Presented By:

Abhishek Pachisia

   B.Tech IT

   090102801
   Program Evaluation and Review Technique.

   Analyze the tasks.

   United States Navy.

   Event-oriented Technique

   Major Factor – Time

   Ex: 1968 Winter Olympics in Grenoble
   The main objective of PERT :
     To facilitate decision making and
     To reduce both the time and cost required to complete a
      project.

   Related Tools:
     Critical Path Method.
     Gantt chart

   Applied to:
     Very large-scale,
     One-time,
     Complex,
     Non-routine infrastructure and
     Research and Development projects
   Specific activities and milestones.

   Sequence of the activities.

   Network diagram.

   Estimate the time.

   Critical path.

   Update the PERT chart.




     Activities.


     Milestones.


     It is helpful to list the tasks in a table.



     May be combined with the activity identification
      step
        Since the activity sequence is evident for some tasks.


     Other tasks may require more analysis
        To determine the exact order in which they must be
         performed.


     Activity sequence information
        A network diagram can be drawn showing the sequence of
         the serial and parallel activities.
     Each activity represents: A node in the network,
     The arrows represent: The relation between
      activities.
     Software packages simplify this task
        By automatically converting tabular activity information into
         a network diagram.




     Weeks are a commonly used unit of time for activity
      completion.
     A distinguishing feature of PERT.
         Its ability to deal with uncertainty in activity completion time.

     Optimistic time(O)
         The shortest time in which the activity can be completed.
         To specify optimistic time to be three standards deviations from the
          mean.

     Most likely time(M)
         The completion time having the highest probability.
 Pessimistic time (P)
    the maximum possible time required to accomplish a task,
     assuming everything goes wrong (but excluding major
     catastrophes).

 PERT assumes a beta probability distribution for the
  time estimates.
 Estimated Time(TE)
    The best estimate of the time required to accomplish a task,
     accounting for the fact that things don't always proceed as
     normal.

          TE = (O + 4M + P) ÷ 6





     The critical path is
         Determined by adding the times for the activities in each sequence.
         Determining the longest path in the project.

     The critical path determines the total calendar time required
      for the project.
     If activities outside the critical path speed up or slow down
      (within limits), the total project time does not change.
     The amount of time that a non – critical path activity can be
      delayed without the project is referred to as a slack time.
 Critical Path is helpful to determine
     ES – Earliest Start time
     EF - Earliest Finish time
     LS – Latest Start time
     LF - Latest Finish time

 The variance in the project completion time can be
  calculated by summing the variances in the completion
  times of the activities in the critical path.
 The project can be accelerated by adding the resources
  required to decrease the time for the activities in the
  critical path.
 Shortening of the project sometimes is referred to as
  Project Crashing.


     Make adjustments in the PERT chart as the project
      progresses.
     As the project unfolds, the estimated times can be
      replaced with actual times.
     In cases where
        There are delays,
        Additional resources may be needed to stay on schedule
        The PERT chart may be modified to reflect the new
         situation.
   Explicitly defines and makes visible dependencies
    between the WBS elements

   Facilitates identification of the critical path.

   Facilitates identification of
     Start date,
     End date, and
     Slack time for each activity,

   Provides potentially reduced project duration.

   The large amount of project data can be organized &
    presented in diagram for use in decision making.
   Hundreds or thousands of activities and individual
    dependency relationships

   Not easily scalable for smaller projects

   The network charts tend to be large and unwieldy requiring
    several pages to print.

   The lack of a timeframe on most charts makes it harder to
    show status although colours can help

   When the charts become unwieldy, they are no longer used
    to manage the project.
   In this Case Study, the Project manager knows


     The succession of the project activities ,
     Optimistic Time,
     Pessimistic Time and
     Most Likely Time
    All the times known are in weeks.
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management
PERT Analysis Technique for Project Management

More Related Content

What's hot (20)

Critical path method
Critical path methodCritical path method
Critical path method
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Critical path method
Critical path methodCritical path method
Critical path method
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Programme evaluation review technique
Programme evaluation review techniqueProgramme evaluation review technique
Programme evaluation review technique
 
PERT
PERTPERT
PERT
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 

Viewers also liked

Operational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPMOperational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPMvckg1987
 
Production Management Introduction
Production Management IntroductionProduction Management Introduction
Production Management IntroductionDr. Gururaj Phatak
 
Numerical assignment
Numerical assignmentNumerical assignment
Numerical assignmentAnupam Kumar
 
Supervised Classification
Supervised ClassificationSupervised Classification
Supervised ClassificationChad Yowler
 
Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)Susan Aragon
 
Land cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, CaliforniaLand cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, CaliforniaLisa Jensen
 
Graphical Method
Graphical MethodGraphical Method
Graphical MethodSachin MK
 
Few Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model MakerFew Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model MakerSwetha A
 
Band Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesBand Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesKabir Uddin
 
Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009Fredy Neira
 
Introduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat imageIntroduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat imageKabir Uddin
 
Original SOINN
Original SOINNOriginal SOINN
Original SOINNSOINN Inc.
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical MethodJoseph Konnully
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 

Viewers also liked (19)

Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Operational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPMOperational research- main techniques PERT and CPM
Operational research- main techniques PERT and CPM
 
Production Management Introduction
Production Management IntroductionProduction Management Introduction
Production Management Introduction
 
Numerical assignment
Numerical assignmentNumerical assignment
Numerical assignment
 
Supervised Classification
Supervised ClassificationSupervised Classification
Supervised Classification
 
Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)Normalized Difference Vegetation Index (NDVI)
Normalized Difference Vegetation Index (NDVI)
 
Land cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, CaliforniaLand cover supervised classification at Toro Park, California
Land cover supervised classification at Toro Park, California
 
graphical method
graphical method graphical method
graphical method
 
Clustering
ClusteringClustering
Clustering
 
Graphical Method
Graphical MethodGraphical Method
Graphical Method
 
NDVI
NDVINDVI
NDVI
 
Few Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model MakerFew Indicies(NDVI... etc) performed on ERDAS software using Model Maker
Few Indicies(NDVI... etc) performed on ERDAS software using Model Maker
 
Band Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite ImagesBand Combination of Landsat 8 Earth-observing Satellite Images
Band Combination of Landsat 8 Earth-observing Satellite Images
 
Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009Presentacion elafis Brasil 2009
Presentacion elafis Brasil 2009
 
Introduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat imageIntroduce variable/ Indices using landsat image
Introduce variable/ Indices using landsat image
 
Original SOINN
Original SOINNOriginal SOINN
Original SOINN
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical Method
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 

Similar to PERT Analysis Technique for Project Management

Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartMathew Varghese V
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique) Tanoj Patidar
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review TechniqueSimonRobertson
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxmamtabisht10
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)AnkitaKadam20
 
Control techniques
Control techniquesControl techniques
Control techniquesAdnan Shakir
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review TechniqueDrAsifMohammad
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 

Similar to PERT Analysis Technique for Project Management (20)

or-pert
or-pertor-pert
or-pert
 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt Chart
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique)
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review Technique
 
Pert and gantt chart.pptx
Pert and gantt chart.pptxPert and gantt chart.pptx
Pert and gantt chart.pptx
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
 
Control techniques
Control techniquesControl techniques
Control techniques
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Pert n gantt
Pert n gantt Pert n gantt
Pert n gantt
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 

More from Abhishek Pachisia (20)

Telecom Industry
Telecom IndustryTelecom Industry
Telecom Industry
 
Strategic alignment model (SAM)
Strategic alignment model (SAM)Strategic alignment model (SAM)
Strategic alignment model (SAM)
 
V.G. siddhartha
V.G. siddharthaV.G. siddhartha
V.G. siddhartha
 
Boeing- The Frontiers
Boeing- The FrontiersBoeing- The Frontiers
Boeing- The Frontiers
 
Top Management of 5 recognized comapanies
Top Management of 5 recognized comapaniesTop Management of 5 recognized comapanies
Top Management of 5 recognized comapanies
 
Fourier transform
Fourier transformFourier transform
Fourier transform
 
Inference engine
Inference engineInference engine
Inference engine
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
IEEE 802.11
IEEE 802.11IEEE 802.11
IEEE 802.11
 
Cloud Service Models
Cloud Service ModelsCloud Service Models
Cloud Service Models
 
Exception handling in Java
Exception handling in JavaException handling in Java
Exception handling in Java
 
Perl
PerlPerl
Perl
 
Rpc
RpcRpc
Rpc
 
Hydrogen energy
Hydrogen energyHydrogen energy
Hydrogen energy
 
Rms titanic
Rms titanicRms titanic
Rms titanic
 
Vb.net (loop structure)
Vb.net (loop structure)Vb.net (loop structure)
Vb.net (loop structure)
 
Matrix Representation Of Graph
Matrix Representation Of GraphMatrix Representation Of Graph
Matrix Representation Of Graph
 
Tree
TreeTree
Tree
 
File System Implementation
File System ImplementationFile System Implementation
File System Implementation
 
Exception handling
Exception handlingException handling
Exception handling
 

Recently uploaded

How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 

Recently uploaded (20)

FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 

PERT Analysis Technique for Project Management

  • 1. Presented By: Abhishek Pachisia B.Tech IT 090102801
  • 2. Program Evaluation and Review Technique.  Analyze the tasks.  United States Navy.  Event-oriented Technique  Major Factor – Time  Ex: 1968 Winter Olympics in Grenoble
  • 3. The main objective of PERT :  To facilitate decision making and  To reduce both the time and cost required to complete a project.  Related Tools:  Critical Path Method.  Gantt chart  Applied to:  Very large-scale,  One-time,  Complex,  Non-routine infrastructure and  Research and Development projects
  • 4. Specific activities and milestones.  Sequence of the activities.  Network diagram.  Estimate the time.  Critical path.  Update the PERT chart.
  • 5.  Activities.  Milestones.  It is helpful to list the tasks in a table.
  • 6.  May be combined with the activity identification step  Since the activity sequence is evident for some tasks.  Other tasks may require more analysis  To determine the exact order in which they must be performed.
  • 7.  Activity sequence information  A network diagram can be drawn showing the sequence of the serial and parallel activities.  Each activity represents: A node in the network,  The arrows represent: The relation between activities.  Software packages simplify this task  By automatically converting tabular activity information into a network diagram.
  • 8.  Weeks are a commonly used unit of time for activity completion.  A distinguishing feature of PERT.  Its ability to deal with uncertainty in activity completion time.  Optimistic time(O)  The shortest time in which the activity can be completed.  To specify optimistic time to be three standards deviations from the mean.  Most likely time(M)  The completion time having the highest probability.
  • 9.  Pessimistic time (P)  the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).  PERT assumes a beta probability distribution for the time estimates.  Estimated Time(TE)  The best estimate of the time required to accomplish a task, accounting for the fact that things don't always proceed as normal. TE = (O + 4M + P) ÷ 6
  • 10.  The critical path is  Determined by adding the times for the activities in each sequence.  Determining the longest path in the project.  The critical path determines the total calendar time required for the project.  If activities outside the critical path speed up or slow down (within limits), the total project time does not change.  The amount of time that a non – critical path activity can be delayed without the project is referred to as a slack time.
  • 11.  Critical Path is helpful to determine  ES – Earliest Start time  EF - Earliest Finish time  LS – Latest Start time  LF - Latest Finish time  The variance in the project completion time can be calculated by summing the variances in the completion times of the activities in the critical path.  The project can be accelerated by adding the resources required to decrease the time for the activities in the critical path.  Shortening of the project sometimes is referred to as Project Crashing.
  • 12.  Make adjustments in the PERT chart as the project progresses.  As the project unfolds, the estimated times can be replaced with actual times.  In cases where  There are delays,  Additional resources may be needed to stay on schedule  The PERT chart may be modified to reflect the new situation.
  • 13. Explicitly defines and makes visible dependencies between the WBS elements  Facilitates identification of the critical path.  Facilitates identification of  Start date,  End date, and  Slack time for each activity,  Provides potentially reduced project duration.  The large amount of project data can be organized & presented in diagram for use in decision making.
  • 14. Hundreds or thousands of activities and individual dependency relationships  Not easily scalable for smaller projects  The network charts tend to be large and unwieldy requiring several pages to print.  The lack of a timeframe on most charts makes it harder to show status although colours can help  When the charts become unwieldy, they are no longer used to manage the project.
  • 15. In this Case Study, the Project manager knows  The succession of the project activities ,  Optimistic Time,  Pessimistic Time and  Most Likely Time All the times known are in weeks.

Editor's Notes

  1. -1-PERT was developed primarily to simplify the planning and scheduling of large and complex projects-3-First developed by the United States Navy in 1950s.-4-Event-oriented Technique rather than start- and completion-oriented.
  2. The critical path method (CPM) is an algorithm for scheduling a set of project activities.
  3. -1-Identify the specific activities and milestones.-2-Determine the proper sequence of the activities.-3-Construct a network diagram.-4-Estimate the time required for each activity.-5-Determine the critical path.-6-Update the PERT chart as the project progresses.
  4. -1-The activities are the tasks required to complete a project.-2-The milestones are the events marking the beginning and the end of one or more activities.-3-It is helpful to list the tasks in a table that in later steps can be expanded to include information on sequence and duration.
  5. -1-Weeks are a commonly used unit of time for activity completion, any consistent unit of time can be used.-3-2-So that there is a approximately a 1% chance that the activity will be completed within the optimistic time.-4-Note that this time is different from the expected time.
  6. The implication being thatthe expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time.
  7. -1-A work breakdown structure element may be a product, data, a service, or any combination-4-Better understanding of dependencies leading to improved overlapping of activities and tasks were feasible.