PROJECT
monitoring and
control
2
Project Monitoring and Control
Monitoring Controlling
uses data from monitor activity
to bring actual performance to
planned performance
collecting, recording, and reporting
information concerning project
performance that project manger
and others wish to know
3
What do we monitor?
Men (human resources)
Machines
Materials
Money
Space
Time
Tasks
Quality/Technical Performance
4
What do we monitor?
Quality/Technical Performance
Time
Money
Resources
Material Usage
Tasks
Progress
Costs
Job starts
Job completion
Engineering / Design changes
Variation order (VO)
INPUT OUTPUT
5
Work Needed
End of the project
Continuously
Regularly
Logically
As soon as possible
At task completion
pre-planned decision points
6
Project Control
Control
process and activities needed to correct deviations from plan
Control the triple constraints
time (schedule)
cost (budget, expenses, etc)
performance (specifications, testing results, etc.)
7
Techniques for monitoring and control
Earned Value Analysis
Critical Ratio
8
Techniques for monitoring and control
Critical Ratio
9
• Cost (spending) variance (CV)
• – difference between budgeted cost of work performed (earned value)
(BCWP) and actual cost of that work (ACWP)
• Schedule variance (SV)
• – difference between earned value (BCWP) and cost of work we
scheduled to perform to date (BCWS)
• Time variance (TV)
• –difference between time scheduled for work performed (STWP) and
actual time to perform it (ATWP)
Earned Value Analysis - Variances
10
6 Possibilities Earned Value Analysis
11
•Need proper project monitoring and control
mechanisms
•Tools available to help in monitoring and
controlling activities
•There are human control and management
aspects not covered here
Summary
Thank
13

project monitoring and control

  • 1.
  • 2.
    2 Project Monitoring andControl Monitoring Controlling uses data from monitor activity to bring actual performance to planned performance collecting, recording, and reporting information concerning project performance that project manger and others wish to know
  • 3.
    3 What do wemonitor? Men (human resources) Machines Materials Money Space Time Tasks Quality/Technical Performance
  • 4.
    4 What do wemonitor? Quality/Technical Performance Time Money Resources Material Usage Tasks Progress Costs Job starts Job completion Engineering / Design changes Variation order (VO) INPUT OUTPUT
  • 5.
    5 Work Needed End ofthe project Continuously Regularly Logically As soon as possible At task completion pre-planned decision points
  • 6.
    6 Project Control Control process andactivities needed to correct deviations from plan Control the triple constraints time (schedule) cost (budget, expenses, etc) performance (specifications, testing results, etc.)
  • 7.
    7 Techniques for monitoringand control Earned Value Analysis Critical Ratio
  • 8.
    8 Techniques for monitoringand control Critical Ratio
  • 9.
    9 • Cost (spending)variance (CV) • – difference between budgeted cost of work performed (earned value) (BCWP) and actual cost of that work (ACWP) • Schedule variance (SV) • – difference between earned value (BCWP) and cost of work we scheduled to perform to date (BCWS) • Time variance (TV) • –difference between time scheduled for work performed (STWP) and actual time to perform it (ATWP) Earned Value Analysis - Variances
  • 10.
  • 11.
    11 •Need proper projectmonitoring and control mechanisms •Tools available to help in monitoring and controlling activities •There are human control and management aspects not covered here Summary