SlideShare a Scribd company logo
1 of 41
LECTURE 4
SELECTION OF CONTRACT FORMS
KIING KIU CHUN 0318727
KOH WEN QI 0323355
KONG ZHEN CHUNG 0319528
TYPES OF CONTRACT
Traditional
Method
Management
Contract
Construction
management
Design and
built
TRADITIONAL METHOD
Employer appoints consultant team to design for the works
Calling for tender
Contractor appointed and construction works be carried out
Three types of contract
under traditional method
Lump sum contracts
Measurement contracts
Cost reimbursement
contracts
1. LUMP SUM CONTRACTS
✘Contractor undertake to complete a defined amount of
work for an agreed sum (=fixed sum) based on BQ /
drawing and specification / both.
✘Appropriate to use where scope and schedule of the
project are defined sufficiently.
✘Drawing is important.
It forms the basis to come out the price.
✘More risk on contractor.
Architect /
client ideas
Drawings BQ
2. MEASUREMENT CONTRACTS
✘Drawing is just a reference. (not complete)
BQ is important. (basis for contractor to fill
up the price)
✘The actual work done at site to be
remeasured upon completion.
Approximate
Quantity
Remeasured
Quantity
✘Also called ‘re-measurement contracts’
✘At tender stage, works are based on approximate BQ but design
substantially completed.
2. MEASUREMENT CONTRACTS
✘Contract sum is provisional. The employer has to accept
the risk involved in starting work with no accurate idea
of the total cost,
✘Appropriate to use this contract when there is not
enough time to come out with detail drawings or where
the quantity of work is very uncertain.
✘Example: civil work
3. COST REIMBURSEMENT CONTRACTS
✘Also called ‘cost plus’ contract.
✘Construction can start earlier without clearly defined project scope
since all costs will be reimbursed and profit is guaranteed.
✘To avoid disputes, the owner and contractor should specify early
on in the process what is a reimbursable expense to the contractor
(for his general conditions such as employees on the project,
insurance, etc.)
Actual cost
(labour, plants
and materials)
Agreed fee
(management,
overhead and
profit)
Payment
received by
contractor
3. COST REIMBURSEMENT CONTRACTS
Advantages Disadvantages
Client
Result in better quality projects
because contractor do not have
to cut corners as they know that
they will be paid for all of the
expenses plus profit.
Limited certainty as what the
final cost will be.
High risk to client.
Minimum efficiency of
contractor.
Contractor Contractor's risk is minimized.
Unable to get advantage on
favourable market price.
3. COST REIMBURSEMENT CONTRACTS
COST + PERCENTAGE FEE
✘ A specific type of contract
where the contractor is paid for
the normal cost for a project
plus an agreed-upon
percentage of the estimated
cost as profits.
✘ The contractor may no
incentive to complete the job
quickly or cheaply – the longer
he takes or the more he
spends, the larger his profit.
COST + FIXED FEE
✘ A specific type of contract
where the contractor is paid
for the normal cost for a
project, plus an additional
fixed fee for their services.
✘ If the scope of the contract
changes, the fee may be
adjusted.
COST + FLUCTUATING FEE
✘ Cost for a project plus
fluctuating fee depending
whether the final cost is above
or below the original ‘target
cost’.
✘ Examples:
Final cost not exceeding 50
million contract sum - value A
Final cost exceed 50 million
contract sum - value B
DESIGN AND BUILT
✘ A contractor is appointed by the client at the outset to
design and built the proposed project.
✘ The contractor will then appoint his own consultant
team to come up with the design.
✘ There are 2 methods which are single entity method
and competitive method.
Single Entity Method
✘ A contractor is appointed to design and built without
any competition.
✘ The client would not know whether he is getting the
best deal.
✘ Normally applicable to less complex building.
Competitive Method
✘ Client may appoint his own consultant team as his
advisor and outline design is prepared by his consultant
team. A few contractor are then invited to submit their
final design, cost and completion time based on the
outline design.
✘ Client would be able to select the best deal out of
several submissions.
Advantages
✘ The contractor is solely responsible for failure in the
design/construction.
✘ The client has only one person to deal with, the
contractor.
✘ The client is aware of his total financial commitment
from the outset.
✘ Close cooperation between contractor’s design and
construction teams.
Disadvantages
✘ Variation from the original design are discouraged by
the contractor because variation can be very expensive.
✘ The client has no means of knowing whether he is
getting value for money unless he employs his own
advisers, which adds to his costs.
MANAGEMENT CONTRACT
✘ The characteristic of management contract is that the
management contractor undertakes to carry out the
construction works through works contractors.
✘ Each of the works contractors will sign a contract with the
Management Contractor.
✘ Management Contractor’s role is to manage the construction
work on daily basis.
✘ The Management Contractor will be reimbursed all cost
incurred by him plus a management fee from the employer.
Advantages
✘ Work can begin on site as soon as the first one or two
works packages have been designed.
✘ The Management Contractor’s knowledge and
management expertise are available to assist the
design team at a very early stage.
Disadvantages
✘ Uncertainty as to the final cost of the project until the
last works contract has been signed.
✘ The number of variations and the amount of re-
measurement required may be greater as compared
with traditional contract.
CONSTRUCTION MANAGEMENT
✘ It is a professional consultant service to the client.
✘ The client has to pay an agreed fee for the service.
✘ The design and construction portion are provided by other
parties.
✘ The construction manager is responsible for the organization
and planning of the construction work. The construction work
itself is carried out by a number of trade contractors.
✘ Each trade contractor enters into a direct contract with the
client.
Advantages
✘ The construction work is more closely managed by the
construction manager.
✘ Contract is signed between the client and each of the
trade contractor hence providing the client with direct
access to the trade contractors.
Disadvantages
✘ The client has to deal with a number of trade
contractors instead of only one main contractor.
✘ The client’s financial commitment is uncertain until the
last of the works contracts has been signed.
MATTERS INFLUENCING
CHOICE OF CONTRACT
FORM
Project complexity
✘ Is the design of the building complex and have high
engineering content.
✘ For example, the lump-sum type of contract, is popular
for the reason that the total cost of the project is
known in advance.
✘ If the project is too complicated, it is not possible to
accurately determine the nature and quantity of the
work prior to the start of site activities, then that type
of contract is not suitable.
Appointment of contractor
✘ Can be in single entity (a contractor is selected to
handle the project include design and build, without
competitor) or
✘ Competitive (outline design of the project is prepared
and every company that compliance is welcome to
submit their final design and cost, the most satisfied
tender will be chosen).
✘ Single entity and competitive project require different
form of contracts.
Client’s experience
✘ The bigger or more experienced clients have their own
preferred protocols which involves specific choice of
contract form.
✘ For example, the client prefers competitive to be able
to compare and choose the most suitable tender.
✘ The choice of contract form would therefore depend
on the client’s experience.
Certainty of final costs
✘ How the contractor calculate the fees they charge to
get the final costs.
✘ For example, Lump sum contracts, measurement
contracts and cost plus contract.
Changes of design/build during constructions
✘ Some contractors/clients will allow the changes of the
design when construction stage start but some will not
allow and every design must follow the tender.
✘ These two required different contract form.
Nature of the project
✘ Different types of project will affect the choice of
contract form.
✘ For example, the project can be build a new building,
extension of building, renovation works, industrial
building and more.
✘ Different projects have different requirements
therefore required different type of contract form.
Allocation of risk
✘ All sorts of risks arising from both the internal and
external environment of a project or organization and
affecting the project performance,
✘ in terms of successful delivery of project on of time,
within budget and of the specified performance.
✘ Important to know how much risk is shared in the
project and how much risk is allocated to the
contractor and client.
QUESTIONS
Q1. In the event, when
variation change or any
dispute arises, what is
the most important
document under lump
sum contract?
Drawing. Drawing is the basis.
It is the main reference to
check whether got any
discrepancy between tender
drawing and construction
drawing.
Q2. What is the
differences between
lump sum contracts and
measurement
contracts?
Lump sum
contracts
Measurement
contracts
Complete drawing
(Drawing important)
Incomplete drawing
BQ is just a guide
BQ is the basis for contractor
to fill up the price
(BQ important)
Fixed contract sum, unless got
changes on drawings
Contract sum is provisional
(=subject to change)
Q3. Management
Contract and
Construction
Management are very
similar. What is the
major difference
between them?
For Management Contract, client only deal with
management contractor. For Construction
Management, client has to deal with a few trade
contractors.
For Management Contract, client sign contract
with the main contractor. For Construcion
Management, client does not direct sign contract
with the main contractor but with each of the
trade contractors.
Q4. What is the difference
of Design and Build
compare with Management
Contract and Construction
Management?
The client’s financial commitment is
already known when the Design and Build
Contractor sign the contract with the
employer. Whereas in Management
Contract and Construction Management,
the client would not know the final cost of
the project until the last works contract
has been signed.
Q5. What are the
factors that causing
lump-sum type of
contract unable be
used?
If it is not possible to accurately
determine the nature and quantity
of the work prior to the start of site
activities, then lum-sump type of
contract is not suitable.
Q6.
How final costs
influence type of
contract form?
If total cost is fixed = lump
sum contract.
If total cost is uncertain
=measurement contract
THANKS!

More Related Content

What's hot

CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract managementVISHAKA BOTHRA
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their typesTouqeer1
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaGuta Mengesha
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 

What's hot (20)

CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Procurement system
Procurement systemProcurement system
Procurement system
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract management
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopia
 
Construction contract
Construction contract Construction contract
Construction contract
 
fidic , jct and nec contracts
fidic , jct and nec contractsfidic , jct and nec contracts
fidic , jct and nec contracts
 
Claims
ClaimsClaims
Claims
 

Viewers also liked

The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
Quality control and quality assurance
Quality control and quality assuranceQuality control and quality assurance
Quality control and quality assuranceLeola Ramirez
 
101313812 دورة-فيديك
101313812 دورة-فيديك101313812 دورة-فيديك
101313812 دورة-فيديكAhmed Fouda
 
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainBob Prieto
 
0105terms And Standard Form Contract
0105terms And Standard Form Contract0105terms And Standard Form Contract
0105terms And Standard Form Contractbtecexpert
 
Construction Law: An Indian Perspective
Construction Law: An Indian PerspectiveConstruction Law: An Indian Perspective
Construction Law: An Indian Perspectivedesignesque
 
Construction law basics 1103041
Construction law basics 1103041Construction law basics 1103041
Construction law basics 1103041Dan Schleck
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery MethodsMcCarthy Holdings, Inc.
 
Lecture 1 introduction to the law of contract
Lecture 1   introduction to the law of contractLecture 1   introduction to the law of contract
Lecture 1 introduction to the law of contractRamona Vansluytman
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
Joint Venture- Success & Failure
Joint Venture- Success & FailureJoint Venture- Success & Failure
Joint Venture- Success & FailureOnkar Satam
 

Viewers also liked (20)

The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
Standard Form Contract
Standard Form ContractStandard Form Contract
Standard Form Contract
 
Quality control and quality assurance
Quality control and quality assuranceQuality control and quality assurance
Quality control and quality assurance
 
101313812 دورة-فيديك
101313812 دورة-فيديك101313812 دورة-فيديك
101313812 دورة-فيديك
 
Design-Build Operate and Finance
Design-Build Operate and FinanceDesign-Build Operate and Finance
Design-Build Operate and Finance
 
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
 
Commentary on fidic iv clauses
Commentary on fidic iv clausesCommentary on fidic iv clauses
Commentary on fidic iv clauses
 
0105terms And Standard Form Contract
0105terms And Standard Form Contract0105terms And Standard Form Contract
0105terms And Standard Form Contract
 
Construction Law: An Indian Perspective
Construction Law: An Indian PerspectiveConstruction Law: An Indian Perspective
Construction Law: An Indian Perspective
 
Real Estate Joint Venture Partnerships Basics
Real Estate Joint Venture Partnerships BasicsReal Estate Joint Venture Partnerships Basics
Real Estate Joint Venture Partnerships Basics
 
Construction law basics 1103041
Construction law basics 1103041Construction law basics 1103041
Construction law basics 1103041
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods
 
Construction law
Construction lawConstruction law
Construction law
 
Lecture 1 introduction to the law of contract
Lecture 1   introduction to the law of contractLecture 1   introduction to the law of contract
Lecture 1 introduction to the law of contract
 
Fidic
FidicFidic
Fidic
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Contract lecture
Contract lectureContract lecture
Contract lecture
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Joint Venture- Success & Failure
Joint Venture- Success & FailureJoint Venture- Success & Failure
Joint Venture- Success & Failure
 
Joint venture
Joint ventureJoint venture
Joint venture
 

Similar to Lecture 4 - selection of contract forms

Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptxjairam131
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt2cd
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptxssuser42980c
 

Similar to Lecture 4 - selection of contract forms (20)

TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Contracts
ContractsContracts
Contracts
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 

More from kohwenqi

CL Seminar
CL SeminarCL Seminar
CL Seminarkohwenqi
 
VM Presentation
VM PresentationVM Presentation
VM Presentationkohwenqi
 
PM Presentation
PM PresentationPM Presentation
PM Presentationkohwenqi
 
BE Assignment
BE AssignmentBE Assignment
BE Assignmentkohwenqi
 
Measurement4
Measurement4Measurement4
Measurement4kohwenqi
 
Software Application
Software ApplicationSoftware Application
Software Applicationkohwenqi
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationkohwenqi
 
Management science
Management scienceManagement science
Management sciencekohwenqi
 
Group 5 sustainable stormwater management(building services1)
Group 5   sustainable stormwater management(building services1)Group 5   sustainable stormwater management(building services1)
Group 5 sustainable stormwater management(building services1)kohwenqi
 
Site visit
Site visitSite visit
Site visitkohwenqi
 
Mid valley finale
Mid valley finaleMid valley finale
Mid valley finalekohwenqi
 

More from kohwenqi (12)

CL Seminar
CL SeminarCL Seminar
CL Seminar
 
VM Presentation
VM PresentationVM Presentation
VM Presentation
 
PM Presentation
PM PresentationPM Presentation
PM Presentation
 
Seminar
SeminarSeminar
Seminar
 
BE Assignment
BE AssignmentBE Assignment
BE Assignment
 
Measurement4
Measurement4Measurement4
Measurement4
 
Software Application
Software ApplicationSoftware Application
Software Application
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Management science
Management scienceManagement science
Management science
 
Group 5 sustainable stormwater management(building services1)
Group 5   sustainable stormwater management(building services1)Group 5   sustainable stormwater management(building services1)
Group 5 sustainable stormwater management(building services1)
 
Site visit
Site visitSite visit
Site visit
 
Mid valley finale
Mid valley finaleMid valley finale
Mid valley finale
 

Recently uploaded

How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 

Recently uploaded (20)

How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 

Lecture 4 - selection of contract forms

  • 1. LECTURE 4 SELECTION OF CONTRACT FORMS KIING KIU CHUN 0318727 KOH WEN QI 0323355 KONG ZHEN CHUNG 0319528
  • 3. TRADITIONAL METHOD Employer appoints consultant team to design for the works Calling for tender Contractor appointed and construction works be carried out Three types of contract under traditional method Lump sum contracts Measurement contracts Cost reimbursement contracts
  • 4. 1. LUMP SUM CONTRACTS ✘Contractor undertake to complete a defined amount of work for an agreed sum (=fixed sum) based on BQ / drawing and specification / both. ✘Appropriate to use where scope and schedule of the project are defined sufficiently. ✘Drawing is important. It forms the basis to come out the price. ✘More risk on contractor. Architect / client ideas Drawings BQ
  • 5. 2. MEASUREMENT CONTRACTS ✘Drawing is just a reference. (not complete) BQ is important. (basis for contractor to fill up the price) ✘The actual work done at site to be remeasured upon completion. Approximate Quantity Remeasured Quantity ✘Also called ‘re-measurement contracts’ ✘At tender stage, works are based on approximate BQ but design substantially completed.
  • 6. 2. MEASUREMENT CONTRACTS ✘Contract sum is provisional. The employer has to accept the risk involved in starting work with no accurate idea of the total cost, ✘Appropriate to use this contract when there is not enough time to come out with detail drawings or where the quantity of work is very uncertain. ✘Example: civil work
  • 7. 3. COST REIMBURSEMENT CONTRACTS ✘Also called ‘cost plus’ contract. ✘Construction can start earlier without clearly defined project scope since all costs will be reimbursed and profit is guaranteed. ✘To avoid disputes, the owner and contractor should specify early on in the process what is a reimbursable expense to the contractor (for his general conditions such as employees on the project, insurance, etc.) Actual cost (labour, plants and materials) Agreed fee (management, overhead and profit) Payment received by contractor
  • 8. 3. COST REIMBURSEMENT CONTRACTS Advantages Disadvantages Client Result in better quality projects because contractor do not have to cut corners as they know that they will be paid for all of the expenses plus profit. Limited certainty as what the final cost will be. High risk to client. Minimum efficiency of contractor. Contractor Contractor's risk is minimized. Unable to get advantage on favourable market price.
  • 9. 3. COST REIMBURSEMENT CONTRACTS COST + PERCENTAGE FEE ✘ A specific type of contract where the contractor is paid for the normal cost for a project plus an agreed-upon percentage of the estimated cost as profits. ✘ The contractor may no incentive to complete the job quickly or cheaply – the longer he takes or the more he spends, the larger his profit. COST + FIXED FEE ✘ A specific type of contract where the contractor is paid for the normal cost for a project, plus an additional fixed fee for their services. ✘ If the scope of the contract changes, the fee may be adjusted. COST + FLUCTUATING FEE ✘ Cost for a project plus fluctuating fee depending whether the final cost is above or below the original ‘target cost’. ✘ Examples: Final cost not exceeding 50 million contract sum - value A Final cost exceed 50 million contract sum - value B
  • 10. DESIGN AND BUILT ✘ A contractor is appointed by the client at the outset to design and built the proposed project. ✘ The contractor will then appoint his own consultant team to come up with the design. ✘ There are 2 methods which are single entity method and competitive method.
  • 11. Single Entity Method ✘ A contractor is appointed to design and built without any competition. ✘ The client would not know whether he is getting the best deal. ✘ Normally applicable to less complex building.
  • 12. Competitive Method ✘ Client may appoint his own consultant team as his advisor and outline design is prepared by his consultant team. A few contractor are then invited to submit their final design, cost and completion time based on the outline design. ✘ Client would be able to select the best deal out of several submissions.
  • 13. Advantages ✘ The contractor is solely responsible for failure in the design/construction. ✘ The client has only one person to deal with, the contractor. ✘ The client is aware of his total financial commitment from the outset. ✘ Close cooperation between contractor’s design and construction teams.
  • 14. Disadvantages ✘ Variation from the original design are discouraged by the contractor because variation can be very expensive. ✘ The client has no means of knowing whether he is getting value for money unless he employs his own advisers, which adds to his costs.
  • 15. MANAGEMENT CONTRACT ✘ The characteristic of management contract is that the management contractor undertakes to carry out the construction works through works contractors. ✘ Each of the works contractors will sign a contract with the Management Contractor. ✘ Management Contractor’s role is to manage the construction work on daily basis. ✘ The Management Contractor will be reimbursed all cost incurred by him plus a management fee from the employer.
  • 16. Advantages ✘ Work can begin on site as soon as the first one or two works packages have been designed. ✘ The Management Contractor’s knowledge and management expertise are available to assist the design team at a very early stage.
  • 17. Disadvantages ✘ Uncertainty as to the final cost of the project until the last works contract has been signed. ✘ The number of variations and the amount of re- measurement required may be greater as compared with traditional contract.
  • 18. CONSTRUCTION MANAGEMENT ✘ It is a professional consultant service to the client. ✘ The client has to pay an agreed fee for the service. ✘ The design and construction portion are provided by other parties. ✘ The construction manager is responsible for the organization and planning of the construction work. The construction work itself is carried out by a number of trade contractors. ✘ Each trade contractor enters into a direct contract with the client.
  • 19. Advantages ✘ The construction work is more closely managed by the construction manager. ✘ Contract is signed between the client and each of the trade contractor hence providing the client with direct access to the trade contractors.
  • 20. Disadvantages ✘ The client has to deal with a number of trade contractors instead of only one main contractor. ✘ The client’s financial commitment is uncertain until the last of the works contracts has been signed.
  • 22. Project complexity ✘ Is the design of the building complex and have high engineering content. ✘ For example, the lump-sum type of contract, is popular for the reason that the total cost of the project is known in advance. ✘ If the project is too complicated, it is not possible to accurately determine the nature and quantity of the work prior to the start of site activities, then that type of contract is not suitable.
  • 23. Appointment of contractor ✘ Can be in single entity (a contractor is selected to handle the project include design and build, without competitor) or ✘ Competitive (outline design of the project is prepared and every company that compliance is welcome to submit their final design and cost, the most satisfied tender will be chosen). ✘ Single entity and competitive project require different form of contracts.
  • 24. Client’s experience ✘ The bigger or more experienced clients have their own preferred protocols which involves specific choice of contract form. ✘ For example, the client prefers competitive to be able to compare and choose the most suitable tender. ✘ The choice of contract form would therefore depend on the client’s experience.
  • 25. Certainty of final costs ✘ How the contractor calculate the fees they charge to get the final costs. ✘ For example, Lump sum contracts, measurement contracts and cost plus contract. Changes of design/build during constructions ✘ Some contractors/clients will allow the changes of the design when construction stage start but some will not allow and every design must follow the tender. ✘ These two required different contract form.
  • 26. Nature of the project ✘ Different types of project will affect the choice of contract form. ✘ For example, the project can be build a new building, extension of building, renovation works, industrial building and more. ✘ Different projects have different requirements therefore required different type of contract form.
  • 27. Allocation of risk ✘ All sorts of risks arising from both the internal and external environment of a project or organization and affecting the project performance, ✘ in terms of successful delivery of project on of time, within budget and of the specified performance. ✘ Important to know how much risk is shared in the project and how much risk is allocated to the contractor and client.
  • 29. Q1. In the event, when variation change or any dispute arises, what is the most important document under lump sum contract?
  • 30. Drawing. Drawing is the basis. It is the main reference to check whether got any discrepancy between tender drawing and construction drawing.
  • 31. Q2. What is the differences between lump sum contracts and measurement contracts?
  • 32. Lump sum contracts Measurement contracts Complete drawing (Drawing important) Incomplete drawing BQ is just a guide BQ is the basis for contractor to fill up the price (BQ important) Fixed contract sum, unless got changes on drawings Contract sum is provisional (=subject to change)
  • 33. Q3. Management Contract and Construction Management are very similar. What is the major difference between them?
  • 34. For Management Contract, client only deal with management contractor. For Construction Management, client has to deal with a few trade contractors. For Management Contract, client sign contract with the main contractor. For Construcion Management, client does not direct sign contract with the main contractor but with each of the trade contractors.
  • 35. Q4. What is the difference of Design and Build compare with Management Contract and Construction Management?
  • 36. The client’s financial commitment is already known when the Design and Build Contractor sign the contract with the employer. Whereas in Management Contract and Construction Management, the client would not know the final cost of the project until the last works contract has been signed.
  • 37. Q5. What are the factors that causing lump-sum type of contract unable be used?
  • 38. If it is not possible to accurately determine the nature and quantity of the work prior to the start of site activities, then lum-sump type of contract is not suitable.
  • 39. Q6. How final costs influence type of contract form?
  • 40. If total cost is fixed = lump sum contract. If total cost is uncertain =measurement contract