SlideShare a Scribd company logo
1 of 18
SNS COLLEGE OF ENGINEERING & TECHNOLOGY
An Autonomous Institutions
Accredited by NBA – AICTE and Accredited by NAAC – UGC with ‘A’ & ‘A+’Grade
Approved by AICTE, New Delhi & Affiliated to Anna University, Chennai
DEPARTMENT OF CIVIL ENGINEERING
COURSE NAME:
CE8701 - ESTIMATION, COSTING AND VALUATION ENGINEERING (SNSCE)
16CE402 - ESTIMATION, COSTING AND VALUATION (SNSCT)
IV YEAR / VII SEMESTER
Topic 1 : Types of Estimate
4-Dec-20
2/18
Types of Estimate
Preliminary
Estimate
Plinth Area
Estimate
Cube Rate
Estimate
Approximate
Quantity
Method
Estimate
Detailed
Estimate
Revised
Estimate
Supplementary
Estimate
Supplementary
and Revised
Estimate
Annual Repair
or maintenance
Estimate
4-Dec-20 3/18
Plinth Area Estimate
.
Plinth area should be calculated for covered area by taking external
dimensions of the building at the floor level.
Corridor and other open area should not be included.
For multi storied building Plinth
Area for each storey is determined
separately.
4-Dec-20
4/18
Difference b/n Plinth & Carpet Area
4-Dec-20
5/18
Cube Rate Estimate
.
Cube rate estimate is again approximate estimate.
Multiplying the length, breadth and height of the building.
External length and breadth at the floor level are calculated
for the purpose.
Height should be taken from the floor level to the top of roof.
For multi storey building height
is taken from floor level of one
storey to top of next higher floor.
Cube rate estimate is more accurate
as compared to the plinth area estimate.
4-Dec-20
6/18
Approximate Quantity Method Estimate
Structure divided into two parts
1. Foundation including plinth
2. Superstructure
Total length of walls is found out.
To find running meter rate of foundation, appx. quantities of various
items are calculated per running meter.
Similarly for superstructure appx. Quantities of brickwork, roof,
flooring etc is calculated per running meter.
4-Dec-20 7/18
Detailed Estimate
It is the accurate estimate prepared by working out quantities of
each items of work.
It is prepared in two stages
1. Details of measurements and calculation of quantities.
2. Abstract of estimated cost – 3% to 5% of estimated cost is added
to cover miscellaneous expenditure.
Detailed estimate is prepared work-wise.
4-Dec-20 8/18
Detailed Estimate
1. Details of measurements and details of quantities
4-Dec-20
9/18
Detailed Estimate
.
2. Abstract of estimation cost
4-Dec-20
10/18
Revised Estimate
Revised estimate is prepared when original sanctioned estimate is likely
to exceed more than 5%.
When expenditure on work is likely to exceed amount of administrative
sanction by more than 10%.
When there are material deviation from original proposal even though
cost may be met from sanctioned cost.
It is accompanied by comparative statement showing variations in each
item of works and reason for the same.
4-Dec-20
11/18
Supplementary Estimate
It is the fresh detailed estimate of the additional works in addition to the
original estimate.
It is required when further development is required during the progress
of work.
Abstract should show the amount of original estimate and total amount
including supplementary amount.
The golden bridge, Vietnam
4-Dec-20 12/18
Supplementary and Revised Estimate
When a work is partially abandoned and the estimate cost of the
remaining work is less then 95% of the original work.
That is less than 95% of original sanctioned estimate.
If any material deviations and changes in the design, which may causes
substantial saving in the estimate, Then the amount of original estimate
is revised by the competent authority.
4-Dec-20 13/18
Annual Repair or Maintenance Estimate
It is prepared to maintain structure or work in proper order and safe
condition
For buildings like white washing, painting, minor repairs etc.
For road works A.R. estimate provides for patch repairing, repairs of
bridges and culverts etc
4-Dec-20 14/18
Approximate or Rough Estimate
The estimation which is prepared using any one of rough method to get
the approximate cost of construction anticipated in a project.
Necessity of Approximate Estimate
To determine the approximate cost of the project
To minimize the time and manpower for preparing detailed estimate.
To decide project can be taken or not.
It useful to decide any alterations or small changes based on the
approximate estimate.
4-Dec-20 15/18
Types of Approximate Estimate
Plinth Area Method
Cubical Content
Method
Service Unit or Unit
Cost Method
Typical Bay Method Carpet Area Method
Rough Quantity
Method
4-Dec-20 16/18
Types of Approximate Estimate
Service Unit or Unit Cost Method
 The cost of the project is prepared by multiplying the cost of number of
unit in the structure.
Example:
1. Per student for school building
2. Per bed for hospital
3. Per kilometer for highway
4. Per seat for an cinema theater.
4-Dec-20
Types of Approximate Estimate
Typical Bay Method
 The number of bay’s or panels are being taken as the basics of the
estimation.
Example:
1. Factory building with steel roof trusses
2. Lengthy halls with intermediate beams spaced at uniform
intervals.
4-Dec-20 18/18
Happy Learning

More Related Content

What's hot

Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costingAyushHajare
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2ArunRavi43
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1ArunRavi43
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorAshwiniChaudhari13
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 

What's hot (20)

ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Types of contract
Types of contractTypes of contract
Types of contract
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
 
Contracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation EngineeringContracts - Estimation, Costing and Valuation Engineering
Contracts - Estimation, Costing and Valuation Engineering
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimator
 
rate analysis
rate analysisrate analysis
rate analysis
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 

Similar to Types of estimate - Estimation, Costing and Valuation Engineering

Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIALNat Rice
 
approximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfapproximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfDeepak37004
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing2cd
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxrikeshbisen
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...Скоробогатов Дмитрий
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Shanmugasundaram N
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 

Similar to Types of estimate - Estimation, Costing and Valuation Engineering (20)

Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
 
approximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfapproximateestimate-200713090343.pdf
approximateestimate-200713090343.pdf
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
CV_Cost Engineer
CV_Cost EngineerCV_Cost Engineer
CV_Cost Engineer
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
ACH 216 Lecture 04a (Estimating)
ACH 216 Lecture 04a (Estimating)ACH 216 Lecture 04a (Estimating)
ACH 216 Lecture 04a (Estimating)
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
 
Ppv ppt
Ppv pptPpv ppt
Ppv ppt
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...Philosophy, purpose of estimation, load bearing and framed structure - Estima...
Philosophy, purpose of estimation, load bearing and framed structure - Estima...
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 

More from Shanmugasundaram N

Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Shanmugasundaram N
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Shanmugasundaram N
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Shanmugasundaram N
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Shanmugasundaram N
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Shanmugasundaram N
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Shanmugasundaram N
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Shanmugasundaram N
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSShanmugasundaram N
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Shanmugasundaram N
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural AnalysisShanmugasundaram N
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural AnalysisShanmugasundaram N
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural AnalysisShanmugasundaram N
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisShanmugasundaram N
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Methods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringMethods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 

More from Shanmugasundaram N (20)

Types of arches
Types of arches   Types of arches
Types of arches
 
Total station survey
Total station surveyTotal station survey
Total station survey
 
Gps survey
Gps surveyGps survey
Gps survey
 
Control surveying
Control surveyingControl surveying
Control surveying
 
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...Response of structures to earthquake - Structural dynamics and Earthquake Eng...
Response of structures to earthquake - Structural dynamics and Earthquake Eng...
 
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
Elements of seismology - Structural dynamics and Earthquake Engineering (SD&EE)
 
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
Lessons learned from past earthquake - Structural dynamics and Earthquake Eng...
 
Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...Techniques for repair and protection methods II- Repair and rehabilitation of...
Techniques for repair and protection methods II- Repair and rehabilitation of...
 
Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...Techniques for repair and protection methods - Repair and rehabilitation of s...
Techniques for repair and protection methods - Repair and rehabilitation of s...
 
Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...Strength and durability of concrete - Repair and rehabilitation of structures...
Strength and durability of concrete - Repair and rehabilitation of structures...
 
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
Special concretes- Repair and rehabilitation of structures(RRS) - Concrete Te...
 
Repair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRSRepair, rehabilitation and retrofitting of structures - RRS
Repair, rehabilitation and retrofitting of structures - RRS
 
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
Maintenance and repair strategies - Repair and rehabilitation of structures(RRS)
 
Moment distribution method - Structural Analysis
Moment distribution method  - Structural AnalysisMoment distribution method  - Structural Analysis
Moment distribution method - Structural Analysis
 
Portal frames with sway - - Structural Analysis
Portal frames with sway -  - Structural AnalysisPortal frames with sway -  - Structural Analysis
Portal frames with sway - - Structural Analysis
 
Basics of sdm and equations - - Structural Analysis
Basics of sdm and equations -  - Structural AnalysisBasics of sdm and equations -  - Structural Analysis
Basics of sdm and equations - - Structural Analysis
 
Determination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural AnalysisDetermination of static and kinematic indeterminacies - Structural Analysis
Determination of static and kinematic indeterminacies - Structural Analysis
 
Basics of structural analysis
Basics of structural analysisBasics of structural analysis
Basics of structural analysis
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
Methods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringMethods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation Engineering
 

Recently uploaded

8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessorAshwiniTodkar4
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesRashidFaridChishti
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesChandrakantDivate1
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 

Recently uploaded (20)

8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 

Types of estimate - Estimation, Costing and Valuation Engineering

  • 1. SNS COLLEGE OF ENGINEERING & TECHNOLOGY An Autonomous Institutions Accredited by NBA – AICTE and Accredited by NAAC – UGC with ‘A’ & ‘A+’Grade Approved by AICTE, New Delhi & Affiliated to Anna University, Chennai DEPARTMENT OF CIVIL ENGINEERING COURSE NAME: CE8701 - ESTIMATION, COSTING AND VALUATION ENGINEERING (SNSCE) 16CE402 - ESTIMATION, COSTING AND VALUATION (SNSCT) IV YEAR / VII SEMESTER Topic 1 : Types of Estimate
  • 2. 4-Dec-20 2/18 Types of Estimate Preliminary Estimate Plinth Area Estimate Cube Rate Estimate Approximate Quantity Method Estimate Detailed Estimate Revised Estimate Supplementary Estimate Supplementary and Revised Estimate Annual Repair or maintenance Estimate
  • 3. 4-Dec-20 3/18 Plinth Area Estimate . Plinth area should be calculated for covered area by taking external dimensions of the building at the floor level. Corridor and other open area should not be included. For multi storied building Plinth Area for each storey is determined separately.
  • 5. 4-Dec-20 5/18 Cube Rate Estimate . Cube rate estimate is again approximate estimate. Multiplying the length, breadth and height of the building. External length and breadth at the floor level are calculated for the purpose. Height should be taken from the floor level to the top of roof. For multi storey building height is taken from floor level of one storey to top of next higher floor. Cube rate estimate is more accurate as compared to the plinth area estimate.
  • 6. 4-Dec-20 6/18 Approximate Quantity Method Estimate Structure divided into two parts 1. Foundation including plinth 2. Superstructure Total length of walls is found out. To find running meter rate of foundation, appx. quantities of various items are calculated per running meter. Similarly for superstructure appx. Quantities of brickwork, roof, flooring etc is calculated per running meter.
  • 7. 4-Dec-20 7/18 Detailed Estimate It is the accurate estimate prepared by working out quantities of each items of work. It is prepared in two stages 1. Details of measurements and calculation of quantities. 2. Abstract of estimated cost – 3% to 5% of estimated cost is added to cover miscellaneous expenditure. Detailed estimate is prepared work-wise.
  • 8. 4-Dec-20 8/18 Detailed Estimate 1. Details of measurements and details of quantities
  • 10. 4-Dec-20 10/18 Revised Estimate Revised estimate is prepared when original sanctioned estimate is likely to exceed more than 5%. When expenditure on work is likely to exceed amount of administrative sanction by more than 10%. When there are material deviation from original proposal even though cost may be met from sanctioned cost. It is accompanied by comparative statement showing variations in each item of works and reason for the same.
  • 11. 4-Dec-20 11/18 Supplementary Estimate It is the fresh detailed estimate of the additional works in addition to the original estimate. It is required when further development is required during the progress of work. Abstract should show the amount of original estimate and total amount including supplementary amount. The golden bridge, Vietnam
  • 12. 4-Dec-20 12/18 Supplementary and Revised Estimate When a work is partially abandoned and the estimate cost of the remaining work is less then 95% of the original work. That is less than 95% of original sanctioned estimate. If any material deviations and changes in the design, which may causes substantial saving in the estimate, Then the amount of original estimate is revised by the competent authority.
  • 13. 4-Dec-20 13/18 Annual Repair or Maintenance Estimate It is prepared to maintain structure or work in proper order and safe condition For buildings like white washing, painting, minor repairs etc. For road works A.R. estimate provides for patch repairing, repairs of bridges and culverts etc
  • 14. 4-Dec-20 14/18 Approximate or Rough Estimate The estimation which is prepared using any one of rough method to get the approximate cost of construction anticipated in a project. Necessity of Approximate Estimate To determine the approximate cost of the project To minimize the time and manpower for preparing detailed estimate. To decide project can be taken or not. It useful to decide any alterations or small changes based on the approximate estimate.
  • 15. 4-Dec-20 15/18 Types of Approximate Estimate Plinth Area Method Cubical Content Method Service Unit or Unit Cost Method Typical Bay Method Carpet Area Method Rough Quantity Method
  • 16. 4-Dec-20 16/18 Types of Approximate Estimate Service Unit or Unit Cost Method  The cost of the project is prepared by multiplying the cost of number of unit in the structure. Example: 1. Per student for school building 2. Per bed for hospital 3. Per kilometer for highway 4. Per seat for an cinema theater.
  • 17. 4-Dec-20 Types of Approximate Estimate Typical Bay Method  The number of bay’s or panels are being taken as the basics of the estimation. Example: 1. Factory building with steel roof trusses 2. Lengthy halls with intermediate beams spaced at uniform intervals.