SlideShare a Scribd company logo
Introduction to
CPM
Guided: Ruchita shah
Presented By:
Kajal Vasar(115371)
Khushi Makwana(115372)
Mahesh Parmar(114352)
Dushyant Nasit(114339)
Project Management
 Managers have been planning, scheduling, monitoring,
and controlling large scale projects for hundred years, but
it has only been in the last 50 years that management
science techniques have been applied to major projects.
 They are two types:
1. Critical Path Method(CPM)
2. Project Evaluation and Review Technique(PERT)
Introduction- CPM
 Defination:-
Critical path is a sequence of activity between a project’s start and
finish that takes the longest time to complete.
 Critical path method is based on mathematical calculations and it is
used for scheduling project activities.
 In 1950, Critical path method(CPM) was developed by Kelly and
Walker to assist in building and maintains of chemical plants.
 The initial critical path method was used for managing plant
maintenance projects.
 Critical path is the sequential activities from start to
the end of a project. Although many projects have only
one critical path, some projects may have more than
one critical paths depending on the flow logic used in
the project
 The essential technique for using CPM is to construct a
model of the project that includes the following:
 A list of all activities required to complete the
project (typically categorized within a work
breakdown structure
 The time (duration) that each activity will take to
completion,
 The dependencies between the activities
.
Terminologies used in CPM
In order to explain the purpose, structure and operation of CPM, it is helpful to
define the following terms:
Activity:An activity carries the arrow symbol.This represent a task or
subproject that uses time or resources
Event:- A node (an event), denoted by a circle , marks the start and
completion of an activity, which contain a number that helps to identify its
location. For example activity A can be drawn as:
Dummy Activity: An activity, which is used to maintain the pre-defined
precedence relationship only during the construction of the project network, is
called a dummy activity. Dummy activity is represented by a dotted arrow and
does not consume any time and resource
21
A
 Parallel activity: There are two activity which being at same
event and end at same event.this activities are called parallel
activity.
Not allowed…..
 Path: A path is a series of adjacent activities leading from one
event to another.
 Critical path: A critical path is the sequence of critical activities
that forms a continuous path between the start of a project and
its completion.
1 2
Situations in network diagram
A
B
C
A must finish before either B or C
can start, it called burst event.
A
B
C both A and B must finish before C
can start, it called merge event.
Dangling events is not allow.
A
C
B
D
Dummy
A must finish before B can start
both A and C must finish before D
can start, it’s called dummy
activity.
A
B
C
Forward pass:
 The Early Start and Early Finish Time
Calculated by moving Forward Through the
Network.
 Consider Maximum.
Backward pass:
 The Latest Start and Latest Finish Time
Calculated by moving Backward Through the
Network.
 Consider Minimum
Float activity:
 Float activity For an Activity is The Difference
between its Earliest and Latest Start Time or
Earliest and Latest Finish Time .
Steps in Critical Path Method
 Step 1: Make a forward pass through the network as
follows: For each activity i beginning at the Start node,
compute:
Earliest Start Time (ES) = the maximum of the earliest finish times
of all activities immediately preceding activity i. (This is 0 for an
activity with no predecessors.). This is the earliest time an activity
can begin without violation of immediate predecessor requirements.
Earliest Finish Time (Ef) = (Earliest Start Time) + (Time to complete
activity i. This represent the earliest time at which an activity can
end.
The project completion time is the maximum of the
Earliest Finish Times at the Finish node.
Continue..........
 Step 2: Make a backwards pass through the network as follows:
Move sequentially backwards from the Finish node to the Start
node. At a given node, j, consider all activities ending at node j.
For each of these activities, (i,j), compute:
Latest Finish Time (LF) = the minimum of the latest start
times beginning at node j. (For node N, this is the project
completion time.). This is the latest time an activity can end
without delaying the entire project.
Latest Start Time (LS) = (Latest Finish Time) - (Time to
complete activity (i,j)). This is the latest time an activity can
begin without delaying the entire project.
Continue..........
 Step 3: Calculate the float time for each activity
by:
float = (Latest Start) - (Earliest Start),
or
= (Latest Finish)-(EarliesFinish).
A critical path is a path of activities, from the
Start node to the Finish node, with 0 float times.
Example
1. Construct the CPM Network using the details below and
determine the critical path
Activity Immediate Completion
predecessors Time (week)
A - 2
B A 3
C A 3
D C 4
E D 8
F B,E 6
G F 2
Total …… 28
1
2
765
43
0
0 25
25
23
23
9
9
17
17
5
5
2
2
A(2) B(3)
D(4)
C(3)
E(8
)
F(6) G(2)
Activity Tme Earliest
Start
(ES)
Earliest
Finish
(EF)
Latest
Start
(LS)
Latest
finish
(LF)
Slack
(LS-ES)
Critical
path
A 2 0 2 0 2 0 Yes
B 3 2 5 14 17 12 No
C 3 2 5 2 5 0 Yes
D 4 5 9 5 9 0 Yes
E 8 9 17 9 17 0 Yes
F 6 17 23 17 23 0 Yes
G 2 23 25 23 25 0 Yes
1
2
765
43
0
0 25
25
23
23
9
9
17
17
5
5
2
2
A(2) B(3)
D(4)
C(3)
E(8
)
F(6) G(2)
Critical Path:-
Cp = 1 - 2 – 3 - 4 – 5 – 6 – 7
= A – C -D - E - F - G
= 2 + 3 + 4 + 8 + 6 + 2
= 25
Benefits of CPM
 Useful at many stages of project management
 Mathematically simple
 Give critical path and float time
 Provide project documentation
 Useful in monitoring costs
 Visual representation
Limitations to CPM
 Specified precedence relationship
 Activity time estimates are subjective and
depend on judgment
 Can be more difficult understand ten grant
charts
 The time needed for tasks is not as clear as with
grant charts

More Related Content

What's hot

Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
hoang tung
 
Network analysis
Network analysisNetwork analysis
Network analysis
Mohit Mahajan
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
Ragjni Govindaraju
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Pulchowk Campus
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
Institute of Rural Management
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Prasad Thanthratey
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
chandkec
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
student
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Project life cycle
Project life cycleProject life cycle
Project life cycle
Jennifer Banzon
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
Ishan Gandhi
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
Munaf Dayee
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
Jeff Hilton
 
Pert analysis
Pert analysisPert analysis
Pert analysis
Hashamuddin Yaakob
 

What's hot (20)

Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 

Viewers also liked

Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
El Moro
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
Nikka Lopez
 
Critical path method
Critical path methodCritical path method
Critical path method
Shubhi Verma
 
Cpm
CpmCpm
Resource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniquesResource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniques
Remi Roques
 
Critical path method example by myassignmenthelp
Critical path method example by myassignmenthelpCritical path method example by myassignmenthelp
Critical path method example by myassignmenthelp
www.myassignmenthelp.net
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Simplilearn
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
Nikhil Raj
 
Project management
Project managementProject management
Project managementSrija Kumar
 
Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
Areef Khan
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
upendar aavula
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method upload
Arun
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Holy Angel University
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueJomari Gingo Selibio
 
MIDLANDS STATE Project management _notes
MIDLANDS  STATE  Project management _notesMIDLANDS  STATE  Project management _notes
MIDLANDS STATE Project management _notes
Kudzai Chibarinya
 
Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)
S. Ali Hasheminejad
 

Viewers also liked (20)

Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Lesson in fs cpm,cpa
Lesson in fs cpm,cpaLesson in fs cpm,cpa
Lesson in fs cpm,cpa
 
Cpm
CpmCpm
Cpm
 
Resource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniquesResource scheduling across multiple projects - Tips and techniques
Resource scheduling across multiple projects - Tips and techniques
 
Critical path method example by myassignmenthelp
Critical path method example by myassignmenthelpCritical path method example by myassignmenthelp
Critical path method example by myassignmenthelp
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
 
Project management
Project managementProject management
Project management
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Session 4 critical path method upload
Session 4   critical path method uploadSession 4   critical path method upload
Session 4 critical path method upload
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review Technique
 
MIDLANDS STATE Project management _notes
MIDLANDS  STATE  Project management _notesMIDLANDS  STATE  Project management _notes
MIDLANDS STATE Project management _notes
 
Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)Time-Cost Trade off (Project Management)
Time-Cost Trade off (Project Management)
 

Similar to Critical path method

Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
SAJID ALI RUK
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
DhesinghRajaLekha
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
Mohammad Younus
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
AaliButt1
 
Spm
SpmSpm
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
Sonali Srivastava
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
Chhaya Narvekar
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
BetshaTizazu2
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMAR
Mitesh Kumar
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
IrtizaMalik
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
Syed Hamza
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
Amit Kumbar
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
HimanshuKaklotar1
 
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docxOperations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
hopeaustin33688
 

Similar to Critical path method (20)

Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
Ovi project
Ovi  projectOvi  project
Ovi project
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
Spm
SpmSpm
Spm
 
Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMAR
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docxOperations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
 

Recently uploaded

The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 

Recently uploaded (20)

The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 

Critical path method

  • 1. Introduction to CPM Guided: Ruchita shah Presented By: Kajal Vasar(115371) Khushi Makwana(115372) Mahesh Parmar(114352) Dushyant Nasit(114339)
  • 2. Project Management  Managers have been planning, scheduling, monitoring, and controlling large scale projects for hundred years, but it has only been in the last 50 years that management science techniques have been applied to major projects.  They are two types: 1. Critical Path Method(CPM) 2. Project Evaluation and Review Technique(PERT)
  • 3. Introduction- CPM  Defination:- Critical path is a sequence of activity between a project’s start and finish that takes the longest time to complete.  Critical path method is based on mathematical calculations and it is used for scheduling project activities.  In 1950, Critical path method(CPM) was developed by Kelly and Walker to assist in building and maintains of chemical plants.  The initial critical path method was used for managing plant maintenance projects.
  • 4.  Critical path is the sequential activities from start to the end of a project. Although many projects have only one critical path, some projects may have more than one critical paths depending on the flow logic used in the project  The essential technique for using CPM is to construct a model of the project that includes the following:  A list of all activities required to complete the project (typically categorized within a work breakdown structure  The time (duration) that each activity will take to completion,  The dependencies between the activities .
  • 5. Terminologies used in CPM In order to explain the purpose, structure and operation of CPM, it is helpful to define the following terms: Activity:An activity carries the arrow symbol.This represent a task or subproject that uses time or resources Event:- A node (an event), denoted by a circle , marks the start and completion of an activity, which contain a number that helps to identify its location. For example activity A can be drawn as: Dummy Activity: An activity, which is used to maintain the pre-defined precedence relationship only during the construction of the project network, is called a dummy activity. Dummy activity is represented by a dotted arrow and does not consume any time and resource 21 A
  • 6.  Parallel activity: There are two activity which being at same event and end at same event.this activities are called parallel activity. Not allowed…..  Path: A path is a series of adjacent activities leading from one event to another.  Critical path: A critical path is the sequence of critical activities that forms a continuous path between the start of a project and its completion. 1 2
  • 7. Situations in network diagram A B C A must finish before either B or C can start, it called burst event. A B C both A and B must finish before C can start, it called merge event. Dangling events is not allow. A C B D Dummy A must finish before B can start both A and C must finish before D can start, it’s called dummy activity. A B C
  • 8. Forward pass:  The Early Start and Early Finish Time Calculated by moving Forward Through the Network.  Consider Maximum.
  • 9. Backward pass:  The Latest Start and Latest Finish Time Calculated by moving Backward Through the Network.  Consider Minimum
  • 10. Float activity:  Float activity For an Activity is The Difference between its Earliest and Latest Start Time or Earliest and Latest Finish Time .
  • 11. Steps in Critical Path Method  Step 1: Make a forward pass through the network as follows: For each activity i beginning at the Start node, compute: Earliest Start Time (ES) = the maximum of the earliest finish times of all activities immediately preceding activity i. (This is 0 for an activity with no predecessors.). This is the earliest time an activity can begin without violation of immediate predecessor requirements. Earliest Finish Time (Ef) = (Earliest Start Time) + (Time to complete activity i. This represent the earliest time at which an activity can end. The project completion time is the maximum of the Earliest Finish Times at the Finish node.
  • 12. Continue..........  Step 2: Make a backwards pass through the network as follows: Move sequentially backwards from the Finish node to the Start node. At a given node, j, consider all activities ending at node j. For each of these activities, (i,j), compute: Latest Finish Time (LF) = the minimum of the latest start times beginning at node j. (For node N, this is the project completion time.). This is the latest time an activity can end without delaying the entire project. Latest Start Time (LS) = (Latest Finish Time) - (Time to complete activity (i,j)). This is the latest time an activity can begin without delaying the entire project.
  • 13. Continue..........  Step 3: Calculate the float time for each activity by: float = (Latest Start) - (Earliest Start), or = (Latest Finish)-(EarliesFinish). A critical path is a path of activities, from the Start node to the Finish node, with 0 float times.
  • 14. Example 1. Construct the CPM Network using the details below and determine the critical path Activity Immediate Completion predecessors Time (week) A - 2 B A 3 C A 3 D C 4 E D 8 F B,E 6 G F 2 Total …… 28
  • 16. Activity Tme Earliest Start (ES) Earliest Finish (EF) Latest Start (LS) Latest finish (LF) Slack (LS-ES) Critical path A 2 0 2 0 2 0 Yes B 3 2 5 14 17 12 No C 3 2 5 2 5 0 Yes D 4 5 9 5 9 0 Yes E 8 9 17 9 17 0 Yes F 6 17 23 17 23 0 Yes G 2 23 25 23 25 0 Yes
  • 18. Critical Path:- Cp = 1 - 2 – 3 - 4 – 5 – 6 – 7 = A – C -D - E - F - G = 2 + 3 + 4 + 8 + 6 + 2 = 25
  • 19. Benefits of CPM  Useful at many stages of project management  Mathematically simple  Give critical path and float time  Provide project documentation  Useful in monitoring costs  Visual representation
  • 20. Limitations to CPM  Specified precedence relationship  Activity time estimates are subjective and depend on judgment  Can be more difficult understand ten grant charts  The time needed for tasks is not as clear as with grant charts

Editor's Notes

  1. <number> Critical Path Method
  2. <number> Critical Path Method
  3. <number> Critical Path Method
  4. <number> Critical Path Method
  5. <number> Critical Path Method
  6. <number> Critical Path Method
  7. <number> Critical Path Method
  8. <number> Critical Path Method
  9. <number> Critical Path Method