SlideShare a Scribd company logo
Critical Path Method
(CPM)
Educator - Ms. Manmeet Kaur
Overview of lecture
O Introduction to CPM - Critical Path
Method
O Steps to use Critical Path Method
O CPM - Advantages
O CPM - Disadvantages
Introduction
O CPM stands for Critical Path Method.
O CPM is a project schedule modeling technique
developed by Mr. Morgan R. Walker and James E.
Kelly in the late 1950s.
O CPM is based on the estimation of the standard time
needed for execution of a activity.
O CPM manages the both time and cost of the project.
Introduction
O In this method, the critical path of the project is
established by identifying the critical activities of the
project.
O Critical activities are the activities whose total float value
is ‘0’.
O The Critical Path is the longest sequence of activities in a
project plan which must be completed on time for the
project to complete on due date.
O CPM is commonly used in conjunction with the Program
Evaluation and Review Technique (PERT).
How to Use the Critical Path
Method?
Step 1
Identify activities based on WBS
O The WBS (Work Breakdown Structure), describes
deliverables, not activities. This is why all its components
are described using nouns or adjectives, not verbs.
O The CPM, however, focuses on activities described using
verbs.
O The first step of the CPM process, therefore, is to list all
the activities required to create deliverables at each level
of the WBS.
Step 1
Identify activities based on WBS
Figure- a
O This list of
activities as in
figure-a , will
form the
foundation of the
CPM
Step 2
Identify all dependencies
O Any project has two types of tasks.
O Tasks that depend on other tasks for their completion, i.e.
dependent tasks
O Tasks that are independent of others and can be done in
parallel to others, i.e. concurrent tasks
O The next step in the CPM process is to establish which of the
tasks are dependent and which are concurrent
Step 2
Identify all dependencies
O Go through the list of activities and identify which tasks each
depends on, and in what order, as follow:
O A list of dependent tasks is called an activity sequence.
These are used to figure out the critical path
Step 3
Create a network diagram
O Once you’ve identified all tasks and their dependencies, it’s
time to create a network diagram, also known as a critical
path analysis chart.
O This chart visualizes separate activity sequences and enables
you to map dependencies easily.
O To create it, make a list of all activity sequences.
O Create separate boxes for each task in the sequence.
Step 3
Create a network diagram
O Next, use arrows to identify dependencies between tasks
in each sequence, as follow:
Step 4
Estimate duration of each activity
O We first need to estimate the duration of each activity. The
activity sequence that takes the longest time would then be our
critical path.
O List the duration (t) of each activity next to its name in the
network diagram.
Step 4
Estimate duration of each activity
Step 5
Calculate the Critical Path
O In the network diagram, write down the start and end time of
each activity next to its box.
O The first activity in the sequence would have a start time
of ‘0’. Mark the Start Time to the left and End time to the right
of the first activity. (Usually, this would be 0). Its end-time would
be its duration.
O The second activity’s start time would be the end-time of the
first activity. Its end-time would be the start time + the duration.
Step 5
Calculate the Critical Path
O In this way now mark the Earliest Start (ES) time of each
activity. This is given by the largest number to the right of the
activity's immediate predecessor (i.e. its Earliest Finish time, or
EF).
O If the activity has two predecessors, the one with the later
EF time would give you the ES of the activity.
Step 5
Calculate the Critical Path
Finally
O The activity sequence with the longest duration would be your
critical path as shown below:
CPM - Advantages
O CPM shows a graphical view of the project.
O CPM helps the project manager in identifying the most
critical elements of the project.
O CPM provides demonstration of dependencies which helps
in the scheduling of individual activities
O CPM aids in project planning, scheduling, and controlling.
CPM - Disadvantages
O For bigger projects, CPM networks can be too
complicated.
O CPM also does not handle the scheduling of the resource
allocation.
O CPM does not consider resource dependencies.
O There is a chance of misusing float or slack in CPM
method.
Thanks
Queries are welcome

More Related Content

What's hot

Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
DagnaygebawGoshme
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
Ragjni Govindaraju
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
DavidMcLachlan1
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
student
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
Mubashir Ali
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Prasad Thanthratey
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
Shashank Kapoor
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
PERT
PERTPERT
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
Sachin Kapoor
 

What's hot (20)

Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
PERT
PERTPERT
PERT
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 

Similar to CPM - Critical Path Method

PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
IrfanPathan88
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pertBhim Upadhyaya
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
Amit Kumbar
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
SHAZEBALIKHAN1
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
IrtizaMalik
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
Salahudin Babar
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
annettsparrow
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
Sougata Das
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
NegeseTeklearegay
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
Syed Hamza
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
PadamNepal1
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
AbdisalamMohamud5
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
DrAsifMohammad
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysispopik25
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
ahsanrabbani
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 

Similar to CPM - Critical Path Method (20)

PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
Critical path method & pert
Critical path method & pertCritical path method & pert
Critical path method & pert
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
pert/cpm
pert/cpmpert/cpm
pert/cpm
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 

Recently uploaded

Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 

Recently uploaded (20)

Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 

CPM - Critical Path Method

  • 2. Overview of lecture O Introduction to CPM - Critical Path Method O Steps to use Critical Path Method O CPM - Advantages O CPM - Disadvantages
  • 3. Introduction O CPM stands for Critical Path Method. O CPM is a project schedule modeling technique developed by Mr. Morgan R. Walker and James E. Kelly in the late 1950s. O CPM is based on the estimation of the standard time needed for execution of a activity. O CPM manages the both time and cost of the project.
  • 4. Introduction O In this method, the critical path of the project is established by identifying the critical activities of the project. O Critical activities are the activities whose total float value is ‘0’. O The Critical Path is the longest sequence of activities in a project plan which must be completed on time for the project to complete on due date. O CPM is commonly used in conjunction with the Program Evaluation and Review Technique (PERT).
  • 5. How to Use the Critical Path Method?
  • 6. Step 1 Identify activities based on WBS O The WBS (Work Breakdown Structure), describes deliverables, not activities. This is why all its components are described using nouns or adjectives, not verbs. O The CPM, however, focuses on activities described using verbs. O The first step of the CPM process, therefore, is to list all the activities required to create deliverables at each level of the WBS.
  • 7. Step 1 Identify activities based on WBS Figure- a O This list of activities as in figure-a , will form the foundation of the CPM
  • 8. Step 2 Identify all dependencies O Any project has two types of tasks. O Tasks that depend on other tasks for their completion, i.e. dependent tasks O Tasks that are independent of others and can be done in parallel to others, i.e. concurrent tasks O The next step in the CPM process is to establish which of the tasks are dependent and which are concurrent
  • 9. Step 2 Identify all dependencies O Go through the list of activities and identify which tasks each depends on, and in what order, as follow: O A list of dependent tasks is called an activity sequence. These are used to figure out the critical path
  • 10. Step 3 Create a network diagram O Once you’ve identified all tasks and their dependencies, it’s time to create a network diagram, also known as a critical path analysis chart. O This chart visualizes separate activity sequences and enables you to map dependencies easily. O To create it, make a list of all activity sequences. O Create separate boxes for each task in the sequence.
  • 11. Step 3 Create a network diagram O Next, use arrows to identify dependencies between tasks in each sequence, as follow:
  • 12. Step 4 Estimate duration of each activity O We first need to estimate the duration of each activity. The activity sequence that takes the longest time would then be our critical path. O List the duration (t) of each activity next to its name in the network diagram.
  • 13. Step 4 Estimate duration of each activity
  • 14. Step 5 Calculate the Critical Path O In the network diagram, write down the start and end time of each activity next to its box. O The first activity in the sequence would have a start time of ‘0’. Mark the Start Time to the left and End time to the right of the first activity. (Usually, this would be 0). Its end-time would be its duration. O The second activity’s start time would be the end-time of the first activity. Its end-time would be the start time + the duration.
  • 15. Step 5 Calculate the Critical Path O In this way now mark the Earliest Start (ES) time of each activity. This is given by the largest number to the right of the activity's immediate predecessor (i.e. its Earliest Finish time, or EF). O If the activity has two predecessors, the one with the later EF time would give you the ES of the activity.
  • 16. Step 5 Calculate the Critical Path
  • 17. Finally O The activity sequence with the longest duration would be your critical path as shown below:
  • 18. CPM - Advantages O CPM shows a graphical view of the project. O CPM helps the project manager in identifying the most critical elements of the project. O CPM provides demonstration of dependencies which helps in the scheduling of individual activities O CPM aids in project planning, scheduling, and controlling.
  • 19. CPM - Disadvantages O For bigger projects, CPM networks can be too complicated. O CPM also does not handle the scheduling of the resource allocation. O CPM does not consider resource dependencies. O There is a chance of misusing float or slack in CPM method.