SlideShare a Scribd company logo
UNIT I
1
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Fixing the point with respect to horizontal
and vertical control.
Using surveying instruments.
Methods
Horizontal control
Vertical control
2
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Horizontal control
3
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Vertical control
4
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Horizontal control and its methods employed:
 Reference mark on known plan position
 Large structure primary and secondary control points are
used
 Primary control points are used in triangulation
 Secondary control points are reference to primary control
stations.
5
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Reference grid:
 Used for accurate setting out of works of large magnitude
Types:
 Survey grid
 Site grid
 Structural grid
 Secondary grid
6
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Survey grid:
 Drawn on survey plan from the original traverse
 Original traverse from the control points on the grid
Site grid:
 Used by the designer
 Design points are related to site grid
 Site grid should be actually the survey grid
7
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Structural grid:
 Used at when the structural components are large
numbers.
 Used for accuracy
 It is set out from the site grid points
Secondary grid:
 Used for internal details of the building
 Other grids are not shown
8
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Vertical control and methods:
 Determine elevation with respect to sea level
 Used to BM for other survey and high accuracy
 Also used for boundary survey, route survey, construction
and topographic surveys
 Need at lest two BM and more may be required at
depending upon the needs and complexity of the project
 Also used for construction of water, sewer system,
highways, bridges, drains and other infrastructures
9
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
cont.....
 Can be done in alone but after often done in conjunction
with a horizontal control survey
 Its used in NOAA ( national oceanic and atmospheric
administration)
10
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Equipments:
 Boning rods and travellers (T shape)
 Sight rails (drilling to ground)
 Slope rails or batter boards (slope area)
 Profile boards (board cuts at edges)
11
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Triangulation:
 The system consists of inter connected triangles in which
the length of one line called base line
 Angle of the triangles are measured very precisely
 Knowing the length of one side and three angles
 The length of other two sides are computed
Disadvantages:
 Accumulate errors and azimuth
12
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Classification of Triangulation system:
 First order or primary triangulation (total whole country)
 Second order or secondary triangulation (in between frame
work)
 Third order or tertiary triangulation (within frame work)
13
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
14
S.
N
PARAMETERS 1st ORDER 2nd ORDER 3rd ORDER
1 Average triangle closure Less than 1 second 3 sec 6 sec
2 Maximum triangle closure Not more than 3
seconds
8 sec 12 sec
3 Length of base line 5 to 15 kilometers 1.5 to 5 km 0.5 to 3 km
4 Length of the sides of triangles 30 to 150
kilometers
8 to 65 km 1.5 to 10 km
5 Actual error of base 1 in 300,000 1 in 150,000 1 in 75,0000
6 Probable error of base 1 in 1,000,000 1 in 500,000 1 in 250,000
7 Discrepancy between two
measures of a section
10 mm kilometers 20 mm kilometers 25 mm kilometers
8 Probable error or computed
distance
1 in 60,000 to 1 in
250,000
1 in 20,000 to 1 in
50,000
1 in 5,000 to 1 in
20,000
9 Probable error in astronomic
azimuth
0.5 seconds - 5 sec.
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Common figure of system:
 Single chain triangulations – not accurate
 Double chain triangulation – used to cover grater area
 Central point figures – flat countries ( pentagon and
hexagon)
 Quadrilateral – hilly countries (four side)
15
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Routine of triangulation survey:
 Reconnaissance survey
 Measurement of base line
 Measurement of horizontal angle
 Erection of signals and towers
 computing
16
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
1.Reconnaissance survey:
Detailed survey
 Location of the site
 Characteristics of the contours
 Selection of triangulation system
17
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Factors governing the selection of triangulation station:
 Easily accessible
 No obstacles
 Material available at nearer area
 Transportation facility
Important factors:
 Determination of distance b/n 2 points or stations
 Determination of elevation
 Profile of the intervening (obstacle) ground
18
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
WHAT IS THIS ?
19
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Signals and Towers:
Towers:
 A tower is a structure erected over a station for the support
of the instrument and observing party and is provided when
the station or the signal or both are to be elevated.
 Inner tower - support the instrument only
 Outer tower- support the observer and signal
20
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Towers:
 Independent to each other-masonry , timber and steel
 For small height masonry suitable otherwise uneconomical
 Timber are commonly used-50m height
 Steel towers are easily erected and dismantled also light
weight (BILBY tower 30 to 40m ht-3hours-5men-3tonnes)
21
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Signals :
 A signal is a devices erected to define the exact position of
an observed station.
Classification :
 Day light or non luminous (opaque) signal
 Sun or luminous signal
 Night signal
22
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Requirements of Signals :
 It should be conspicuous- clear visible against any
background
 Accurate cantered over the station mark
 It should be suitable for accurate bisection
 It should be free from phase or exhibit little phase
23
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Day light or non luminous (opaque) signal:
 Consist of various type-Direct sight less then 30km
 Pole signals used for 6km
 Signal should be dark colour for visibility against the sky and should
painted white.
 Flag at top the signal
 Diameter of the signal pole in cm = 1.3D to 1.9D (D in km)
 Height of signal pole in cm = 13.3D (D in km)
24
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Sun or luminous signal:
 Sun signals are those in which the sun’s rays are reflected to the
observing theodolite, either directly as from a beacon or
indirectly from a signal target.
 Used to when the length of sight exceed 30km
Instruments used:
 Heliotrope – consist of plane mirror- Direct reflected rays
 Heliograph – cantered over the station mark.
25
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Night signal:
 Used in triangulation system at night time.
 Various forms of oil lamps with reflector or optical
collimators for line of sight less than 80km
 Acetylence lamp designed by captain G.T.Mccaw line of
sight up to 80km
26
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Phase of signals:
 Phase signal is the error of bisection which arises from the fact
that under lateral illumination the signal is partly in light and
partly in shade.
 Observer sees only the illumination portion and bisects.
Two conditions
1. When the observation is made on the bright portion – ref fig A
2. When the observation is made on the bright line – ref fig B
27
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Base line measurement:
 It is most important part of triangulation operations and
need to great accuracy
Selection of site for base line
 Fairly level, slope should be uniform and gentle
 Free from obstruction
 Base should be inter visible at ground level
 Firm and smooth, water gaps should be few
 The site should be extension to primary triangulation
28
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Standard of lengths:
 Marked on meters by metals but small changes in
accuracy
a) Great britian – yard of bronze
b) The united states – meter to feet
c) India – old 10 feet bar A = 9.9999566 British feet
29
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Base measuring apparatus:
 Rigid bars (before tape)
a) Contact apparatus (continue end)
b) Optical apparatus (microscope)
c) Compensating base bar (maintain length by 2
metals)
d) Bimetallic non-compensating base bars (using
thermometer)
e) Monometallic base bar ( using ice)
 Flexible apparatus
30
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
The Colby apparatus:
 Designed by Maj-Gen
 Eliminate the effect of change of temperature
 Linear expansion 3:5 ratio
 Steel and brass metals are using
 Brass is coated with a special preparation for steel
 Compound bar and sprite level are fixed at middle
 Consist of micro wires (cross wires)
 5 frame works (10 ft x 5 + 6 in x 5) = 52ft 6in
 This work is continued till the end of the base is
reached.
31
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Flexible apparatus:
 Long length, time saving, no losses, accuracy, using
rough ground also, water gap areas, less expansive,
speed of measurements and more check bases.
1. Steel and inverted tape
2. Steel and brass wires
Steel tape
 Thermal expansion nearly 0.00000645/ºF
 Not accurate at day time, accurate at cloudy and night
time
32
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Inver tape and wires:
 Steel alloy containing about 36% nickel
 The co-efficient of thermal expansion is 0.0000005/ºF
 Length is changed slowly so never used standard
Equipment for base line measurement:
 Three standardised tapes
 Straining device, marking tripod or sticks
 Six thermometers
 Accurate spring balance
33
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
The field work:
 The setting out party
Two surveyors and a number of parties
 The measuring party
Two observers, recorder, leveller and staff man
(accurate at 0.5 to 1km)
Methods:
1.Wheeler’s method by wheeler’s base line apparatus
2.Jaderin’s method
34
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Tape corrections:
 Correction for absolute length
 Correction for temperature
 Correction for pull or tension
 Correction for sag
 Correction for slope
 Correction for alignment
 Reduction to sea level
 Correction to measurement in vertical plane
35
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Correction for absolute length (Ca):
Ca = L.c/l
 Ca- correction for absolute length
 L-measure length of the line
 C-correction per tape length
 L-designed length of the tape
Correction for temperature (Ct):
Ct = α (Tm-To)L
 α- co efficient of thermal expansion
 Tm-mean temperature in the field during measurements
 To- mean temperature during standardisation of the tape
 L- measured length
36
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Correction for temperature (Ct):
Jaderin’s method:
Ct (brass) = αb (Ls-Lb)/αb - αs
Ct (steel) = αs (Ls-Lb)/αb – αs
Correction for pull or tension (Cp or Ct):
Cp = (P-Po)L/AE
 P- pull applied during measurements (N)
 Po- standard pull (N)
 L-measurement length (m)
 A-cross section area of the tape (cm2)
 E-young’s modulus of elasticity (N/cm2)
 The pull applied in the field should be less than 20 times
the weight of the tape.
37
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Correction for Sag (Cs):
Cs = NCs + sag correction for any
fractional tape length
 N-number of whole length tape
 Cs – tape correction per tape length
Cs = nlw2/24p2
l -total length of the tape
W-total weight of the tape
n = number of equal span
P = pull applied
38
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Normal tension(Pn):
Pn = 0.204w1 √AE/√ (Pn - Po )
The value of Pn is to be determined by trial and
error method.
Correction for slope or vertical alignment:
AB = L = inclined length measured
AB1 = horizontal length
h = difference in elevation between the ends.
Cv = slope correction or correction due to vertical
alignment
39
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Cv = AB- AB1 = L-√L2-h2
If the grades are uniform length L, we get total slope
correction = sum of h2 /2L
If the angle (θ) of slope is measured insted of h, the correction
is given by
Cv = L-Lcosθ = l(1-cosθ)
Cv =2Lsin2θ/2
Correction for horizontal alignment
(a) Bad ranging = Ch = d2/2L
(b) Deformation of the tape in horizontal plane = Ch =
(d2/2L1)+(d2/2L1)
(c) Broken base = Ch = (acβ2 /(a+c)) x 4.2308x10-8
40CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
CONTROL SURVEYING
Reduction to mean sea level:
Correction (Cmsl) = L-D = Lh/R
Correction to measurement in vertical plane:
Sx = gx/AE ((M+0.5m(2l-x)-po/g))
41
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Measurement of horizontal angle:
 Two types of instruments are used in triangulation of
high precision
1. Repeating theodolite (Double vertical axis, using 2
or more verniers)
2. Direction theodolite (1 vertical axis and accuracy)
(a) Wild T-3 precision theodolite
(b) Wild T-4 universal theodolite
42
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Methods of horizontal angle:
 Method of repetition
 Reiteration or direct or method of series
43
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
44
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
Methods of horizontal angle:
 Method of repetition
 Reiteration or direct or method of series
Satellite station : Reduction to centre:
 In order to secure well conditioned triangle or better
visibility objects such as church spires, steel post,
flag poles, towers etc..
 Sometimes selected as triangulation station, when the
observations are to taken from such a station, it is
impossible to set up an instrument over it.
45
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
 In such cases a subsidiary station known as satellite
station or eccentric station or false station is
selected as near to the main station.
 Observations are taken from same precision as would
have been used in the measurement of angle at the
true stations.
46
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N
CONTROL SURVEYING
47
 Gale’s Table
CE6404-Surveying II/Unit 1 by,
Shanmugasundaram.N

More Related Content

What's hot

1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
Rakesh Verma
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying ppt
Naufil Sayyad
 
Triangulation
Triangulation Triangulation
Chain survey_Surveying, Civil Engineering
Chain survey_Surveying, Civil EngineeringChain survey_Surveying, Civil Engineering
Chain survey_Surveying, Civil Engineering
A Makwana
 
Curves
CurvesCurves
Curves
CurvesCurves
Levelling
LevellingLevelling
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
GAURAV. H .TANDON
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying
Krish Bhavsar
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
neharajpl
 
Hydrographic Survey
Hydrographic SurveyHydrographic Survey
Hydrographic Survey
Shubham Bathwal
 
Classification of triangulation
Classification of triangulationClassification of triangulation
Classification of triangulation
Fayaz Ahamed A P
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
neharajpl
 
Ce6304 surveying 1 contour (iv unit) lecture ppt notes
Ce6304 surveying 1   contour (iv unit) lecture ppt notesCe6304 surveying 1   contour (iv unit) lecture ppt notes
Ce6304 surveying 1 contour (iv unit) lecture ppt notes
nandishsajjan
 
Modern Surveying Equipment Presentation
Modern Surveying Equipment PresentationModern Surveying Equipment Presentation
Modern Surveying Equipment Presentation
Land Surveyors United Community
 
Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016
Mitiku Chachu
 
EDM
EDMEDM
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptx
SaddoAjmal
 
methods of plane table surveying
methods of plane table surveyingmethods of plane table surveying
methods of plane table surveying
ghazanfarali786
 

What's hot (20)

1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying ppt
 
Triangulation
Triangulation Triangulation
Triangulation
 
Chain survey_Surveying, Civil Engineering
Chain survey_Surveying, Civil EngineeringChain survey_Surveying, Civil Engineering
Chain survey_Surveying, Civil Engineering
 
Curves
CurvesCurves
Curves
 
Curves
CurvesCurves
Curves
 
Levelling
LevellingLevelling
Levelling
 
Levelling
LevellingLevelling
Levelling
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Hydrographic Survey
Hydrographic SurveyHydrographic Survey
Hydrographic Survey
 
Classification of triangulation
Classification of triangulationClassification of triangulation
Classification of triangulation
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Ce6304 surveying 1 contour (iv unit) lecture ppt notes
Ce6304 surveying 1   contour (iv unit) lecture ppt notesCe6304 surveying 1   contour (iv unit) lecture ppt notes
Ce6304 surveying 1 contour (iv unit) lecture ppt notes
 
Modern Surveying Equipment Presentation
Modern Surveying Equipment PresentationModern Surveying Equipment Presentation
Modern Surveying Equipment Presentation
 
Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016
 
EDM
EDMEDM
EDM
 
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptx
 
methods of plane table surveying
methods of plane table surveyingmethods of plane table surveying
methods of plane table surveying
 

Similar to Control surveying

Gps survey
Gps surveyGps survey
Gps survey
Shanmugasundaram N
 
Total station survey
Total station surveyTotal station survey
Total station survey
Shanmugasundaram N
 
surveying ii
surveying iisurveying ii
surveying ii
nandishsajjan
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
brett_grocock
 
Surveying pdf
Surveying pdfSurveying pdf
Surveying pdf
Saqib Imran
 
Site surveying report ii
Site surveying   report iiSite surveying   report ii
Site surveying report ii마 이환
 
Distance Measurement & Chain Surveying
Distance Measurement & Chain SurveyingDistance Measurement & Chain Surveying
Distance Measurement & Chain Surveying
Bahzad5
 
Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...
amansingh2914
 
lecture_1a.ppt
lecture_1a.pptlecture_1a.ppt
lecture_1a.ppt
ArisamTom
 
GNSS and Total Station Survey
GNSS and Total Station SurveyGNSS and Total Station Survey
GNSS and Total Station Survey
nihal navin
 
Survey work presentation
Survey work presentationSurvey work presentation
Survey work presentation
Arun pratap singh
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdf
NkosiAnsari
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
KishanKelothu
 
Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka
Sudip khadka
 
Surveying i
Surveying iSurveying i
Surveying i
Self employed
 
Ce6304 surveying i-2015_07_16_10_57_06_997
Ce6304 surveying i-2015_07_16_10_57_06_997Ce6304 surveying i-2015_07_16_10_57_06_997
Ce6304 surveying i-2015_07_16_10_57_06_997
Massanja Tollah
 
Introduction of Surveying
Introduction of Surveying Introduction of Surveying
Introduction of Surveying
hussainbasha hussain
 
Basic civil
Basic civilBasic civil
Basic civil
sreejithksasidharan
 
Surveying
Surveying Surveying
Surveying
civilsmvec
 

Similar to Control surveying (20)

Gps survey
Gps surveyGps survey
Gps survey
 
Total station survey
Total station surveyTotal station survey
Total station survey
 
surveying ii
surveying iisurveying ii
surveying ii
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
 
30838893 chain-survey
30838893 chain-survey30838893 chain-survey
30838893 chain-survey
 
Surveying pdf
Surveying pdfSurveying pdf
Surveying pdf
 
Site surveying report ii
Site surveying   report iiSite surveying   report ii
Site surveying report ii
 
Distance Measurement & Chain Surveying
Distance Measurement & Chain SurveyingDistance Measurement & Chain Surveying
Distance Measurement & Chain Surveying
 
Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...
 
lecture_1a.ppt
lecture_1a.pptlecture_1a.ppt
lecture_1a.ppt
 
GNSS and Total Station Survey
GNSS and Total Station SurveyGNSS and Total Station Survey
GNSS and Total Station Survey
 
Survey work presentation
Survey work presentationSurvey work presentation
Survey work presentation
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdf
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka
 
Surveying i
Surveying iSurveying i
Surveying i
 
Ce6304 surveying i-2015_07_16_10_57_06_997
Ce6304 surveying i-2015_07_16_10_57_06_997Ce6304 surveying i-2015_07_16_10_57_06_997
Ce6304 surveying i-2015_07_16_10_57_06_997
 
Introduction of Surveying
Introduction of Surveying Introduction of Surveying
Introduction of Surveying
 
Basic civil
Basic civilBasic civil
Basic civil
 
Surveying
Surveying Surveying
Surveying
 

More from Shanmugasundaram N

Types of arches
Types of arches   Types of arches
Types of arches
Shanmugasundaram N
 
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Shanmugasundaram N
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Shanmugasundaram N
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Shanmugasundaram N
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...
Shanmugasundaram N
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...
Shanmugasundaram N
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...
Shanmugasundaram N
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Shanmugasundaram N
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
Shanmugasundaram N
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Shanmugasundaram N
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural Analysis
Shanmugasundaram N
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural Analysis
Shanmugasundaram N
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural Analysis
Shanmugasundaram N
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural Analysis
Shanmugasundaram N
 
Basics of structural analysis
Basics of structural analysisBasics of structural analysis
Basics of structural analysis
Shanmugasundaram N
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Shanmugasundaram N
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation Engineering
Shanmugasundaram N
 

More from Shanmugasundaram N (20)

Types of arches
Types of arches   Types of arches
Types of arches
 
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural Analysis
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural Analysis
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural Analysis
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural Analysis
 
Basics of structural analysis
Basics of structural analysisBasics of structural analysis
Basics of structural analysis
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation Engineering
 
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation Engineering
 

Recently uploaded

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 

Recently uploaded (20)

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 

Control surveying

  • 1. UNIT I 1 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 2. CONTROL SURVEYING Fixing the point with respect to horizontal and vertical control. Using surveying instruments. Methods Horizontal control Vertical control 2 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 4. CONTROL SURVEYING Vertical control 4 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 5. CONTROL SURVEYING Horizontal control and its methods employed:  Reference mark on known plan position  Large structure primary and secondary control points are used  Primary control points are used in triangulation  Secondary control points are reference to primary control stations. 5 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 6. CONTROL SURVEYING Reference grid:  Used for accurate setting out of works of large magnitude Types:  Survey grid  Site grid  Structural grid  Secondary grid 6 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 7. CONTROL SURVEYING Survey grid:  Drawn on survey plan from the original traverse  Original traverse from the control points on the grid Site grid:  Used by the designer  Design points are related to site grid  Site grid should be actually the survey grid 7 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 8. CONTROL SURVEYING Structural grid:  Used at when the structural components are large numbers.  Used for accuracy  It is set out from the site grid points Secondary grid:  Used for internal details of the building  Other grids are not shown 8 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 9. CONTROL SURVEYING Vertical control and methods:  Determine elevation with respect to sea level  Used to BM for other survey and high accuracy  Also used for boundary survey, route survey, construction and topographic surveys  Need at lest two BM and more may be required at depending upon the needs and complexity of the project  Also used for construction of water, sewer system, highways, bridges, drains and other infrastructures 9 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 10. CONTROL SURVEYING cont.....  Can be done in alone but after often done in conjunction with a horizontal control survey  Its used in NOAA ( national oceanic and atmospheric administration) 10 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 11. CONTROL SURVEYING Equipments:  Boning rods and travellers (T shape)  Sight rails (drilling to ground)  Slope rails or batter boards (slope area)  Profile boards (board cuts at edges) 11 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 12. CONTROL SURVEYING Triangulation:  The system consists of inter connected triangles in which the length of one line called base line  Angle of the triangles are measured very precisely  Knowing the length of one side and three angles  The length of other two sides are computed Disadvantages:  Accumulate errors and azimuth 12 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 13. CONTROL SURVEYING Classification of Triangulation system:  First order or primary triangulation (total whole country)  Second order or secondary triangulation (in between frame work)  Third order or tertiary triangulation (within frame work) 13 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 14. CONTROL SURVEYING 14 S. N PARAMETERS 1st ORDER 2nd ORDER 3rd ORDER 1 Average triangle closure Less than 1 second 3 sec 6 sec 2 Maximum triangle closure Not more than 3 seconds 8 sec 12 sec 3 Length of base line 5 to 15 kilometers 1.5 to 5 km 0.5 to 3 km 4 Length of the sides of triangles 30 to 150 kilometers 8 to 65 km 1.5 to 10 km 5 Actual error of base 1 in 300,000 1 in 150,000 1 in 75,0000 6 Probable error of base 1 in 1,000,000 1 in 500,000 1 in 250,000 7 Discrepancy between two measures of a section 10 mm kilometers 20 mm kilometers 25 mm kilometers 8 Probable error or computed distance 1 in 60,000 to 1 in 250,000 1 in 20,000 to 1 in 50,000 1 in 5,000 to 1 in 20,000 9 Probable error in astronomic azimuth 0.5 seconds - 5 sec. CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 15. CONTROL SURVEYING Common figure of system:  Single chain triangulations – not accurate  Double chain triangulation – used to cover grater area  Central point figures – flat countries ( pentagon and hexagon)  Quadrilateral – hilly countries (four side) 15 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 16. CONTROL SURVEYING Routine of triangulation survey:  Reconnaissance survey  Measurement of base line  Measurement of horizontal angle  Erection of signals and towers  computing 16 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 17. CONTROL SURVEYING 1.Reconnaissance survey: Detailed survey  Location of the site  Characteristics of the contours  Selection of triangulation system 17 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 18. CONTROL SURVEYING Factors governing the selection of triangulation station:  Easily accessible  No obstacles  Material available at nearer area  Transportation facility Important factors:  Determination of distance b/n 2 points or stations  Determination of elevation  Profile of the intervening (obstacle) ground 18 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 19. WHAT IS THIS ? 19 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 20. CONTROL SURVEYING Signals and Towers: Towers:  A tower is a structure erected over a station for the support of the instrument and observing party and is provided when the station or the signal or both are to be elevated.  Inner tower - support the instrument only  Outer tower- support the observer and signal 20 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 21. CONTROL SURVEYING Towers:  Independent to each other-masonry , timber and steel  For small height masonry suitable otherwise uneconomical  Timber are commonly used-50m height  Steel towers are easily erected and dismantled also light weight (BILBY tower 30 to 40m ht-3hours-5men-3tonnes) 21 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 22. CONTROL SURVEYING Signals :  A signal is a devices erected to define the exact position of an observed station. Classification :  Day light or non luminous (opaque) signal  Sun or luminous signal  Night signal 22 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 23. CONTROL SURVEYING Requirements of Signals :  It should be conspicuous- clear visible against any background  Accurate cantered over the station mark  It should be suitable for accurate bisection  It should be free from phase or exhibit little phase 23 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 24. CONTROL SURVEYING Day light or non luminous (opaque) signal:  Consist of various type-Direct sight less then 30km  Pole signals used for 6km  Signal should be dark colour for visibility against the sky and should painted white.  Flag at top the signal  Diameter of the signal pole in cm = 1.3D to 1.9D (D in km)  Height of signal pole in cm = 13.3D (D in km) 24 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 25. CONTROL SURVEYING Sun or luminous signal:  Sun signals are those in which the sun’s rays are reflected to the observing theodolite, either directly as from a beacon or indirectly from a signal target.  Used to when the length of sight exceed 30km Instruments used:  Heliotrope – consist of plane mirror- Direct reflected rays  Heliograph – cantered over the station mark. 25 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 26. CONTROL SURVEYING Night signal:  Used in triangulation system at night time.  Various forms of oil lamps with reflector or optical collimators for line of sight less than 80km  Acetylence lamp designed by captain G.T.Mccaw line of sight up to 80km 26 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 27. CONTROL SURVEYING Phase of signals:  Phase signal is the error of bisection which arises from the fact that under lateral illumination the signal is partly in light and partly in shade.  Observer sees only the illumination portion and bisects. Two conditions 1. When the observation is made on the bright portion – ref fig A 2. When the observation is made on the bright line – ref fig B 27 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 28. CONTROL SURVEYING Base line measurement:  It is most important part of triangulation operations and need to great accuracy Selection of site for base line  Fairly level, slope should be uniform and gentle  Free from obstruction  Base should be inter visible at ground level  Firm and smooth, water gaps should be few  The site should be extension to primary triangulation 28 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 29. CONTROL SURVEYING Standard of lengths:  Marked on meters by metals but small changes in accuracy a) Great britian – yard of bronze b) The united states – meter to feet c) India – old 10 feet bar A = 9.9999566 British feet 29 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 30. CONTROL SURVEYING Base measuring apparatus:  Rigid bars (before tape) a) Contact apparatus (continue end) b) Optical apparatus (microscope) c) Compensating base bar (maintain length by 2 metals) d) Bimetallic non-compensating base bars (using thermometer) e) Monometallic base bar ( using ice)  Flexible apparatus 30 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 31. CONTROL SURVEYING The Colby apparatus:  Designed by Maj-Gen  Eliminate the effect of change of temperature  Linear expansion 3:5 ratio  Steel and brass metals are using  Brass is coated with a special preparation for steel  Compound bar and sprite level are fixed at middle  Consist of micro wires (cross wires)  5 frame works (10 ft x 5 + 6 in x 5) = 52ft 6in  This work is continued till the end of the base is reached. 31 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 32. CONTROL SURVEYING Flexible apparatus:  Long length, time saving, no losses, accuracy, using rough ground also, water gap areas, less expansive, speed of measurements and more check bases. 1. Steel and inverted tape 2. Steel and brass wires Steel tape  Thermal expansion nearly 0.00000645/ºF  Not accurate at day time, accurate at cloudy and night time 32 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 33. CONTROL SURVEYING Inver tape and wires:  Steel alloy containing about 36% nickel  The co-efficient of thermal expansion is 0.0000005/ºF  Length is changed slowly so never used standard Equipment for base line measurement:  Three standardised tapes  Straining device, marking tripod or sticks  Six thermometers  Accurate spring balance 33 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 34. CONTROL SURVEYING The field work:  The setting out party Two surveyors and a number of parties  The measuring party Two observers, recorder, leveller and staff man (accurate at 0.5 to 1km) Methods: 1.Wheeler’s method by wheeler’s base line apparatus 2.Jaderin’s method 34 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 35. CONTROL SURVEYING Tape corrections:  Correction for absolute length  Correction for temperature  Correction for pull or tension  Correction for sag  Correction for slope  Correction for alignment  Reduction to sea level  Correction to measurement in vertical plane 35 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 36. CONTROL SURVEYING Correction for absolute length (Ca): Ca = L.c/l  Ca- correction for absolute length  L-measure length of the line  C-correction per tape length  L-designed length of the tape Correction for temperature (Ct): Ct = α (Tm-To)L  α- co efficient of thermal expansion  Tm-mean temperature in the field during measurements  To- mean temperature during standardisation of the tape  L- measured length 36 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 37. CONTROL SURVEYING Correction for temperature (Ct): Jaderin’s method: Ct (brass) = αb (Ls-Lb)/αb - αs Ct (steel) = αs (Ls-Lb)/αb – αs Correction for pull or tension (Cp or Ct): Cp = (P-Po)L/AE  P- pull applied during measurements (N)  Po- standard pull (N)  L-measurement length (m)  A-cross section area of the tape (cm2)  E-young’s modulus of elasticity (N/cm2)  The pull applied in the field should be less than 20 times the weight of the tape. 37 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 38. CONTROL SURVEYING Correction for Sag (Cs): Cs = NCs + sag correction for any fractional tape length  N-number of whole length tape  Cs – tape correction per tape length Cs = nlw2/24p2 l -total length of the tape W-total weight of the tape n = number of equal span P = pull applied 38 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 39. CONTROL SURVEYING Normal tension(Pn): Pn = 0.204w1 √AE/√ (Pn - Po ) The value of Pn is to be determined by trial and error method. Correction for slope or vertical alignment: AB = L = inclined length measured AB1 = horizontal length h = difference in elevation between the ends. Cv = slope correction or correction due to vertical alignment 39 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 40. CONTROL SURVEYING Cv = AB- AB1 = L-√L2-h2 If the grades are uniform length L, we get total slope correction = sum of h2 /2L If the angle (θ) of slope is measured insted of h, the correction is given by Cv = L-Lcosθ = l(1-cosθ) Cv =2Lsin2θ/2 Correction for horizontal alignment (a) Bad ranging = Ch = d2/2L (b) Deformation of the tape in horizontal plane = Ch = (d2/2L1)+(d2/2L1) (c) Broken base = Ch = (acβ2 /(a+c)) x 4.2308x10-8 40CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 41. CONTROL SURVEYING Reduction to mean sea level: Correction (Cmsl) = L-D = Lh/R Correction to measurement in vertical plane: Sx = gx/AE ((M+0.5m(2l-x)-po/g)) 41 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 42. CONTROL SURVEYING Measurement of horizontal angle:  Two types of instruments are used in triangulation of high precision 1. Repeating theodolite (Double vertical axis, using 2 or more verniers) 2. Direction theodolite (1 vertical axis and accuracy) (a) Wild T-3 precision theodolite (b) Wild T-4 universal theodolite 42 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 43. CONTROL SURVEYING Methods of horizontal angle:  Method of repetition  Reiteration or direct or method of series 43 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 45. CONTROL SURVEYING Methods of horizontal angle:  Method of repetition  Reiteration or direct or method of series Satellite station : Reduction to centre:  In order to secure well conditioned triangle or better visibility objects such as church spires, steel post, flag poles, towers etc..  Sometimes selected as triangulation station, when the observations are to taken from such a station, it is impossible to set up an instrument over it. 45 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 46. CONTROL SURVEYING  In such cases a subsidiary station known as satellite station or eccentric station or false station is selected as near to the main station.  Observations are taken from same precision as would have been used in the measurement of angle at the true stations. 46 CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N
  • 47. CONTROL SURVEYING 47  Gale’s Table CE6404-Surveying II/Unit 1 by, Shanmugasundaram.N