SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1154
A STUDY ON FACTORS AFFECTING ESTIMATION OF CONSTRUCTION
PROJECT
Dr. S Kanchana1, Ms. S Janani2
1Head of the Department, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India,
2PG Student, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India
----------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Construction industry is considered as a very
important sector for development in all over the world and
the construction cost estimation is the most important
element in it. Realistic estimation of construction cost is
essential for both successful planning and completion of
every construction project. The key factor for a successful
project is the accurate cost estimation at its early stage. It is
very difficult to quickly and accuratelyestimateconstruction
costs at the planning stage itself when project information is
limited. This study aim at caring out to identify the factors
affecting construction cost estimation. The factors were
identified based on questionnaire survey. Questionnaires
were given to 64 experts in theconstructionindustryaimsto
determine the importance of construction cost estimation
and to determine the score of each factor. Statistical analysis
will be carried out on the feedback of the respondents of the
survey. RII value of the factors to be found using Microsoft
Excel. The mean score of each factor to be determined and
the p-value was calculated using the SPSS software. The
significance of each factor used in the questionnaire to be
determined. The important factors were identifiedusingthe
mean score and their p-value.
Key Words: Cost estimation, Questionnairepreparation,
SPSS
1. INTRODUCTION
Several factors affect the accuracy of building project’s cost
estimation which must be considered at the early stage of
the estimation process.Some factorscanrapidlyincreasethe
estimated costs and the possibility of contractual strifes
between the various parties involved. There are other
factors that can help the estimator to decrease the
unnecessary cost of an item and thus lead to successful
tendering in a very competitive market. Therefore, for
accurate estimating detailed study of the biding documents
and the environmental situation are required. In order to
arrive to the most accurate estimate of the probable cost
consistent with the bidding time available and the accuracy
and completeness of the information submitted, it also
requires careful analysis of data of all projects.
Realistic estimation of construction cost is essential forboth
successful planning and completion of all construction
project. Also due to uncertain conditions, validcostforecasts
become an significant source of information for decision
making by all construction parties. Accurate cost estimation
at the early stage of a construction project is a significant
factor in a successful project. But it is very difficulttoquickly
and accurately estimate construction costs at the planning
stage, when drawings, documentation and the like are still
incomplete. As such, numerous techniques have been
applied to accurately estimate construction costs at an early
stage, when project information is limited. While the
numerous techniques have their pros and cons, thus there
must be a little effort made to determine the best technique
in terms of cost estimating performance. The purposeofthis
paper is to find the important factors affecting the cost
estimation of construction projects.
1.1 OBJECTIVES
 To explore the existing common practices in cost
estimating.
 To identify the significant factors affecting the
construction cost.
2. LITERATURE REVIEW
Aftab et.al., (2010) mentioned that the personnel ofProject
Management Consultant (PMC) ranked ineffective planning
and scheduling by contractors as quite significant factor
affecting construction cost. This issue seems to be true as it
is highly related to cash flow and financial difficulties faced
by contractors.
Chimwaso K.D. (2001) mentioned that design changes,
inadequate planning, unpredictable weather conditionsand
fluctuations in the cost of building materials are common
factors causing cost overruns.
Collier K (1987) emphasized the importanceofthedemand
for construction works. He stated that:"Itwouldbewrong to
give the impression that all estimates and bids for
construction work are made up of costs of labors, materials,
equipment, job overhead costs, and operating overhead
costs. All estimated from determined facts and calculated
probabilities, and with a profit margin precisely computed
according to current economic indicators". He added;"there
are other things that at times may have a greater influence
on the amount of a bid than any variations of those costsand
the most important of these is the demand for construction
work”.
Harvey J (1979) has analyzed the "time" effectin relationto
several of the other factors. Using dummy variables for
"years", she found no significant interaction effects with the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1155
number of bidders or geographical location but a significant
interaction effect with project size and the three-way
interaction of number of bidders/project size/ years.
Huawang Shi et.al., (2014) Construction cost estimation
and prediction, the basis of cost budgeting and cost
management, is crucial for construction firms to surviveand
grow in the industry. The objective of thispaperistopresent
a novel method integrating rough sets (RS) theory and an
artificial neural network (ANN) to forecast construction
project cost. Because there are many factors affecting the
cost of building and some of the factors are related and
redundant, rough sets theory is applied to find relevant
factors to the cost, which are used as inputs of an artificial
neural-network to predict the cost of construction project.
Therefore, the maincharacteristic attributeswere withdraw,
the complexity of neural network system and thecomputing
time was reduced, as well. A case study was carried out on
the cost estimate of a sample project using the model.
Khaled Hesham Hyari et.al., (2015) Cost estimation for
public projects includes, but is not limited to, construction
costs and engineering services costs. The available cost
estimation models for these projects focus on the
construction phase, with little or no consideration given to
engineering services. This paper presentsanartificial neural
network model for the conceptual cost estimation of
engineering services for public construction projects that
considers both design costs and construction supervision
costs. In developing the model, the authors first identify the
factors that influence the cost of engineering services, and
then apply a suitable artificial neural network for a cost
estimation model.Themodel predictsthecost ofengineering
services as a percentage of construction cost based on
project type, engineering services category, projectlocation,
and project scope.
Li Liu et.al., (2010) Central to cost-based competitionisthe
capability to accurately predict the cost of delivering a
project. Most literatureoncostestimationfocusesonspecific
estimation methods as generic techniques and little
attention has been paid to the unique requirements at each
project stage. This note attempts to identify the critical
factors for effective estimation at various stages of typical
construction projects. Drawing from organization control
theory and cost estimating literature, this note develops a
theoretical framework that identifies the critical factors for
effective cost estimation during each project phase of a
conventional construction project.
Muhammad T. Hatamleh et.al., (2018) Cost estimating
process is an important element within the project lifecycle.
Comprehensive information, expanded knowledge,
considerable expertise, and continuous improvement are
needed to obtain accurate cost estimation. The purpose of
this paper is to identify the critical factors that affect
accuracy of cost estimation and evaluatethedegreeto which
these factors are important from contractors' and
consultants' viewpoints. Qualitative and quantitative
research approaches were adopted in collecting and
analyzing the data, and testing the hypotheses. Based on the
literature review, a questionnaire was prepared and then
was modified according to the results of face-to-face open-
ended interviews conducted with 11 project managers. The
final version of the questionnaire was distributed to a
random sample of 265 respondents. For analyzing the
collected data Kendall's and Mann-Whitney tests were
conducted. The analysis revealed that there is a strong
agreement between contractors and consultants in the
ranking of the factors related to consultant, contractor,
design parameters, and information. A slightly weak
agreement between contractors and consultants was noted
regarding the factors related to market conditions (external
factors) and factors related to project characteristics.
Furthermore, the results show that the top ten factors
affecting the accuracy of cost estimate are clear and detail
drawings and specification, pricing experience of
construction projects, perception of estimation importance,
equipment (cost/availability/ performance), project
complexity, clear scope definition, accuracyandreliability of
cost information, site constraints (access, storage, services),
material availability, financial capabilities of the client, and
availability of database of bids on similar project (historical
data).
Neufville et.al., (1977) analyzed data on all new
constructioncostingover$100,000bytheCommonwealthof
Massachusetts BureauofBuildingConstructionfrom1961to
1974. The data included 167 contracts valued at over
$900,000,000 in total (or $1,332 billion in 1974 dollars).
Their analysis showed a curved negative relationship
between low bid/engineers' estimate ratios andthenumber
of bids received. This trend still appeared to hold in .good
years and "bad years".
Strandell M (1978) emphasized the importance of
productivity in construction. He stated that: "There is
general agreement by owners, engineers and contractors
that productivity in the construction industry is a problem
worthy of serious study. There is no question as to its effect
on the cost and time involved in completing a constructed
facility."
Uppal K.B. (1997) considers that cost estimation is the
determination of quantity and the predicting or forecasting
“within a defined scope” of the costs required to construct
and equip a facility, to manufacture goods, or to furnish a
service. In conclusion, cost estimating is the means of
forecasting and foreseeing the future costs of a construction
project before it actually exists. However, the final project
cost will not be known until the construction is finished and
facility is operated.
Wilson et.al., (1987) provide a diagram of their
summarized data which indicates a curved negative
correlation between the low bid/estimate ratios and the
number of bids. This trend exists for each of their four
groups of data studied although the larger contracts have a
shallower curve. The smoothness of the curves connecting
the medians on accuracy improved only slightly with the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1156
increasing number of previous bills used with no
improvement observed with the use ofmorethanthreebills.
3. RESEARCH METHODOLOGY
The methodology for this project proceeds as follows:-
[1] Literature collection
[2] Review of literature
[3] Identification of factors
[4] Questionnaire preparation
[5] Questionnaire survey
[6] Analysis of data
[7] Recommendations
The research conducted in this study is mostly exploratory
in nature. This research, and data hasbeenobtainedthrough
primary avenues – desk research and questionnaire. The
factors are listed below:-
Table 1: FACTORS AFFECTING BUILDING COST
Time / Cost related
1. Importance for project to be completed
within budget
2. Importance for project to be delivered
3. Time given to consultant to evaluate bids
4. Extent to which contract period is allowed
to vary
5. Importance for project to be completed on
time
6. Bidding environment
7. Consultant’s level of construction
sophistication
8. Owner’s level of construction sophistication
Parties experience related
1. Consultant experience with similar project
2. Owners experience with similar project
3. Consultant staffing level to attend to
contractor
4. Owners staffing level to attend to contractor
5. Contractor’s experience with similar type of
projects
6. Contractor’s experience with similar size of
projects
7. Contractors experience with project in
location
8. Subcontractor experience and capability
9. Communication among project team
10. Contractor’s prior working relationship
with the owners
11. Contractor prior working relationship with
consultant
12. Contractor track record for completion on
time
13. Contractor track record for completion on
budget
14. Contractor track records for completion on
quality
15. Contractor staffing level
16. Adequacy of contractor plant and
equipment
17. Magnitude of change orders in contractor
past project
Financial issues
1. Periodical payments
2. Inflation pressure
3. Economic instability
4. Uncertainty of taxes
5. State of market
6. Accuracy of estimated financing cost
7. Currency exchange fluctuation average
8. Availability of management and finance
plans
Bidding situations
1. Number of competitors
2. Level of competition
3. Time between project announcement and bid
opening average
4. Accuracy of bidding documents provided by
client
Project Characteristics
1. Type of contract
2. Size of contract
3. Project location
4. Site condition
5. Competent and leadership of project
manager
6. Experience and incentives of field staff
7. Quality of firm’s project planning and
management
8. Labor and equipment required
9. Content of the project specifications
10. Punitive damages
11. Arbitration clause
12. Knowledge of client and consultant average
13. Attitude towards changes
14. Environmental issues
15. Impact of project schedule
16. Quality of specification code
17. Unforeseeable change in local laws and
procedures
18. Weather
19. Nationality of labor
20. Social and cultural impact
21. Religious regulations
22. Estimating method
23. Public exposure
Estimating Process
1. Availability of productivity standards
2. Availability of cost indexes average
3.Relevant experience of estimating team
4. Ability of estimating team
5. Standard procedure for updating cost
information
6. Method used in determining contingency
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1157
4. QUESTIONNAIRE PREPARATION
A questionnaire was designed based on the objectives of the
study, which are causes of building cost estimation. A
questionnaire survey was developed to get the opinion and
understanding from the experienced respondentsregarding
to the cost estimating problem. The questionnaires are all
classified into 2 sections:
 SECTION A: Company and respondent profile
 SECTION B: Factors affecting building cost
Based on the literature and factors considered, a
questionnaire was designed. The above mentioned factors
were adapted to measure factor affecting in construction
project.
5. CONCLUSIONS
Different views of various authors on cost estimation were
discussed. Based on these information obtained from
literature search, seventy two factors were identified and
used for the study. The study gave the six most important
factors and they are: Design related factors, Time or Cost
related factors, Parties experience related, Financial issues,
Bidding situations, Project Characteristics, Estimating
Process. Therefore the major conclusion is that costoverrun
in building construction is still a adverse problem due to
various known reasons and thus, there is an urgent need for
developing an advanced cost in building construction that
should yield better result.
REFERENCES
[1] Aftab, H., Ismail, A., Mohd, A. andAde,A.(2010)‘Factors
Affecting Construction Cost in Mara LargeConstruction
Project: Perspective of Project Management
Consultant’, International Journal Of Sustainable
Construction Engineering & Technology.
[2] Chimwaso K.D. (2001) ‘An Evaluation of Cost
Performance of Public Projects; Case of Botswana’, 2nd
International Conference on Construction in
Developing Countires, Rotterdam (Netherlands).
[3] Collier K. (1987) ‘Fundamentals of Construction
Estimating & Cost Accounting’, Englewood Cliff, NJ:
Prentice Hall, Inc.
[4] Harvey, J. (1979), ‘Competitive Bidding on Canadian
Public Construction Contracts: Stochastic Analysis for
Optimization’,Thesis, (PhD).University of Western
Ontario.
[5] Huawang Shi, Wanqing Li (2014), ‘The Integrated
Methodology of Rough Set TheoryandArtificial Neural-
Network for Construction Project Cost Prediction’,
IEEE.
[6] Khaled Hesham Hyari, Ahmad Al-Daraiseh, and
Mohammad El Mashaleh (2015), ‘Conceptual Cost
Estimation Model for Engineering Services in Public
Construction Projects’, ASCE.
[7] Li Liu and Kai Zhu (2014), ‘ImprovingCostEstimatesof
Construction ProjectsUsing PhasedCostFactors’,ASCE.
[8] Muhammad T. Hatamleh, Mohammed Hiyassat, Ghaleb
Jalil Sweis and Rateb Jalil Sweis, (2018), ‘Factors
affecting the accuracy of cost estimate: case of Jordan’,
Engineering, Construction and Architectural
Management, Vol. 25 Issue: 1, pp.113-131.
[9] Neufville, R.D., Hani, E.N.and Lesage,Y.(1977),‘Bidding
Models Effects of Bidder’s Risk Aversion’ Journal of the
Construction Division, ASCE, Vol.103, pp 57-70.
[10] Strandell M. (1978), ‘Productivity in the construction
industry’, AACE Bulletin, Vol.20, No.2.
[11] Uppal, K. B. (1997), ‘Cost Estimating Made Simple
Hydrocarbon Processing,’ September 1997. p168c.
[12] Wilson, O.D, Atkins, A.S, Sharpe, K. and Kenley R.
(1987). ‘Competitive Tendering: The ideal number of
tenders’, The Organisation and Management of
Construction-5th International Symposium, London,
September 1987.
.

More Related Content

What's hot

A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
IJERA Editor
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
Cost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen RaymentCost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen Rayment
Stephen Rayment UK
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
IAEME Publication
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET Journal
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
IRJET Journal
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
Vamsi Kovalam
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
IRJET Journal
 
Strategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic StudyStrategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic Study
civej
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Publishing House
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
ijtsrd
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
IOSR Journals
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
ijceronline
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
Oyeniyi Samuel
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
Engr_Emad Khan
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
IRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
ijtsrd
 
IRJET- The Impact of Effective Planning on Project Success – A Literature Review
IRJET- The Impact of Effective Planning on Project Success – A Literature ReviewIRJET- The Impact of Effective Planning on Project Success – A Literature Review
IRJET- The Impact of Effective Planning on Project Success – A Literature Review
IRJET Journal
 
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
IRJET Journal
 

What's hot (19)

A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Cost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen RaymentCost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen Rayment
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
Strategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic StudyStrategic Cost Management for Construction Project Success : A Systematic Study
Strategic Cost Management for Construction Project Success : A Systematic Study
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
IRJET- The Impact of Effective Planning on Project Success – A Literature Review
IRJET- The Impact of Effective Planning on Project Success – A Literature ReviewIRJET- The Impact of Effective Planning on Project Success – A Literature Review
IRJET- The Impact of Effective Planning on Project Success – A Literature Review
 
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
Framework for Establishing Risk Impacts on Forecasted Construction Cash Flows...
 

Similar to IRJET- A Study on Factors Affecting Estimation of Construction Project

Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
IRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
ijsrd.com
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET Journal
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
IRJET Journal
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
KarthikeyanP288430
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
civejjour
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
Nat Rice
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET Journal
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
IRJET Journal
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
World-Academic Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET Journal
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET Journal
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A Review
IRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
IAEME Publication
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET Journal
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET Journal
 
A Review on Earned Value Management and Earned Schedule Method for Constructi...
A Review on Earned Value Management and Earned Schedule Method for Constructi...A Review on Earned Value Management and Earned Schedule Method for Constructi...
A Review on Earned Value Management and Earned Schedule Method for Constructi...
IRJET Journal
 

Similar to IRJET- A Study on Factors Affecting Estimation of Construction Project (20)

Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A Review
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTSISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
ISSUES RELATED TO SUBCONTRACTING PRACTICES IN CONSTRUCTION PROJECTS
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 
A Review on Earned Value Management and Earned Schedule Method for Constructi...
A Review on Earned Value Management and Earned Schedule Method for Constructi...A Review on Earned Value Management and Earned Schedule Method for Constructi...
A Review on Earned Value Management and Earned Schedule Method for Constructi...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 

Recently uploaded (20)

CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 

IRJET- A Study on Factors Affecting Estimation of Construction Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1154 A STUDY ON FACTORS AFFECTING ESTIMATION OF CONSTRUCTION PROJECT Dr. S Kanchana1, Ms. S Janani2 1Head of the Department, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India, 2PG Student, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India ----------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Construction industry is considered as a very important sector for development in all over the world and the construction cost estimation is the most important element in it. Realistic estimation of construction cost is essential for both successful planning and completion of every construction project. The key factor for a successful project is the accurate cost estimation at its early stage. It is very difficult to quickly and accuratelyestimateconstruction costs at the planning stage itself when project information is limited. This study aim at caring out to identify the factors affecting construction cost estimation. The factors were identified based on questionnaire survey. Questionnaires were given to 64 experts in theconstructionindustryaimsto determine the importance of construction cost estimation and to determine the score of each factor. Statistical analysis will be carried out on the feedback of the respondents of the survey. RII value of the factors to be found using Microsoft Excel. The mean score of each factor to be determined and the p-value was calculated using the SPSS software. The significance of each factor used in the questionnaire to be determined. The important factors were identifiedusingthe mean score and their p-value. Key Words: Cost estimation, Questionnairepreparation, SPSS 1. INTRODUCTION Several factors affect the accuracy of building project’s cost estimation which must be considered at the early stage of the estimation process.Some factorscanrapidlyincreasethe estimated costs and the possibility of contractual strifes between the various parties involved. There are other factors that can help the estimator to decrease the unnecessary cost of an item and thus lead to successful tendering in a very competitive market. Therefore, for accurate estimating detailed study of the biding documents and the environmental situation are required. In order to arrive to the most accurate estimate of the probable cost consistent with the bidding time available and the accuracy and completeness of the information submitted, it also requires careful analysis of data of all projects. Realistic estimation of construction cost is essential forboth successful planning and completion of all construction project. Also due to uncertain conditions, validcostforecasts become an significant source of information for decision making by all construction parties. Accurate cost estimation at the early stage of a construction project is a significant factor in a successful project. But it is very difficulttoquickly and accurately estimate construction costs at the planning stage, when drawings, documentation and the like are still incomplete. As such, numerous techniques have been applied to accurately estimate construction costs at an early stage, when project information is limited. While the numerous techniques have their pros and cons, thus there must be a little effort made to determine the best technique in terms of cost estimating performance. The purposeofthis paper is to find the important factors affecting the cost estimation of construction projects. 1.1 OBJECTIVES  To explore the existing common practices in cost estimating.  To identify the significant factors affecting the construction cost. 2. LITERATURE REVIEW Aftab et.al., (2010) mentioned that the personnel ofProject Management Consultant (PMC) ranked ineffective planning and scheduling by contractors as quite significant factor affecting construction cost. This issue seems to be true as it is highly related to cash flow and financial difficulties faced by contractors. Chimwaso K.D. (2001) mentioned that design changes, inadequate planning, unpredictable weather conditionsand fluctuations in the cost of building materials are common factors causing cost overruns. Collier K (1987) emphasized the importanceofthedemand for construction works. He stated that:"Itwouldbewrong to give the impression that all estimates and bids for construction work are made up of costs of labors, materials, equipment, job overhead costs, and operating overhead costs. All estimated from determined facts and calculated probabilities, and with a profit margin precisely computed according to current economic indicators". He added;"there are other things that at times may have a greater influence on the amount of a bid than any variations of those costsand the most important of these is the demand for construction work”. Harvey J (1979) has analyzed the "time" effectin relationto several of the other factors. Using dummy variables for "years", she found no significant interaction effects with the
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1155 number of bidders or geographical location but a significant interaction effect with project size and the three-way interaction of number of bidders/project size/ years. Huawang Shi et.al., (2014) Construction cost estimation and prediction, the basis of cost budgeting and cost management, is crucial for construction firms to surviveand grow in the industry. The objective of thispaperistopresent a novel method integrating rough sets (RS) theory and an artificial neural network (ANN) to forecast construction project cost. Because there are many factors affecting the cost of building and some of the factors are related and redundant, rough sets theory is applied to find relevant factors to the cost, which are used as inputs of an artificial neural-network to predict the cost of construction project. Therefore, the maincharacteristic attributeswere withdraw, the complexity of neural network system and thecomputing time was reduced, as well. A case study was carried out on the cost estimate of a sample project using the model. Khaled Hesham Hyari et.al., (2015) Cost estimation for public projects includes, but is not limited to, construction costs and engineering services costs. The available cost estimation models for these projects focus on the construction phase, with little or no consideration given to engineering services. This paper presentsanartificial neural network model for the conceptual cost estimation of engineering services for public construction projects that considers both design costs and construction supervision costs. In developing the model, the authors first identify the factors that influence the cost of engineering services, and then apply a suitable artificial neural network for a cost estimation model.Themodel predictsthecost ofengineering services as a percentage of construction cost based on project type, engineering services category, projectlocation, and project scope. Li Liu et.al., (2010) Central to cost-based competitionisthe capability to accurately predict the cost of delivering a project. Most literatureoncostestimationfocusesonspecific estimation methods as generic techniques and little attention has been paid to the unique requirements at each project stage. This note attempts to identify the critical factors for effective estimation at various stages of typical construction projects. Drawing from organization control theory and cost estimating literature, this note develops a theoretical framework that identifies the critical factors for effective cost estimation during each project phase of a conventional construction project. Muhammad T. Hatamleh et.al., (2018) Cost estimating process is an important element within the project lifecycle. Comprehensive information, expanded knowledge, considerable expertise, and continuous improvement are needed to obtain accurate cost estimation. The purpose of this paper is to identify the critical factors that affect accuracy of cost estimation and evaluatethedegreeto which these factors are important from contractors' and consultants' viewpoints. Qualitative and quantitative research approaches were adopted in collecting and analyzing the data, and testing the hypotheses. Based on the literature review, a questionnaire was prepared and then was modified according to the results of face-to-face open- ended interviews conducted with 11 project managers. The final version of the questionnaire was distributed to a random sample of 265 respondents. For analyzing the collected data Kendall's and Mann-Whitney tests were conducted. The analysis revealed that there is a strong agreement between contractors and consultants in the ranking of the factors related to consultant, contractor, design parameters, and information. A slightly weak agreement between contractors and consultants was noted regarding the factors related to market conditions (external factors) and factors related to project characteristics. Furthermore, the results show that the top ten factors affecting the accuracy of cost estimate are clear and detail drawings and specification, pricing experience of construction projects, perception of estimation importance, equipment (cost/availability/ performance), project complexity, clear scope definition, accuracyandreliability of cost information, site constraints (access, storage, services), material availability, financial capabilities of the client, and availability of database of bids on similar project (historical data). Neufville et.al., (1977) analyzed data on all new constructioncostingover$100,000bytheCommonwealthof Massachusetts BureauofBuildingConstructionfrom1961to 1974. The data included 167 contracts valued at over $900,000,000 in total (or $1,332 billion in 1974 dollars). Their analysis showed a curved negative relationship between low bid/engineers' estimate ratios andthenumber of bids received. This trend still appeared to hold in .good years and "bad years". Strandell M (1978) emphasized the importance of productivity in construction. He stated that: "There is general agreement by owners, engineers and contractors that productivity in the construction industry is a problem worthy of serious study. There is no question as to its effect on the cost and time involved in completing a constructed facility." Uppal K.B. (1997) considers that cost estimation is the determination of quantity and the predicting or forecasting “within a defined scope” of the costs required to construct and equip a facility, to manufacture goods, or to furnish a service. In conclusion, cost estimating is the means of forecasting and foreseeing the future costs of a construction project before it actually exists. However, the final project cost will not be known until the construction is finished and facility is operated. Wilson et.al., (1987) provide a diagram of their summarized data which indicates a curved negative correlation between the low bid/estimate ratios and the number of bids. This trend exists for each of their four groups of data studied although the larger contracts have a shallower curve. The smoothness of the curves connecting the medians on accuracy improved only slightly with the
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1156 increasing number of previous bills used with no improvement observed with the use ofmorethanthreebills. 3. RESEARCH METHODOLOGY The methodology for this project proceeds as follows:- [1] Literature collection [2] Review of literature [3] Identification of factors [4] Questionnaire preparation [5] Questionnaire survey [6] Analysis of data [7] Recommendations The research conducted in this study is mostly exploratory in nature. This research, and data hasbeenobtainedthrough primary avenues – desk research and questionnaire. The factors are listed below:- Table 1: FACTORS AFFECTING BUILDING COST Time / Cost related 1. Importance for project to be completed within budget 2. Importance for project to be delivered 3. Time given to consultant to evaluate bids 4. Extent to which contract period is allowed to vary 5. Importance for project to be completed on time 6. Bidding environment 7. Consultant’s level of construction sophistication 8. Owner’s level of construction sophistication Parties experience related 1. Consultant experience with similar project 2. Owners experience with similar project 3. Consultant staffing level to attend to contractor 4. Owners staffing level to attend to contractor 5. Contractor’s experience with similar type of projects 6. Contractor’s experience with similar size of projects 7. Contractors experience with project in location 8. Subcontractor experience and capability 9. Communication among project team 10. Contractor’s prior working relationship with the owners 11. Contractor prior working relationship with consultant 12. Contractor track record for completion on time 13. Contractor track record for completion on budget 14. Contractor track records for completion on quality 15. Contractor staffing level 16. Adequacy of contractor plant and equipment 17. Magnitude of change orders in contractor past project Financial issues 1. Periodical payments 2. Inflation pressure 3. Economic instability 4. Uncertainty of taxes 5. State of market 6. Accuracy of estimated financing cost 7. Currency exchange fluctuation average 8. Availability of management and finance plans Bidding situations 1. Number of competitors 2. Level of competition 3. Time between project announcement and bid opening average 4. Accuracy of bidding documents provided by client Project Characteristics 1. Type of contract 2. Size of contract 3. Project location 4. Site condition 5. Competent and leadership of project manager 6. Experience and incentives of field staff 7. Quality of firm’s project planning and management 8. Labor and equipment required 9. Content of the project specifications 10. Punitive damages 11. Arbitration clause 12. Knowledge of client and consultant average 13. Attitude towards changes 14. Environmental issues 15. Impact of project schedule 16. Quality of specification code 17. Unforeseeable change in local laws and procedures 18. Weather 19. Nationality of labor 20. Social and cultural impact 21. Religious regulations 22. Estimating method 23. Public exposure Estimating Process 1. Availability of productivity standards 2. Availability of cost indexes average 3.Relevant experience of estimating team 4. Ability of estimating team 5. Standard procedure for updating cost information 6. Method used in determining contingency
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 11 | Nov 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1157 4. QUESTIONNAIRE PREPARATION A questionnaire was designed based on the objectives of the study, which are causes of building cost estimation. A questionnaire survey was developed to get the opinion and understanding from the experienced respondentsregarding to the cost estimating problem. The questionnaires are all classified into 2 sections:  SECTION A: Company and respondent profile  SECTION B: Factors affecting building cost Based on the literature and factors considered, a questionnaire was designed. The above mentioned factors were adapted to measure factor affecting in construction project. 5. CONCLUSIONS Different views of various authors on cost estimation were discussed. Based on these information obtained from literature search, seventy two factors were identified and used for the study. The study gave the six most important factors and they are: Design related factors, Time or Cost related factors, Parties experience related, Financial issues, Bidding situations, Project Characteristics, Estimating Process. Therefore the major conclusion is that costoverrun in building construction is still a adverse problem due to various known reasons and thus, there is an urgent need for developing an advanced cost in building construction that should yield better result. REFERENCES [1] Aftab, H., Ismail, A., Mohd, A. andAde,A.(2010)‘Factors Affecting Construction Cost in Mara LargeConstruction Project: Perspective of Project Management Consultant’, International Journal Of Sustainable Construction Engineering & Technology. [2] Chimwaso K.D. (2001) ‘An Evaluation of Cost Performance of Public Projects; Case of Botswana’, 2nd International Conference on Construction in Developing Countires, Rotterdam (Netherlands). [3] Collier K. (1987) ‘Fundamentals of Construction Estimating & Cost Accounting’, Englewood Cliff, NJ: Prentice Hall, Inc. [4] Harvey, J. (1979), ‘Competitive Bidding on Canadian Public Construction Contracts: Stochastic Analysis for Optimization’,Thesis, (PhD).University of Western Ontario. [5] Huawang Shi, Wanqing Li (2014), ‘The Integrated Methodology of Rough Set TheoryandArtificial Neural- Network for Construction Project Cost Prediction’, IEEE. [6] Khaled Hesham Hyari, Ahmad Al-Daraiseh, and Mohammad El Mashaleh (2015), ‘Conceptual Cost Estimation Model for Engineering Services in Public Construction Projects’, ASCE. [7] Li Liu and Kai Zhu (2014), ‘ImprovingCostEstimatesof Construction ProjectsUsing PhasedCostFactors’,ASCE. [8] Muhammad T. Hatamleh, Mohammed Hiyassat, Ghaleb Jalil Sweis and Rateb Jalil Sweis, (2018), ‘Factors affecting the accuracy of cost estimate: case of Jordan’, Engineering, Construction and Architectural Management, Vol. 25 Issue: 1, pp.113-131. [9] Neufville, R.D., Hani, E.N.and Lesage,Y.(1977),‘Bidding Models Effects of Bidder’s Risk Aversion’ Journal of the Construction Division, ASCE, Vol.103, pp 57-70. [10] Strandell M. (1978), ‘Productivity in the construction industry’, AACE Bulletin, Vol.20, No.2. [11] Uppal, K. B. (1997), ‘Cost Estimating Made Simple Hydrocarbon Processing,’ September 1997. p168c. [12] Wilson, O.D, Atkins, A.S, Sharpe, K. and Kenley R. (1987). ‘Competitive Tendering: The ideal number of tenders’, The Organisation and Management of Construction-5th International Symposium, London, September 1987. .