Critical Path Method
Critical Path Method
▪ Scheduling and Project Management tool developed in the 1950’s

▪ Allow us to plan all tasks which must be completed in a project
▪ Aids time scheduling and resource planning

▪ They allow progress towards project goals to be tracked
Using the Critical Path Method
▪ Some activities cannot be started until previous activities have been completed

▪ Activities in a critical path method need to be completed in sequence
▪ These activities are known as sequential activities
▪ In addition to these, other tasks can be completed at any time
▪ These activities are known as non-dependent or parallel tasks
Drawing a CPM Chart: Step 1

• This can be done using a Work Breakdown Structure
• For each task state:
• The earliest start date
•The estimated time it will take
Drawing a CPM Chart: Step 2

Establish sequence by looking at:
• Which tasks should take place before this task happens.
• Which tasks should be completed at the same time as this task.

• Which tasks should happen immediately after this task.
Drawing a CPM Chart: Step 3

▪ Each circle/node should show a task within the project;
▪ Each circle/node should give start and finish times;
▪ Each circle/node should be numbered;
▪ The arrows/arcs should the sequence of the tasks;
▪ A description and duration of the task should be written under the arrows;

▪ Arrows should always run left to right
Examples of Critical Path Method
Drawing a CPM Chart: Step 4
▪ Determining the four parameters of each task in the network
1.
2.
3.
4.

Earliest start time (ES) - The earliest time an activity can start once the previous dependent
activities are over.
Earliest finish time (EF) - ES + activity duration.
Latest finish time (LF) - The latest time an activity can finish without delaying the project.
Latest start time (LS) - LF - activity duration.

▪ The float time for an activity is the time between the earliest (ES) and the latest (LS)
start time or between the earliest (EF) and latest (LF) finish times.
▪ During the float time, an activity can be delayed without delaying the project finish
date.
▪ The activities in the critical path have an effect on the deadline of the project.
▪ If an activity of this path is delayed, the project will be delayed.
Benefits of the Critical Path Method
▪ Visual representation
▪ The project plan can be tested to ensure it is well thought out

▪ It identifies key tasks which could cause delays to the project if not completed
on time
▪ It identifies tasks which could be delayed in order to complete other tasks which
are more time crucial

▪ It identifies the minimum amount of time a project will take to complete
▪ It identifies any project steps which can be completed faster in order to
complete the project on time
Disadvantages of Critical Path Method

▪ Can be more difficult to understand than Gantt Charts
▪ The time needed for tasks is not as clear as with Gantt Charts
More Information on Critical Path Method
This is a useful video which sums the information given in the slides and
will aid understanding of the critical path method

http://www.youtube.com/watch?v=SF53ZZsP4ik
Further Reading
▪ Kelley, J. E. (1963). The critical-path method: Resources planning and
scheduling. Industrial scheduling, 347-365.
▪ Leach, L. P. (1999). Critical chain project management improves
project performance. Project Management Journal, 30, 39-51.
▪ Maylor, Project Management. Chapter 7
References
▪ Maylor, H., 2010. Project Management. 4th Ed. Chester: Pearson.

▪ MindTools, 2013. Critical Path Analysis and PERT Charts. [Online] Available at:
http://www.mindtools.com/critpath.html [Accessed on 07/11/13]
▪ Margaret Rouse, 2011. Critical Path Method (CPM). [Online] Available at:
http://whatis.techtarget.com/definition/critical-path-method-CPM [Accessed
on 07/11/13]
▪ Tutorialspoint, 2013. Critical Path Method. [Online] Available at:
http://www.tutorialspoint.com/management_concepts/critical_path_method.h
tm [Accessed on 07/11/13]

Critical path method

  • 1.
  • 2.
    Critical Path Method ▪Scheduling and Project Management tool developed in the 1950’s ▪ Allow us to plan all tasks which must be completed in a project ▪ Aids time scheduling and resource planning ▪ They allow progress towards project goals to be tracked
  • 3.
    Using the CriticalPath Method ▪ Some activities cannot be started until previous activities have been completed ▪ Activities in a critical path method need to be completed in sequence ▪ These activities are known as sequential activities ▪ In addition to these, other tasks can be completed at any time ▪ These activities are known as non-dependent or parallel tasks
  • 4.
    Drawing a CPMChart: Step 1 • This can be done using a Work Breakdown Structure • For each task state: • The earliest start date •The estimated time it will take
  • 5.
    Drawing a CPMChart: Step 2 Establish sequence by looking at: • Which tasks should take place before this task happens. • Which tasks should be completed at the same time as this task. • Which tasks should happen immediately after this task.
  • 6.
    Drawing a CPMChart: Step 3 ▪ Each circle/node should show a task within the project; ▪ Each circle/node should give start and finish times; ▪ Each circle/node should be numbered; ▪ The arrows/arcs should the sequence of the tasks; ▪ A description and duration of the task should be written under the arrows; ▪ Arrows should always run left to right
  • 7.
  • 8.
    Drawing a CPMChart: Step 4 ▪ Determining the four parameters of each task in the network 1. 2. 3. 4. Earliest start time (ES) - The earliest time an activity can start once the previous dependent activities are over. Earliest finish time (EF) - ES + activity duration. Latest finish time (LF) - The latest time an activity can finish without delaying the project. Latest start time (LS) - LF - activity duration. ▪ The float time for an activity is the time between the earliest (ES) and the latest (LS) start time or between the earliest (EF) and latest (LF) finish times. ▪ During the float time, an activity can be delayed without delaying the project finish date. ▪ The activities in the critical path have an effect on the deadline of the project. ▪ If an activity of this path is delayed, the project will be delayed.
  • 9.
    Benefits of theCritical Path Method ▪ Visual representation ▪ The project plan can be tested to ensure it is well thought out ▪ It identifies key tasks which could cause delays to the project if not completed on time ▪ It identifies tasks which could be delayed in order to complete other tasks which are more time crucial ▪ It identifies the minimum amount of time a project will take to complete ▪ It identifies any project steps which can be completed faster in order to complete the project on time
  • 10.
    Disadvantages of CriticalPath Method ▪ Can be more difficult to understand than Gantt Charts ▪ The time needed for tasks is not as clear as with Gantt Charts
  • 11.
    More Information onCritical Path Method This is a useful video which sums the information given in the slides and will aid understanding of the critical path method http://www.youtube.com/watch?v=SF53ZZsP4ik
  • 12.
    Further Reading ▪ Kelley,J. E. (1963). The critical-path method: Resources planning and scheduling. Industrial scheduling, 347-365. ▪ Leach, L. P. (1999). Critical chain project management improves project performance. Project Management Journal, 30, 39-51. ▪ Maylor, Project Management. Chapter 7
  • 13.
    References ▪ Maylor, H.,2010. Project Management. 4th Ed. Chester: Pearson. ▪ MindTools, 2013. Critical Path Analysis and PERT Charts. [Online] Available at: http://www.mindtools.com/critpath.html [Accessed on 07/11/13] ▪ Margaret Rouse, 2011. Critical Path Method (CPM). [Online] Available at: http://whatis.techtarget.com/definition/critical-path-method-CPM [Accessed on 07/11/13] ▪ Tutorialspoint, 2013. Critical Path Method. [Online] Available at: http://www.tutorialspoint.com/management_concepts/critical_path_method.h tm [Accessed on 07/11/13]