SlideShare a Scribd company logo
Claims according to FIDIC Red Book
By
Naresh Gattupalli,PMP®
B.Tech (Civil), M.Tech (SE), PGD ACM & PGD ADR
 The International Federation of Consulting Engineers (FIDIC) has devoted itself to the compilation of management
documents for all kinds of projects, among which the FIDIC Conditions of Contract are of the highest influence
and are the most popular Application
 The first edition of FIDIC Conditions of Contract for Works of Civil Engineering Construction (use “Red Book” in the
following) was compiled in 1957, and later its second, third, and fourth edition were issued in 1963, 1977, and
1987 respectively
 With the investigation of the governments, employers, contractors and consulting engineers all over the world
about their application of the “Red Book”, 204 findings reports were returned. According to the findings, the FIDIC
Contract Committee organized a group of experts to compile the new Contract Condition models to be applied in
the 21stcentury
 The test edition of these models was published in 1998, and FIDIC solicited opinions throughout the world for
additional time to publish the official texts in 1999.
 Now FIDIC condition of contract has been applied worldwide, especially in the projects invested by World Bank,
Asia Development Bank, Africa Development Bank etc.
Background
The new models include :
1. FIDIC Conditions of Contract for Construction, the (New Red Book)
2. FIDIC Conditions of Contract for Plant and Design/Build, the (New Yellow Book)
3. FIDIC Conditions of Contract for EPC Turnkey Projects, the (Silver Book)
4. FIDIC Short Form of Contract, the (Green Book)
 New Red Book --- Any kind of Engineering Construction Contract.
 New Yellow Book --- Lump sum contract project where the Contractor takes participation in the design work.
 Silver Book --- Turnkey projects of infrastructures or large-scale factories, where the Contractor takes
on more work and risk while the Employer’s participation is small (private financing or
government financing), but it is strictly defined upon the investment and construction
period.
 Green Book --- All kinds of small-scale projects
 Gold Book --- Design-Build Operate contract, Published on Sep-2007
Apart from these FIDIC published a Multilateral Development Bank Harmonized Edition in June 2010
Applicability
Claims
Claims are generally made by the Parties due to the following circumstances :
 Entitlement to an extension of time
 Entitlement to additional payments
 Entitlement to the recovery of costs
 Non fulfilment by one party of an obligation under the contract
 Additional payments due to legal entitlement
Claims by Employer– Clause 2.5
Clauses requiring notice under clause 2 .5 include:
 Clause 7.5 Rejection
 Clause 7.6 Remedial work
 Clause 8.6 Rate of progress
 Clause 8.7 Delay damages
 Clause 9.4 Tests on completion
 Clause 11.3 Extension of defects notification period
 Clause 15.4 Payment after termination
Clauses not requiring notice under clause 2.5 include:
 Clause 4.19 Electricity water and gas
 Clause 4.20 Employer’s equipment and free issue material
 Other services requested by the contractor
Claims by Employer– Clause 2.5
Other clauses allowing for claims a deduction by the employer include:
 Clause 4.2 Performance security
 Clause 5.4 Evidence of payments to nominated subcontractors
 Clause 9.2 Delayed tests
 Clause 10.2 Taking over of parts of the works
 Clause 11.4 Failure to remedy defects
 Clause 11.6 Further tests
 Clause 11.11 Clearance of site
 Clause 13.7 Adjustments in legislation
 Clause 17.1 Indemnities
 Clause 18.1 General requirements for insurances
 Clause 18.2 Insurance for works and contractors equipment
Claims by Contractor
Clauses which require the contractor to give notice of an event which may cause delay or additional cost:
 Clause 1.9 Delayed drawings or instructions
 Clause 4.12 Unforeseeable physical conditions
 Clause 4.24 Fossils
 Clause 16.1 Contractor’s entitlement to suspend work
 Clause 17.4 Consequences of Employer’s risks
 Clause 19.4 Consequences of force majeure
Claims by Contractor
Clauses which entitled the contract out to an extension of time and or additional payments:
 Clause 1.9 Delayed drawings or instructions
 Clause 2.1 Right of access to the site
 Clause 4.7 Setting out
 Clause 4.12 Unforeseeable physical conditions
 Clause 4.24 Fossils
 Clause 7.4 Testing
 Clause 10.2 Taking over parts of the works
 Clause 10.3 Interference with tests on completion
 Clause 11.8 Contractor to search
 Clause 13.7 Adjustments for changes in legislation
 Clause 16.1 Contractor’s entitlement to suspend work
 Clause 17.4 Consequences of Employers risks
 Clause 19.4 Consequences of force majeure
Claims by Contractor
Clauses which involve valuation or similar requirements:
 Clause 12.3 Evaluation
 Clause 12.4 Omissions
 Clause 15.3 Valuation at date of termination
 Clause 16.4 Payment on termination
 Clause 18.1 General requirements for insurances
Classes which provide for the Contractor to claim profit as well as costs:
 Clause 1.9 Delayed drawings are instructions
 Clause 2.1 Right of access to the site
 Clause 4.7 Setting out
 Clause 7.4 Testing
 Clause 10.2 Taking over parts of the works
 Clause 10.3 Interference with tests on completion in
 Clause 11.8 Contractor to search
 Clause 16.1 Contractor’s entitlement to suspend work
 Clause 16.4 Payment on termination
 Clause 17.4 Consequences of Employers risks on

More Related Content

What's hot

Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
Jeff B
 
Fidic
FidicFidic
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
Moustafa Ismail Abu Dief
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
Haytham Baraka, PMP, CCP, SP, RMP,APC-RICS Candidate.
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
CNC
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
Kheng Hoe Advocates
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Project Controls Expo
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
Francis Ho
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
SN Panigrahi, PMP
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
Loay Ghazaleh MBA, BSc Civil Eng.
 

What's hot (20)

Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Fidic
FidicFidic
Fidic
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 

Similar to Ppt on fidic claims

CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
Bahzad5
 
17 10 16
17 10 1617 10 16
17 10 16
Suhaib Jibran
 
FIDIC 2019
FIDIC 2019FIDIC 2019
Fidic db-yellow-book
Fidic db-yellow-bookFidic db-yellow-book
Fidic db-yellow-book
Vedants Sharma
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
Vance Ang
 
dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
afadlalla
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
Aditya Mane
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
Yash Patel
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen AntovAssen Antov
 
Fidic.pptx
Fidic.pptxFidic.pptx
Fidic.pptx
Zeeshan Yousaf
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
AhmetArslan47
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
Cerasela Angelescu
 
2 procurement and legal aspects
2 procurement and legal aspects 2 procurement and legal aspects
2 procurement and legal aspects
Archiver
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
drmujahidkhan85
 
Major Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdfMajor Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdf
ssuser6d14e4
 
Presentation sidig med-jts
Presentation sidig med-jtsPresentation sidig med-jts
Presentation sidig med-jtsAnna Codazzi
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
mohammedAlmusawi11
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 

Similar to Ppt on fidic claims (20)

CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
17 10 16
17 10 1617 10 16
17 10 16
 
FIDIC 2019
FIDIC 2019FIDIC 2019
FIDIC 2019
 
Fidic db-yellow-book
Fidic db-yellow-bookFidic db-yellow-book
Fidic db-yellow-book
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
 
dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov11.05 - 11.15 Asen Antov
11.05 - 11.15 Asen Antov
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Fidic.pptx
Fidic.pptxFidic.pptx
Fidic.pptx
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
 
2 procurement and legal aspects
2 procurement and legal aspects 2 procurement and legal aspects
2 procurement and legal aspects
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
ICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract managementICE-Learned-Event-Dubai-event for understanding contract management
ICE-Learned-Event-Dubai-event for understanding contract management
 
Major Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdfMajor Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdf
 
Presentation sidig med-jts
Presentation sidig med-jtsPresentation sidig med-jts
Presentation sidig med-jts
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 

Recently uploaded

The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
BridgeWest.eu
 
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
shweeta209
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
anjalidixit21
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Thomas (Tom) Jasper
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
KHURRAMWALI
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
9ib5wiwt
 
Cold War - 1, talks about cold water bro
Cold War - 1, talks about cold water broCold War - 1, talks about cold water bro
Cold War - 1, talks about cold water bro
SidharthKashyap5
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
OmGod1
 
Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.
Purushottam Jha
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
anvithaav
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
Daffodil International University
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
9ib5wiwt
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
ssuser0576e4
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
Abdul-Hakim Shabazz
 
Agrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quizAgrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quiz
gaelcabigunda
 
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
MwaiMapemba
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
Knowyourright
 
DNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptxDNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptx
patrons legal
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Gabe Whitley
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 

Recently uploaded (20)

The Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot CitizenshipThe Main Procedures for Obtaining Cypriot Citizenship
The Main Procedures for Obtaining Cypriot Citizenship
 
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
 
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselMilitary Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
 
Cold War - 1, talks about cold water bro
Cold War - 1, talks about cold water broCold War - 1, talks about cold water bro
Cold War - 1, talks about cold water bro
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
 
Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
 
Agrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quizAgrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quiz
 
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
 
DNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptxDNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptx
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 

Ppt on fidic claims

  • 1. Claims according to FIDIC Red Book By Naresh Gattupalli,PMP® B.Tech (Civil), M.Tech (SE), PGD ACM & PGD ADR
  • 2.  The International Federation of Consulting Engineers (FIDIC) has devoted itself to the compilation of management documents for all kinds of projects, among which the FIDIC Conditions of Contract are of the highest influence and are the most popular Application  The first edition of FIDIC Conditions of Contract for Works of Civil Engineering Construction (use “Red Book” in the following) was compiled in 1957, and later its second, third, and fourth edition were issued in 1963, 1977, and 1987 respectively  With the investigation of the governments, employers, contractors and consulting engineers all over the world about their application of the “Red Book”, 204 findings reports were returned. According to the findings, the FIDIC Contract Committee organized a group of experts to compile the new Contract Condition models to be applied in the 21stcentury  The test edition of these models was published in 1998, and FIDIC solicited opinions throughout the world for additional time to publish the official texts in 1999.  Now FIDIC condition of contract has been applied worldwide, especially in the projects invested by World Bank, Asia Development Bank, Africa Development Bank etc. Background
  • 3. The new models include : 1. FIDIC Conditions of Contract for Construction, the (New Red Book) 2. FIDIC Conditions of Contract for Plant and Design/Build, the (New Yellow Book) 3. FIDIC Conditions of Contract for EPC Turnkey Projects, the (Silver Book) 4. FIDIC Short Form of Contract, the (Green Book)
  • 4.  New Red Book --- Any kind of Engineering Construction Contract.  New Yellow Book --- Lump sum contract project where the Contractor takes participation in the design work.  Silver Book --- Turnkey projects of infrastructures or large-scale factories, where the Contractor takes on more work and risk while the Employer’s participation is small (private financing or government financing), but it is strictly defined upon the investment and construction period.  Green Book --- All kinds of small-scale projects  Gold Book --- Design-Build Operate contract, Published on Sep-2007 Apart from these FIDIC published a Multilateral Development Bank Harmonized Edition in June 2010 Applicability
  • 5. Claims Claims are generally made by the Parties due to the following circumstances :  Entitlement to an extension of time  Entitlement to additional payments  Entitlement to the recovery of costs  Non fulfilment by one party of an obligation under the contract  Additional payments due to legal entitlement
  • 6. Claims by Employer– Clause 2.5 Clauses requiring notice under clause 2 .5 include:  Clause 7.5 Rejection  Clause 7.6 Remedial work  Clause 8.6 Rate of progress  Clause 8.7 Delay damages  Clause 9.4 Tests on completion  Clause 11.3 Extension of defects notification period  Clause 15.4 Payment after termination Clauses not requiring notice under clause 2.5 include:  Clause 4.19 Electricity water and gas  Clause 4.20 Employer’s equipment and free issue material  Other services requested by the contractor
  • 7. Claims by Employer– Clause 2.5 Other clauses allowing for claims a deduction by the employer include:  Clause 4.2 Performance security  Clause 5.4 Evidence of payments to nominated subcontractors  Clause 9.2 Delayed tests  Clause 10.2 Taking over of parts of the works  Clause 11.4 Failure to remedy defects  Clause 11.6 Further tests  Clause 11.11 Clearance of site  Clause 13.7 Adjustments in legislation  Clause 17.1 Indemnities  Clause 18.1 General requirements for insurances  Clause 18.2 Insurance for works and contractors equipment
  • 8. Claims by Contractor Clauses which require the contractor to give notice of an event which may cause delay or additional cost:  Clause 1.9 Delayed drawings or instructions  Clause 4.12 Unforeseeable physical conditions  Clause 4.24 Fossils  Clause 16.1 Contractor’s entitlement to suspend work  Clause 17.4 Consequences of Employer’s risks  Clause 19.4 Consequences of force majeure
  • 9. Claims by Contractor Clauses which entitled the contract out to an extension of time and or additional payments:  Clause 1.9 Delayed drawings or instructions  Clause 2.1 Right of access to the site  Clause 4.7 Setting out  Clause 4.12 Unforeseeable physical conditions  Clause 4.24 Fossils  Clause 7.4 Testing  Clause 10.2 Taking over parts of the works  Clause 10.3 Interference with tests on completion  Clause 11.8 Contractor to search  Clause 13.7 Adjustments for changes in legislation  Clause 16.1 Contractor’s entitlement to suspend work  Clause 17.4 Consequences of Employers risks  Clause 19.4 Consequences of force majeure
  • 10. Claims by Contractor Clauses which involve valuation or similar requirements:  Clause 12.3 Evaluation  Clause 12.4 Omissions  Clause 15.3 Valuation at date of termination  Clause 16.4 Payment on termination  Clause 18.1 General requirements for insurances Classes which provide for the Contractor to claim profit as well as costs:  Clause 1.9 Delayed drawings are instructions  Clause 2.1 Right of access to the site  Clause 4.7 Setting out  Clause 7.4 Testing  Clause 10.2 Taking over parts of the works  Clause 10.3 Interference with tests on completion in  Clause 11.8 Contractor to search  Clause 16.1 Contractor’s entitlement to suspend work  Clause 16.4 Payment on termination  Clause 17.4 Consequences of Employers risks on