SlideShare a Scribd company logo
Measure And Pay
Contract
Procurement Strategies
 Traditional Contract
 Modern or Design & Build Contract
 Management Contract
 Collaborative Contract
Traditional Contract
• Lump sum contract
• Measurement contract
• Cost plus contract
Measure And Pay Contract
Called as,
• Re-measurement contract
• Unit price contract
• Measure and Value contract
• Measurement contract
Measure And Pay Contract
Re-measurement contracts are seldom used
for an entire major construction project, but
they are frequently used for agreements with
sub-contractors
Measure And Pay Contract
• Contains a BOQ and Design of the project provided by
the employer or his consultants
• The contractor will quote against each BOQ item
• Enter a unit rate or unit price to build up the total
contract price on basis of those BOQ quantities
• At completion of contract , the exact quantity of works
finally executed under each BOQ item will be again re-
measured
Measure And Pay Contract
• During the construction period , the actual quantity
of works executed under each BOQ item will be
jointly measured
• And valued at the quoted rate for interim payment
purpose
• After re-measure valued at the quoted rate to
evaluate the final account
Measure And Pay Contract
• In variation or additional works that are without
basis of BOQ rate(s) , the contractor can build up
new rates or SRS for those works for valuation
Measure And Pay Contract
This type of contract is fair with the employer (
Client ) at risk for total quantities
Requirements;
• Experience in developing bills of quantities
• Payment terms properly tied to measured work
completion
• Quantity sensitive analysis of unit prices to
evaluate total bid price for potential quantity
variations
Requirements;
• Adequate breakdown and definition of work
units
• Good quantity surveying and reporting system
• Sufficient design definition to estimate
quantities of units
• Owner-furnished drawings and materials must
arrive on time
Advantages
• Complete design definition not required at
tender
• “Typical” drawings can be used for bidding
• Suitable for competitive bidding
• Easy for contractor selection
• Early project start possible
• Scope and quantities easily adjustable
Disadvantages
• The exact final price of the project is not
known to the owner until the completion of
the project
• More staff maybe needed to measure,
control, and report on units completed
• Re-measurement contracts tend to draw
unbalanced bidding
In comparing with lump-sum contract,
- Changes in contract documents can be made
easily by the owner
- Lower risk for contractor.
Thank you

More Related Content

What's hot

Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
Shahin MB
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
jagadish108
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
Sakshi Kirar
 
Construction contract
Construction contractConstruction contract
Construction contract
Delhi Technological University
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
Avinash Kumar Gupta
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
Dr K M SONI
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Types of contract
Types of contractTypes of contract
Types of contract
HarshalNarkhede7
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
Gide India
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
cynfang Fong
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
Dr K M SONI
 
Construction tender process
Construction tender processConstruction tender process
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
anojan kanagarathnam
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
Tulsi Pokhrel
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
srinivas2036
 

What's hot (20)

Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Construction process
Construction processConstruction process
Construction process
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 

Similar to Measure And Pay Contract

types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
ssuser42980c
 
Contracts
ContractsContracts
Contracts
krrish706
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
Waleed Liaqat
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
Abadit Tadesse
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
jairam131
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
HASMANIRA
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
HASMANIRA
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
Adi Iskandar Iliyas
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
Anil Kumar(6)
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
Association for Project Management
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
mianmohsinmumtazshb
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
kohwenqi
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
fritzlejarso
 
Contract Negotiations
Contract NegotiationsContract Negotiations
Contract Negotiations
TanyaGupta888342
 
Negotiated contracts
Negotiated contractsNegotiated contracts
Negotiated contracts
SHUBHAM SINGH
 
Contract account
Contract accountContract account
Contract account
daminigyanchandani
 
Unit4_Managing Contracts.ppt
Unit4_Managing Contracts.pptUnit4_Managing Contracts.ppt
Unit4_Managing Contracts.ppt
KGSCSEPSGCT
 
Contract and Job costing
Contract and Job costing Contract and Job costing
Contract and Job costing
Ashwitha shetty
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project managementAli Heydari
 

Similar to Measure And Pay Contract (20)

types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 
Contracts
ContractsContracts
Contracts
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
Contract Negotiations
Contract NegotiationsContract Negotiations
Contract Negotiations
 
Negotiated contracts
Negotiated contractsNegotiated contracts
Negotiated contracts
 
Contract account
Contract accountContract account
Contract account
 
Unit4_Managing Contracts.ppt
Unit4_Managing Contracts.pptUnit4_Managing Contracts.ppt
Unit4_Managing Contracts.ppt
 
Contract and Job costing
Contract and Job costing Contract and Job costing
Contract and Job costing
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 

Recently uploaded

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 

Recently uploaded (20)

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 

Measure And Pay Contract

  • 2. Procurement Strategies  Traditional Contract  Modern or Design & Build Contract  Management Contract  Collaborative Contract
  • 3. Traditional Contract • Lump sum contract • Measurement contract • Cost plus contract
  • 4. Measure And Pay Contract Called as, • Re-measurement contract • Unit price contract • Measure and Value contract • Measurement contract
  • 5. Measure And Pay Contract Re-measurement contracts are seldom used for an entire major construction project, but they are frequently used for agreements with sub-contractors
  • 6. Measure And Pay Contract • Contains a BOQ and Design of the project provided by the employer or his consultants • The contractor will quote against each BOQ item • Enter a unit rate or unit price to build up the total contract price on basis of those BOQ quantities • At completion of contract , the exact quantity of works finally executed under each BOQ item will be again re- measured
  • 7. Measure And Pay Contract • During the construction period , the actual quantity of works executed under each BOQ item will be jointly measured • And valued at the quoted rate for interim payment purpose • After re-measure valued at the quoted rate to evaluate the final account
  • 8. Measure And Pay Contract • In variation or additional works that are without basis of BOQ rate(s) , the contractor can build up new rates or SRS for those works for valuation
  • 9. Measure And Pay Contract This type of contract is fair with the employer ( Client ) at risk for total quantities
  • 10. Requirements; • Experience in developing bills of quantities • Payment terms properly tied to measured work completion • Quantity sensitive analysis of unit prices to evaluate total bid price for potential quantity variations
  • 11. Requirements; • Adequate breakdown and definition of work units • Good quantity surveying and reporting system • Sufficient design definition to estimate quantities of units • Owner-furnished drawings and materials must arrive on time
  • 12. Advantages • Complete design definition not required at tender • “Typical” drawings can be used for bidding • Suitable for competitive bidding • Easy for contractor selection • Early project start possible • Scope and quantities easily adjustable
  • 13. Disadvantages • The exact final price of the project is not known to the owner until the completion of the project • More staff maybe needed to measure, control, and report on units completed • Re-measurement contracts tend to draw unbalanced bidding
  • 14. In comparing with lump-sum contract, - Changes in contract documents can be made easily by the owner - Lower risk for contractor.
  • 15.