High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
Chapter 5- Contract Management
1. Claims
Mada Walabu
University
Procurement Management and Contract Administration
CoTM 4242
Chapter 5
College of Engineering
Construction Technology and Management Department
Lecture by: Andualem Endris (M.Sc)
Email: andualem@anenypublishing.org
www.andualem.site123.me
3. Claim
Claim is a request by a contractor for additional
compensation or time extension for occurrences beyond
the contractor’s control including:
• differing or unexpected site conditions
• change in scope
• delays caused by the owner
Owner has duty to provide adequate and accurate data
to the bidders
31 July 2021 COTM 4242 3
4. Claim
• Owner is liable to contractor when:
– inaccurate data are given
– extras develop because of improper design
– design is significantly changed after the contract is
signed (constructive change)
• Contractor must prove entitlement and the associated
damages
• Contractor must provide timely notice of claim upon
discovering impact
31 July 2021 COTM 4242 4
5. Causes of Claims
• Contractors attempt to submit an artificially low price and
hoping to make up the difference through claims later on;
• The constraints of time, finances and other factors force
a contractor to cut corners;
• Where the form of contract transfers the risks to the
employer (esp. DBB system);
• Poor or unclear tender and/or contract documents;
• Poor or inadequate administration of responsibilities by
stake holders; and
• Unforeseen or situations during project execution.
31 July 2021 COTM 4242 5
6. Types of Claims
Typical claims against owner are:
• Poor project planning
• Scope changes
• Constructive change orders
• Errors and omissions
• Contract accelerations and stoppages
• Site access or availability
• Other construction interference and delays
• Strikes and acts of God.
31 July 2021 COTM 4242 6
7. 31 July 2021 COTM 4242 7
Types of Claims …cont’d
Typical claims against contractor are:
• Late completion - liquidated damages
• Out of specification materials
• Defective work
• Property damage
8. Claims Prevention
• Producing comprehensive and accurate contract
documents
• Constructability review
• Clear understanding of contract requirements prior to
bidding
• Having good administrative procedures in place
• Open and honest communication
• Timely troubleshooting
Claim prevention begins in the pre-construction phase
31 July 2021 COTM 4242 8
9. Design Professionals should:
• Specify locally available material
• Allow substitution of the same quality material
• Avoid one-of–a-kind or non-standard items where
possibly
• Design structures with as many surplus elements as
possible
• Design should allow construction using the prevailing
methods and equipment
31 July 2021 COTM 4242 9
10. Design Professionals should:
• Design to minimize required labor
• Specify a quality of workmanship consistent with the
quality of the project
• Do not require the contractor to assume responsibility
for information that should be furnished by the design
engineer/architect
• Produce simple, straight-forward specs - clearly state
what is expected
31 July 2021 COTM 4242 10
12. Variations
• Variation is the addition, omission or substitution of
works.
• Variation management is an organized effort to eliminate
unnecessary cost and time impact as a result of
processing project work outside the scope of the
contract.
• Variation is not a Claim
31 July 2021 COTM 4242 12
13. Variation Order
– A written order issued by the owner to the contractor
for a change to the contract within the scope of work
– Variation orders are written for:
• extra work
• increasing or decreasing the contract quantities
• alterations
– Variation orders state the basis and amount of
payment and time extensions
31 July 2021 COTM 4242 13
14. Types of Variations
• Formal
– Via contract variation clause (Ex. See Clause 15 of
PPA, 2011)
• Constructive
– Action of owner that has the effect of directing a
change, although not initially documented as such.
• Cardinal
– Variations totally out of scope of original contract.
– Should re-negotiate entire contract.
31 July 2021 COTM 4242 14
15. Sources of Variations
• Unanticipated site conditions
• Owner requested design modifications, additions or
deletions
• Clarification of contract documents
31 July 2021 COTM 4242 15
17. ASSIGNMENT 2
• Please review construction claim
analysis and management
process model. And discuss step
wise please.
Group Assignment (5 students/Group)
Submission date: May 16, 2019
31 July 2021 COTM 4242 17