This document discusses the process of updating a project network diagram based on actual project progress and changes. It provides definitions and explanations of updating, describes the data and steps required for the updating process, and gives an illustrative example of updating the network for a project after 12 days where some activities finished earlier than planned while others were delayed. The example network is updated by assigning completion times, remaining durations and revised estimates based on new information, and recalculating the critical path.