-Way ANOVA has been applied for data analysis and
inference. It is found that delay in construction projects significantly lead to cost overrun, time overrun, litigation
and project abandonment. The findings of the study also provide significant insights to the construction industry
so that they may formulate strategies in order to avoid delay and its consequences. Moreover, the
recommendations and limitations are discussed in the conclusion part of the study.
Keywords - Construction Projects, Delay, Cost overrun, Time overrun, Litigation, Abandonment.
I. Introduction
The Delay in construction projects is a major problem facing the whole world. Completion of construction projects
contributes to global economic development by the effective use of cost and time as a whole, which solely results
in saving the cost for the country. Factors which cause delay in the construction projects also have some effects on
the overall project to some extend. When there is delay in construction projects, the scheduled time for the
completion of the project is extended. This results in cost overrun. Main reasons for cost overrun in the
construction projects include the delays in the delivery of materials to the project sites, revision and approving of
design documents, delay in getting approval, delay in sub-contractor work and the conflicts in sub-contractor
schedule, changes made by the owners, contractor’s inadequacy during work and poor planning are the main
causes of cost overrun.
II. METHODOLOGY
For this research, a questionnaire survey approach has been adopted to find the impact of various attributes on
delay in the Indian construction sector drawing from various international researchers mentioned above. A survey
of construction professionals representing various stakeholders involved in construction projects in India was
conducted. Heterogeneity of respondents is an important criteria in capturing the impact of various attributes on
construction delay.
1. Assessment
2. Determining factors & Preparing Questionnaire
3. Collecting Response
4. Analysis
1. Assessment
Initial stage in this project is to find the proper factors affecting the delay in the construction industry. Later it was
acknowledged that the issues can be arranged according to various factors responsible for causing such issues. The
factors can be related to the client, contractor or either parties. In India, most of the issues are related to poor
quality control issues. This review helps to understand the factors and the practical approach to those factors.
VIVA-Tech International Journal for Research and Innovation Volume 1, Issue 4 (2021)
ISSN(Online): 2581-7280 Article No. X
PP XX-XX
VIVA Institute of Technology
9th National Conference on Role of Engineers in Nation Building – 2021 (NCRENB-2021)
2
www.viva-technology.org/New/IJRI
2. Determining factors & Preparing Questionnaire
The thirty three most crucial factors were adopted from the literature. As the factors were identified from the
literature, a practical approach was needed to arrange the factors according to their impact. The response of people
associated with the construction industry plays an important role in determining the importance of the factors.
Hence a questionnaire survey was prepared, with all the factors listed. A total of one fifty responses were recorded.
3. Collecting Response
The responses were compiled and average of responses were calculated. For better explanation a horizontal graph
was created with the factors on the X-axis and the importance of factors ranging from 0 to 5 on the Y-axis. Where 0
indicates low impact and indicates high impact.
4. Analysis
Once the data was collected, it has to be further verified that the probability of the people answering the survey was
true. Hence the Analysis Of Variance (ANOVA) is adopted for ranking the factors and determining the most
severe impact.
The delay factors were summarized into three major categories:
● Production Elements (PE) includes: Labor, Materials and Equipment related factors.
● Internal Environment (IE) includes: Consultant, Contractor and Owner related factors.
● External Environment (EE) includes: Weather, Government Regulations and Other reasons.
A one way analysis of variance ANOVA is to be conducted among the means of responses from the three groups to
check for any significant differences among the groups perceptions regarding the importance of the various delay
causes. The mean values under the three groups, F statistics, and the P values at which hypothesis of equality of
mean values across different groups could be rejected is to be calculated.
III. Figures and TABLES
Factors considered from Literature
VIVA-Tech International Journal for Research and Innovation Volume 1, Issue 4 (2021)
ISSN(Online): 2581-7280 Article No. X
PP XX-XX
VIVA Institute of Technology
9th National Conference on Role of Engineers in Nation Building – 2021 (NCRENB-2021)
3
www.viva-technology.org/New/IJRI
Factors categorized
IV. Conclusion
The stated objective of this paper is to identify the causes of delay that produce the greatest effects and
the extent to which these effects can be controlled in the private construction industry. A literature review was
conducted to identify the causes of delay stipulated in the literature. The importance index of each cause is
calculated as an average of the frequency indices of each cause. Total 50 causes of delay were identified through
research. The identified causes are combined into three categories. The following points can be recommended by
all parties to minimize and control delays in construction projects:
Consultants should look to the following points:
 Should not be late in reviewing and approving the given documents and drawings.
Contractors should consider the following factors:
 Should try to increase the productivity of labor as far as possible and take efforts to motivate it.
 Financial and cash flow problems should be managed by the contractor with proper financial planning
beforehand.
 Efficient coordination between contractors and subcontractors is a must.
Owners should give special attention to the following factors:
 Check for resources and capabilities, before awarding the contract to the lowest bidder.
 Efficient cash flow to contractors on part of the owner's responsibility.
References
[1 ]Doloi et al(2011), “Analysing factors affecting delays in Indian construction projects” International Journal of Project Management 30
(2012).
[2] K.C. Iyer, K.N. Jha(2005), “Factors affecting cost performance: evidence from Indian construction projects” International Journal of
Project Management 23 (2005).
[3] S. Shanmugapriya1, Dr. K. Subramanian, “Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction
Projects” Volume 3, Issue 10 October 2013.
[4] Ahmed Senouci ( 2016 ), “Time Delay and Cost Overrun in Qatari Public Construction Projects” Creative Construction Conference 2016,
CCC 2016, 25-28 June 2016.
[5] Nabil Al-Hazim, Zaydoun Abu Salem, Hesham Ahmad, “Delay and Cost Overrun in Infrastructure Project in Jordan” 7 th International
Conference on Engineering, Project , and Production Management.
VIVA-Tech International Journal for Research and Innovation Volume 1, Issue 4 (2021)
ISSN(Online): 2581-7280 Article No. X
PP XX-XX
VIVA Institute of Technology
9th National Conference on Role of Engineers in Nation Building – 2021 (NCRENB-2021)
4
www.viva-technology.org/New/IJRI
[6] Abdulelah Aljohani, Dominic Ahiaga-Dagbui, and David Moore (2017), “Construction Projects Cost Overrun” International Journal of
Innovation, Management and Technology, Vol. 8, No. 2, April 2017.
[7] N. Hamzaha , M.A. Khoirya , I. Arshada , N. M. Tawilb, “Cause of Construction Delay - Theoretical Framework” The 2nd International
Building Control Conference 2011.
[8] Michal Ghuszak (2015), “Construction Delays in clients opinion - multivariate statistical analysis” Creative Construction Conference 2015.
[9] Vaibhav Y. Katre1, Dr. D.M. Ghaitidak, “Elements of Cost and Schedule Overrun in Construction Projects ” Volume 12, Issue 7(July 2016).
[10] Abdussalam Shibani, Kumar Arumugam “Avoiding Cost Overruns in Construction Projects in India” Management Studies,August
2015,Vol.3.
[11] T. Subramani1, M.Kannan, P.Vinoth, K.mohan Doss, S.Priyanka, March - April 2018,“Cost Escalation and Delays in Construction
Industry Using SPSS ” Volume 7.
[12] Swapnil P Wanjari and Gaurav Dobariya, “Identifying factors causing cost overrun of the construction projects in India” Vol. 41, No. 6,
June 2016.
[13] Kodwo Amoa-Abban Seth, “Cost overruns in Building Construction Projects: A Case Study of a Government of Ghana Project in Accra”,
Vol.4, No.24, 2014.
[14] SAVITA SHARMA1 & PRADEEP K. GOYAL, May 2014, “Cost Overrun Factors and Project Cost Risk Assessment in Construction
Industry”, Vol. 3, Issue 3.
[15] Jafri S. Jongo, Dennis N. G. A. K. Tesha, Raymond Kasonga, Justine J. Teyanga1, Kenan S. Lyimo, “Mitigation Measures in Dealing with
Delays and Cost Overrun in Public Building Projects in Dar-E-Salaam”, Tanzania.

More Related Content

What's hot

IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET Journal
 
Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...
Alexander Decker
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
IJLT EMAS
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET Journal
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET Journal
 
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
A Makwana
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
Alexander Decker
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
Dr. Amarjeet Singh
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
Rifan Fhazi
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
A Makwana
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET Journal
 
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET Journal
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
IRJET Journal
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
theijes
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
Oyeniyi Samuel
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET Journal
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approach
Madhumanti Samaddar
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in Iraq
Dr. Amarjeet Singh
 

What's hot (20)

IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
 
Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...IRJET-  	  A case Study on Risk Identification and Risk Assessment in Real Es...
IRJET- A case Study on Risk Identification and Risk Assessment in Real Es...
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approach
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in Iraq
 

Similar to Time delay and cost escalation in construction works

Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
IAEME Publication
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
saeedahmed433704
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
IRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
D012261521
D012261521D012261521
D012261521
IOSR Journals
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
IRJET Journal
 
20320140503023
2032014050302320320140503023
20320140503023
IAEME Publication
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
IRJET Journal
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
IAEME Publication
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
IAEME Publication
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET Journal
 
An empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayAn empirical study on key determinants of construction Delay
An empirical study on key determinants of construction Delay
IRJET Journal
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
IRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
ijtsrd
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
eSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
eSAT Journals
 
Ijciet 10 01_054
Ijciet 10 01_054Ijciet 10 01_054
Ijciet 10 01_054
IAEME Publication
 

Similar to Time delay and cost escalation in construction works (20)

Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
D012261521
D012261521D012261521
D012261521
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
20320140503023
2032014050302320320140503023
20320140503023
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
 
An empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayAn empirical study on key determinants of construction Delay
An empirical study on key determinants of construction Delay
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Ijciet 10 01_054
Ijciet 10 01_054Ijciet 10 01_054
Ijciet 10 01_054
 

More from vivatechijri

Understanding the Impact and Challenges of Corona Crisis on Education Sector...
Understanding the Impact and Challenges of Corona Crisis on  Education Sector...Understanding the Impact and Challenges of Corona Crisis on  Education Sector...
Understanding the Impact and Challenges of Corona Crisis on Education Sector...
vivatechijri
 
LEADERSHIP ONLY CAN LEAD THE ORGANIZATION TOWARDS IMPROVEMENT AND DEVELOPMENT
LEADERSHIP ONLY CAN LEAD THE ORGANIZATION  TOWARDS IMPROVEMENT AND DEVELOPMENT  LEADERSHIP ONLY CAN LEAD THE ORGANIZATION  TOWARDS IMPROVEMENT AND DEVELOPMENT
LEADERSHIP ONLY CAN LEAD THE ORGANIZATION TOWARDS IMPROVEMENT AND DEVELOPMENT
vivatechijri
 
A study on solving Assignment Problem
A study on solving Assignment ProblemA study on solving Assignment Problem
A study on solving Assignment Problem
vivatechijri
 
Structural and Morphological Studies of Nano Composite Polymer Gel Electroly...
Structural and Morphological Studies of Nano Composite  Polymer Gel Electroly...Structural and Morphological Studies of Nano Composite  Polymer Gel Electroly...
Structural and Morphological Studies of Nano Composite Polymer Gel Electroly...
vivatechijri
 
Theoretical study of two dimensional Nano sheet for gas sensing application
Theoretical study of two dimensional Nano sheet for gas sensing  applicationTheoretical study of two dimensional Nano sheet for gas sensing  application
Theoretical study of two dimensional Nano sheet for gas sensing application
vivatechijri
 
METHODS FOR DETECTION OF COMMON ADULTERANTS IN FOOD
METHODS FOR DETECTION OF COMMON  ADULTERANTS IN FOODMETHODS FOR DETECTION OF COMMON  ADULTERANTS IN FOOD
METHODS FOR DETECTION OF COMMON ADULTERANTS IN FOOD
vivatechijri
 
The Business Development Ethics
The Business Development EthicsThe Business Development Ethics
The Business Development Ethics
vivatechijri
 
Digital Wellbeing
Digital WellbeingDigital Wellbeing
Digital Wellbeing
vivatechijri
 
An Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGE
An Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGEAn Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGE
An Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGE
vivatechijri
 
Enhancing The Capability of Chatbots
Enhancing The Capability of ChatbotsEnhancing The Capability of Chatbots
Enhancing The Capability of Chatbots
vivatechijri
 
Smart Glasses Technology
Smart Glasses TechnologySmart Glasses Technology
Smart Glasses Technology
vivatechijri
 
Future Applications of Smart Iot Devices
Future Applications of Smart Iot DevicesFuture Applications of Smart Iot Devices
Future Applications of Smart Iot Devices
vivatechijri
 
Cross Platform Development Using Flutter
Cross Platform Development Using FlutterCross Platform Development Using Flutter
Cross Platform Development Using Flutter
vivatechijri
 
3D INTERNET
3D INTERNET3D INTERNET
3D INTERNET
vivatechijri
 
Recommender Systems
Recommender SystemsRecommender Systems
Recommender Systems
vivatechijri
 
Light Fidelity(LiFi)- Wireless Optical Networking Technology
Light Fidelity(LiFi)- Wireless Optical Networking TechnologyLight Fidelity(LiFi)- Wireless Optical Networking Technology
Light Fidelity(LiFi)- Wireless Optical Networking Technology
vivatechijri
 
Social media platform and Our right to privacy
Social media platform and Our right to privacySocial media platform and Our right to privacy
Social media platform and Our right to privacy
vivatechijri
 
THE USABILITY METRICS FOR USER EXPERIENCE
THE USABILITY METRICS FOR USER EXPERIENCETHE USABILITY METRICS FOR USER EXPERIENCE
THE USABILITY METRICS FOR USER EXPERIENCE
vivatechijri
 
Google File System
Google File SystemGoogle File System
Google File System
vivatechijri
 
A Study of Tokenization of Real Estate Using Blockchain Technology
A Study of Tokenization of Real Estate Using Blockchain TechnologyA Study of Tokenization of Real Estate Using Blockchain Technology
A Study of Tokenization of Real Estate Using Blockchain Technology
vivatechijri
 

More from vivatechijri (20)

Understanding the Impact and Challenges of Corona Crisis on Education Sector...
Understanding the Impact and Challenges of Corona Crisis on  Education Sector...Understanding the Impact and Challenges of Corona Crisis on  Education Sector...
Understanding the Impact and Challenges of Corona Crisis on Education Sector...
 
LEADERSHIP ONLY CAN LEAD THE ORGANIZATION TOWARDS IMPROVEMENT AND DEVELOPMENT
LEADERSHIP ONLY CAN LEAD THE ORGANIZATION  TOWARDS IMPROVEMENT AND DEVELOPMENT  LEADERSHIP ONLY CAN LEAD THE ORGANIZATION  TOWARDS IMPROVEMENT AND DEVELOPMENT
LEADERSHIP ONLY CAN LEAD THE ORGANIZATION TOWARDS IMPROVEMENT AND DEVELOPMENT
 
A study on solving Assignment Problem
A study on solving Assignment ProblemA study on solving Assignment Problem
A study on solving Assignment Problem
 
Structural and Morphological Studies of Nano Composite Polymer Gel Electroly...
Structural and Morphological Studies of Nano Composite  Polymer Gel Electroly...Structural and Morphological Studies of Nano Composite  Polymer Gel Electroly...
Structural and Morphological Studies of Nano Composite Polymer Gel Electroly...
 
Theoretical study of two dimensional Nano sheet for gas sensing application
Theoretical study of two dimensional Nano sheet for gas sensing  applicationTheoretical study of two dimensional Nano sheet for gas sensing  application
Theoretical study of two dimensional Nano sheet for gas sensing application
 
METHODS FOR DETECTION OF COMMON ADULTERANTS IN FOOD
METHODS FOR DETECTION OF COMMON  ADULTERANTS IN FOODMETHODS FOR DETECTION OF COMMON  ADULTERANTS IN FOOD
METHODS FOR DETECTION OF COMMON ADULTERANTS IN FOOD
 
The Business Development Ethics
The Business Development EthicsThe Business Development Ethics
The Business Development Ethics
 
Digital Wellbeing
Digital WellbeingDigital Wellbeing
Digital Wellbeing
 
An Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGE
An Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGEAn Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGE
An Alternative to Hard Drives in the Coming Future:DNA-BASED DATA STORAGE
 
Enhancing The Capability of Chatbots
Enhancing The Capability of ChatbotsEnhancing The Capability of Chatbots
Enhancing The Capability of Chatbots
 
Smart Glasses Technology
Smart Glasses TechnologySmart Glasses Technology
Smart Glasses Technology
 
Future Applications of Smart Iot Devices
Future Applications of Smart Iot DevicesFuture Applications of Smart Iot Devices
Future Applications of Smart Iot Devices
 
Cross Platform Development Using Flutter
Cross Platform Development Using FlutterCross Platform Development Using Flutter
Cross Platform Development Using Flutter
 
3D INTERNET
3D INTERNET3D INTERNET
3D INTERNET
 
Recommender Systems
Recommender SystemsRecommender Systems
Recommender Systems
 
Light Fidelity(LiFi)- Wireless Optical Networking Technology
Light Fidelity(LiFi)- Wireless Optical Networking TechnologyLight Fidelity(LiFi)- Wireless Optical Networking Technology
Light Fidelity(LiFi)- Wireless Optical Networking Technology
 
Social media platform and Our right to privacy
Social media platform and Our right to privacySocial media platform and Our right to privacy
Social media platform and Our right to privacy
 
THE USABILITY METRICS FOR USER EXPERIENCE
THE USABILITY METRICS FOR USER EXPERIENCETHE USABILITY METRICS FOR USER EXPERIENCE
THE USABILITY METRICS FOR USER EXPERIENCE
 
Google File System
Google File SystemGoogle File System
Google File System
 
A Study of Tokenization of Real Estate Using Blockchain Technology
A Study of Tokenization of Real Estate Using Blockchain TechnologyA Study of Tokenization of Real Estate Using Blockchain Technology
A Study of Tokenization of Real Estate Using Blockchain Technology
 

Recently uploaded

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 

Recently uploaded (20)

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 

Time delay and cost escalation in construction works

  • 1. VIVA-Tech International Journal for Research and Innovation Volume 1, Issue 4 (2021) ISSN(Online): 2581-7280 Article No. X PP XX-XX VIVA Institute of Technology 9th National Conference on Role of Engineers in Nation Building – 2021 (NCRENB-2021) 1 www.viva-technology.org/New/IJRI Time delay and cost escalation in construction works Ankit Jaiswal, Dennies Thomas, Rahul Kushwaha, Ravikant Mahato (Civil Department, Viva Institute of Technology, India) Abstract : The objective of the present study was to measure the effects of delay in construction projects like cost- overrun, time-overrun, litigation and project abandonment. Data on the study variables has been collected through a structured questionnaire. Statistical tool One-Way ANOVA has been applied for data analysis and inference. It is found that delay in construction projects significantly lead to cost overrun, time overrun, litigation and project abandonment. The findings of the study also provide significant insights to the construction industry so that they may formulate strategies in order to avoid delay and its consequences. Moreover, the recommendations and limitations are discussed in the conclusion part of the study. Keywords - Construction Projects, Delay, Cost overrun, Time overrun, Litigation, Abandonment. I. Introduction The Delay in construction projects is a major problem facing the whole world. Completion of construction projects contributes to global economic development by the effective use of cost and time as a whole, which solely results in saving the cost for the country. Factors which cause delay in the construction projects also have some effects on the overall project to some extend. When there is delay in construction projects, the scheduled time for the completion of the project is extended. This results in cost overrun. Main reasons for cost overrun in the construction projects include the delays in the delivery of materials to the project sites, revision and approving of design documents, delay in getting approval, delay in sub-contractor work and the conflicts in sub-contractor schedule, changes made by the owners, contractor’s inadequacy during work and poor planning are the main causes of cost overrun. II. METHODOLOGY For this research, a questionnaire survey approach has been adopted to find the impact of various attributes on delay in the Indian construction sector drawing from various international researchers mentioned above. A survey of construction professionals representing various stakeholders involved in construction projects in India was conducted. Heterogeneity of respondents is an important criteria in capturing the impact of various attributes on construction delay. 1. Assessment 2. Determining factors & Preparing Questionnaire 3. Collecting Response 4. Analysis 1. Assessment Initial stage in this project is to find the proper factors affecting the delay in the construction industry. Later it was acknowledged that the issues can be arranged according to various factors responsible for causing such issues. The factors can be related to the client, contractor or either parties. In India, most of the issues are related to poor quality control issues. This review helps to understand the factors and the practical approach to those factors.
  • 2. VIVA-Tech International Journal for Research and Innovation Volume 1, Issue 4 (2021) ISSN(Online): 2581-7280 Article No. X PP XX-XX VIVA Institute of Technology 9th National Conference on Role of Engineers in Nation Building – 2021 (NCRENB-2021) 2 www.viva-technology.org/New/IJRI 2. Determining factors & Preparing Questionnaire The thirty three most crucial factors were adopted from the literature. As the factors were identified from the literature, a practical approach was needed to arrange the factors according to their impact. The response of people associated with the construction industry plays an important role in determining the importance of the factors. Hence a questionnaire survey was prepared, with all the factors listed. A total of one fifty responses were recorded. 3. Collecting Response The responses were compiled and average of responses were calculated. For better explanation a horizontal graph was created with the factors on the X-axis and the importance of factors ranging from 0 to 5 on the Y-axis. Where 0 indicates low impact and indicates high impact. 4. Analysis Once the data was collected, it has to be further verified that the probability of the people answering the survey was true. Hence the Analysis Of Variance (ANOVA) is adopted for ranking the factors and determining the most severe impact. The delay factors were summarized into three major categories: ● Production Elements (PE) includes: Labor, Materials and Equipment related factors. ● Internal Environment (IE) includes: Consultant, Contractor and Owner related factors. ● External Environment (EE) includes: Weather, Government Regulations and Other reasons. A one way analysis of variance ANOVA is to be conducted among the means of responses from the three groups to check for any significant differences among the groups perceptions regarding the importance of the various delay causes. The mean values under the three groups, F statistics, and the P values at which hypothesis of equality of mean values across different groups could be rejected is to be calculated. III. Figures and TABLES Factors considered from Literature
  • 3. VIVA-Tech International Journal for Research and Innovation Volume 1, Issue 4 (2021) ISSN(Online): 2581-7280 Article No. X PP XX-XX VIVA Institute of Technology 9th National Conference on Role of Engineers in Nation Building – 2021 (NCRENB-2021) 3 www.viva-technology.org/New/IJRI Factors categorized IV. Conclusion The stated objective of this paper is to identify the causes of delay that produce the greatest effects and the extent to which these effects can be controlled in the private construction industry. A literature review was conducted to identify the causes of delay stipulated in the literature. The importance index of each cause is calculated as an average of the frequency indices of each cause. Total 50 causes of delay were identified through research. The identified causes are combined into three categories. The following points can be recommended by all parties to minimize and control delays in construction projects: Consultants should look to the following points:  Should not be late in reviewing and approving the given documents and drawings. Contractors should consider the following factors:  Should try to increase the productivity of labor as far as possible and take efforts to motivate it.  Financial and cash flow problems should be managed by the contractor with proper financial planning beforehand.  Efficient coordination between contractors and subcontractors is a must. Owners should give special attention to the following factors:  Check for resources and capabilities, before awarding the contract to the lowest bidder.  Efficient cash flow to contractors on part of the owner's responsibility. References [1 ]Doloi et al(2011), “Analysing factors affecting delays in Indian construction projects” International Journal of Project Management 30 (2012). [2] K.C. Iyer, K.N. Jha(2005), “Factors affecting cost performance: evidence from Indian construction projects” International Journal of Project Management 23 (2005). [3] S. Shanmugapriya1, Dr. K. Subramanian, “Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects” Volume 3, Issue 10 October 2013. [4] Ahmed Senouci ( 2016 ), “Time Delay and Cost Overrun in Qatari Public Construction Projects” Creative Construction Conference 2016, CCC 2016, 25-28 June 2016. [5] Nabil Al-Hazim, Zaydoun Abu Salem, Hesham Ahmad, “Delay and Cost Overrun in Infrastructure Project in Jordan” 7 th International Conference on Engineering, Project , and Production Management.
  • 4. VIVA-Tech International Journal for Research and Innovation Volume 1, Issue 4 (2021) ISSN(Online): 2581-7280 Article No. X PP XX-XX VIVA Institute of Technology 9th National Conference on Role of Engineers in Nation Building – 2021 (NCRENB-2021) 4 www.viva-technology.org/New/IJRI [6] Abdulelah Aljohani, Dominic Ahiaga-Dagbui, and David Moore (2017), “Construction Projects Cost Overrun” International Journal of Innovation, Management and Technology, Vol. 8, No. 2, April 2017. [7] N. Hamzaha , M.A. Khoirya , I. Arshada , N. M. Tawilb, “Cause of Construction Delay - Theoretical Framework” The 2nd International Building Control Conference 2011. [8] Michal Ghuszak (2015), “Construction Delays in clients opinion - multivariate statistical analysis” Creative Construction Conference 2015. [9] Vaibhav Y. Katre1, Dr. D.M. Ghaitidak, “Elements of Cost and Schedule Overrun in Construction Projects ” Volume 12, Issue 7(July 2016). [10] Abdussalam Shibani, Kumar Arumugam “Avoiding Cost Overruns in Construction Projects in India” Management Studies,August 2015,Vol.3. [11] T. Subramani1, M.Kannan, P.Vinoth, K.mohan Doss, S.Priyanka, March - April 2018,“Cost Escalation and Delays in Construction Industry Using SPSS ” Volume 7. [12] Swapnil P Wanjari and Gaurav Dobariya, “Identifying factors causing cost overrun of the construction projects in India” Vol. 41, No. 6, June 2016. [13] Kodwo Amoa-Abban Seth, “Cost overruns in Building Construction Projects: A Case Study of a Government of Ghana Project in Accra”, Vol.4, No.24, 2014. [14] SAVITA SHARMA1 & PRADEEP K. GOYAL, May 2014, “Cost Overrun Factors and Project Cost Risk Assessment in Construction Industry”, Vol. 3, Issue 3. [15] Jafri S. Jongo, Dennis N. G. A. K. Tesha, Raymond Kasonga, Justine J. Teyanga1, Kenan S. Lyimo, “Mitigation Measures in Dealing with Delays and Cost Overrun in Public Building Projects in Dar-E-Salaam”, Tanzania.