Schedule Delay Analysis
Jack A. Lazarczyk, CPA, CCC
Senior Consultant
Types of Construction Delay
Basic Distinctions:
• Excusable and Non-Excusable
• Compensable and Non-Compensable
• Concurrent and Non-Concurrent
• Critical versus Non-Critical
Types of Construction Delay
Excusable Delays:
• General labor strikes
• Fires, floods and other natural disasters
• Owner directed changes
• Errors and omissions in the plans and specifications
• Differing site conditions or concealed conditions
• Lack of action by government bodies
• Intervention by outside agencies
Types of Construction Delay
Excusable Delays (defined):
“Excusable delays are caused by conditions that are
reasonably unforseeable and not within the contractor’s
control”
Note: Always check the particular construction contract
documents for valid delay factors and limitations.
Types of Construction Delay
Non-Excusable Delays:
• Late performance of subcontractors
• Late performance by suppliers
• Faulty workmanship by the contractor or subcontractors
• A project specific labor strike caused by either the
contractor’s unwillingness to negotiate or by unfair job
practices
Types of Construction Delay
Non-Excusable Delays:
Again: Verify the particular contract
language for definitions and limitations!
Categories of Delays
Is the delay excusable?
compensable
nonexcusable
Is the delay compensable
noncompensable
excusable
Assess delay
Critical Documentation
As Planned Schedule:
• Detailed Critical Path Method schedule;
or
• Bar chart schedule;
or
• Narrative schedule
Critical Documentation
As Built Schedule:
• Final as-built CPM schedule with periodic updates;
and
• Project daily reports;
• Meeting minutes;
• Inspection reports by the designer, owner, bldg inspector
• Correspondence
• Memos to file
As Planned Schedule
(Sample Project)
As Built Schedule
(Sample Project)
Schedule Analysis Methods
1. As Planned versus As Built Comparison
2. The Impacted As Planned Method
3. Collapsed (But for) As Built Method
4. Contemporaneous Period (Windows)
Analysis
As Planned versus As Built
Comparison
As Planned versus As Built
Comparison
Benefits:
• Simple to Prepare:
168 actual days – 112 planned days = 56 delay days
Shortcomings:
• No information on particular delay events;
• Similar to “Total Cost” approach
Impacted As Planned Method
• Begin with As Planned Schedule
• Add Owner or Contractor Delays
• Compute Owner caused delay and
Contractor caused delay
As Built with Delays
As Planned with Owner Delays
As Planned with Owner Delays
• Total duration of As Built = 168 days
• Total duration of As Planned with Owner Delays = 154
days
• Total duration of original As Planned = 112 days
• The Owner is responsible for the difference between
impacted and the original as planned:
154 – 112 = 42 days
• Contractor is responsible for the remaining difference:
168 – 154 = 14 days
As Planned with Contractor Delays
As Planned with Contractor Delays
• Total duration of As Built = 168 days
• Total duration of As Planned with Contractor Delays =
140 days
• Total duration of original As Planned = 112 days
• The Contractor is responsible for the difference between
impacted and the original as planned:
140 – 112 = 28 days
• The Owner is responsible for the remaining difference:
168 – 140 = 28 days
As Planned Method Discussion
Benefits:
• Relatively simple to implement
• Allows for mitigation of delays
Shortcomings:
• Highly subjective
• Assumes as-planned (baseline) logic holds.
Collapsed (But For) As Built Method
• Begin with As Built Schedule, including;
• Owner and Contractor Delays.
• Remove Owner (Contractor) caused
delays.
• Resulting schedule shows when
Contractor (Owner) would have finished
“but for” Owner (Contractor) delays.
As Built with Delays
Collapsed As Built without (but for)
Owner Delays
Collapsed As Built without (but for)
Owner Delays
• Total duration of As Built = 168 days
• Total duration of Collapsed As Built without Owner’s
Delays = 147 days
• Total duration of original As Planned = 112 days
• The Owner is responsible for the difference between
collapsed as built and the as built schedules:
168 – 147 = 21 days
• The Contractor is responsible for the remaining
difference between collapsed as built and as planned:
147 – 112 = 35 days
Collapsed As Built Discussion
Benefits:
• Very good accuracy
Shortcomings:
• No allowance for mitigation of delays
Contemporaneous Period Analysis
(Windows)
• Begin with As Planned Schedule;
• Select periods (windows) to analyze;
• Enter actual progress and delay activities using
contemporaneous project documents;
• Calculate the schedule;
• Repeat the process for the next window
CPA Method – Window 1
CPA Method – Window 1
• The first update is compared to the original schedule.
• Delays in that period are analyzed using “but for”
method.
• The first update becomes the new baseline for
subsequent window.
• Evaluation of non-excusable, compensable and non-
compensable delays performed at each update
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
CPA Method – Window 2
CPA Method – Window 2
• No delays during 2nd window
• Note activities that were supposed to start by now.
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
CPA Method – Window 3
CPA Method – Window 3
• Two overlapping delays
• 2 weeks charged to concurrent delay (excusable and
non-compensable)
• 1 week charged to contractor (non-excusable)
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
3 12 154 21 7 14 0
Subcontractor left job; Owner
changed window design
CPA Method – Window 4
CPA Method – Window 4
• Contractor-caused delay not on critical path.
• As long as the delay is within available float there is no
effect on the final completion date.
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
3 12 154 21 7 14 0
Subcontractor left job; Owner
changed window design
4 16 154 0 0 0 0
Garage walls delay; not on critical
path.
CPA Method – Window 5
CPA Method – Window 5
• Owner’s delay of 4 weeks in Garage door revision.
• Net change to the project is only 2 weeks; other 2 weeks
absorbed by available float.
Update Schedule Project Delay Delays
Number Date Completion During Non Excusable Excusable Comments
(Week No.) (days) Period Excusable Noncompensable Compensable
0 0 112 0 0 0 0
1 4 133 21 0 0 21 Unforseen site condition
2 8 133 0 0 0 0 No delay
3 12 154 21 7 14 0
Subcontractor left job; Owner
changed window design
4 16 154 0 0 0 0
Garage walls delay; not on critical
path.
5 20 168 14 0 0 14 Owner's revision to Garage doors
TOTALS 56 7 14 35
Contemporaneous Period Analysis
(Windows) Discussion
Benefits:
• Most accurate results
• Considers dynamic nature of the critical path
Shortcomings
• Time consuming
• Costly to prepare
Comparison of Results
Delays
Method Non Excusable Excusable
Excusable Noncompensable Compensable
Comparison Method (Total Time) 1
56 (0) 0 (56)
Impacted As-Planned (Owner Delays) 14 42
Impacted As-Planned (Contractor Delays) 28 28
Collapsed As-Built (But For) 35 21
Contemporaneous Period (Windows) Analysis 7 14 35
1. Schedule comparison itself does not indicate which party is
responsible for the delay.
Method Selection Criteria
METHOD Data Required Effort/Cost Accuracy Expected
Comparison Method (Total Time) Low $ Poor
Impacted As-Planned (Owner Delays) Moderate $$ Good
Impacted As-Planned (Contractor Delays) Moderate $$ Good
Collapsed As-Built (But For) Above Moderate $$$ Very Good
Contemporaneous Period (Windows) Analysis Extensive $$$$$ Excellent

More Related Content

What's hot

VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 

What's hot (20)

VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 

Similar to Construction delays

PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Managementbrainquisitive
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
Chapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfChapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfFREDERICKOKPAISE
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionGalala University
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction ContractsMelissa Brumback
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
15 Annual General Meeting
15 Annual General Meeting15 Annual General Meeting
15 Annual General MeetingNamgay Tshering
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Controlakashpadole
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 

Similar to Construction delays (20)

PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Chapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfChapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdf
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
15 Annual General Meeting
15 Annual General Meeting15 Annual General Meeting
15 Annual General Meeting
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Job Order Contracting 101
Job Order Contracting 101Job Order Contracting 101
Job Order Contracting 101
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Project management
Project managementProject management
Project management
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 

Recently uploaded

CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxSaujanya Jung Pandey
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectivesmintusiprd
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentationthomas851723
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentationthomas851723
 

Recently uploaded (20)

CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Risk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptxRisk management in surgery (bailey and love).pptx
Risk management in surgery (bailey and love).pptx
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectives
 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentation
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentation
 

Construction delays

  • 1. Schedule Delay Analysis Jack A. Lazarczyk, CPA, CCC Senior Consultant
  • 2. Types of Construction Delay Basic Distinctions: • Excusable and Non-Excusable • Compensable and Non-Compensable • Concurrent and Non-Concurrent • Critical versus Non-Critical
  • 3. Types of Construction Delay Excusable Delays: • General labor strikes • Fires, floods and other natural disasters • Owner directed changes • Errors and omissions in the plans and specifications • Differing site conditions or concealed conditions • Lack of action by government bodies • Intervention by outside agencies
  • 4. Types of Construction Delay Excusable Delays (defined): “Excusable delays are caused by conditions that are reasonably unforseeable and not within the contractor’s control” Note: Always check the particular construction contract documents for valid delay factors and limitations.
  • 5. Types of Construction Delay Non-Excusable Delays: • Late performance of subcontractors • Late performance by suppliers • Faulty workmanship by the contractor or subcontractors • A project specific labor strike caused by either the contractor’s unwillingness to negotiate or by unfair job practices
  • 6. Types of Construction Delay Non-Excusable Delays: Again: Verify the particular contract language for definitions and limitations!
  • 7. Categories of Delays Is the delay excusable? compensable nonexcusable Is the delay compensable noncompensable excusable Assess delay
  • 8. Critical Documentation As Planned Schedule: • Detailed Critical Path Method schedule; or • Bar chart schedule; or • Narrative schedule
  • 9. Critical Documentation As Built Schedule: • Final as-built CPM schedule with periodic updates; and • Project daily reports; • Meeting minutes; • Inspection reports by the designer, owner, bldg inspector • Correspondence • Memos to file
  • 12. Schedule Analysis Methods 1. As Planned versus As Built Comparison 2. The Impacted As Planned Method 3. Collapsed (But for) As Built Method 4. Contemporaneous Period (Windows) Analysis
  • 13. As Planned versus As Built Comparison
  • 14. As Planned versus As Built Comparison Benefits: • Simple to Prepare: 168 actual days – 112 planned days = 56 delay days Shortcomings: • No information on particular delay events; • Similar to “Total Cost” approach
  • 15. Impacted As Planned Method • Begin with As Planned Schedule • Add Owner or Contractor Delays • Compute Owner caused delay and Contractor caused delay
  • 16. As Built with Delays
  • 17. As Planned with Owner Delays
  • 18. As Planned with Owner Delays • Total duration of As Built = 168 days • Total duration of As Planned with Owner Delays = 154 days • Total duration of original As Planned = 112 days • The Owner is responsible for the difference between impacted and the original as planned: 154 – 112 = 42 days • Contractor is responsible for the remaining difference: 168 – 154 = 14 days
  • 19. As Planned with Contractor Delays
  • 20. As Planned with Contractor Delays • Total duration of As Built = 168 days • Total duration of As Planned with Contractor Delays = 140 days • Total duration of original As Planned = 112 days • The Contractor is responsible for the difference between impacted and the original as planned: 140 – 112 = 28 days • The Owner is responsible for the remaining difference: 168 – 140 = 28 days
  • 21. As Planned Method Discussion Benefits: • Relatively simple to implement • Allows for mitigation of delays Shortcomings: • Highly subjective • Assumes as-planned (baseline) logic holds.
  • 22. Collapsed (But For) As Built Method • Begin with As Built Schedule, including; • Owner and Contractor Delays. • Remove Owner (Contractor) caused delays. • Resulting schedule shows when Contractor (Owner) would have finished “but for” Owner (Contractor) delays.
  • 23. As Built with Delays
  • 24. Collapsed As Built without (but for) Owner Delays
  • 25. Collapsed As Built without (but for) Owner Delays • Total duration of As Built = 168 days • Total duration of Collapsed As Built without Owner’s Delays = 147 days • Total duration of original As Planned = 112 days • The Owner is responsible for the difference between collapsed as built and the as built schedules: 168 – 147 = 21 days • The Contractor is responsible for the remaining difference between collapsed as built and as planned: 147 – 112 = 35 days
  • 26. Collapsed As Built Discussion Benefits: • Very good accuracy Shortcomings: • No allowance for mitigation of delays
  • 27. Contemporaneous Period Analysis (Windows) • Begin with As Planned Schedule; • Select periods (windows) to analyze; • Enter actual progress and delay activities using contemporaneous project documents; • Calculate the schedule; • Repeat the process for the next window
  • 28. CPA Method – Window 1
  • 29. CPA Method – Window 1 • The first update is compared to the original schedule. • Delays in that period are analyzed using “but for” method. • The first update becomes the new baseline for subsequent window. • Evaluation of non-excusable, compensable and non- compensable delays performed at each update Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition
  • 30. CPA Method – Window 2
  • 31. CPA Method – Window 2 • No delays during 2nd window • Note activities that were supposed to start by now. Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay
  • 32. CPA Method – Window 3
  • 33. CPA Method – Window 3 • Two overlapping delays • 2 weeks charged to concurrent delay (excusable and non-compensable) • 1 week charged to contractor (non-excusable) Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay 3 12 154 21 7 14 0 Subcontractor left job; Owner changed window design
  • 34. CPA Method – Window 4
  • 35. CPA Method – Window 4 • Contractor-caused delay not on critical path. • As long as the delay is within available float there is no effect on the final completion date. Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay 3 12 154 21 7 14 0 Subcontractor left job; Owner changed window design 4 16 154 0 0 0 0 Garage walls delay; not on critical path.
  • 36. CPA Method – Window 5
  • 37. CPA Method – Window 5 • Owner’s delay of 4 weeks in Garage door revision. • Net change to the project is only 2 weeks; other 2 weeks absorbed by available float. Update Schedule Project Delay Delays Number Date Completion During Non Excusable Excusable Comments (Week No.) (days) Period Excusable Noncompensable Compensable 0 0 112 0 0 0 0 1 4 133 21 0 0 21 Unforseen site condition 2 8 133 0 0 0 0 No delay 3 12 154 21 7 14 0 Subcontractor left job; Owner changed window design 4 16 154 0 0 0 0 Garage walls delay; not on critical path. 5 20 168 14 0 0 14 Owner's revision to Garage doors TOTALS 56 7 14 35
  • 38. Contemporaneous Period Analysis (Windows) Discussion Benefits: • Most accurate results • Considers dynamic nature of the critical path Shortcomings • Time consuming • Costly to prepare
  • 39. Comparison of Results Delays Method Non Excusable Excusable Excusable Noncompensable Compensable Comparison Method (Total Time) 1 56 (0) 0 (56) Impacted As-Planned (Owner Delays) 14 42 Impacted As-Planned (Contractor Delays) 28 28 Collapsed As-Built (But For) 35 21 Contemporaneous Period (Windows) Analysis 7 14 35 1. Schedule comparison itself does not indicate which party is responsible for the delay.
  • 40. Method Selection Criteria METHOD Data Required Effort/Cost Accuracy Expected Comparison Method (Total Time) Low $ Poor Impacted As-Planned (Owner Delays) Moderate $$ Good Impacted As-Planned (Contractor Delays) Moderate $$ Good Collapsed As-Built (But For) Above Moderate $$$ Very Good Contemporaneous Period (Windows) Analysis Extensive $$$$$ Excellent