SlideShare a Scribd company logo
CONTRACT CONDITIONS - II:
VARIATIONS/DEVIATIONS
Dr K M Soni, ADG(Retd.), CPWD,
New Delhi
Variations/Deviations
• Variations or Deviations are the changes from
the scope of work of a contract resulting during
execution of work except duration of the
contract.
• Mostly, Variations or Deviations are considered
the changes from the quantities or items of the
bill of quantities (Schedule of quantities) of a
contract resulting during execution of work as
changes in design, quantity or conditions
ultimately lead to affect BOQ/SOQ.
Variations/Deviations
• Variation/Deviation in quantities of items
• Extra items
• Substituted items
Deviation in Quantities
• These are the deviations or variations from
the quantities taken in Bill of Quantities or
Schedule of Quantities
• These are the items for which rates are
available in the contract
• The deviations/variations may be +ve or –ve
i.e. Quantities may increase or decrease from
the quantities available in BOQ/SOQ
Reasons of Deviations in Quantities
• Wrong assessment or mistake during preparation of detailed
estimate/BOQ/tender documents
• Assessment of quantities without availability of
architectural, structural or MEP drawings.
• Revision of drawings/design
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials at a particular
time
• Revisions due to client, architect, or engineer and contractor
Rates of Deviations in Quantities
• Rates of such items are available in the contract
• Deviations are +ve or –ve
• Rates can be based on;
• Available in contract for all deviations
• Rates available in the contract upto additional quantities
as mentioned in the contract (deviation limit, described in
percentage) and beyond it, market rates, Schedule rates
+/- quoted percentage, Schedule rates or cost plus basis or
any other method as mentioned in the contract or agreed
upon by the parties.
Extra or Additional items
• Items that are completely new and in addition
to the items contained in the contract
• These are the items other than those available
in BOQ and not covered in the conditions of
contract
• In some contracts, these are the items which are
not available in contract and not taken up in
substitution of items available in BOQ
Reasons of Extra/Additional items
• Left or mistake during preparation of detailed estimate/BOQ/tender
documents
• Specifications not available during preparation of detailed estimate/BOQ
• Non availability of architectural, structural or MEP drawings during
preparation of detailed estimate/tender document
• Revision of drawings/design
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials at a particular time
• Items not anticipated during preparation of tender documents i.e.
Contingent items
• Revisions due to client, architect, or engineer and contractor
Rates of Extra or Additional Items
• Market rates
• Schedule rates +/- quoted percentage
• Schedule rates
• Cost plus basis or
• Any other method as mentioned in the
contract or agreed upon by the parties.
Substituted item
• Items taken up as partial substitution or in
lieu of items of work available in the contract
• Therefore, the items are basically due to
change of specifications during execution
from those considered during preparation of
detailed estimate/BOQ/tender documents
Reasons of Substituted items
• Specifications/drawings not available during preparation of
detailed estimate/BOQ i.e. Non availability of architectural,
structural or MEP drawings
• Revision of drawings/design/specifications
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials or non
feasibility of the execution of the item at a particular time
• Revisions due to client, architect, or engineer and contractor
Rates of Substituted Items
• Agreement rates increased or decreased by the
difference in market rates of item substituted
compared to market rates of agreement item
• Market rates
• Schedule rates +/- quoted percentage
• Schedule rates
• Cost plus basis or
• Any other method as mentioned in the contract
or agreed upon by the parties.
Implications of Variations/ Deviations
• Extension of time
• Possible justification of regularisation of delay caused
by the contractor
• Chances of non compatibility of such items with
respect to other services
• Source of Disputes about the rates, time extension,
loss of profit, idle establishment and thus arbitration
• Delayed decisions
• Non approval of items and rates of variations
• Time overrun and cost overrun
Thanks for attending
Dr K M Soni, ADG (Retd.), CPWD, New Delhi
Also available on Youtube: KRISHNA MURARI Soni at
https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw

More Related Content

What's hot

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
guestdb5e498
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
Fakhar-un -Nisa
 

What's hot (20)

Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Construction contract
Construction contract Construction contract
Construction contract
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Contracts
ContractsContracts
Contracts
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Fidic
FidicFidic
Fidic
 
Claims
ClaimsClaims
Claims
 

Similar to Variations in works contracts

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
Aditya Mane
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
TRIslides
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
Pang Khai Shuen
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
D.Pawan Kumar
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
Allan Berry
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolution
Alex Iskandar
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
Samantha Ip
 

Similar to Variations in works contracts (20)

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolution
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
ACH 216 Lecture 04b (Bidding) Part 1
ACH 216 Lecture 04b (Bidding) Part 1ACH 216 Lecture 04b (Bidding) Part 1
ACH 216 Lecture 04b (Bidding) Part 1
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 

More from Dr K M SONI

More from Dr K M SONI (20)

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
 
Project Management
Project ManagementProject Management
Project Management
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
 
Contract Management
Contract Management Contract Management
Contract Management
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
 
Contract Management
Contract Management Contract Management
Contract Management
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 
Maintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural PlanningMaintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural Planning
 
Safety in Public Works
Safety in Public WorksSafety in Public Works
Safety in Public Works
 
About me i.e. Dr. K M Soni
About me i.e. Dr. K M SoniAbout me i.e. Dr. K M Soni
About me i.e. Dr. K M Soni
 

Recently uploaded

Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 

Recently uploaded (20)

Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturing
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptx
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 

Variations in works contracts

  • 1. CONTRACT CONDITIONS - II: VARIATIONS/DEVIATIONS Dr K M Soni, ADG(Retd.), CPWD, New Delhi
  • 2. Variations/Deviations • Variations or Deviations are the changes from the scope of work of a contract resulting during execution of work except duration of the contract. • Mostly, Variations or Deviations are considered the changes from the quantities or items of the bill of quantities (Schedule of quantities) of a contract resulting during execution of work as changes in design, quantity or conditions ultimately lead to affect BOQ/SOQ.
  • 3. Variations/Deviations • Variation/Deviation in quantities of items • Extra items • Substituted items
  • 4. Deviation in Quantities • These are the deviations or variations from the quantities taken in Bill of Quantities or Schedule of Quantities • These are the items for which rates are available in the contract • The deviations/variations may be +ve or –ve i.e. Quantities may increase or decrease from the quantities available in BOQ/SOQ
  • 5. Reasons of Deviations in Quantities • Wrong assessment or mistake during preparation of detailed estimate/BOQ/tender documents • Assessment of quantities without availability of architectural, structural or MEP drawings. • Revision of drawings/design • Revision due to local bye laws or local body agencies • Revision due to non availability of materials at a particular time • Revisions due to client, architect, or engineer and contractor
  • 6. Rates of Deviations in Quantities • Rates of such items are available in the contract • Deviations are +ve or –ve • Rates can be based on; • Available in contract for all deviations • Rates available in the contract upto additional quantities as mentioned in the contract (deviation limit, described in percentage) and beyond it, market rates, Schedule rates +/- quoted percentage, Schedule rates or cost plus basis or any other method as mentioned in the contract or agreed upon by the parties.
  • 7. Extra or Additional items • Items that are completely new and in addition to the items contained in the contract • These are the items other than those available in BOQ and not covered in the conditions of contract • In some contracts, these are the items which are not available in contract and not taken up in substitution of items available in BOQ
  • 8. Reasons of Extra/Additional items • Left or mistake during preparation of detailed estimate/BOQ/tender documents • Specifications not available during preparation of detailed estimate/BOQ • Non availability of architectural, structural or MEP drawings during preparation of detailed estimate/tender document • Revision of drawings/design • Revision due to local bye laws or local body agencies • Revision due to non availability of materials at a particular time • Items not anticipated during preparation of tender documents i.e. Contingent items • Revisions due to client, architect, or engineer and contractor
  • 9. Rates of Extra or Additional Items • Market rates • Schedule rates +/- quoted percentage • Schedule rates • Cost plus basis or • Any other method as mentioned in the contract or agreed upon by the parties.
  • 10. Substituted item • Items taken up as partial substitution or in lieu of items of work available in the contract • Therefore, the items are basically due to change of specifications during execution from those considered during preparation of detailed estimate/BOQ/tender documents
  • 11. Reasons of Substituted items • Specifications/drawings not available during preparation of detailed estimate/BOQ i.e. Non availability of architectural, structural or MEP drawings • Revision of drawings/design/specifications • Revision due to local bye laws or local body agencies • Revision due to non availability of materials or non feasibility of the execution of the item at a particular time • Revisions due to client, architect, or engineer and contractor
  • 12. Rates of Substituted Items • Agreement rates increased or decreased by the difference in market rates of item substituted compared to market rates of agreement item • Market rates • Schedule rates +/- quoted percentage • Schedule rates • Cost plus basis or • Any other method as mentioned in the contract or agreed upon by the parties.
  • 13. Implications of Variations/ Deviations • Extension of time • Possible justification of regularisation of delay caused by the contractor • Chances of non compatibility of such items with respect to other services • Source of Disputes about the rates, time extension, loss of profit, idle establishment and thus arbitration • Delayed decisions • Non approval of items and rates of variations • Time overrun and cost overrun
  • 14. Thanks for attending Dr K M Soni, ADG (Retd.), CPWD, New Delhi Also available on Youtube: KRISHNA MURARI Soni at https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw