SlideShare a Scribd company logo
“HYDRO POWER PLANT”
 PREPARED BY :
DISHANT PATEL 140123109009
VISHAL GOHEL 140123109003
JAY PANCHAL 140123109007
MANTHAN PANCHAL 140123109008
GUIDED BY : Prof. Rahil Parikh
CONTENTS:
Introduction
Site selection
Schematic diagram
Working
Elements of HPS
Classification of HPS
Types of turbine
Advantages & Disadvantages
Comparison
Power plant in gujarat
INTRODUCTION
 In Hydro Power Plant the water is utilized to move
the turbines which in turn run the electric
generator’s.
 The Potential energy of the water stored in the
dam gets converted into the Kinetic Energy of the
moving water in the penstock. And this Kinetic
Energy gets converted into the Electrical Energy
with the help of Turbine & Generator combination.
 Hydro Power Plant was invented by H.F. Rogers.
 Hydro power = WQH × n × 9.81 watts
SITE SELECTION
1. Availability of water
– All other designs are based on it.
– Estimate should be made about the average
quantity of water available throughout the year
and also about maximum and minimum quantity
of water available during the year.
– These details are necessary to decide the
capacity of the hydropower plant, and
– It also provide adequate spillways or gate relief
during flood period.
2. Water storage
– Since there a is wide variation in rainfall during
the year, therefore it is necessary to store the
water for continuous generation of power. The
storage capacity can be calculated with the help
of mass curve.
– The two types of storages in use are
1. The storage is so constructed that it can make water
available for power generation for one year only.
2. Water is available in sufficient quantity even during
the worst dry periods.
3. Water head
– In order to generate a requisite quantity of power it
is necessary that a large quantity of water at
sufficient head should be available.
– An increase in effective head for a given output,
reduces the quantity of water required to be
supplied to the turbines.
4. Accessibility of site
– The site where hydro-electric plant is to be
constructed should be easy accessible. This is
important if the electric power generated is to be
utilized at or near the plant site.
– The site selected should have transportation
facilities of rail and road.
5. Distance from the load centre
– Power plant should be set up near the load centre,
this will reduce the cost of maintenance of
transmission line.
6. Type of the land of the site
– The land to be selected for the site should be
cheap and rocky.
– The ideal site will be one where the dam will have
largest catchment area to store water at high head
and will be economical in construction.
SCHEMATIC DIAGRAM
WORKING
 Initially the water of the river is in Catchments Area.
 From catchments area the water flows to the dam.
 At the dam the water gets accumulated . Thus the potential
energy of the water increases due to the height of the dam .
 When the gates of the dam are opened then the water moves
with high Kinetic Energy into the penstock.
 Through the penstock water goes to the turbine house.
 Since the penstock makes water to flow from high altitude to
low altitude, Thus the Kinetic Energy of the water is again
raised.
In the turbine house the pressure of the water is controlled
by the controlling valves as per the requirements.
 The controlled pressurized water is fed to the turbine.
 Due to the pressure of the water the light weight turbine
rotates.
 Due to the high speed rotation of the turbine the shaft
connected between the turbine and the generator rotates .
 Due to the rotation of generator the ac current is produced.
 This current is supplied to the powerhouse .
 From powerhouse it is supplied for the commercial
purposes.
ELEMENTS OF HPS
1. CATCHMENT AREA :
2. RESERVOIR :
3. DAM :
The whole area behind the clam training into a stream as river
across which the dam has been built at suitable place is
called catchments area.
A reservoir is employed to store water which is further utilized
to generate power by running the hydroelectric turbines.
 A dam is a barrier which confines or raise water for storage or
diversion to create a hydraulic head.
 Dam’s are generally made of concrete, Stone masonary, Rock
fill or Timber.
4. SPILWAYS :
5. SURGE TANK :
6. PENSTOCKS :
 Spill Way’s is a kind of canal provided besides the dam.
 Spill Way’s is used to arrange the excess of accumulation of
water on the dam because excess accumulation of water
may damage the dam structure.
 Penstock is the connecting pipe between the dam & the
turbine house.
 It helps to increase the kinetic energy of the water coming from
the dam.
 Penstock is made up of a very strong material which can
sustain the high pressure of water.
 Surge tank is used to absorb the fluctuation in pressure
caused due to changing demand of water quantity.
7. POWER HOUSE :
 The power house is a building in which the turbines, alternator
and other auxiliary are housed.
8.TAIL RACE :
 Tail race is a passage for discharging the water leaving the
turbines, into the river.
9.SWICH YARD FOR TRANSMISSION OF
POWER :
 The electrical equipment of a hydro-electric power station
includes like transformer, circuit breaker & other switching &
protective devices.
CLASSIFICATION OF HPS
1. LOW HEAD PLANTS :
Low head hydro power applications use river
current or tidal flows of 60 meters or less to
produce energy.
These applications do not need to dam or
retain water to create hydraulic head, the head
is only a few meters.
Using the current of a river or the naturally
occurring tidal flow to create electricity may
provide a renewable energy source that will
have a minimal impact on the environment.
• MEDIUM HEAD PLANT :
A power station operating under heads from 60m to 300m.
3. HIGH HEAD PLANTS :
A power station operating under heads above about 300m.
A head of 200m/250m is considered as the limit between
medium and high head power stations.
Figure- high head hydropower plant
1. Impulse Turbine
TYPES OF HYDRAULIC TURBINE
 Impulse turbine : One in which all the energy of
water is converted to kinetic energy before the water
strikes the vanes of the runner wheel.
 This is done by passing the flow through nozzle or
some guidelines.
 The runner is rotated by the force of water and
water passes over the wheel at atmospheric
pressure.
2. Reaction Turbine : Here, water entering the runner wheel of
the turbine has both kinetic energy and pressure energy that is
total head of water striking the runner wheel ,consist partly of
pressure head.
E.g.- Francis turbine, Kaplan turbine
ADANTAGES OF HYDRO POWER PLANT:
 No fuel charges,
 Running cost almost nil,
 No stand by losses,
 Highly reliable,
 Efficiency does not decrease with time,
 Construction and operation wise very simple,
 Maintenance cost very less,
 Starts quickly and synchronizes fast,
 Minimum staff when plant is operational,
 No ash problems thus pollution free,
Also useful in flood control and irrigation and
drinking water purpose,
 Comparatively quiet long life.
DISADVANTAGES OF HYDRO POWER PLANT:
 Higher initial cost,
 Takes long time of erection,
 Plants are setup at distant places so transmission
losses increases,
 Totally dependent on the availability of water,
 Larger area required,
 Period of installation time is high,
COMPARISON OF HYDRO,THERMAL &
NULCEAR POWER PLANT:
HYDROELECTRIC POWER PLANTS IN GUJARAT
STATE NAME OF
POWER PLANT
LOCATION
RIVER
CAPACITY
(MW)
GUJARAT
SARDAR
SAROVAR DAM NARMADA 1450
UKAI TAPI 305
KADANA MAHI 242
REFRENCES :
 Dr. D.M.Patel
 Wikipedia
hydro power plant

More Related Content

What's hot

Working of hydroelectric power plant
Working of hydroelectric power plant Working of hydroelectric power plant
Working of hydroelectric power plant
Hussan Sheikh
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plant
Satish Taji
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Pradeep Yadav
 
Hydro-Electric Power
Hydro-Electric PowerHydro-Electric Power
Hydro-Electric Power
GAURAV. H .TANDON
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantDr. Ramesh B
 
Hydro Power Plant
Hydro Power PlantHydro Power Plant
Hydro Power Plant
tavinav
 
Hydro power plants
Hydro power plants Hydro power plants
Hydro power plants
FAHAD KHAN
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
Nishkam Dhiman
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Ashvani Shukla
 
Hydro ppt
Hydro pptHydro ppt
Hydro ppt
Mayank Rathi
 
Hydro electric power plant ppt
Hydro electric power plant pptHydro electric power plant ppt
Hydro electric power plant ppt
Mohammad Nafey
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plant
CraZzy Shubh
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
Md. Rimon Mia
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTS
Raju D
 
Hydroelectric powerplant
Hydroelectric powerplantHydroelectric powerplant
Hydroelectric powerplant
Gurkirat Singh
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
Prashant Arora
 
Hydroelectric power
Hydroelectric power Hydroelectric power
Hydroelectric power
Bibhabasu Mohanty
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
Vignesh Sekar
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTS
RAJ BAIRWA
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
snelkoli
 

What's hot (20)

Working of hydroelectric power plant
Working of hydroelectric power plant Working of hydroelectric power plant
Working of hydroelectric power plant
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro-Electric Power
Hydro-Electric PowerHydro-Electric Power
Hydro-Electric Power
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydro Power Plant
Hydro Power PlantHydro Power Plant
Hydro Power Plant
 
Hydro power plants
Hydro power plants Hydro power plants
Hydro power plants
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro ppt
Hydro pptHydro ppt
Hydro ppt
 
Hydro electric power plant ppt
Hydro electric power plant pptHydro electric power plant ppt
Hydro electric power plant ppt
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plant
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTS
 
Hydroelectric powerplant
Hydroelectric powerplantHydroelectric powerplant
Hydroelectric powerplant
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
 
Hydroelectric power
Hydroelectric power Hydroelectric power
Hydroelectric power
 
Hydro Power Plants
Hydro Power PlantsHydro Power Plants
Hydro Power Plants
 
TYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTSTYPES OF HYDRO POWER PLANTS
TYPES OF HYDRO POWER PLANTS
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 

Viewers also liked

Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
rjrohit6
 
Micro hydro power plant final 1
Micro hydro power plant final 1Micro hydro power plant final 1
Micro hydro power plant final 1richa khatri
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Nimesh Mahadik
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
Yuri Melliza
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
pranavn007
 
Hydro power plant design
Hydro power plant designHydro power plant design
Hydro power plant design
Aamir Hassan
 
Performance prediction of a thermal system using Artificial Neural Networks
Performance prediction of a thermal system using Artificial Neural NetworksPerformance prediction of a thermal system using Artificial Neural Networks
Performance prediction of a thermal system using Artificial Neural Networks
IJERD Editor
 
Development of an Embedded System and MATLAB Program for Industrial and Biome...
Development of an Embedded System and MATLAB Program for Industrial and Biome...Development of an Embedded System and MATLAB Program for Industrial and Biome...
Development of an Embedded System and MATLAB Program for Industrial and Biome...
Heerok Mutsuddy
 
coventional Sources of energy
coventional Sources of energycoventional Sources of energy
coventional Sources of energy
rjrohit6
 
OPTIMIZING ENERGY PRODUCTION WITH A LOW/INTERMITTENT WIND RESOURCE
OPTIMIZING ENERGY  PRODUCTION WITH A LOW/INTERMITTENT WIND  RESOURCE    OPTIMIZING ENERGY  PRODUCTION WITH A LOW/INTERMITTENT WIND  RESOURCE
OPTIMIZING ENERGY PRODUCTION WITH A LOW/INTERMITTENT WIND RESOURCE
David Parker
 
Case study - Santa Clara Power Plant Automation
Case study - Santa Clara Power Plant AutomationCase study - Santa Clara Power Plant Automation
Case study - Santa Clara Power Plant Automation
Norbert Penner
 
Hydro Power Plant -Surya
Hydro Power Plant -SuryaHydro Power Plant -Surya
Hydro Power Plant -Surya
suryakant soni
 
Hydropower
HydropowerHydropower
Hydropower
Idriz Mustafic
 
Solar Thermal Systems
Solar Thermal SystemsSolar Thermal Systems
Solar Thermal Systems
Dr Naim R Kidwai
 
SARVESH hydro electric-power-plant
SARVESH hydro electric-power-plantSARVESH hydro electric-power-plant
SARVESH hydro electric-power-plant
sarvesh kumar
 
SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...
SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...
SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...
IAEME Publication
 

Viewers also liked (20)

Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Micro hydro power plant final 1
Micro hydro power plant final 1Micro hydro power plant final 1
Micro hydro power plant final 1
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro power presentation
Hydro power presentationHydro power presentation
Hydro power presentation
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydro power-plant
Hydro power-plantHydro power-plant
Hydro power-plant
 
Hydro power plant design
Hydro power plant designHydro power plant design
Hydro power plant design
 
Performance prediction of a thermal system using Artificial Neural Networks
Performance prediction of a thermal system using Artificial Neural NetworksPerformance prediction of a thermal system using Artificial Neural Networks
Performance prediction of a thermal system using Artificial Neural Networks
 
Development of an Embedded System and MATLAB Program for Industrial and Biome...
Development of an Embedded System and MATLAB Program for Industrial and Biome...Development of an Embedded System and MATLAB Program for Industrial and Biome...
Development of an Embedded System and MATLAB Program for Industrial and Biome...
 
coventional Sources of energy
coventional Sources of energycoventional Sources of energy
coventional Sources of energy
 
Wind Energy_Power Plant_Yagna (Autosaved)
Wind Energy_Power Plant_Yagna (Autosaved)Wind Energy_Power Plant_Yagna (Autosaved)
Wind Energy_Power Plant_Yagna (Autosaved)
 
OPTIMIZING ENERGY PRODUCTION WITH A LOW/INTERMITTENT WIND RESOURCE
OPTIMIZING ENERGY  PRODUCTION WITH A LOW/INTERMITTENT WIND  RESOURCE    OPTIMIZING ENERGY  PRODUCTION WITH A LOW/INTERMITTENT WIND  RESOURCE
OPTIMIZING ENERGY PRODUCTION WITH A LOW/INTERMITTENT WIND RESOURCE
 
Case study - Santa Clara Power Plant Automation
Case study - Santa Clara Power Plant AutomationCase study - Santa Clara Power Plant Automation
Case study - Santa Clara Power Plant Automation
 
Hydro Power Plant -Surya
Hydro Power Plant -SuryaHydro Power Plant -Surya
Hydro Power Plant -Surya
 
Hydropower
HydropowerHydropower
Hydropower
 
Solar Thermal Systems
Solar Thermal SystemsSolar Thermal Systems
Solar Thermal Systems
 
SARVESH hydro electric-power-plant
SARVESH hydro electric-power-plantSARVESH hydro electric-power-plant
SARVESH hydro electric-power-plant
 
SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...
SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...
SIMULATION OF SOLAR THERMAL CENTRAL RECEIVER POWER PLANT AND EFFECT OF WEATHE...
 

Similar to hydro power plant

Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008
Pratik Diyora
 
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaHYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
MayurjyotiNeog
 
seminar on hydropower presentation
seminar on hydropower presentationseminar on hydropower presentation
seminar on hydropower presentation
ram sundar singh
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Ripuranjan Singh
 
Hydroelectric power Plants.ppt
Hydroelectric power Plants.pptHydroelectric power Plants.ppt
Hydroelectric power Plants.ppt
Farhan573170
 
Hydro power
Hydro powerHydro power
Hydro power
Ibrahim R
 
waris.pptx
waris.pptxwaris.pptx
waris.pptx
Basit861379
 
Naveen
NaveenNaveen
Naveen
vinayvickky
 
Hydro power plant
Hydro power plant Hydro power plant
Hydro power plant
AmitKumar6931
 
Unit 5 Energy engg.ppsx
Unit 5 Energy engg.ppsxUnit 5 Energy engg.ppsx
Unit 5 Energy engg.ppsx
MohsinAnsari73
 
Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.
Salman Jailani
 
Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.
Salman Jailani
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
WajidMalik27
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -Hydraulics
Civil Zone
 
Hydropower
HydropowerHydropower
Hydropower
Divya Vishnoi
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
Muddassar Awan
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
Muddassar Awan
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
JUNAID SK
 

Similar to hydro power plant (20)

Hydroelectric powerplant
Hydroelectric powerplant Hydroelectric powerplant
Hydroelectric powerplant
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008
 
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in IndiaHYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
HYDROELECTRIC POWERPLANTS : Major hydroelectric plants operational in India
 
seminar on hydropower presentation
seminar on hydropower presentationseminar on hydropower presentation
seminar on hydropower presentation
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydroelectric power Plants.ppt
Hydroelectric power Plants.pptHydroelectric power Plants.ppt
Hydroelectric power Plants.ppt
 
Hydro power
Hydro powerHydro power
Hydro power
 
waris.pptx
waris.pptxwaris.pptx
waris.pptx
 
Naveen
NaveenNaveen
Naveen
 
Hydro power plant
Hydro power plant Hydro power plant
Hydro power plant
 
Unit 5 Energy engg.ppsx
Unit 5 Energy engg.ppsxUnit 5 Energy engg.ppsx
Unit 5 Energy engg.ppsx
 
Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.Calculation Efficiency of 2GW Hydropower Plant.
Calculation Efficiency of 2GW Hydropower Plant.
 
Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.Calculation Efficiency of 5GW Hydropower Plant.
Calculation Efficiency of 5GW Hydropower Plant.
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -Hydraulics
 
Hydropower
HydropowerHydropower
Hydropower
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
 
Hydroelectric power plant
Hydroelectric power plantHydroelectric power plant
Hydroelectric power plant
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
 
Nhpc
NhpcNhpc
Nhpc
 

More from vishalgohel12195

Variable frequency drive and variable frequency control
Variable frequency drive and variable frequency controlVariable frequency drive and variable frequency control
Variable frequency drive and variable frequency control
vishalgohel12195
 
Self control of synchronous motor drives
Self control of synchronous motor drivesSelf control of synchronous motor drives
Self control of synchronous motor drives
vishalgohel12195
 
Owen’s bridge and measurement of increment inductance
Owen’s bridge and measurement of increment inductanceOwen’s bridge and measurement of increment inductance
Owen’s bridge and measurement of increment inductance
vishalgohel12195
 
Initial and final condition for circuit
Initial and final condition for circuitInitial and final condition for circuit
Initial and final condition for circuit
vishalgohel12195
 
FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS
FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS  FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS
FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS
vishalgohel12195
 
Differential equations of first order
Differential equations of first orderDifferential equations of first order
Differential equations of first order
vishalgohel12195
 
Cost for production including breaking analysis
Cost for production including breaking  analysisCost for production including breaking  analysis
Cost for production including breaking analysis
vishalgohel12195
 
Concept of general terms pertaining to rotating machines
Concept of general terms pertaining to rotating machinesConcept of general terms pertaining to rotating machines
Concept of general terms pertaining to rotating machines
vishalgohel12195
 
Transfer function and mathematical modeling
Transfer  function  and  mathematical  modelingTransfer  function  and  mathematical  modeling
Transfer function and mathematical modeling
vishalgohel12195
 
armature Winding
armature Windingarmature Winding
armature Winding
vishalgohel12195
 
Switching regulators
Switching regulatorsSwitching regulators
Switching regulators
vishalgohel12195
 
Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chart
vishalgohel12195
 
Rectifier
RectifierRectifier
Rectifier
vishalgohel12195
 
Protection against overvoltage
Protection against overvoltageProtection against overvoltage
Protection against overvoltage
vishalgohel12195
 
Pantograph,catenary wire,smothing reactor
Pantograph,catenary wire,smothing reactorPantograph,catenary wire,smothing reactor
Pantograph,catenary wire,smothing reactor
vishalgohel12195
 
On load tap changer in a.c. locomotive transformer & air blast circuit b...
On load tap changer in a.c. locomotive transformer  & air blast circuit b...On load tap changer in a.c. locomotive transformer  & air blast circuit b...
On load tap changer in a.c. locomotive transformer & air blast circuit b...
vishalgohel12195
 
Logical instruction of 8085
Logical instruction of 8085Logical instruction of 8085
Logical instruction of 8085
vishalgohel12195
 
Effect of non sinusoidal waveform of a.c. machine performance
Effect of non sinusoidal waveform of a.c. machine performanceEffect of non sinusoidal waveform of a.c. machine performance
Effect of non sinusoidal waveform of a.c. machine performance
vishalgohel12195
 
Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...
vishalgohel12195
 
Design, Planning and Layout of high voltage laboratory
Design, Planning and Layout of high voltage laboratory Design, Planning and Layout of high voltage laboratory
Design, Planning and Layout of high voltage laboratory
vishalgohel12195
 

More from vishalgohel12195 (20)

Variable frequency drive and variable frequency control
Variable frequency drive and variable frequency controlVariable frequency drive and variable frequency control
Variable frequency drive and variable frequency control
 
Self control of synchronous motor drives
Self control of synchronous motor drivesSelf control of synchronous motor drives
Self control of synchronous motor drives
 
Owen’s bridge and measurement of increment inductance
Owen’s bridge and measurement of increment inductanceOwen’s bridge and measurement of increment inductance
Owen’s bridge and measurement of increment inductance
 
Initial and final condition for circuit
Initial and final condition for circuitInitial and final condition for circuit
Initial and final condition for circuit
 
FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS
FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS  FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS
FSK , FM DEMODULATOR & VOLTAGE REGULATOR ICS
 
Differential equations of first order
Differential equations of first orderDifferential equations of first order
Differential equations of first order
 
Cost for production including breaking analysis
Cost for production including breaking  analysisCost for production including breaking  analysis
Cost for production including breaking analysis
 
Concept of general terms pertaining to rotating machines
Concept of general terms pertaining to rotating machinesConcept of general terms pertaining to rotating machines
Concept of general terms pertaining to rotating machines
 
Transfer function and mathematical modeling
Transfer  function  and  mathematical  modelingTransfer  function  and  mathematical  modeling
Transfer function and mathematical modeling
 
armature Winding
armature Windingarmature Winding
armature Winding
 
Switching regulators
Switching regulatorsSwitching regulators
Switching regulators
 
Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chart
 
Rectifier
RectifierRectifier
Rectifier
 
Protection against overvoltage
Protection against overvoltageProtection against overvoltage
Protection against overvoltage
 
Pantograph,catenary wire,smothing reactor
Pantograph,catenary wire,smothing reactorPantograph,catenary wire,smothing reactor
Pantograph,catenary wire,smothing reactor
 
On load tap changer in a.c. locomotive transformer & air blast circuit b...
On load tap changer in a.c. locomotive transformer  & air blast circuit b...On load tap changer in a.c. locomotive transformer  & air blast circuit b...
On load tap changer in a.c. locomotive transformer & air blast circuit b...
 
Logical instruction of 8085
Logical instruction of 8085Logical instruction of 8085
Logical instruction of 8085
 
Effect of non sinusoidal waveform of a.c. machine performance
Effect of non sinusoidal waveform of a.c. machine performanceEffect of non sinusoidal waveform of a.c. machine performance
Effect of non sinusoidal waveform of a.c. machine performance
 
Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...Disadvantages of corona, radio interference, inductive interference between p...
Disadvantages of corona, radio interference, inductive interference between p...
 
Design, Planning and Layout of high voltage laboratory
Design, Planning and Layout of high voltage laboratory Design, Planning and Layout of high voltage laboratory
Design, Planning and Layout of high voltage laboratory
 

Recently uploaded

J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 

Recently uploaded (20)

J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 

hydro power plant

  • 1. “HYDRO POWER PLANT”  PREPARED BY : DISHANT PATEL 140123109009 VISHAL GOHEL 140123109003 JAY PANCHAL 140123109007 MANTHAN PANCHAL 140123109008 GUIDED BY : Prof. Rahil Parikh
  • 2. CONTENTS: Introduction Site selection Schematic diagram Working Elements of HPS Classification of HPS Types of turbine Advantages & Disadvantages Comparison Power plant in gujarat
  • 3. INTRODUCTION  In Hydro Power Plant the water is utilized to move the turbines which in turn run the electric generator’s.  The Potential energy of the water stored in the dam gets converted into the Kinetic Energy of the moving water in the penstock. And this Kinetic Energy gets converted into the Electrical Energy with the help of Turbine & Generator combination.  Hydro Power Plant was invented by H.F. Rogers.  Hydro power = WQH × n × 9.81 watts
  • 4. SITE SELECTION 1. Availability of water – All other designs are based on it. – Estimate should be made about the average quantity of water available throughout the year and also about maximum and minimum quantity of water available during the year. – These details are necessary to decide the capacity of the hydropower plant, and – It also provide adequate spillways or gate relief during flood period.
  • 5. 2. Water storage – Since there a is wide variation in rainfall during the year, therefore it is necessary to store the water for continuous generation of power. The storage capacity can be calculated with the help of mass curve. – The two types of storages in use are 1. The storage is so constructed that it can make water available for power generation for one year only. 2. Water is available in sufficient quantity even during the worst dry periods.
  • 6. 3. Water head – In order to generate a requisite quantity of power it is necessary that a large quantity of water at sufficient head should be available. – An increase in effective head for a given output, reduces the quantity of water required to be supplied to the turbines. 4. Accessibility of site – The site where hydro-electric plant is to be constructed should be easy accessible. This is important if the electric power generated is to be utilized at or near the plant site. – The site selected should have transportation facilities of rail and road.
  • 7. 5. Distance from the load centre – Power plant should be set up near the load centre, this will reduce the cost of maintenance of transmission line. 6. Type of the land of the site – The land to be selected for the site should be cheap and rocky. – The ideal site will be one where the dam will have largest catchment area to store water at high head and will be economical in construction.
  • 8.
  • 10. WORKING  Initially the water of the river is in Catchments Area.  From catchments area the water flows to the dam.  At the dam the water gets accumulated . Thus the potential energy of the water increases due to the height of the dam .  When the gates of the dam are opened then the water moves with high Kinetic Energy into the penstock.  Through the penstock water goes to the turbine house.  Since the penstock makes water to flow from high altitude to low altitude, Thus the Kinetic Energy of the water is again raised.
  • 11. In the turbine house the pressure of the water is controlled by the controlling valves as per the requirements.  The controlled pressurized water is fed to the turbine.  Due to the pressure of the water the light weight turbine rotates.  Due to the high speed rotation of the turbine the shaft connected between the turbine and the generator rotates .  Due to the rotation of generator the ac current is produced.  This current is supplied to the powerhouse .  From powerhouse it is supplied for the commercial purposes.
  • 12. ELEMENTS OF HPS 1. CATCHMENT AREA : 2. RESERVOIR : 3. DAM : The whole area behind the clam training into a stream as river across which the dam has been built at suitable place is called catchments area. A reservoir is employed to store water which is further utilized to generate power by running the hydroelectric turbines.  A dam is a barrier which confines or raise water for storage or diversion to create a hydraulic head.  Dam’s are generally made of concrete, Stone masonary, Rock fill or Timber.
  • 13. 4. SPILWAYS : 5. SURGE TANK : 6. PENSTOCKS :  Spill Way’s is a kind of canal provided besides the dam.  Spill Way’s is used to arrange the excess of accumulation of water on the dam because excess accumulation of water may damage the dam structure.  Penstock is the connecting pipe between the dam & the turbine house.  It helps to increase the kinetic energy of the water coming from the dam.  Penstock is made up of a very strong material which can sustain the high pressure of water.  Surge tank is used to absorb the fluctuation in pressure caused due to changing demand of water quantity.
  • 14. 7. POWER HOUSE :  The power house is a building in which the turbines, alternator and other auxiliary are housed. 8.TAIL RACE :  Tail race is a passage for discharging the water leaving the turbines, into the river. 9.SWICH YARD FOR TRANSMISSION OF POWER :  The electrical equipment of a hydro-electric power station includes like transformer, circuit breaker & other switching & protective devices.
  • 15. CLASSIFICATION OF HPS 1. LOW HEAD PLANTS :
  • 16. Low head hydro power applications use river current or tidal flows of 60 meters or less to produce energy. These applications do not need to dam or retain water to create hydraulic head, the head is only a few meters. Using the current of a river or the naturally occurring tidal flow to create electricity may provide a renewable energy source that will have a minimal impact on the environment.
  • 17. • MEDIUM HEAD PLANT : A power station operating under heads from 60m to 300m.
  • 18. 3. HIGH HEAD PLANTS : A power station operating under heads above about 300m. A head of 200m/250m is considered as the limit between medium and high head power stations. Figure- high head hydropower plant
  • 19. 1. Impulse Turbine TYPES OF HYDRAULIC TURBINE
  • 20.  Impulse turbine : One in which all the energy of water is converted to kinetic energy before the water strikes the vanes of the runner wheel.  This is done by passing the flow through nozzle or some guidelines.  The runner is rotated by the force of water and water passes over the wheel at atmospheric pressure.
  • 21. 2. Reaction Turbine : Here, water entering the runner wheel of the turbine has both kinetic energy and pressure energy that is total head of water striking the runner wheel ,consist partly of pressure head. E.g.- Francis turbine, Kaplan turbine
  • 22. ADANTAGES OF HYDRO POWER PLANT:  No fuel charges,  Running cost almost nil,  No stand by losses,  Highly reliable,  Efficiency does not decrease with time,  Construction and operation wise very simple,  Maintenance cost very less,  Starts quickly and synchronizes fast,  Minimum staff when plant is operational,  No ash problems thus pollution free, Also useful in flood control and irrigation and drinking water purpose,  Comparatively quiet long life.
  • 23. DISADVANTAGES OF HYDRO POWER PLANT:  Higher initial cost,  Takes long time of erection,  Plants are setup at distant places so transmission losses increases,  Totally dependent on the availability of water,  Larger area required,  Period of installation time is high,
  • 24. COMPARISON OF HYDRO,THERMAL & NULCEAR POWER PLANT:
  • 25. HYDROELECTRIC POWER PLANTS IN GUJARAT STATE NAME OF POWER PLANT LOCATION RIVER CAPACITY (MW) GUJARAT SARDAR SAROVAR DAM NARMADA 1450 UKAI TAPI 305 KADANA MAHI 242
  • 26. REFRENCES :  Dr. D.M.Patel  Wikipedia