MAYA INSTITUTE OF TECHNOLOGY AND
MANAGEMENT SELAQUI, DEHRADUN
PREPARED BY:
RAM SUNDAR SINGH
120710104032
MECHANICAL ENGG.
1. INRTODUCTION
2. LOCATION AND HISTORY
3. ESSENTIAL ELEMENTS
4. WORKING PRINCIPAL
5. ADVANTAGE & DISADVNTAGE
In Hydro Power Plant the water is utilized to move the
turbines which in turn run the electric generator’s.
The Potential energy of the water stored in the dam
gets converted into the Kinetic Energy of the moving
water in the penstock. And this Kinetic Energy gets
converted into the Electrical Energy with the help of
Turbine & Generator (T-G) combination.
I have done my vocational summer training from
kulekhani hydro power plant. The kulekhani Hydro-
electric power station is situated in lower Mahabarat
range of Makawanpur distric , Central region of
nepal.
In 1963 a preliminary design report on the kulekhani
hydel project is prepared by a japanese team to develop
112 KW to utilize a potential head of more than 1000m .
1st Unit was commissioned in 14th may 1982 and the
project was completed in 4th December of the same
year with project total cost of US$ 117.843.
PRIMARY ELEMENT’S
CATCHMENTS AREA
RESERVOIR
DAM
PRIME MOVERS
DRAFT TUBES
PENSTOKE & OTHER EQUIPMENT
SAFETY DEVICE’S
SPILL WAY’S
SURGE TANK
TRASH RACK
The catchment area of a hydro plant is the
whole area behind the dam, draining into a stream or
river across which the dam has been built at a suitable
place.
catchment area of kulekhani is 126 sq.km.
A reservoir is employed to store water which is
further utilized to generate power by running the
hydroelectric turbines.
The reservoir area of kulekhani plant is 2.2
sq.km at highest water Level 1530 m .
A dam is a barrier which confines or raise water for
storage or diversion to create a hydraulic head.
Dam’s are generally made of concrete, Stone masory,
Rockfill or Timber .
Turbine & Generator is the most important part of any
power plant.
Turbine :
a machine for producing continuous power in which a
wheel or rotor, typically fitted with vanes, is made to
revolve by a fast-moving flow of water is called
turbine. It converts the K.E. of water into mechanical
energy.
Generator is a machine in which when there is
rotation of coil between the strong Magnetic Field
then it produces an Alternating Current.
It is a machine for converting mechanical energy
into electricity.
The draft tube is a conduit which connects the runner
exit to the tail race where the water is being finally
discharged from the turbine.
. It serves in following purpose’s :
1. It allows the turbine to be set above tail water level
without loss of head, to facilitate inspection and
maintenance.
2. It regains by diffuser action , the major portion of the
kinetic energy delivered to it from the runner.
3. It increases the output power.
4. It increases the efficiency of Hydro Power Plant.
Penstock is an enclosed pipe that connect between the
dam & the turbine house.
It helps to increase the kinetic energy of the water
coming from the dam.
Penstock is made up of a very strong material which
can sustain the high pressure of water
Some more components are required for the
proper, user friendly & smooth functioning of the
power plant. These components are as follow:
VALVE :- This the instrument which is used to
control the pressure of flow of water .
PUMPS :- This device is used to send water or
any fluid from lower potential to higher potential.
A spillway is a structure used to provide the
controlled release of flows from a dam or levee into
a downstream area, typically being the river that
was dammed.
Spillways is used to arrange the excess of
accumulation of water on the dam because excess
accumulation of water may damage the dam
structure
A surge tank is a standpipe or storage reservoir at the
downstream end of dam or barrage pipe to absorb sudden rises
of pressure, as well as to quickly provide extra water during a
brief drop in pressure.
When there is a sudden close or decrease in pressure due to
control valve then there is a back flow of water. This creates a
high pressure zone in the penstock due to which it may burst .
This effect is known as WATER HAMMERING EFFECT .
To avoid this a tank is attached to the penstock which stores
water in it . This tank is called as Surge Tank.
A trash rack is a wooden or metal structure,
frequently supported by masonry, that prevents water-
borne debris (such as logs, boats, animals, masses of
cut waterweed, etc.) from entering the intake of
a water.
This protects waterwheels, penstocks, and sluice gates
from destruction during floods.
No fuel charges.
Less supervising staff is required.
Maintenance & operation charges are very low.
Running cost of the plant is low.
No fuel transportation is required.
No ash & flue gas problem & does not pollute the
atmosphere.
These plants are used for flood control & irrigation purpose.
Long life in comparison with the Thermal & Nuclear Power
Plant
The initial cost of the power plant is very high.
Takes long time for construction of the dam.
Generally, Such plant’s are located in hilly area’s far away
from load center & thus they require long transmission lines &
losses in them will be more.
Power generation by hydro power plant is only dependant
on natural phenomenon of rain .Therefore at the time of
drought or summer session the Hydro Power Plant will not
work.
Thank you

seminar on hydropower presentation

  • 1.
    MAYA INSTITUTE OFTECHNOLOGY AND MANAGEMENT SELAQUI, DEHRADUN PREPARED BY: RAM SUNDAR SINGH 120710104032 MECHANICAL ENGG.
  • 2.
    1. INRTODUCTION 2. LOCATIONAND HISTORY 3. ESSENTIAL ELEMENTS 4. WORKING PRINCIPAL 5. ADVANTAGE & DISADVNTAGE
  • 3.
    In Hydro PowerPlant the water is utilized to move the turbines which in turn run the electric generator’s. The Potential energy of the water stored in the dam gets converted into the Kinetic Energy of the moving water in the penstock. And this Kinetic Energy gets converted into the Electrical Energy with the help of Turbine & Generator (T-G) combination.
  • 5.
    I have donemy vocational summer training from kulekhani hydro power plant. The kulekhani Hydro- electric power station is situated in lower Mahabarat range of Makawanpur distric , Central region of nepal. In 1963 a preliminary design report on the kulekhani hydel project is prepared by a japanese team to develop 112 KW to utilize a potential head of more than 1000m . 1st Unit was commissioned in 14th may 1982 and the project was completed in 4th December of the same year with project total cost of US$ 117.843.
  • 6.
    PRIMARY ELEMENT’S CATCHMENTS AREA RESERVOIR DAM PRIMEMOVERS DRAFT TUBES PENSTOKE & OTHER EQUIPMENT SAFETY DEVICE’S SPILL WAY’S SURGE TANK TRASH RACK
  • 7.
    The catchment areaof a hydro plant is the whole area behind the dam, draining into a stream or river across which the dam has been built at a suitable place. catchment area of kulekhani is 126 sq.km.
  • 8.
    A reservoir isemployed to store water which is further utilized to generate power by running the hydroelectric turbines. The reservoir area of kulekhani plant is 2.2 sq.km at highest water Level 1530 m .
  • 9.
    A dam isa barrier which confines or raise water for storage or diversion to create a hydraulic head. Dam’s are generally made of concrete, Stone masory, Rockfill or Timber .
  • 10.
    Turbine & Generatoris the most important part of any power plant. Turbine : a machine for producing continuous power in which a wheel or rotor, typically fitted with vanes, is made to revolve by a fast-moving flow of water is called turbine. It converts the K.E. of water into mechanical energy.
  • 11.
    Generator is amachine in which when there is rotation of coil between the strong Magnetic Field then it produces an Alternating Current. It is a machine for converting mechanical energy into electricity.
  • 13.
    The draft tubeis a conduit which connects the runner exit to the tail race where the water is being finally discharged from the turbine. . It serves in following purpose’s : 1. It allows the turbine to be set above tail water level without loss of head, to facilitate inspection and maintenance. 2. It regains by diffuser action , the major portion of the kinetic energy delivered to it from the runner. 3. It increases the output power. 4. It increases the efficiency of Hydro Power Plant.
  • 14.
    Penstock is anenclosed pipe that connect between the dam & the turbine house. It helps to increase the kinetic energy of the water coming from the dam. Penstock is made up of a very strong material which can sustain the high pressure of water
  • 15.
    Some more componentsare required for the proper, user friendly & smooth functioning of the power plant. These components are as follow: VALVE :- This the instrument which is used to control the pressure of flow of water . PUMPS :- This device is used to send water or any fluid from lower potential to higher potential.
  • 16.
    A spillway isa structure used to provide the controlled release of flows from a dam or levee into a downstream area, typically being the river that was dammed. Spillways is used to arrange the excess of accumulation of water on the dam because excess accumulation of water may damage the dam structure
  • 17.
    A surge tankis a standpipe or storage reservoir at the downstream end of dam or barrage pipe to absorb sudden rises of pressure, as well as to quickly provide extra water during a brief drop in pressure. When there is a sudden close or decrease in pressure due to control valve then there is a back flow of water. This creates a high pressure zone in the penstock due to which it may burst . This effect is known as WATER HAMMERING EFFECT . To avoid this a tank is attached to the penstock which stores water in it . This tank is called as Surge Tank.
  • 18.
    A trash rackis a wooden or metal structure, frequently supported by masonry, that prevents water- borne debris (such as logs, boats, animals, masses of cut waterweed, etc.) from entering the intake of a water. This protects waterwheels, penstocks, and sluice gates from destruction during floods.
  • 19.
    No fuel charges. Lesssupervising staff is required. Maintenance & operation charges are very low. Running cost of the plant is low. No fuel transportation is required. No ash & flue gas problem & does not pollute the atmosphere. These plants are used for flood control & irrigation purpose. Long life in comparison with the Thermal & Nuclear Power Plant
  • 20.
    The initial costof the power plant is very high. Takes long time for construction of the dam. Generally, Such plant’s are located in hilly area’s far away from load center & thus they require long transmission lines & losses in them will be more. Power generation by hydro power plant is only dependant on natural phenomenon of rain .Therefore at the time of drought or summer session the Hydro Power Plant will not work.
  • 21.

Editor's Notes

  • #5 Fig. block diagram of power plant