SlideShare a Scribd company logo
1 of 126
Construction Documents
Presented by:
Allan Berry
Today’s Presentation
• Obtaining work in the construction industry
• Project Manual
• Drawings and Specifications
• Types of Contracts
• Insurance Requirements
• Project Correspondence
• Change Orders
• Contractor Payments
• Closeout
Overview
• Documentation is vital !!!
• Poor documentation causes problems
– Most problems
– Second most, poor administration
• Documentation
– Who, what when, where, why and how
– Facts, facts, facts
– Specific to the type of project
Trade terms
• Addenda
• Bid bond
• Change Order
• Construction
Specification Institute
(CSI)
• Punch list
• Scope
• Specifications
• Shop drawings
Introduction
• Documentation:
– Records the progress
• Controls the time spent
– Keeps track of costs
– Need procedures in place early
• Maintain throughout the project
– Types
• Daily log
• Photographs
• Correspondence
What is Documentation?
• Documentation includes...
–a complete record of the project
–all contract documents
–records of circumstances
–daily reports
–meeting minutes
What is Documentation?
• Other items include
–Schedules
–Site visit records
–Telephone logs
–Minutes of Meetings
–Job correspondence
–Diaries
–Job logs
–Time cards
–Photos
Documentation Systems
– Documentation is...
• a systematic process for keeping regular,
accurate, complete and legible records of daily
activities, actual circumstances, and unusual
events on a project
Why Documentation Is So
Important
• Good documentation can...
–identify issues
–resolve conflicts
–settle disputes
–avoid litigation
–provide tangible proof
Why Documentation Is So
Important
Good Documentation
Practices
• Good documentation must be...
–accurate
–objective
–complete
–uniform
–credible
–timely
What to Document
• Everything !!!
•Murphy’s Law
–The most insignificant piece of information will
become the item that is most important if you don’t
document it
–The item you don’t document will be the one that
someone wants to see
What to Document
• No opinions
•No placing of blame
•No guesses
•No theories
•And absolutely do not modify notes
How to Document
• Documentation Tools
–Computers
–Photographs
–Video cameras
–Audio recorders
–Written reports
–Daily logs
Obtaining work in the Construction
Industry
• Competitive bid
• Invited bid
• Negotiation
• Design-build
• Construction Management
Obtaining work in the Construction
Industry
• Competitive bid
– Owner produces documents
– Contractor reviews documents
• Solicits subcontractor input
– Submits bid for completion of the work
– Owner awards to lowest, responsive bidder
Obtaining work in the Construction
Industry
• Invited bid
– Similar to standard process except
• Prequalification
– Experience
– Finances
– Workload
– Goal is to limit pool to similarly qualified
contractors
Obtaining work in the Construction
Industry
• Negotiation
– Proposal based
– Interview
• Cost
• Schedule
• Approach
• Staffing
• Experience
Obtaining work in the Construction
Industry
• Design-build
– One entity
• Provides
– Design
– Construction
Obtaining work in the Construction
Industry
• Construction Management
– CM-GC
– Third party CM
Summary
• Traditional (Competitive / Invited)
OWNER
CONTRACTOR
DESIGN
PROFESSIONAL
SUB-
CONTRACTORS
SUBCONSULTANTS
Summary
• CM-GC
OWNER
CONSTRUCTION
MANAGER
DESIGN
PROFESSIONAL
CONTRACTORS
SUBCONSULTANTS
Summary
• Design-build
OWNER
CONSTRUCTION
MANAGER
DESIGN
PROFESSIONAL
SUB-
CONTRACTORS
SUBCONSULTANTS
GENERAL
CONTRACTOR /
ENGINEER
Summary
• You may split your pursuits across all these
lines
– What do you do ?
• Whatever you do
– Use your resources the most effectively
Project Manual
• Aka “spec book” + drawings etc
• Includes
– Bidding documents
– Contract forms
– Specifications
– Drawings
– Other information (depends on project)
• Permits, geotechnical, etc etc
Contract Documents
• Drawings graphically provide:
– arrangements
– materials
– dimensions
– configurations
– other...
Contract Documents
• Drawings provide:
–Arrangement, materials, dimensions,
configuration, and other information about
the project that communicate the
engineer’s design for the project.
Contract Documents
• Specifications provide:
–written instructions that detail project
requirements
–information that is not easily shown on
drawings
Specification Sections
•Advertisement
•Instructions to Bidders
•Proposal
•Agreement
•Bond
•Insurance
•Wage Rates
•General conditions
•Technicals
Additional Key Contract
Documents
• Other key documents:
–contract
–subcontract
–general conditions
–supplemental conditions
–addenda and change orders
–purchase orders
–request for information (RFI)
Contract Documents
• Precedence:
–Set by the Author of the specifications
–Normally
• Special provisions
• General Provisions
• Detailed Drawings
• General Drawings
• Standard Specifications and Drawings
Other Documents
• Special Instructions
•Stop Work Orders
•Soil Reports
•Purchasing Lists
•Substantial Completion
•Final Completion
Peripheral Documents
• Shop Drawings
•Submittals
•Codes and Permits
•Agreements
•ASK QUESTIONS
–What, Why, Who, and What do I need to do ?
Contract Documents
• Identify and learn to recognize contract
documents
• Define a contract and understand basic legal
terms used in construction documents
• Study the relationships among various
contractual parties
Project Manual
• Typical manual will include:
– Invitation to bid
– Instructions to bidders
– Bid form
– Bid bond
– Performance/payment bond
– Agreement
– General conditions
– Supplementary conditions
– Specifications
– Drawings and addenda
Invitation to bid
• This is what you see in the DJC or on the Contractors
Plan Center website
– Gives you the information to know whether the project is one you are
interested in
• Includes
– Project Owner, A/E, Agency
– Description
– Type of bid
– Time for completion
– Bid date
– Where you can get the documents
– Requirements for prequalification / mandatory pre-bids
– Etc
Instructions to bidders
• Explains what you need to do
– To comply with the bid requirements i.e. be responsive
• Could include
– Resolution of discrepancies
– Substitution of products
– Bid submittal requirements
• How many copies
• Signatures
• Where to send it
• Subcontractor lists
• Etc etc
– Laws and Regulations
Bid Form
• Reports what your offer is
– Standardized to allow easy comparison
– Evaluated
• Balanced
• Unbalanced
• Responsive
• Unresponsive
• Totals add up
• Addenda received
Bid Bond
• Makes agreement that the bid will be honored for a
period of time
• Makes an agreement that the contractor will perform
the work if awarded the contract
• Percentage of bid amount
• Comes from your bonding agent
• Can be forfeited if you back away from the project
Performance and Payment Bond
• Guarantees that the contractor will fulfill the contract
terms
• Provides indemnity for liens
• 100% of bid amount
• Comes from your bonding agent
• If contractor defaults
– Surety (bonding company) takes over the project
• Assumes financial responsibility
• Solicits another contractor
Form of Agreement
• Included in project manual
– It is a contract
– Needs to be reviewed by legal counsel
General Conditions
• GCs define the contractual relationships
• Different types
– AIA
– EJCDC
– AGC
– Owner Provided
• Specific to the particular project
• The General Conditions...
–establish a common basis for relationships on a
project
–classify and clarify duties
–help to avoid disputes
–guide contractors in the execution of the project
–They are overall procedures of how the contract
provisions are to be implemented.
General Conditions
Using GCs to Make Decisions
• General Conditions
– remember there are different forms
–GCs are often incorporated into other forms
•Owner/Architect
•Owner /Engineer
•Contractor/Subcontractor
•Goal is to be consistent at all levels
Using GCs to Make Decisions
• As a Supervisor
–Determine what level of authority you have
•Basis of Authority
–Contractor
–Owner
–Design Professional
Using GCs to Make Decisions
•Basis of Authority
–Contractor – Perform the work in accordance with
the contract documents
–Owner – has the ultimate “Say”
–Design Professional – responsible for technical
evaluations
Remember, these levels of authority are
covered in the General Conditions
• Supplementary Conditions...
–provide information that is specific to a project
–immediately follows the General Conditions
–are also referred to as Special Conditions
–should be reviewed and discussed prior to starting a
project
Supplementary Conditions
• Information that supports and describes the
construction drawings
Specifications
Addenda
• Used to modify the contract before the bid date
• Issued by Owner
– Deficiencies
– Discrepancies
– Errors
– Clarification
An addendum is exactly the same as a change order
except that it occurs pre-bid
Drawings And Specifications
• Project Managers have to be able to read and
understand the drawings and specifications !!!
– You have to be willing and able to discuss and communicate
their content
Types of Drawings
• Conceptual
– Used for evaluation of project during planning phase
• Preliminary
– Used to perform reviews, submit for agency review, estimating
(budget)
• Working or Construction
– Used in the bidding process
Reading Drawings
• Conceptual
– Used for evaluation of project during planning phase
• Preliminary
– Used to perform reviews, submit for agency review, estimating
(budget)
• Working or Construction
– Used in the bidding process
Reading Drawings
• Understand the notation and nomenclature
• Get an idea of the methods being used
• Composites sometimes can help
Reading Drawings
• Review
– Site drawings ( C and G)
– Structural (S)
– Architectural (A)
– Mechanical (M or P)
– Electrical (E)
– Detail sheets
– Overlay and coordinate disciplines
– Erosion control
Specifications
• Three purposes
– Define roles
– Provide detailed technical information
– Support the drawings as part of the Project Manual
Specifications
• Three purposes
– Define roles
– Provide detailed technical information
– Support the drawings as part of the Project Manual
• Format
– CSI
– ODOT/APWA
– WSDOT
– FHWA
Technical Specification
Section Divisions - Old
•Division 1 General
•Division 2 Site work
•Division 3 Concrete
•Division 4 Masonry
•Division 5 Metals
•Division 6 Carpentry
•Division 7 Moisture Protection
•Division 8 Doors, Windows and Glass
•Division 9 Finishes
•Division 10 Specialties
•Division 11 Equipment
•Division 12 Furnishings
•Division13 Special Construction
•Division 14 Conveying Systems
•Division 15 Mechanical
•Division 16 Electrical
Technical Specification
Section Divisions - New
•Division 1: General Requirements
•Division 2: Existing Conditions
•Division 3: Concrete
•Division 4: Masonry
•Division 5: Metals
•Division 6: Wood, Plastics and Composites
•Division 7: Thermal and Moisture Protection
•Division 8: Openings
•Division 9: Finishes (interior finishes)
•Division 10: Specialties (for example, signs,
toilet accessories)
•Division 11: Equipment (for example, kitchen
equipment)
•Division 12: Furnishings
•Division 13: Special Construction (for example,
greenhouses)
•Division 14: Conveying Equipment (elevators,
escalators, lifts)
•Division 21: Fire Suppression
•Division 22: Plumbing
•Division 23: Heating, Ventilating and Air
Conditioning
•Division 26: Electrical
•Division 27: Communications
•Division 28: Electronic Safety and Security
•Division 31: Earthwork
•Division 32: Exterior Improvements
•Division 33: Utilities
Technical Specification
Section Divisions - New
• For the latest, up to date listing
http://www.csinet.org/s_csi/docs/9400/9361.pdf
Types of contracts
• Owner – GC
• GC – Subcontractor
• Written
• Oral
• One party agrees to do something for
another in return for something !!!
Contract Documents
• You all work with many contract
documents every day
–Most common
• the plans and specs
Definition: Contract documents are the documented
instructions provided by the Owner or Agency to the
Contractor to construct a specific project
Contract Basics
• Common elements of a contract include:
–mutual consent
–offer and acceptance
–exchanging something of value
–operating in good faith
–delivering and performing
–no violations of public policy
Contract
• Contract Law Basics
– A contract is a legally enforceable agreement
between two or more parties that creates an
obligation to do or not do particular things
– 3 parts for a contract: Offer, Acceptance, and
Consideration. For construction, they must be in
writing
– Who, What, When, Where, and How Much
– Failure to Perform Under the Contract: “Breach”
Contract
Contract Law Basics: Contract drafting tips
• An effective contract should always be clear, specific,
and focussed
• Sentences should be short to avoid unnecessary
complexity and ambiguity
• Make sure all party names are accurate. Include their
business titles if applicable
• A contract should be consistent in its tone, grammar,
word useage, and abbreviations
Contract
Contract drafting tips
– Define Important terms
– Anticipate litigation by including sections regarding
venue, choice of law, and attorney fees.
– All parties should sign the contract, including
business titles if applicable
– Pages should be numbered. Avoid the appearance
that pages could have been added after the
agreement was signed
– As with any business writing, proofread very
carefully
Contract
As the PM, review contract carefully …
• Name of parties
• Date
• Scope
• Schedule
• Insurance
• Bonding
• Payment terms
• Indemnifications
• Termination
• LDs
• Special conditions
• Safety
• Warranties
• C.O. procedures
Lump Sum Contract
• Fixed Price / Lump Sum
– Pre-determined price
– Assumes risk for some unforseen conditions
– Owner pays price regardless of profit or loss
– Change Orders
• Additional work
• Design changes
• Unforseen conditions
– Liquidated damages
– Bonus payment (some contracts)
Cost-Plus Contract
• Cost-Plus contract
– Actual costs plus fee to cover OH & P
– Minimizes
• Escalation
• Unforseen conditions
• Material costs
• Changes
– Reimbursables have to be defined in the contract
– Creates atmosphere to find cost-effective solutions
– Have to document EVERYTHING !!!
Cost-Plus Contract
• Cost-Plus contract
– Reimbursables: materials, labor, salaries related to the
project, taxes, subcontractor payments, equipment, fees,
bonds, insurance etc
– Non-reimbursables: office overhead costs, damages,
negligence etc
– LOOK AT THE VARIATIONS ON PAGE 5.9
Target Contract
• Variation of lump sum + cost-plus
– Agreement on target costs
– Target profit (or fee)
– Not to Exceed price
Unit Price
• Price per unit remains the same
• If quantities increase or decrease (>25%)
– renegotiation
Letter contract
• Preliminary document to get project going
– Maximum costs
– Fees
– Scope
– Payment
– Cancellation
Fast-track Contract
• Design-build
– As design is completed in an area, construction contract is
processed
• Looks like a lot of work orders
Subcontract
• Contract between GC and subcontractor
– Prime contract conditions need to apply (make sure you
watch this)
– There is no contract with the Owner
– Careful with liens and PWR
– Manage your subs
Purchase Order
• Contract between GC and supplier
Insurance Requirements
• Lots needed
– Protect employees
– Protect Owners
– Protect the public
– Protect the Company
• Normally an office function separate from
PM
– But know what is required and what is in place
Workers’ Compensation
• Pays employees who are hurt on the job
– State statute
– Company has to maintain coverage
• In each state in which you work
– Injuries have to be reported
General Liability
• Covers claims for bodily injury or property
damage
– Company offices
– Construction activities
– Liability for subcontractor
– Completed work
– Liability assumed under the contract
• Therefore read it !!!
• There may be exclusions
Vehicle Insurance
• Make sure you have a company policy
• What if your employee pulls his own trailer,
boat outside of work hours ?
• Coverage
– Fire
– Theft
– Collision
– Vandalism
Builders’ Risk
• Covers damage to the work being performed
– Losses of materials
• Fire
• Theft
• Vandalism
• Unless provided by Owner, contractor
provides at 100% contract value
Equipment Floater
• Covers equipment not specifically covered
on the builders’ risk policy
• PM should make sure the office knows what
rental equipment is on the site
– Make sure coverage is in place
Property Insurance
• Covers all the other stuff ….
Project Correspondence
• Projects can generate a lot of paper
• As PM, you are the focal point
– Sets communication channels
– Relationship channels
– Affected parties
The Project Team
Task Owner Design Team Contractor
Establish the
standards of
performance
Prime Responsibility Assist / Advise Assist / Advise
Appoint advisors for
the Owner
Prime Responsibility
Select the Project
Manager
Prime Responsibility
Delegate authority
by contract
Prime Responsibility Reviews Reviews
Conceive, plan, &
design
Reviews Prime Responsibility
Provide technically
qualified team
members
Reviews Prime Responsibility Prime Responsibility
Construct to plans &
specifications
Reviews Reviews Prime Responsibility
Avoid conflicts of
interest
Prime Responsibility Prime Responsibility Prime Responsibility
Comply with official
requirements
Prime Responsibility Prime Responsibility Prime Responsibility
Project Chart of Authority
• PM tracks communications
•Communication often through
correspondence
•Correspondence includes:
•Drafted material
•Written material
•Printed material
Project Correspondence
• To handle the process
– Need a good filing system
• Has to be maintained
• A good filing system has
– Easy recovery abilities
– Good tracking capabilities
Project Correspondence
•Formal letters
•Memos
•Speed messages
•E-mails
•Directives
•R.F.I.s
•R.F.C.s
•N.O.I.s
•P.O.s
•Transmittals
•Minutes
•Reports
Project Correspondence
• Guidelines for correspondence
– Must address the subject
– Reflect company policy
– Think it through
– Re-read it
– Remember
• Know your audience
• How will they react
– Be concise
– Be polite
– Facts only !!!
Why Good Documents Matter
Reasons Good Documents are so Important
– Jobs take a long time/Hard to remember
– Thousand of documents - contract, notes,
telephone notes, faxes, drawings, photographs,
correspondence
– Years later
– Needed for reconstruction
Why Good Documents Matter
Reasons Good Documents are so Important
– Helps refute allegations of:
• Causation in delay cases
• Acceleration in delay cases
• Damage and cost
• What was said at the site
Why Good Documents Matter
Reasons Good Documents are so Important
– May be only record available
– Party with documentation appears on top of
things
– Helps you keep track
– Can’t predict the future/Personnel changes
Daily Reports
• Logs and tracks issues
• Permanent record of project
• Normally by field personnel
• Must be done daily
– Check !!!
What You Should Record on a
Daily Report
General Issues
• Job name
• Job number
• Report number
• Day
• Date
• Contract days left (if applicable)
What You Should Record on a
Daily Report
General Issues Continued
• Weather, including temperature range if
relevant-especially if it had an impact on the
work
• Do not use negative nicknames for site
problems
– Glory Hole #1
• Be factual
• Location of the work
• Sign in a legible manner
What You Should Record on a Daily
Report Continued...
Personnel Issues
• Keep it informative, not personal
• Who was at the site
• Who left the site and when
• Whether or not they returned and when
• Who was left in charge
What You Should Record on a Daily
Report Continued...
Delivery Related Issues
• When were key materials delivered
• Documentation related to delivery
• Who took possession
• Conditions of material upon delivery
• Where items were stored
• How long on site before inspection by contractor
What You Should Record on a Daily
Report Continued...
Equipment Related Issues
• What equipment was at the site
• If contract specified equipment - was it ever used
• When did it arrive
• How long did it stay
• What equipment broke down
• How long was it down
• Who repaired it
What You Should Record on a Daily
Report Continued...
Equipment Related Issues
• How long before someone came to repair it
• When was it repaired
• What was the replacement equipment
• If different, how did that affect efficiency
• How any delay affected the work
• What did the contractor work on during the repair
period
• Could other work have been done
What You Should Record on a Daily
Report Continued...
Work Related Issues
• Quality of work issues
• Quantity of material issues
• On-site conditions
• Occurrences
• Utilities encountered
• Work interruption/shutdown
• Testing Efforts/Results
What You Should Record on a Daily
Report Continued...
Work Related Issues
• Any event that had an adverse affect and who caused
it
• All changes to the work
– Who authorized
– How authorized
• Importance of change orders
• Force account of work in detail
• Complaints and the results of any investigation
• Overtime inspection
• Construction Methods
What You Should Record on a Daily
Report Continued...
Damage to Property
• Public or Private
• When it occurred
• When it was discovered
• How it was discovered i.e. did we happen upon it ?,
did the contractor reveal it ?, did the contractor
conceal it ?
• What photographs were taken
• Contractors response to discovery, comments too
• Contact between the contractor and private citizens
What You Should Record on a Daily
Report Continued...
On-Site Working conditions
• Water
• Any and all efforts to dewater - timing, methods, and
consequences
• Weather
• Rock - size, number, location
• Sand, silt, clay
• Photographs very useful here
• Comments regarding failure to make pre-bid
inspection or having insufficient time to make pre-bid
inspection
What You Should Record on a Daily
Report Continued...
On-Site Working conditions
• Any comments regarding anticipated conditions and
how existing conditions differ
• Contacts regarding pre-bid contract interpretation
relating to soils
Making Daily Reports Only a
Lawyer Could Love
• You never know which fact will be
key
• Treat each day as if it held the key
to a major suit - Even before
construction begins
Templates for Daily Reports
• Fisk
• Others
Meetings
• Meetings should be planned
• Agenda should be written
• Minutes should be taken
• Minutes should be distributed
– Obtain approval
– Correct errors
Project Photographs
• Good way to track
– Daily progress
– Existing conditions
– Quality of work
– Stored materials
– Methods being used
– Issues (by sending a picture !!!)
Schedule
Overview
• Estimate of time
• Sequence of activities
• Should be reviewed and updated regularly
• Include everything that affects your project timeline
Time cards
Overview
• Records labor and equipment in real time
• Helps verify extras
• Include
– Hours worked
– Area of work
– Work accomplished
– Material used
Shop Drawings
Overview
• Supplements the contract drawings
• More detail
– Some can be used for production/fabrication
• Include
– Drawings
– Schedules
– Lists
– Performance data
– Samples
– Vendor drawings
– submittals
Shop Drawings
• Submittal process
– Submit before delivering material
– Material has to be approved for use in the work
– Some projects have extensive submittal requirements
– Maintain a log !!!
Shop Drawings
• Submittal process
– Log in drawings when received
– Verify you have the correct data
– Verify the contract requirements for number
– Review for accuracy
– Submit to A/E
– Review when returned
• Careful
– Revise and resubmit
– No exceptions taken
Back Charges
• For work outside the scope of the contract
• Work performed by one party that should have been
performed by the other
• Sometimes they are arranged
• Back charges are a form of change order
– Handle accordingly
– Review documentation
Back Charge Examples
• Contractor loans scaffolding
• Loan of a pump
• Clean up of site
• Materials provided to another entity
Change Orders
• Cause work
• Cause anxiety
• Change orders
– Reflect a change in design or construction process
• Directed by Owner
• Approved by Owner
• Can be additive or deductive
• Typically are unavoidable
– Make sure you evaluate all directives
• In terms of your contract
– Not in contract ?
» Change order
Reasons for Change Orders
• Document errors or omissions
• Scope changes by Owner
• Adjustment to schedule
• Code changes
• Change in specified materials
Change Order Process
•Process should include:
• Scope
• Justification
• Cost impact
• Schedule impact
• Overall impact
• Include in progress meetings
• Keep everyone informed
Cost of Change Orders
• Define the work
• Determine quantities
• Obtain costs
– Material, labor, equipment, subs, suppliers
• Analyze impact on schedule
• Determine O/H
• Determine allowable markup / fee
• Determine impact on bond
Cost of Change Orders
DESCRIPTION/REQUEST
MATERIAL
Material $0.00
Equipment Fees $0.00
Material & Equipment Sub-Total $0.00
Material & Equipment Mark-Up 10.00% $0.00
LABOR
Laborer 0.00 Manhours @ $60.00 $0.00
Supervisor 3.00 Manhours @ $70.00 $210.00
Labor Sub-Total $210.00
Labor Mark-Up 15.00% $31.50
SUBCONTRACTORS
Subcontract- $4,885.00
Subcontractors Sub-Total $4,885.00
Subcontractor Mark-Up 10.00% $488.50
MISCELLANEOUS
Permits & Fees $0.00
Direct Job Costs $0.00
Misc. - $56.15
Miscellaneous Sub-Total $56.15
SUBTOTAL $5,671.15
General Conditions 2.41% $136.67
3.20% $181.48
TOTAL PRICE OF CHANGE ORDER REQUEST $5,989.00
This is a change order for all the over excavation (to date) that was requested to be over excavated by the Geo teck. The
quanitys to date are 118 CYof bad soils.
Fuel
Bond & Insurance
Change Orders & Claims
• If change order is disputed, it can become a claim
• Make sure all documentation is in order
– This is the foundation for your claim
• Remember
– Meeting minutes
– Discussion notes
– Change order procedures
– Weather conditions
– Workforce issues
– Schedule impacts
– Revised design drawings
– Photographs
Contractor Payments
• Payment documentation
– Request for payment
– Waivers and affadavits
– Certificate for payment
– Final payment request
ALL THIS IS DISCUSSED IN THE CONTRACT PROVISIONS
Know them !!!
Contractor Payments
• Request for payment
– Based on completed work, up to a specific date
– Sometimes can include materials on hand
– Schedule of values ( lump sum projects)
– Reviewed by Owner
• Waivers and affadavits
– Payments to subcontractors
– Payments to suppliers
• Certificate for Payment
– For lending institution
– Discuss
• Final Payment Request
– Release of retainage
– Final lien releases
Close-out
• Begins at substantial completion
• Purpose is to assure the Owner has a finished product
• Discuss
Close-out
• Substantial completion
• Close-out procedures
– Don’t forget the suppliers and subcontractors
– Testing
– Inspections
– Certifications
– Records
• Project Inspection
• Punchlist (Deficiency List)
• Owner Acceptance
• Certificate of Occupancy
• Record Drawings
• O&M Manuals
Summary Thoughts
• Accuracy
– Do not mis-state the facts
• Objectivity
– Do not be biased
• Completeness
– Fill out documents completely
• Uniformity
– Be precise, concise and well defined
• Credibility
• Timeliness
We Have Arrived !!!

More Related Content

What's hot

Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentationcynfang Fong
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingSubash Bhattarai
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project managementMC Tubera
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction pptgyan singh
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 

What's hot (20)

ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Construction management
Construction managementConstruction management
Construction management
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and scheduling
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Quantity Surveyors (Practice)
Quantity Surveyors (Practice)Quantity Surveyors (Practice)
Quantity Surveyors (Practice)
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
Estimation
EstimationEstimation
Estimation
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 

Viewers also liked

Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 
Construction Documents Checklist
Construction Documents ChecklistConstruction Documents Checklist
Construction Documents ChecklistMilton Grew
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project managementAli Heydari
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender ManagementAnand Subramaniam
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Types of contract
Types of contractTypes of contract
Types of contractSweetp999
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Current e manual
Current e manualCurrent e manual
Current e manualAYM1979
 
Compile version communication in consruction
Compile version communication in consructionCompile version communication in consruction
Compile version communication in consructionYap Xin
 
The Agile Architect - CAMUG - Oct 1, 2015
The Agile Architect - CAMUG - Oct 1, 2015The Agile Architect - CAMUG - Oct 1, 2015
The Agile Architect - CAMUG - Oct 1, 2015Chris Edwards, P.Eng.
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
How To Manage Projects Effectively
How To Manage Projects EffectivelyHow To Manage Projects Effectively
How To Manage Projects Effectivelyguest1e7427
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documentselliegirl07
 

Viewers also liked (20)

Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Construction Documents Checklist
Construction Documents ChecklistConstruction Documents Checklist
Construction Documents Checklist
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
ACH 231 Lecture 07 (Contract Documents) Part 3
ACH 231 Lecture 07 (Contract Documents) Part 3ACH 231 Lecture 07 (Contract Documents) Part 3
ACH 231 Lecture 07 (Contract Documents) Part 3
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Types of contract
Types of contractTypes of contract
Types of contract
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Current e manual
Current e manualCurrent e manual
Current e manual
 
Compile version communication in consruction
Compile version communication in consructionCompile version communication in consruction
Compile version communication in consruction
 
The Agile Architect - CAMUG - Oct 1, 2015
The Agile Architect - CAMUG - Oct 1, 2015The Agile Architect - CAMUG - Oct 1, 2015
The Agile Architect - CAMUG - Oct 1, 2015
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
How To Manage Projects Effectively
How To Manage Projects EffectivelyHow To Manage Projects Effectively
How To Manage Projects Effectively
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 

Similar to Construction Documents

Renovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner ViewRenovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner ViewConstruction Cicerone
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalZakee Kazmee
 
Construction Management - L1 (1).ppt
Construction Management - L1 (1).pptConstruction Management - L1 (1).ppt
Construction Management - L1 (1).pptmona700185
 
Construction management l1
Construction management   l1Construction management   l1
Construction management l1Faisal Rana
 
Specification writing
Specification writingSpecification writing
Specification writingBSRIA
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consultingThis account is closed
 
Lecture series on Civil Engineering - Understanding Crucial aspects of constr...
Lecture series on Civil Engineering - Understanding Crucial aspects of constr...Lecture series on Civil Engineering - Understanding Crucial aspects of constr...
Lecture series on Civil Engineering - Understanding Crucial aspects of constr...John Sushil Packiaraj
 
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...Galala University
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Construction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptxConstruction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptxMaxwellAcquah1
 
Brokerage Simplified
Brokerage SimplifiedBrokerage Simplified
Brokerage Simplifiedmcmahonkevin
 
Model Format for Building Services Specifications
Model Format for Building Services SpecificationsModel Format for Building Services Specifications
Model Format for Building Services SpecificationsBSRIA
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
working drawing basic
working drawing basic working drawing basic
working drawing basic download26
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Professional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbalProfessional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbalZakee Kazmee
 
How to get builders wanting to work with you as a landlord
How to get builders wanting to work with you as a landlordHow to get builders wanting to work with you as a landlord
How to get builders wanting to work with you as a landlordRob Turner
 

Similar to Construction Documents (20)

Renovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner ViewRenovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner View
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbal
 
Construction Management - L1 (1).ppt
Construction Management - L1 (1).pptConstruction Management - L1 (1).ppt
Construction Management - L1 (1).ppt
 
Construction management l1
Construction management   l1Construction management   l1
Construction management l1
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Specification writing
Specification writingSpecification writing
Specification writing
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 
Lecture series on Civil Engineering - Understanding Crucial aspects of constr...
Lecture series on Civil Engineering - Understanding Crucial aspects of constr...Lecture series on Civil Engineering - Understanding Crucial aspects of constr...
Lecture series on Civil Engineering - Understanding Crucial aspects of constr...
 
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...Guc arct 702 legislations   lecture 10 - contract issues for architectural fi...
Guc arct 702 legislations lecture 10 - contract issues for architectural fi...
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Construction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptxConstruction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptx
 
Brokerage Simplified
Brokerage SimplifiedBrokerage Simplified
Brokerage Simplified
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Model Format for Building Services Specifications
Model Format for Building Services SpecificationsModel Format for Building Services Specifications
Model Format for Building Services Specifications
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
working drawing basic
working drawing basic working drawing basic
working drawing basic
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Professional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbalProfessional practices (lec 04) by k.iqbal
Professional practices (lec 04) by k.iqbal
 
How to get builders wanting to work with you as a landlord
How to get builders wanting to work with you as a landlordHow to get builders wanting to work with you as a landlord
How to get builders wanting to work with you as a landlord
 

Construction Documents

  • 2. Today’s Presentation • Obtaining work in the construction industry • Project Manual • Drawings and Specifications • Types of Contracts • Insurance Requirements • Project Correspondence • Change Orders • Contractor Payments • Closeout
  • 3. Overview • Documentation is vital !!! • Poor documentation causes problems – Most problems – Second most, poor administration • Documentation – Who, what when, where, why and how – Facts, facts, facts – Specific to the type of project
  • 4. Trade terms • Addenda • Bid bond • Change Order • Construction Specification Institute (CSI) • Punch list • Scope • Specifications • Shop drawings
  • 5. Introduction • Documentation: – Records the progress • Controls the time spent – Keeps track of costs – Need procedures in place early • Maintain throughout the project – Types • Daily log • Photographs • Correspondence
  • 6. What is Documentation? • Documentation includes... –a complete record of the project –all contract documents –records of circumstances –daily reports –meeting minutes
  • 7. What is Documentation? • Other items include –Schedules –Site visit records –Telephone logs –Minutes of Meetings –Job correspondence –Diaries –Job logs –Time cards –Photos
  • 8. Documentation Systems – Documentation is... • a systematic process for keeping regular, accurate, complete and legible records of daily activities, actual circumstances, and unusual events on a project
  • 9. Why Documentation Is So Important • Good documentation can... –identify issues –resolve conflicts –settle disputes –avoid litigation –provide tangible proof
  • 10. Why Documentation Is So Important
  • 11. Good Documentation Practices • Good documentation must be... –accurate –objective –complete –uniform –credible –timely
  • 12. What to Document • Everything !!! •Murphy’s Law –The most insignificant piece of information will become the item that is most important if you don’t document it –The item you don’t document will be the one that someone wants to see
  • 13. What to Document • No opinions •No placing of blame •No guesses •No theories •And absolutely do not modify notes
  • 14. How to Document • Documentation Tools –Computers –Photographs –Video cameras –Audio recorders –Written reports –Daily logs
  • 15. Obtaining work in the Construction Industry • Competitive bid • Invited bid • Negotiation • Design-build • Construction Management
  • 16. Obtaining work in the Construction Industry • Competitive bid – Owner produces documents – Contractor reviews documents • Solicits subcontractor input – Submits bid for completion of the work – Owner awards to lowest, responsive bidder
  • 17. Obtaining work in the Construction Industry • Invited bid – Similar to standard process except • Prequalification – Experience – Finances – Workload – Goal is to limit pool to similarly qualified contractors
  • 18. Obtaining work in the Construction Industry • Negotiation – Proposal based – Interview • Cost • Schedule • Approach • Staffing • Experience
  • 19. Obtaining work in the Construction Industry • Design-build – One entity • Provides – Design – Construction
  • 20. Obtaining work in the Construction Industry • Construction Management – CM-GC – Third party CM
  • 21. Summary • Traditional (Competitive / Invited) OWNER CONTRACTOR DESIGN PROFESSIONAL SUB- CONTRACTORS SUBCONSULTANTS
  • 24. Summary • You may split your pursuits across all these lines – What do you do ? • Whatever you do – Use your resources the most effectively
  • 25. Project Manual • Aka “spec book” + drawings etc • Includes – Bidding documents – Contract forms – Specifications – Drawings – Other information (depends on project) • Permits, geotechnical, etc etc
  • 26. Contract Documents • Drawings graphically provide: – arrangements – materials – dimensions – configurations – other...
  • 27. Contract Documents • Drawings provide: –Arrangement, materials, dimensions, configuration, and other information about the project that communicate the engineer’s design for the project.
  • 28. Contract Documents • Specifications provide: –written instructions that detail project requirements –information that is not easily shown on drawings
  • 29. Specification Sections •Advertisement •Instructions to Bidders •Proposal •Agreement •Bond •Insurance •Wage Rates •General conditions •Technicals
  • 30. Additional Key Contract Documents • Other key documents: –contract –subcontract –general conditions –supplemental conditions –addenda and change orders –purchase orders –request for information (RFI)
  • 31. Contract Documents • Precedence: –Set by the Author of the specifications –Normally • Special provisions • General Provisions • Detailed Drawings • General Drawings • Standard Specifications and Drawings
  • 32. Other Documents • Special Instructions •Stop Work Orders •Soil Reports •Purchasing Lists •Substantial Completion •Final Completion
  • 33. Peripheral Documents • Shop Drawings •Submittals •Codes and Permits •Agreements •ASK QUESTIONS –What, Why, Who, and What do I need to do ?
  • 34. Contract Documents • Identify and learn to recognize contract documents • Define a contract and understand basic legal terms used in construction documents • Study the relationships among various contractual parties
  • 35. Project Manual • Typical manual will include: – Invitation to bid – Instructions to bidders – Bid form – Bid bond – Performance/payment bond – Agreement – General conditions – Supplementary conditions – Specifications – Drawings and addenda
  • 36. Invitation to bid • This is what you see in the DJC or on the Contractors Plan Center website – Gives you the information to know whether the project is one you are interested in • Includes – Project Owner, A/E, Agency – Description – Type of bid – Time for completion – Bid date – Where you can get the documents – Requirements for prequalification / mandatory pre-bids – Etc
  • 37. Instructions to bidders • Explains what you need to do – To comply with the bid requirements i.e. be responsive • Could include – Resolution of discrepancies – Substitution of products – Bid submittal requirements • How many copies • Signatures • Where to send it • Subcontractor lists • Etc etc – Laws and Regulations
  • 38. Bid Form • Reports what your offer is – Standardized to allow easy comparison – Evaluated • Balanced • Unbalanced • Responsive • Unresponsive • Totals add up • Addenda received
  • 39. Bid Bond • Makes agreement that the bid will be honored for a period of time • Makes an agreement that the contractor will perform the work if awarded the contract • Percentage of bid amount • Comes from your bonding agent • Can be forfeited if you back away from the project
  • 40. Performance and Payment Bond • Guarantees that the contractor will fulfill the contract terms • Provides indemnity for liens • 100% of bid amount • Comes from your bonding agent • If contractor defaults – Surety (bonding company) takes over the project • Assumes financial responsibility • Solicits another contractor
  • 41. Form of Agreement • Included in project manual – It is a contract – Needs to be reviewed by legal counsel
  • 42. General Conditions • GCs define the contractual relationships • Different types – AIA – EJCDC – AGC – Owner Provided • Specific to the particular project
  • 43. • The General Conditions... –establish a common basis for relationships on a project –classify and clarify duties –help to avoid disputes –guide contractors in the execution of the project –They are overall procedures of how the contract provisions are to be implemented. General Conditions
  • 44. Using GCs to Make Decisions • General Conditions – remember there are different forms –GCs are often incorporated into other forms •Owner/Architect •Owner /Engineer •Contractor/Subcontractor •Goal is to be consistent at all levels
  • 45. Using GCs to Make Decisions • As a Supervisor –Determine what level of authority you have •Basis of Authority –Contractor –Owner –Design Professional
  • 46. Using GCs to Make Decisions •Basis of Authority –Contractor – Perform the work in accordance with the contract documents –Owner – has the ultimate “Say” –Design Professional – responsible for technical evaluations Remember, these levels of authority are covered in the General Conditions
  • 47. • Supplementary Conditions... –provide information that is specific to a project –immediately follows the General Conditions –are also referred to as Special Conditions –should be reviewed and discussed prior to starting a project Supplementary Conditions
  • 48. • Information that supports and describes the construction drawings Specifications
  • 49. Addenda • Used to modify the contract before the bid date • Issued by Owner – Deficiencies – Discrepancies – Errors – Clarification An addendum is exactly the same as a change order except that it occurs pre-bid
  • 50. Drawings And Specifications • Project Managers have to be able to read and understand the drawings and specifications !!! – You have to be willing and able to discuss and communicate their content
  • 51. Types of Drawings • Conceptual – Used for evaluation of project during planning phase • Preliminary – Used to perform reviews, submit for agency review, estimating (budget) • Working or Construction – Used in the bidding process
  • 52. Reading Drawings • Conceptual – Used for evaluation of project during planning phase • Preliminary – Used to perform reviews, submit for agency review, estimating (budget) • Working or Construction – Used in the bidding process
  • 53. Reading Drawings • Understand the notation and nomenclature • Get an idea of the methods being used • Composites sometimes can help
  • 54. Reading Drawings • Review – Site drawings ( C and G) – Structural (S) – Architectural (A) – Mechanical (M or P) – Electrical (E) – Detail sheets – Overlay and coordinate disciplines – Erosion control
  • 55. Specifications • Three purposes – Define roles – Provide detailed technical information – Support the drawings as part of the Project Manual
  • 56. Specifications • Three purposes – Define roles – Provide detailed technical information – Support the drawings as part of the Project Manual • Format – CSI – ODOT/APWA – WSDOT – FHWA
  • 57. Technical Specification Section Divisions - Old •Division 1 General •Division 2 Site work •Division 3 Concrete •Division 4 Masonry •Division 5 Metals •Division 6 Carpentry •Division 7 Moisture Protection •Division 8 Doors, Windows and Glass •Division 9 Finishes •Division 10 Specialties •Division 11 Equipment •Division 12 Furnishings •Division13 Special Construction •Division 14 Conveying Systems •Division 15 Mechanical •Division 16 Electrical
  • 58. Technical Specification Section Divisions - New •Division 1: General Requirements •Division 2: Existing Conditions •Division 3: Concrete •Division 4: Masonry •Division 5: Metals •Division 6: Wood, Plastics and Composites •Division 7: Thermal and Moisture Protection •Division 8: Openings •Division 9: Finishes (interior finishes) •Division 10: Specialties (for example, signs, toilet accessories) •Division 11: Equipment (for example, kitchen equipment) •Division 12: Furnishings •Division 13: Special Construction (for example, greenhouses) •Division 14: Conveying Equipment (elevators, escalators, lifts) •Division 21: Fire Suppression •Division 22: Plumbing •Division 23: Heating, Ventilating and Air Conditioning •Division 26: Electrical •Division 27: Communications •Division 28: Electronic Safety and Security •Division 31: Earthwork •Division 32: Exterior Improvements •Division 33: Utilities
  • 59. Technical Specification Section Divisions - New • For the latest, up to date listing http://www.csinet.org/s_csi/docs/9400/9361.pdf
  • 60. Types of contracts • Owner – GC • GC – Subcontractor • Written • Oral • One party agrees to do something for another in return for something !!!
  • 61. Contract Documents • You all work with many contract documents every day –Most common • the plans and specs Definition: Contract documents are the documented instructions provided by the Owner or Agency to the Contractor to construct a specific project
  • 62. Contract Basics • Common elements of a contract include: –mutual consent –offer and acceptance –exchanging something of value –operating in good faith –delivering and performing –no violations of public policy
  • 63. Contract • Contract Law Basics – A contract is a legally enforceable agreement between two or more parties that creates an obligation to do or not do particular things – 3 parts for a contract: Offer, Acceptance, and Consideration. For construction, they must be in writing – Who, What, When, Where, and How Much – Failure to Perform Under the Contract: “Breach”
  • 64. Contract Contract Law Basics: Contract drafting tips • An effective contract should always be clear, specific, and focussed • Sentences should be short to avoid unnecessary complexity and ambiguity • Make sure all party names are accurate. Include their business titles if applicable • A contract should be consistent in its tone, grammar, word useage, and abbreviations
  • 65. Contract Contract drafting tips – Define Important terms – Anticipate litigation by including sections regarding venue, choice of law, and attorney fees. – All parties should sign the contract, including business titles if applicable – Pages should be numbered. Avoid the appearance that pages could have been added after the agreement was signed – As with any business writing, proofread very carefully
  • 66. Contract As the PM, review contract carefully … • Name of parties • Date • Scope • Schedule • Insurance • Bonding • Payment terms • Indemnifications • Termination • LDs • Special conditions • Safety • Warranties • C.O. procedures
  • 67. Lump Sum Contract • Fixed Price / Lump Sum – Pre-determined price – Assumes risk for some unforseen conditions – Owner pays price regardless of profit or loss – Change Orders • Additional work • Design changes • Unforseen conditions – Liquidated damages – Bonus payment (some contracts)
  • 68. Cost-Plus Contract • Cost-Plus contract – Actual costs plus fee to cover OH & P – Minimizes • Escalation • Unforseen conditions • Material costs • Changes – Reimbursables have to be defined in the contract – Creates atmosphere to find cost-effective solutions – Have to document EVERYTHING !!!
  • 69. Cost-Plus Contract • Cost-Plus contract – Reimbursables: materials, labor, salaries related to the project, taxes, subcontractor payments, equipment, fees, bonds, insurance etc – Non-reimbursables: office overhead costs, damages, negligence etc – LOOK AT THE VARIATIONS ON PAGE 5.9
  • 70. Target Contract • Variation of lump sum + cost-plus – Agreement on target costs – Target profit (or fee) – Not to Exceed price
  • 71. Unit Price • Price per unit remains the same • If quantities increase or decrease (>25%) – renegotiation
  • 72. Letter contract • Preliminary document to get project going – Maximum costs – Fees – Scope – Payment – Cancellation
  • 73. Fast-track Contract • Design-build – As design is completed in an area, construction contract is processed • Looks like a lot of work orders
  • 74. Subcontract • Contract between GC and subcontractor – Prime contract conditions need to apply (make sure you watch this) – There is no contract with the Owner – Careful with liens and PWR – Manage your subs
  • 75. Purchase Order • Contract between GC and supplier
  • 76. Insurance Requirements • Lots needed – Protect employees – Protect Owners – Protect the public – Protect the Company • Normally an office function separate from PM – But know what is required and what is in place
  • 77. Workers’ Compensation • Pays employees who are hurt on the job – State statute – Company has to maintain coverage • In each state in which you work – Injuries have to be reported
  • 78. General Liability • Covers claims for bodily injury or property damage – Company offices – Construction activities – Liability for subcontractor – Completed work – Liability assumed under the contract • Therefore read it !!! • There may be exclusions
  • 79. Vehicle Insurance • Make sure you have a company policy • What if your employee pulls his own trailer, boat outside of work hours ? • Coverage – Fire – Theft – Collision – Vandalism
  • 80. Builders’ Risk • Covers damage to the work being performed – Losses of materials • Fire • Theft • Vandalism • Unless provided by Owner, contractor provides at 100% contract value
  • 81. Equipment Floater • Covers equipment not specifically covered on the builders’ risk policy • PM should make sure the office knows what rental equipment is on the site – Make sure coverage is in place
  • 82. Property Insurance • Covers all the other stuff ….
  • 83. Project Correspondence • Projects can generate a lot of paper • As PM, you are the focal point – Sets communication channels – Relationship channels – Affected parties
  • 84. The Project Team Task Owner Design Team Contractor Establish the standards of performance Prime Responsibility Assist / Advise Assist / Advise Appoint advisors for the Owner Prime Responsibility Select the Project Manager Prime Responsibility Delegate authority by contract Prime Responsibility Reviews Reviews Conceive, plan, & design Reviews Prime Responsibility Provide technically qualified team members Reviews Prime Responsibility Prime Responsibility Construct to plans & specifications Reviews Reviews Prime Responsibility Avoid conflicts of interest Prime Responsibility Prime Responsibility Prime Responsibility Comply with official requirements Prime Responsibility Prime Responsibility Prime Responsibility
  • 85. Project Chart of Authority • PM tracks communications •Communication often through correspondence •Correspondence includes: •Drafted material •Written material •Printed material
  • 86. Project Correspondence • To handle the process – Need a good filing system • Has to be maintained • A good filing system has – Easy recovery abilities – Good tracking capabilities
  • 87. Project Correspondence •Formal letters •Memos •Speed messages •E-mails •Directives •R.F.I.s •R.F.C.s •N.O.I.s •P.O.s •Transmittals •Minutes •Reports
  • 88. Project Correspondence • Guidelines for correspondence – Must address the subject – Reflect company policy – Think it through – Re-read it – Remember • Know your audience • How will they react – Be concise – Be polite – Facts only !!!
  • 89. Why Good Documents Matter Reasons Good Documents are so Important – Jobs take a long time/Hard to remember – Thousand of documents - contract, notes, telephone notes, faxes, drawings, photographs, correspondence – Years later – Needed for reconstruction
  • 90. Why Good Documents Matter Reasons Good Documents are so Important – Helps refute allegations of: • Causation in delay cases • Acceleration in delay cases • Damage and cost • What was said at the site
  • 91. Why Good Documents Matter Reasons Good Documents are so Important – May be only record available – Party with documentation appears on top of things – Helps you keep track – Can’t predict the future/Personnel changes
  • 92. Daily Reports • Logs and tracks issues • Permanent record of project • Normally by field personnel • Must be done daily – Check !!!
  • 93. What You Should Record on a Daily Report General Issues • Job name • Job number • Report number • Day • Date • Contract days left (if applicable)
  • 94. What You Should Record on a Daily Report General Issues Continued • Weather, including temperature range if relevant-especially if it had an impact on the work • Do not use negative nicknames for site problems – Glory Hole #1 • Be factual • Location of the work • Sign in a legible manner
  • 95. What You Should Record on a Daily Report Continued... Personnel Issues • Keep it informative, not personal • Who was at the site • Who left the site and when • Whether or not they returned and when • Who was left in charge
  • 96. What You Should Record on a Daily Report Continued... Delivery Related Issues • When were key materials delivered • Documentation related to delivery • Who took possession • Conditions of material upon delivery • Where items were stored • How long on site before inspection by contractor
  • 97. What You Should Record on a Daily Report Continued... Equipment Related Issues • What equipment was at the site • If contract specified equipment - was it ever used • When did it arrive • How long did it stay • What equipment broke down • How long was it down • Who repaired it
  • 98. What You Should Record on a Daily Report Continued... Equipment Related Issues • How long before someone came to repair it • When was it repaired • What was the replacement equipment • If different, how did that affect efficiency • How any delay affected the work • What did the contractor work on during the repair period • Could other work have been done
  • 99. What You Should Record on a Daily Report Continued... Work Related Issues • Quality of work issues • Quantity of material issues • On-site conditions • Occurrences • Utilities encountered • Work interruption/shutdown • Testing Efforts/Results
  • 100. What You Should Record on a Daily Report Continued... Work Related Issues • Any event that had an adverse affect and who caused it • All changes to the work – Who authorized – How authorized • Importance of change orders • Force account of work in detail • Complaints and the results of any investigation • Overtime inspection • Construction Methods
  • 101. What You Should Record on a Daily Report Continued... Damage to Property • Public or Private • When it occurred • When it was discovered • How it was discovered i.e. did we happen upon it ?, did the contractor reveal it ?, did the contractor conceal it ? • What photographs were taken • Contractors response to discovery, comments too • Contact between the contractor and private citizens
  • 102. What You Should Record on a Daily Report Continued... On-Site Working conditions • Water • Any and all efforts to dewater - timing, methods, and consequences • Weather • Rock - size, number, location • Sand, silt, clay • Photographs very useful here • Comments regarding failure to make pre-bid inspection or having insufficient time to make pre-bid inspection
  • 103. What You Should Record on a Daily Report Continued... On-Site Working conditions • Any comments regarding anticipated conditions and how existing conditions differ • Contacts regarding pre-bid contract interpretation relating to soils
  • 104. Making Daily Reports Only a Lawyer Could Love • You never know which fact will be key • Treat each day as if it held the key to a major suit - Even before construction begins
  • 105. Templates for Daily Reports • Fisk • Others
  • 106. Meetings • Meetings should be planned • Agenda should be written • Minutes should be taken • Minutes should be distributed – Obtain approval – Correct errors
  • 107. Project Photographs • Good way to track – Daily progress – Existing conditions – Quality of work – Stored materials – Methods being used – Issues (by sending a picture !!!)
  • 108. Schedule Overview • Estimate of time • Sequence of activities • Should be reviewed and updated regularly • Include everything that affects your project timeline
  • 109. Time cards Overview • Records labor and equipment in real time • Helps verify extras • Include – Hours worked – Area of work – Work accomplished – Material used
  • 110. Shop Drawings Overview • Supplements the contract drawings • More detail – Some can be used for production/fabrication • Include – Drawings – Schedules – Lists – Performance data – Samples – Vendor drawings – submittals
  • 111. Shop Drawings • Submittal process – Submit before delivering material – Material has to be approved for use in the work – Some projects have extensive submittal requirements – Maintain a log !!!
  • 112. Shop Drawings • Submittal process – Log in drawings when received – Verify you have the correct data – Verify the contract requirements for number – Review for accuracy – Submit to A/E – Review when returned • Careful – Revise and resubmit – No exceptions taken
  • 113. Back Charges • For work outside the scope of the contract • Work performed by one party that should have been performed by the other • Sometimes they are arranged • Back charges are a form of change order – Handle accordingly – Review documentation
  • 114. Back Charge Examples • Contractor loans scaffolding • Loan of a pump • Clean up of site • Materials provided to another entity
  • 115. Change Orders • Cause work • Cause anxiety • Change orders – Reflect a change in design or construction process • Directed by Owner • Approved by Owner • Can be additive or deductive • Typically are unavoidable – Make sure you evaluate all directives • In terms of your contract – Not in contract ? » Change order
  • 116. Reasons for Change Orders • Document errors or omissions • Scope changes by Owner • Adjustment to schedule • Code changes • Change in specified materials
  • 117. Change Order Process •Process should include: • Scope • Justification • Cost impact • Schedule impact • Overall impact • Include in progress meetings • Keep everyone informed
  • 118. Cost of Change Orders • Define the work • Determine quantities • Obtain costs – Material, labor, equipment, subs, suppliers • Analyze impact on schedule • Determine O/H • Determine allowable markup / fee • Determine impact on bond
  • 119. Cost of Change Orders DESCRIPTION/REQUEST MATERIAL Material $0.00 Equipment Fees $0.00 Material & Equipment Sub-Total $0.00 Material & Equipment Mark-Up 10.00% $0.00 LABOR Laborer 0.00 Manhours @ $60.00 $0.00 Supervisor 3.00 Manhours @ $70.00 $210.00 Labor Sub-Total $210.00 Labor Mark-Up 15.00% $31.50 SUBCONTRACTORS Subcontract- $4,885.00 Subcontractors Sub-Total $4,885.00 Subcontractor Mark-Up 10.00% $488.50 MISCELLANEOUS Permits & Fees $0.00 Direct Job Costs $0.00 Misc. - $56.15 Miscellaneous Sub-Total $56.15 SUBTOTAL $5,671.15 General Conditions 2.41% $136.67 3.20% $181.48 TOTAL PRICE OF CHANGE ORDER REQUEST $5,989.00 This is a change order for all the over excavation (to date) that was requested to be over excavated by the Geo teck. The quanitys to date are 118 CYof bad soils. Fuel Bond & Insurance
  • 120. Change Orders & Claims • If change order is disputed, it can become a claim • Make sure all documentation is in order – This is the foundation for your claim • Remember – Meeting minutes – Discussion notes – Change order procedures – Weather conditions – Workforce issues – Schedule impacts – Revised design drawings – Photographs
  • 121. Contractor Payments • Payment documentation – Request for payment – Waivers and affadavits – Certificate for payment – Final payment request ALL THIS IS DISCUSSED IN THE CONTRACT PROVISIONS Know them !!!
  • 122. Contractor Payments • Request for payment – Based on completed work, up to a specific date – Sometimes can include materials on hand – Schedule of values ( lump sum projects) – Reviewed by Owner • Waivers and affadavits – Payments to subcontractors – Payments to suppliers • Certificate for Payment – For lending institution – Discuss • Final Payment Request – Release of retainage – Final lien releases
  • 123. Close-out • Begins at substantial completion • Purpose is to assure the Owner has a finished product • Discuss
  • 124. Close-out • Substantial completion • Close-out procedures – Don’t forget the suppliers and subcontractors – Testing – Inspections – Certifications – Records • Project Inspection • Punchlist (Deficiency List) • Owner Acceptance • Certificate of Occupancy • Record Drawings • O&M Manuals
  • 125. Summary Thoughts • Accuracy – Do not mis-state the facts • Objectivity – Do not be biased • Completeness – Fill out documents completely • Uniformity – Be precise, concise and well defined • Credibility • Timeliness